HomeMy WebLinkAboutAQ_F_0400052_20200605_CMPL_InspRpt NORTH CAROLINA DIVISION OF Fayetteville Regional Office AIR QUALITY Anson County Waste Management Facility NC Facility ID 0400052 Inspection Report County/FIPS:Anson/007 Date: 06/05/2020 Facility Data Permit Data Anson County Waste Management Facility Permit 09835/T04 375 Dozer Drive Issued 2/26/2019 Polkton,NC 28135 Expires 1/31/2024 Lat: 35d 0.2610m Long: 80d 9.7720m Class/Status Title V SIC: 4953/Refuse Systems Permit Status Active NAICS: 562212/Solid Waste Landfill Current Permit Application(s)None Contact Data Program Applicability Facility Contact Authorized Contact Technical Contact SIP/Title V Tyler Fitzgerald Tyler Fitzgerald Lana Brown MACT Part Subpart 6C District Manager District Manager Eastern Region Env. NSPS: Subpart t XXX (704)694-6900 (704)694-6900 Manager (901)500-1812 Compliance Data Comments: PARTIAL INSPECTION—COVID-19 Inspection Date 06/05/2020 y� Inspector's Name Jeffrey D.Cole Operating Status Operating Inspector's Signature: Compliance Code Compliance-inspection Action Code PCE On-Site Inspection Result Compliance Date of Signature: S y® Total Actual emissions in TONS/YEAR: TSP S02 NOX VOC CO PM10 *HAP 2018 0.8800 0.6000 3.56 3.32 19.35 0.8800 1974.04 2017 1.07 0.7300 4.36 2.83 23.70 1.07 1664.09 2016 0.9900 0.6700 4.03 2.35 21.91 0.9900 1413.25 *Highest HAP Emitted in ounds Five Year Violation History: None Date Letter Type Rule Violated Violation Resolution Date Performed Stack Tests since last FCE:None Date Test Results Test Method(s) Source(s)Tested Anson County Waste Management Facility Partial Compliance Inspection Page 2 of 4 I. LOCATION/DIRECTIONS: Anson County Waste Management Facility is located at 375 Dozer Drive, near Polkton,NC,Anson County. Directions: From FRO,take Raeford Road,Hwy 401, south to Wagram,—32 miles. Just past Wagram turn right onto Old Wire Road(SR 144)to Laurel Hill. Turn right(west)on Highway 74 and go approx. 41 miles. Turn right between NC DMV office building and bridge over Brown Creek. Go approx. 0.4 mile and the landfill office is on the right. IL SAFETY: Hard hat, safety boots and safety vest are required when near the working face of the landfill. The principal hazards are from truck traffic and falls/sprains from walking on the uneven ground. III.FACILITY DESCRIPTION: The Anson County Waste Management Facility(ACWMF) is a municipal solid waste (MSW) landfill located near the town of Polkton, Anson County,North Carolina. The landfill began accepting waste in 2001. The facility installed a voluntary gas collection and control system to control odor, to minimize landfill gas migration,to allow the facility to build carbon credits, and to pursue gas-to-energy projects. The initial Air Quality permit was a state issued Synthetic Minor Permit for a waste gas flare because at that time the design capacity was less than Title V thresholds. On September 24,2013, the facility was issued the initial Title V permit. The design capacity of this facility is currently greater than the NSPS, Subpart W W W,applicability threshold of 2.5 million cubic meters by volume and 2.5 million mega grams by mass. The facility performed Tier 2 testing on December 15, 2011 and the results indicated that the NMOC emissions were below 50 mega grams per year(threshold to require a mandatory gas collection and control system). The Tier II results indicated an additional 5 years, with no GCCS requirement by Air Regulations NSPS WW W thru 2016. This facility performed its most recent Tier II test in December 2018 and into January 2019 and submitted a test report on February 28, 2019. The data summary of that report that was approved by DAQ indicates the facility continues to test out, less than 50 Mg/yr NMOC until 2022 (28.89 Mg/yr in 2022) On March 26, 2018,NCDEQ Solid Waste Division issued to ACWMF a Permit-To-Construct for Phase 3 and 4. On May 9,2018, construction of Phase 3 began and triggered NSPS XXX. The Initial Design Capacity Report to meet the requirements of NSPS XXX,40 CFR 60.767(a)(1)(i)and 40 CFR 60.676(b)(1)(i)(A)was submitted to DAQ on August 3,2018 to meet an August 7,2018 deadline. That report contained a NMOC Tier 1 calculation indicating the NMOC 867.5 Mg/yr. This facility elected to perform a Tier 2 Test to determine actual NMOC emissions. As noted above,the facility performed another Tier II test in December 2018 and into January 2019. The data summary of that report that was approved by DAQ indicates the facility continues to test out, less than 34 Mg/yr. NMOC until 2022. The facility has options to perform further testing as contained in NSPS XXX. However, should the facility not be able to test out of the requirement of a GCCS as required by NSPS XXX,the facility has 30 months from the Initial Design Capacity Report submitted on August 3, 2018 to fully comply with NSPS XXX. Also,ACWMF has submitted a permit application to include NSPS XXX into their permit. That permit action is under review in Raleigh Central Office Permit Section. FV. INSPECTION SUMMARY: On Friday, June 5,2020, I,Jeffrey Cole, of the DAQ Fayetteville Regional Office, spoke by phone with Mr. Tyler Fitzgerald, District Manager at Anson County Waste Management Facility. The purpose of this call was to perform a partial compliance inspection during the COVID-19 outbreak. No physical inspection of the facility was performed. Anson County Waste Management Facility Partial Compliance Inspection Page 3 of 4 Items that were discussed during the phone call were: a. Is the facility operating? The landfill is operating with normal staffing. On 4/1 1/20 they stopped accepting commercial waste on Saturdays(usually 6 AM to I IAM)due to COVID-19's economics effects on commercial waste generation. They are resuming their Saturday hours on 6/20/20. b. Is the facility continuing to operate all relevant control devices? Yes, all control devices are being operated. c. Are all the required monitoring, inspection, and recordkeeping activities being conducted as required in the air permit? Yes, all these activities are being conducted as required. d. Are all periodic reports being submitted per the permit requirements? Yes, all reports have been submitted as required. It is expected that all reports will be submitted as per the permit requirements. e. Is the permit nearing expiration? No,their permit does not expire until 1131/2024. f. Is the Air Quality Emission Inventory due soon? Yes, their AQEI is due before 6/30/20. It is currently being drafted. g. Is there any upcoming testing required? No It. Are there any operating issues at this time, or do they foresee any operating issues that will affect their ability to meet the air quality requirements? No. i. Do they require any assistance from DAQ at this time? No assistance is required at this time. Anson County Waste Management Facility Partial Compliance Inspection Page 4 of 4 V. NON-COMPLIANCE HISTORY SINCE 2010: • None VI. CONCLUSIONS AND RECOMMENDATIONS: Based on the information obtained during the phone conversation on June 5, 2020, Anson County Waste Management Facility APPEARS IN COMPLIANCE with the requirements outlined in their current air permit, 09835T04. /jdc