March 9, 2021
Mr. Issa J. Zarzar
General Manager- Central Carolina Projects
Duke Energy Progress, LLC
500 C P and L Road
Moncure,NC 27559-9517
SUBJECT: Review of STAR®Unit S02/CO2 CEMS Certification Report
Duke Energy Progress LLC - Cape Fear STAR® Facility
Moncure, Chatham County,North Carolina
Air Permit No. 10583ROI
Facility ID No. 1900134
Dear Mr. Zarzar:
The Division of Air Quality(DAQ) has reviewed the subject certification report for the
sulfur dioxide (S02) /carbon dioxide (CO2) continuous emissions monitoring systems (CEMS)
installed on the Staged Turbulent Air Reactor(STAR®) Unit(ID No. ES-5) at the Cape Fear
STAR® Facility. The purpose of the report was to obtain certification of the following
monitoring systems:
Source Parameter Manufacturer/Model Serial Number
STAR® Unit(ES-5) S02 Teledyne API T100 5017
CO2 Teledyne API T360 416
Based on our review, we have the following comments:
1. Duke Energy installed the S02/CO2 CEMS on the ash beneficiation STAR®process
pursuant to NCAC 2D .0516 - Sulfur Dioxide Emissions from Combustion Sources and Air
Permit No. 10583, Specific Condition 2.LA.2.
2. Certification testing was performed in accordance with 40 CFR Part 60, Appendix B,
Performance Specification 2 (PS-2) for S02 and PS-3 for CO2. The certification report
included a 7-day calibration error test performed on operating days between December 31,
2020 and January 12, 2021, and a relative accuracy test audit (RATA)performed by Grace
Consulting, Inc. on January 27, 2021. Since the CEMS appear to have met the requirements
of PS-2 and PS-3, the S02/CO2 CEMS operating on the STAR®Unit are certified effective
January 27, 2021.
D EQ
North Carolina Department of Environmental Quality I Division of Air Quality
217 West Jones Street 1 1641 Mail Service Center I Raleigh,North Carolina 27699-1641
NORTH CAROLINA _
oeparnmem of eammameami Quality /`� 919.707.8400
Mr. Issa J. Zarzar
March 9, 2021
Page 2
3. The certification report included a CEMS Monitoring Plan along with a CEMS Quality
Assurance Plan (QAP) in accordance with Specific Condition 2.I.A.2.d.iii and NCAC 02D
.0613 Quality Assurance Program [which contains information required by 40 CFR Part 60,
Appendix F, Section 3 - Quality Assurance Procedures]. The plans have been reviewed and
are acceptable.
4. Finally, your facility's CEMS QAP requires that quarterly audits must be conducted: either a
cylinder gas audit (CGA) or a RATA being conducted at least once every four calendar
quarters. The next RATA for this source must be completed by March 31, 2022. Please
ensure the Quality Assurance/Quality Control (QA/QC)requirements are met and complied
with at all times. In addition, please notify this office at least 45 days prior to performing the
annual RATA so arrangements can be made to observe the test.
Due to the COVID-19 restrictions on DAQ staff and our office operations, the mailing of
this letter may be delayed. In the meantime, an electronic copy(e-copy) is being provided for
your records. If you should have any questions, please contact me at(919) 707-8410 or
dennis.igboko@ncdenr.gov.
Sincerely,
Dennis U. ;g2oko, Environmen 1 Engineer
Division of Air Quality,NCD
c: Issa Zarzar, Duke Energy (e-copy)
Jonathan Stamas, Duke Energy(e-copy)
Erin Wallace, Duke Energy(e-copy)
Martin Williams, Duke Power(e-copy)
Taylor Hartsfield, DAQ RRO (e-copy)
Gary Saunders, DAQ SSCB (e-copy)
IBEAM Documents, 1900134 (e-copy)
Central File, Chatham County