August 25, 2004
Mr. Gary Willer
The Plant Manager
Cogentrix of North Carolina,Inc.
P.O.Box 10836
Southport,North Carolina 28461-0836
Subject: Excess Emissions Report(EER)for the 2nd Quarter,2004
Facility I.D. No, 1000067
Dear Mr.Willer:
The Division of Air Quality(DAQ)has reviewed the subject report dated July 29,2004 and submitted
by Cogentrix of Southport,Inc. for Units No. 1 and 2. The report was reviewed for compliance with
the applicable emission standards set forth in 40 CFR Part 60 Subpart Db,the general provisions of 40
CFR 60.11(d) and 40 CFR 60.13.
For Units 1 and 2, compliance with the nitrogen oxide emission standard is determined through the use
of a 30-day rolling average emission rate in accordance with 40 CFR 60.46b. There were no violations
of the NO,,emission standard for Units 1 and 2.
Also,Units 1 and 2 are subject to the opacity standards set forth in 40 CFR 60 Subpart Db. Thus,when
reviewed for compliance with the standards, the report indicated 384 minutes(61 periods)of opacity
excursions for Unit 1 and 300 minutes (50 periods) of opacity excursions for Unit 2. The six-minute
opacity excess emission incidents for Unit 1 occurred due to boiler shutdown, broken baghouse bags,
high ash coal, and mechanical seals. The six-minute opacity excess emission incidents for Unit 2
occurred due to boiler shutdown,broken baghouse bags, and mechanical seals.
DAQ's review of the Continuous Emissions Monitoring Compliance Report(CEMCR)for NO,,,the
Excess Emissions Report(EER)for opacity,and Continuous Monitoring System(CMS)downtime
(DT) for Units 1 and 2 during the quarter ending June 30, 2004 confirmed the reported results as
follows:
Units: No. 1 No. 2
NO,Excess Emission: 0.00% 0.00%
NO,CMS Downtime: 1.67% 0.06%
Opacity Excess Emission: 0.32% 0.27%
Opacity CMS Downtime: 0.31% 0.09%
Technical Services Section One
1641 Mail Service Center,Raleigh,North Carolina 27699-1641 NofthCuolina
2728 Capital Blvd,,Raleigh,North Carolina 27604
Phone: 919-733.1728/FAX 919-733.1812/Internet: www.ncair.org Natwrallw
Mr. Gary E.Willer
August 25, 2004
Page Two
For the purpose of assessing good operation and maintenance(O&M)practices for particulate emission
control devices and all continuous monitoring systems, the DAQ uses,among other things,the EPA
Region IV CEM Enforcement Plan(CEP). Based on this plan, excess emissions(opacity only)and/or
monitor downtime(all CMS)greater than 2%, 5% for two consecutive quarters or 10%for any one
quarter is followed by appropriate agency response and for enforcement purposes only. All data in your
second quarter report indicated you were below the CEP threshold levels for all of your Units 1 and 2.
Finally,unless the permit or any applicable rule states otherwise,your future quarterly Continuous
Emission Monitoring Compliance Report and Excess Emission Reports will be reviewed consistent
with the compliance of the emission control standards set forth in 40 CFR 60,Subpart Db, and the CEP
will be used to assess excess opacity emissions and CMS downtime. All violations of the NOX emission
standard may result in enforcement actions.
If you have any questions regarding the issues discussed in this letter,please contact me at
(919)715-0726.
Sincerely,
, /
Richard R. Simpson