HomeMy WebLinkAboutAQ_F_0400033_20110420_CMPL_InspRpt NORTH CAROLINA DIVISION OF Fayetteville Regional Office
AIR QUALITY Martin Marietta Aggr Pee Dee Quarry
NC Facility ID 0400033
Inspection Report County/FIPS:Anson/007
Date: 04/25/2011
Facility Data Compliance Data
Martin Marietta Aggr Pee Dee Quarry Inspection Date 04/20/2011
2710 Wycliff Road Inspector's Name Cindy Grimes
Pee Dee,NC 28091 Operating Status Operating
Lat: 34d 56.2500m Long: 79d 53.0000m Compliance Code Compliance-inspection
SIC: 1423/Crushed And Broken Granite Action Code FCE
NAICS: 212313 /Crushed and Broken Granite Mining and Quarrying On-Site Inspection Result Compliance
Contact Data Permit Data
Facility Contact Authorized Contact Technical Contact Permit 06334/R05
Brian North Daniel Shephard Brian North Issued 10/19/2007
PE Manager,Engineering Executive Vice President PE Manager,Engineering Expires 9/30/2012
Services (919)784-4550 Services Classification Small
(336)389-6616 (336)389-6616 Permit Status Active
Inspector's Signam 0: ( Comments:
i ✓
Date of Signature:
MACT/GACT Applicability: None(Facility has not broken ground on site yet,thus is not operating;with
the permit information DAQ FRO has been given thus far, facility should not be subject to any MACTs).
1) Location
Martin Marietta Aggregate-Pee Dee Quarry is located at 2710 Wycliff Road in Pee Dee(just west of the
Pee Dee River),NC,Anson County.
Directions
From FRO,take Hwy 401 South to Wagram.Turn right at Old Wire Road(Hwyl44)and go— 11 V2 miles to
Laurel Hill.Tutn7ight at Hwy 74,and go west—24 miles until Hwy 145 (— I mile after crossing the Pee Dee
River).Turn left onto Hwy 145 South and drive about V4 mile. Planned site is on the right hand side.
Safety Considerations:Standard DAQ safety equipment required.When facility starts operating,be alert to
large equipment on site.
2) Facility and Process Description
Martin Marietta Aggregate Pee Dee Quarry is a rock quarry that is permitted to produce gravel and
aggregate used in construction. This facility is permitted under Air Permit No.63341105,effective from
19 October 2007 until 30 September 2012. Cindy Grimes conducted the last compliance inspection on
26 May 2010.This facility has not been constructed yet.
This facility is(will be)a quarry which extracts mainly granite from the earth.The granite and crushed stone
products are loosened by drilling and blasting,and then are loaded by power shovel or front-end loader into
large haul trucks that transport the material to the processing operations. Primary operations include a jaw,
which is used for initial crusher reduction,and a series of conveyors.This crusher product is next fed through
a grizzly feeder for undersize material,and then is discharged onto a conveyor,where it goes through more
screening processes, until it is conveyed to a surge pile for temporary storage or sold as coarse aggregate.
a) Throughputs for 2010
Employees: 0 (same in 2009)
Hours: 0 (same in 2009)
Production: 0 (same in 2009)
b) Permitted Sources
Emission Emission Source Control Control System
_ T
Source ID Description F System ID ; Description
Non Metallic Mineral Processing Plant,800 tons per hour rating, utilizing water suppression with no other
control devices,including
Crushers(NSPS) FCruslnng Operations
Conveyors(NSPS) FConveymg Operations WS Wet suppression water spray system
Screens(NSPS) CScreening Operations
3) Inspection Summary
This facility has not begun operations at its proposed site.I drove by the site on 20 April 2011 and did
not observe any equipment or evidence of ground-breaking.
I also called Brian North,the Technical and Authorized Contact of this facility,on 25 April 2011 to verify
the status of the quarry.He was not available,but I spoke to another person in his office,and they told me
that they have no plans to develop the site in the near future.
4) Permit Stipulations
Per permit.
5) Reporting Requirements
Within 15 days after start-up of the rock crushing operation,the Permittee shall notify, in writing,the
Regional Supervisor of the start-up.
6) 112R Status
Unknown at this time. Facility has not been constructed to date.
7) DAQ Compliance History
This facility has not started operations since its initial permit; it has had no prior DAQ violations.
8) Comments and Compliance Statement
This facility has not been established on site as of the date of this inspection.FRO has been informed that the
company still plans on developing the site sometime in the future.
Since the permit expires on 30 September 2012,Brian North(Facility Contact) should be contacted-in
April-May 2012 to discuss the renewal process/emissions inventory.
Martin Marietta Aggregate Pee Dee Quarry appeared to be in compliance on 20 April 2011.