HomeMy WebLinkAbout19980260 Ver 3_R-2247EB 4B Meeting Minutes FINAL_20190405sTv 100
�
MEETING MINUTES
DATE: March 19, 2019
CLIENT: NCDOT
PROJECT: R-2247EB Winston-Salem Northern Beltway Interchange at US 52 (Future I-74)
MEETING LOCATION: NCDOT Roadway Design Conference Room, Building A
STARTING TIME: 8:00 am
ENDING TIME: 10:00 am
SUBJECT: 4B Merger Meeting Minutes
Meeting Attendees
Robert Patterson, NCDEQ-DWR
Dave Wanucha, NCDEQ-DWR (via phone)
Nicholle BraspennickY, USACE
Marla Chambers, NCWRC
Amy Euliss, NCDOT-Division DEO (via phone)
Craig Lee, NCDOT-Hydraulics (via phone)
Michael Shumsky, NCDOT-Design Build
Jon Nance, NCDOT-Design Build
Andy Hussey, NCDOT-Design Build
Bill Barrett, NCDOT-EAU
John Jamison, NCDOT-EPU
Mike Sanderson, NCDOT-EPU
Mark Staley, Roadside (via phone)
Matt Adams, Blythe Construction
Luca Pellegrini, Blythe Construction
Richard Hiner, Wood PLC (via phone)
Eddie Vance, STV
Adam Alvey, STV
Mark Pugh, STV
Note: Discussion and comments from meeting are in blue
General
• Project Overview
• Plan Sheet 4— Begin Project at North End of US 52
• P1an Sheet 17 — End Project at South End of US 52
• P1an Sheet 12 — Tie to U-2579DEF (Winston-Salem Outer Beltway)
• Plan Sheet 13 — Future Beltway Project R-2247EA
• Plan Sheets 7, 8& 9— Project Encompasses Current Design-Build Project R-2247EC
960 WESTTRADf STREET, SUITE 715
AN EMALRYEf-OWNED [pMAANY PApVIOINGQUAl1TYSEAV7CE5IN[f 1412 I CHARLQTTE, P!C 28:202-11AA
f704! 372-1885 FAX: (7041 372-3393
sTv 100
e�r r.�
■ Blyth Construction has both Design-Build Contracts (R-2247 & EC)
■ Proposed drainage for EC Project is shown as existing on EB Plans
• Project located within the Yadkin River Basin. There are no specific stormwater
requirements, but will use maximum extent practicable
• Identified 2 potential locations for stormwater basin which are under review
• Culverts
10 Large Culverts on the Project
■ Including 3 extensions
■ 2 replacements
■ 5 new crossings
■ 2 FEMA (Grassy Creek)
■ Use streambed riprap protection if outlet velocity is greater than 10 fps
■ Use energy dissipator if outlet velocity is greater than 15 fps
• Avoidance and Minimization
Reduced earthwork (million cubic yards of borrow to balanced on-site)
■ Lowered interchange/reduced footprint
■ Eliminated a new continuous 1200' culvert (Ramp & Loop B)
• Retained 350' open channel inside Loop B
• Retained 100' minimum open channel between culverts
Shifted Ramp DB and Loop D away from Grassy Creek
■ Eliminated Ramp DB crossing over Grassy Creek
■ Reduced 1600' mainline culvert to 1200'
• Based on preliminary design reduced stream impacts by 20%
• General Comments
■ Culverts that will not be buried should be called out on plans as "Do Not Bury" and those
that are to be buried should be noted as such. For permitting phase a table is to be
developed listing all culverts and noting whether they are buried or not; and including
buried depth.
■ Any buried culvert should consider using sills to avoid head-cutting. If we are burying a
new RCBC then we will provide sills but if it is an extension that is currently buried
without sills, then using sills may not be possible due to hydraulic constraints.
■ Provide inlet and outlet details which display the culvert and channel cross section on
Permit Drawings (4C Plans).
■ Use geotextile liner under rip rap in channel changes unless there is a flood bench. In that
case, use Class II stone on the toe of the bench and coir fiber matting on the bench. If
bench is built on fill material, use riprap.
■ Riprap outlet pads should be flush with the streambed.
■ Marla Chambers w/ NCWRC mentioned several times to assess using low-flow and high-
flow ban-els for multiple-barrel culverts.
SHT 4
Culvert extension up and downstream for Beaver Dam Creek (QQQ)
• Team currently evaluating a retaining wall to avoid utility conflict on downstream end
which will reduce impacts
Impacts to 2 small tributaries (PPP & SSS) from embankment
Discussion about adding sills and backfilling existing culvert extension:
sTv 100
�
Amy Euliss opposed backiill existing culverts running under US 52 d e to the difiiculty
getting equipment into the culvert and the high cost to the department. If the hydraulic
capacity allows sills to be added, the culvert will fill in on its own over time.
Provide a cross section of the culvert showing the floodplain in the permit plans.
Craig Lee is open to further discussion of sills based on meeting design flow
SHT 5
SHT 6
SHT 7
Culvert extension up and downstream for Muddy Creek (UU)
• Adding a supplementa160" trenchless pipe for capacity
• Team currently evaluating a retaining wall to avoid utility conflict on downstream end
which will reduce impacts
Impacts to small tributary (000) from embankment
Same comments as sheet 4
No Jurisdictional Impacts
Evaluating a U-shaped retaining wall to avoid utility conflict at tributary (WWW)
Tributary TT and W49 are impacted from EC Section (Site 1)
• Additional impacts from SB 52 split on downstream end
Discussion on method to distinguish new EB impacts from previous EC impacts
• Perhaps a note or table at each site
• Use different hatching or shading
• STV will provide an example prior to submittal
SHT 8-A
• Tributary LLL is impacted from EC Section (Site 2)
• No additional impacts anticipated
SHT 8-B
• Tributary SS and W50 are impacted from EC Section (Site 4)
• Additional impacts due to NB 52 tie in will be included
SHT 8-C
• Tributary LLL is impacted from EC Section (Site 2)
• Additional impacts from SB 52 split will be included
SHT 8-D
SHT 9
Tributary SS and W26 are impacted from EC Section (Site 6)
• Additional impacts from SB 52 split will be included for impacts to wetland and stream
(SS, W48 and W26).
Amy F,uliss recoinmended that W26 be a total take
Show EC riprap pads
Note: Plan sheet 9 was revised after posted for agency review; an updated sheet was provided at
the 4b meeting.
• Revised cross pipe location
• Elevations did not work with preliminary layout
• Tie to new 42" trenchless pipe from EC Section
• Generally positive co�nnlents about revised cross pipe location
SHT 9-A
• Tributary III is impacted from EC Section (Site 7)
• No additional impacts anticipated
SHT 9-B
sTv 100
�
• New impacts to tributary DDD and W30 `
• New impacts to tributary WW
• Replacing existing 72" CMP with 7'x7' RCBC
• It was noted that this is a long culvert (approx. 1,200'), so will not be buried.
• Also, Amy requested that for the 4c plans, that appropriated details be included (e.g. for bank
stabilization).
• Preliminary stormwater basin
• Replace 30" CMP outfall pipe
SHT 9-C
• Impacts to tributaries VV and III
• Drainage from cross pipe diverted from III to VV
• It was requested that the Stream Form for Stream V V be checked to see if there was any biology
in the stream. The Stream Form is attached with Lines 20-24 outlined. It is noted that the stream
assessment was conductcd "abovc culvcrt," which should bc a good justification to not providc
fish passage.
• Impacts to W42
SHT 9-D
• 4 culverts replaced single 1200' culvert
• Culverts buried 1'
• Reduced total impacts
• Amy Euliss recommended arming the banks in-between the culverts, for short segments (100' or
less), and for any segments that are currently incised and unstable.
• Culverts do not need to be buried
SHT 10-A
• Realigned Ramp DB out of Grassy Creek floodplain and eliminated culvert
• Reduced length of 7'x7' RCBC from 1600' to 1200'
• Culvert not buried because of length
• Preliminary starmwater basin inside Loop D
• Chccic to scc if adding a bench is possible (may not be due to already large cut)
SHT 11-A&B
• Approximately 550' double RCBC buried 1' w/ 1' flood bench (Grassy Creek)
• Riprap lined channel change (Is riprap bottom preferred?)
• Single 7'x6' RCBC buried 1'
• Show detail at tributary culvert outlet and make sure it flows to low portion of channel change,
not to the bench
• Amy requested that the side slope of the bench be armored with Class 2 riprap. We need to ensure
that the larger rock is used to line the benches, especially at the lowest rocks on the bench.
• Malce sure that the outfall ditch along slope prior to bridge is stable; possibly add riprap
protection to the toe of slope
SHT 12
• No Jurisdiction Features
SHT 13-A
• Downstream culvert from sheet 9-D
• Channel change (Riprap?)
• No impacts to W34 and W35
• Amy stated that there will be impacts to W34 for the tie-in.
• Impacts to W43
Impacts not in functional design
sTv 100
�
• Riprap line the channel change
• Amy Euliss recommended that W43 be a total take
• Grass hatching missing in wetland
SHT 14-A
• W29 is an abandoned stormwater basin
• Breach dam and provide stable channel to Grassy Creek
• Impacts to tributary ZZ
• Bank stabilization at Grassy Creek
• Discussion about abandoned stormwater basin being a permitted NPDES basin
• Note: Per an email from Joe Fogarty, PE (City of Winston-Salem), there is no record of a
stormwater feature at this location; most likely an old sediment basin left in place after
construction. A copy of the email will be attached to these minutes.
SHT 14-B
• Replace existing 36" CMP with trenchless pipe
• Bank stabilization only
• Ties to 48" RCP pipe system
SHT 14-C
• Extend existing 9'x9' RCBC (Grassy Creek)
SHT 15
• Inlet end of 1200' 7'x7' RCBC
SHT 16
• No Jurisdictional Impacts
SHT 17
• No Jurisdictional Impacts
From: Shumsky, Michael J <mshumsky@ncdot.gov>
Sent: Wednesday, February 13, 2019 4:05 PM
To: PELLEGRINI Luca; ADAMS Matthew; Robbins, Mark; Vance, Edward; Bailey,
Stacey
Cc: Euliss, Amy; Lee, Craig J; Capps, Karen B; Archer Sr, Wright; Nance, Jon G
Subject: FW: [External] RE: stormwater feature impacted by R-2247EB
**This e-mail is from outside SN*"
For your records.
Michael J. Shumsky, PE
Design-Build Engineer
Design-Build Unit
North Carolina Department of Transportation
919 707 6627 office
mshumsky(a�ncdot.qov
1595 Mail Service Center
Raleigh, NC 27699-1595
^� r � '��
, :
J�`�.r �p
-, � -�_>;
-, .
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
From: Patterson, Robert D <robert.patterson@ncdenr.�ov>
Sent: Wednesday, February 13, 2019 1:48 PM
To: Euliss, Amy <aeuliss@ncdot.gov>; Lee, Craig J<cllee@ncdot.gov>; Shumsky, Michael J
<mshumsky@ncdot.�ov>
Cc: Braspennickx, Nicholle M CIV USARMY CESAW (US) <Nicholle.M.Braspennickx@usace.army.mil>;
Barrett, William A<wabarrett@ncdot.�ov>; Wanucha, Dave <dave.wanucha@ncdenr.�ov>
Subject: RE: [External] RE: stormwater feature impacted by R-2247E6
Sounds good. Thank you for verifying!
Robert D. Patterson, P.E.
Stormwater Engineer
919-707-3880* � Robert.Patterson@ncdenr.gov � *Notenewnumberasoflan.30,2019
https://deq.nc.�ov/about/divisions/water-resources/water-quality-permittin�/transportation-permitting
NC Dept. of Environmental Quality � DWR Transportation Permitting
512 N. Salisbury St., 12`h floor � 1617 Mail Service Center � Raleigh, NC 27699-1617
Email correspondence to and from this address is subject to the North Carolina Public Records Law and may be disclosed to third parties.
From: Euliss, Amy
Sent: Wednesday, February 13, 2019 1:26 PM
To: Patterson, Robert D<robert.patterson@ncdenr.�ov>; Lee, Craig J<cilee@ncdot.�ov>; Shumsky,
Michael J <mshumsky@ncdot.�ov>
Cc: Braspennickx, Nicholle M CIV USARMY CESAW (US) <Nicholle.M.Braspennickx@usace.army.mil>;
Barrett, William A<wabarrett@ncdot.�ov>; Wanucha, Dave <dave.wanucha@ncdenr.�ov>
Subject: FW: [External] RE: stormwater feature impacted by R-2247EB
Robert,
I reached out to the City of WS after our 4B meeting this morning. They have no record of a permitted
stormwater device at the approximate location on the attached map. Unless you have any objections,
we will proceed with the feature as a wetland and not a permitted post construction stormwater
device.
Michael,
Can you share this email and Robert's response with the rest of the Design Build team? Thanks.
Craig,
Can you add a note to the meeting minutes? Thanks.
For referenced this is for wetland W29 on plan sheet 14-A or R-2247EB.
Amy Euliss
Division 9 Environmental Officer
North Carolina Department of Transportation
336 747 7802 office
aeuliss(a�ncdot.gov
375 Silas Creek Parkway
Winston Salem, NC 27127-7167
,..,,;, .
^�.1��. �:
�r��,�/'
;, . -�� . �iY�>
-• � .
From: Joe Fogarty <josephf@cityofws.org>
Sent: Wednesday, February 13, 2019 1:19 PM
To: Euliss, Amy <aeuliss@ncdot.gov>; Keith Huff <keithhl@cityofws.org>
Cc: Shumsky, Michael J<mshumsky@ncdot.�ov>; Lee, Craig J<cilee@ncdot.gov>; Barrett, William A
<wa ba rrett@ ncdot.�ov>
Subject: [External] RE: stormwater feature impacted by R-2247EB
External email. Do not click links or open attachments unless you verify. Send all suspicious email as an
� attaChment to report.spam@nc.gov
Amy,
We have no records of a Stormwater feature tied to a permit at this location. My initial assumption is
that it is likely an old sediment basin that was just left in place after the construction of the
development it may have served.
Rega rds,
Joe Fogarty PE
City of Winston-Salem
Stormwater Engineer
City Hall — Suite 53
101 N. Main Street,
Winston-Salem NC 27101
Tel: (336) 747-6961
E-mail: iosephf@citvofws.or�
From: Euliss, Amy <aeuliss@ncdot.gov>
Sent: Wednesday, February 13, 2019 12:43 PM
To: Keith Huff <keithhl@cityofws.org>; Joe Fogarty <josephf@cityofws.or�>
Cc: Shumsky, Michael J<mshumsky@ncdot.�ov>; Lee, Craig J<cllee@ncdot.gov>; Barrett, William A
<wa ba rrett@ ncdot.�ov>
Subject: stormwater feature impacted by R-2247EB
CAUTION: This email originated from outside of the organization. Do not click links or open
attachments unless you recognize the sender and know the content is safe.
Keith and Joseph,
NCDOT is impacting a feature as part of the WS beltway that has a riser pipe. We need to know if this is
a stormwater feature that is tied to a permit. It is currently unmaintained and overgrown. DWR is
asking us to research if there is a permit tied to it. If it is a permitted device, I also need to know if it was
a Phase II requirement. I have attached a screen shot of the approximate location. Thanks.
Amy Euliss
Division 9 Environmental Officer
North Carolina Department of Transportation
336 747 7802 office
aeuliss(a�ncdot.gov
375 Silas Creek Parkway
Winston Salem, NC 27127-7167
,,.urr ,
'�;r={- �
: `� r�� '�
� -�Y�>�r
-,� �:
Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third parties.
Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third parties.
� V
NC DW Stream Identification Form Version 4.11 �%v 0�, �e �ci; fl ;
Date: � �..r ProjecUSite: Z2 ��. � Latitude: �6� ���y
Evaluator: r) r� } l���a�T� County: �, h Longitude:��� 3,OI�
�
Total Points: � �-- Stream Determination (c' Other
Stream is at least intermittent �/` � Ephemeral Intermitten Perennial e.g. Quad Name:
if 2 19 or perennia! if 2 30` 1
A. Geomor holo (Subtotal = :t
1 a Continuity of channel bed and bank
2. Sinuosity of channel along thalweg
3. In-channel structure: ex. riffle-pool, step-pool,
ripple-pool sequence
4. Particle size of stream substrate
5. Active/relict floodplain
6. Depositional bars or benches
7. Recent alluvial deposits
8. Headcuts
9. Grade control
10. Natural valley
� 11. Second or greater order channel
a artificial ditches are not rated; see discussions in manual
B. Hydrolog (Subtotal =
12. Presence of Baseflow
13. Iron oxidizing bacteria
14. Leaf litter
15. Sediment on plants or debris
16. Organic debris lines or piles
17. Soil-based evidence of high water table?
C. Biology (Subtotal = S
.�
'0
0
�
0
0
0
ri7
�
Weak
1
1 .�
1
1
1
1
1
1�
1�
1�
1�
1�
�. �
�
�
�r;
2
2
1
1
2
18. Fibrous roots in streambed � 2 �
19. Rooted upland plants in streambed �
20. Macrobenthos (note diversity and abundance 6 � 2
21. Aquatic Mollusks � 2
22. Fish 0.5 1
23. Crayfish �
24. Amphibians 0 0.5 1
25. Algae 0 .5 1
26. Wetland plants in streambed FACW = 0.75; OBL = 1.5 �
"perennial streams may also identified using other methods. See p. 35 of manual.
Notes: �
�. �;.� p , a �'
��
��
.�
��
��
����
��'�%
��
��
Yes=3
�
3
3
0
1.5
1.5
0
0
3
3
1.5
1.5
1.5
1.5
Sketch: