HomeMy WebLinkAbout20181638 Ver 1_Project Description_20181130Irl Mountain Vail,e�r
MVP Southgate Project
Pre -Construction Notification —
Joint Permit Application
U.S. Army Corps of Engineers —
Wilmington District (SAW -2018-00887)
North Carolina Department of
Environmental Quality,
Division of Water Resources
November 2018
M Mountain Valley Joint Permit Application
'T PIPELINE US Army Corps of Engineers & NC Dept of Environmental Quality
Docket No. PF18-4-000
TABLE OF CONTENTS
1.0
INTRODUCTION........................................................................................................................1-1
1.1
SCOPE OF THE JOINT PERMIT APPLICATION.......................................................1-1
2.0
PROJECT DESCRIPTION...........................................................................................................2-1
2.1
PURPOSE AND NEED...................................................................................................2-1
2.2
LOCATION.....................................................................................................................2-3
2.3
PROPOSED FACILITIES...............................................................................................2-4
2.3.1 Pipeline Facilities................................................................................................2-5
2.3.2 Additional Temporary Workspace......................................................................2-5
2.3.3 Access Roads......................................................................................................2-6
2.3.4 Contractor Yards.................................................................................................2-6
2.3.5 Aboveground Facilities.......................................................................................2-7
2.3.5.1 Meter Stations.....................................................................................2-7
2.3.5.2 Mainline Valves..................................................................................2-8
2.3.5.3 Pig Launchers and Receivers..............................................................2-8
2.4
CONSTRUCTION...........................................................................................................2-8
2.4.1 General Practices................................................................................................2-8
2.4.2 Typical Upland Pipeline Construction Procedures.............................................2-9
2.4.3 Typical Wetland Pipeline Construction..............................................................2-3
2.4.4 Typical Waterbody Crossings.............................................................................2-4
2.4.5 Aboveground Facilities.....................................................................................2-17
2.4.6 Access Roads....................................................................................................2-17
2.5
RESTORATION............................................................................................................2-17
2.5.1 Pipeline.............................................................................................................2-18
2.5.1.1 Uplands.............................................................................................2-18
2.5.1.2 Wetlands............................................................................................2-18
2.5.1.3 Waterbodies.......................................................................................2-19
2.5.2 Access Roads....................................................................................................2-19
2.5.3 Aboveground Facilities.....................................................................................2-19
2.5.4 Contractor Yards...............................................................................................2-19
2.6
QUALITY ASSURANCE MEASURES.......................................................................2-20
2.7
SCHEDULE...................................................................................................................2-21
2.8
OPERATION AND MAINTENANCE.........................................................................2-21
2.9
FUTURE PLANS AND ABANDONMENT................................................................2-22
2.10
ROUTE ALTERNATIVES ANALYSIS......................................................................2-22
3.0
EXISTING SITE CONDITIONS.................................................................................................3-1
3.1
WETLAND AND WATERBODY DELINEATION......................................................3-1
3. 1.1 Wetlands.............................................................................................................3-1
3.1.2 Waterbodies........................................................................................................3-1
3.1.3 Preliminary Jurisdictional Determination...........................................................3-9
4.0
WETLAND AND WATERBODY IMPACT ASSESSMENT....................................................4-1
4.1
WETLAND IMPACTS...................................................................................................4-6
4. 1.1 Temporary Construction Impacts.......................................................................4-6
4.1.2 Permanent Conversion of Forested Wetlands to Nonforested Wetlands ............
4-6
4.1.2.1 Permanent Fill for Access Road..........................................................4-6
November 2018
M Mountain Valley
Ir PIPELINE
Joint Permit Application
USACE-Wilmington Districts and NCDEQ
SAW -20188-00887
4.2
WATERBODY IMPACTS..............................................................................................4-7
4.2.1 Temporary Construction Impacts.......................................................................4-7
4.2.2 Permanent Impacts..............................................................................................4-7
4.3
RIPARIAN BUFFER IMPACTS....................................................................................4-7
4.3.1.1 Diffuse Flow Requirement................................................................4-14
4.3.1.2 No Practicable Alternatives...............................................................4-14
4.3.1.3 Impact Mitigation..............................................................................4-14
4.4
IMPACT AVOIDANCE AND MINIMIZATION MEASURES..................................4-14
4.4.1 Stormwater Management and Diffuse Flow Plan.............................................4-18
4.4.1.1 Stormwater Management Plan..........................................................4-18
4.4.1.2 Certified Local Government Stormwater Review.............................4-18
5.0 ADDITIONAL SUPPORTING INFORMATION.......................................................................5-1
5.1
ENVIRONMENTAL DOCUMENTATION...................................................................5-1
5.2
VIOLATIONS.................................................................................................................5-1
5.3
CUMULATIVE IMPACTS.............................................................................................5-1
5.4
SEWAGE DISPOSAL.....................................................................................................5-5
5.5
ENDANGERED SPECIES AND DESIGNATED CRITICAL HABITAT
....................5-5
5.5.1 Consultation........................................................................................................5-5
5.5.2 Findings..............................................................................................................5-6
5.5.3 Wildlife Species..................................................................................................5-6
5.5.4 Aquatic Species...................................................................................................5-7
5.5.5 Plant Species.......................................................................................................5-8
5.5.6 Conclusions.........................................................................................................5-8
5.6
ESSENTIAL FISH HABITAT........................................................................................5-9
5.7
CULTURAL RESOURCES INFORMATION...............................................................5-9
5.8
FLOOD ZONE DESIGNATION....................................................................................5-9
6.0 REFERENCES.............................................................................................................................6-1
November 2018
M Mountain Valley Joint Permit Application
'T PIPELINE USACE-Wilmington Districts and NCDEQ
SAW -20188-00887
LIST OF FIGURES
Figure 1. Southgate Project Overview Map ...................
Figure 2. Typical Pipeline Construction Sequence ........
Figure 3. Dam and Pump Crossing Method Typical......
Figure 4. Flume Crossing Method Typical ....................
Figure 5. Cofferdam Crossing Typical ..........................
Figure 6. Conventional Bore Typical ............................
Figure 7. Horizontal Directional Drill Typical ..............
..........................................................................1-2
........................................................................ 2-10
.......................................................................... 2-7
............................Error! Bookmark not defined.
........................................................................2-11
........................................................................ 2-13
........................................................................ 2-16
LIST OF TABLES
Table 2-1 Major Regions, 8 -digit HUC and 10 -digit HUCs crossed by the Project ........................2-3
Table 2-2 Proposed Southgate Project Facilities and Land Requirements in North Carolina .......... 2-4
Table 2-3 Southgate Project Contractor Yards in North Carolina...................................................2-7
Table 2-4 Southgate Project Mainline Valve and Meter Station (Interconnect) Locations .............2-8
Table 2-5 Construction Schedule for Major Components of the MVP Southgate Project.............2-21
Table 2-6 Minor Route Variations to Avoid or Minimize Impacts to Wetlands or Waterways in North
Carolina.......................................................................................................................... 2-23
Table 3-1 Summary of Wetlands Delineated and Desktop Reviewed in the North Carolina Project
Survey Area by Sub-watershed........................................................................................ 3-2
Table 3-2 Summary of Waterbodies Delineated and Desktop Reviewed in the North Carolina Project
Survey Area by Sub-watershed........................................................................................ 3-5
Table 4-1 Summary of Proposed Wetland Impacts in North Carolina............................................4-2
Table 4-2 Summary of Proposed Waterbody Impacts in North Carolina........................................4-4
Table 4-3 North Carolina Riparian Buffer Impacts within the Jordan Watershed ...........................4-9
Table 5-1 Projects with Potential Cumulative Impacts....................................................................5-3
Table 5-2 100 -Year Floodplain areas crossed................................................................................5-10
LIST OF APPENDICES
Appendix A
North Carolina USGS 7.5 -Minute Topographic Map Excerpts
Appendix B
North Carolina Alignment Sheets
Appendix C
Typical Construction Detail Drawings
Appendix D
FERC Upland Erosion Control, Revegetation, and Maintenance Plan
Appendix E
FERC Wetland and Waterbody Construction and Mitigation Procedures
Appendix F
Spill Prevention and Countermeasure Control Plan
Appendix G
Wetland and Waterbody Crossing Analysis
Appendix H
HDD Site Specific Crossing Plans
Appendix I
HDD Contingency Plan
Appendix J
FERC Environmental Document
Appendix K
North Carolina Wetland and Waterbody Delineation Report
Appendix L-1
Proposed Wetland Impacts by ID and Impact Type
Appendix L-2
Proposed Waterbody Impacts by ID and Impact Type
Appendix M
North Carolina Proposed Impact Drawings
Appendix N
Compliance Statement for NWT 12 Terms and Conditions
iv November 2018
IT Mountain Valley Joint Permit Application
PIPELINEJu USACE-Wilmington Districts and NCDEQ
SAW -20188-00887
Appendix O Water Resources Identification and Testing Plan
Appendix P Unanticipated Cultural Resources Discoveries Plan
Appendix Q FEMA Flood Zone Maps
v November 2018
M Mountain Valley
Ir PIPELINE
Joint Permit Application
USACE-Wilmington Districts and NCDEQ
SAW -20188-00887
LIST OF ACRONYMS AND ABBREVIATIONS
API
American Petroleum Institute
ATWS
Additional temporary construction workspace
BA
Biological Assessment
BMPs
best management practices
CEQ
Council on Environmental Quality
Certificate
Certificate of Public Convenience and Necessity
CFR
Code of Federal Regulations
Corps
US Army Corps of Engineers or USACE
DOE
US Department of Energy
ECD
Erosion Control Device
EI
Environmental Inspector
E&SCP
Erosion and Sediment Control Plan
East Tennessee
East Tennessee Natural Gas, LLC
FERC or Commission
Federal Energy Regulatory Commission
EFH
Essential Fish Habitat
EFSO
Ecological Field Services Office
EPA
Environmental Protection Agency
ESI
Environmental Services Inc.
FEMA
Federal Emergency Management Agency
FWS
Fish and Wildlife Service
HDD Plan
Horizontal Directional Drill Fluid Monitoring, Operations, and
Contingency Plan
HDD
Horizontal Directional Drill
HUC
Hydrologic Unit Code
hp
horsepower
IPaC System
Information Planning and Conservation System
MLV
mainline valve
MP
milepost
NCDEMLR
North Carolina Department of Energy, Mineral and Land Resources
NCDEQ
North Carolina Department of Environmental Quality
NCDWR
North Carolina Department of Water Resources
NGO
non-governmental organization
NHD
National Hydrography Dataset
NHI
National Heritage Inventory
NMFS
National Marine Fisheries Service
NOAA
National Oceanic and Atmospheric Administration
NWI
National Wetland Inventory
NWP
Nationwide Permit
Plan
FERC Upland Erosion Control, Revegetation, and Maintenance Plan
PCN
Pre -Construction Notification
Procedures
FERC Wetland and Waterbody Construction and Mitigation Procedures
Project
MVP Southgate Project
psig
pounds per square inch gauge
PSNC Energy
PSNC Energy, a wholly owned subsidiary of SCANA Corporation
A November 2018
M Mountain Valley
Ir PIPELINE
Joint Permit Application
USACE-Wilmington Districts and NCDEQ
SAW -20188-00887
SPCC Plan
Spill Prevention, Control, and Countermeasures Plan
The Project
Mountain Valley Pipeline, LLC
Transco
Transcontinental Gas Pipe Line Company, LLC
U.S.
United States
USACE
U.S. Army Corps of Engineers
USDOT
United States Department of Transportation
USGS
United States Geological Survey
USFWS
United States Fish and Wildlife Service
WQC
Water Quality Certification
vii November 2018
M Mountain Valley Joint Permit Application
PIPELINE USACE — Wilmington District and NCDEQ
SAW -2018-008887
1.0 INTRODUCTION
Mountain Valley Pipeline, LLC ("Mountain Valley") is proposing to construct and operate the MVP
Southgate Project ("Southgate Project" or "Project"). The Southgate Project will provide timely, cost-
effective access to new natural gas supplies to meet the growing needs of natural gas users in the
southeastern United States ("U.S."). The Project is expected to be in service by late 2020 and is a separate
project from the 303 -mile Mountain Valley Pipeline that is currently under construction.
The Southgate Project includes an approximately 0.4 -mile -long 24 -inch -diameter pipeline (H-605), 73
miles of 24- and 16 -inch -diameter natural gas pipeline (H-650), a new 28,915 nominal horsepower ("hp")
compressor station (Lambert Compressor Station), meter stations and other ancillary facilities (e.g.
contractor yards and access roads) required for the safe and reliable operation of the pipeline. The
Southgate Project facilities will be located in Pittsylvania County, Virginia and Rockingham County and
Alamance County, North Carolina. A location map (Figure 1) illustrates the proposed Project facilities.
The Project is regulated by the Federal Energy Regulatory Commission ("FERC" or "Commission")
pursuant to Section 7(c) of the Natural Gas Act and requires a Certificate of Public Convenience and
Necessity ("Certificate") to construct and operate. The FERC will conduct a full review of the Project under
its regulations in compliance with the Natural Gas Act ("NGA") and the National Environmental Policy
Act. On May 3, 2018, the Project requested approval from the FERC to initiate the Pre -filing review process
for the Project, and the FERC issued its approval of the request on May 15, 2018, under Docket No. PF 18-
4-000. The Pre -filing review process allows for active participation by interested stakeholders early in
Project development while maintaining a coordinated schedule and helps to ensure the timely review and
determination on the Certificate application. The Project filed an application with the Commission for a
Certificate to construct, install, own, operate, and maintain the Project on November 6th, 2018.
1.1 SCOPE OF THE JOINT PERMIT APPLICATION
In addition to the FERC Certificate, the Southgate Project will require several additional permits, clearances
and / or approvals to construct or operate the Project facilities. This application is limited to the portion of
the Project within the State of North Carolina, and is being submitted in support of requests for the
following:
• Nationwide Permit 12 verification from the U.S. Army Corps of Engineers ("USACE")
Wilmington District for wetland and waterbody impacts under Section 404 of the Clean Water Act
(33 U.S.C. § 1344);
• 401 Water Quality Certification from the North Carolina Department of Environmental Quality
("NCDEQ") for activities in state surface waters and wetlands under Section 401 of the Clean
Water Act (33 U.S.C. § 1341), N.C. General Statue § 143-215.3(c), and Title 15A N.C.
Administrative Code § 02H.0500 et seq.; and
• Riparian Buffer Authorization from NCDEQ under N.C. General Statue § 143-214.5 and Title 15A
N.C. Administrative Code § 02B.0262 et seq.
A separate Joint State/Federal Permit application is being prepared for the portion of the Project within
Virginia under USACE Action # NAO-2018-1574.
1-1 November 2018
M Mountain Valley
Ir PIPELINE iu
Franklin -
County
0 0 44
0
Joint Permit Application
USACE — Wilmington District and NCDEQ
SAW -2018-008887
y - r Pittsylvania
Yp i County mm�n
H e n ry
County - 10
+olllusrlll,= O
't 1
1f20
1
, T1
'=3 1
CSG!
-------� -------
—.
--x... _..—..—.. �..�-.—.-_—..—..---
30
o 4
l
Rockingham40
50
o
------__------1=-----------------------------------------•r-----
.-I �►/0 ,ice
Silnlmrcl•.I�k
�,Tati faarf1 «�1. ti�fi� 60 Alamance
!a �1ittfit I County
Guilfore7.' �✓ J
.:
s County
^'.7i L� IG14A®F! I
r
' 70 +
• I' .I p 1.1eG:.h��
U 3 11
r r r
n I I
i0 4. - 6 ', Fores-t Oaks -
Pleasant �- I I
nnIAG G,vtden
lgend
—Proposed Pipeline Route
0 Compressor Station
❑ Contractor Yard
• Meter Station
L Valve Site
— iState Boundary
_—_'County Boundary
1 inch = 8 miles
Data Sources: ESRI, USGS, TRC, EQT When Printed 8.5x11
Figure 1. Southgate Project Overview Map.
Halifax f
C ou m y Soulh\liasi o
:LL
Hyco,'L!ke ese
Person
County
Orange
County
t
186 ' ❑
Hip I2WOU .+ti- " a:;*
\+i
�F�7�pl Hili
1T1 Mountain Valley
Figure 1
Project overview
OCT 2018
TRCWO Wilowbroek Ln
1"'[�+ �/ye st Cheffier, PA19382
1-2 November 2018
M Mountain Valle
PIPELINE
2.0 PROJECT DESCRIPTION
2.1 PURPOSE AND NEED
Joint Permit Application
USACE — Wilmington District and NCDEQ
SAW -2018-008887
The proposed Southgate Project is a new pipeline designed to (1) meet the growing needs of natural gas
users in the southeastern U.S.; (2) add a new natural gas transmission pipeline to provide competition and
enhance the reliability and resiliency of the existing pipeline infrastructure in southern Virginia and North
Carolina; and (3) provide southern Virginia and North Carolina with direct pipeline access to the Marcellus
and Utica gas regions in West Virginia, Ohio and southwestern Pennsylvania. The Project will enhance the
diversity of gas supply and create additional pipeline capacity in the region. The overall purpose and need
with respect to the single and complete projects included in this preconstruction notification is to provide a
timely, efficient, and cost-effective means of transporting natural gas from the existing terminus of the
Mountain Valley Pipeline in Pittsylvania County, Virginia to the T-15 Dan River Interconnect in
Rockingham County and then on to the T-21 Haw River Interconnect in Alamance County, North Carolina,
so that that the natural gas may be distributed to local and regional end users via those interconnects.
In 2017, PSNC Energy, a wholly owned subsidiary of SCANA Corporation, solicited interest from existing
and proposed interstate pipeline providers for additional natural gas transportation capacity. PSNC Energy
is a local distribution company primarily engaged in the purchase, transportation, distribution, and sale of
natural gas to more than 563,000 customers in North Carolina. PSNC Energy solicited interest because it
requires additional pipeline capacity to meet forecasted incremental demand on its distribution system.
Over the past four years, PSNC Energy has experienced a 15 percent increase in peak daily throughput on
its system. This trend will carry forward into the future, as PSNC Energy expects its design day
requirements to increase an additional 11 percent over the next five years. This past, present, and future
demand growth on PSNC Energy's system reflects, at least in part, the substantial population increase in
North Carolina. North Carolina's population is expected to increase by nearly 2 million people between
2020 and 2035.1
After consideration of other existing and proposed interstate pipeline providers, PSNC Energy committed
to 300 million cubic feet per day ("MMcf/d") of firm transportation service to be made available by the
Project. Mountain Valley and PSNC Energy entered into binding long-term agreements in December 2017
that made PSNC Energy an anchor shipper for the Project.2 In choosing the Southgate Project to provide
its needed incremental pipeline capacity, PSNC Energy cited numerous reasons, including transportation
cost, supply cost, supply diversity, reliability/resiliency, and operational efficiencies:
• PSNC Energy found the Southgate Project provides the best -cost transportation alternative
available to satisfy PSNC Energy's long-term interstate capacity needs.
1 See North Carolina Office of State Budget and Management population projections, available at:
http s://files. nc. gov/nco sbm/demog/countytotals_populationoverview. html
2 Mountain Valley and PSNC Energy entered into binding agreements for the Southgate Project more than three years
after Mountain Valley entered the pre -filing process, and more than two months after the Commission issued its
certificate, for the 303 -mile Mountain Valley Pipeline Project. While the Mountain Valley Pipeline Project is targeted
to commence service during 2019, Mountain Valley expects the Southgate Project to commence service in late 2020.
2-1 November 2018
M Mountain Valley
Ir PIPELINE
Joint Permit Application
USACE — Wilmington District and NCDEQ
SAW -2018-008887
The Southgate Project will provide PSNC Energy with a third direct interstate pipeline connection,
which will improve reliability and add resiliency to the interstate pipeline services PSNC Energy
receives.' The addition of a third interstate pipeline diversifies risk by giving PSNC Energy
multiple options on geographically -diverse interstate pipelines. In the event of outages or
constraints on one of the pipelines serving the region, PSNC Energy would have access to the other
pipelines to continue serving its customers.
• The Southgate Project will provide PSNC Energy additional direct access to low-cost natural gas
produced in the prolific Marcellus and Utica shale regions.'
PSNC Energy will have more competitive and diverse options for natural gas supply. PSNC
Energy will gain optionality in selecting best -cost supply sources and will be able to take advantage
of price differentials across more gas supply regions.
The Southgate Project will provide a direct connection between PSNC Energy's distribution system
and the East Tennessee Natural Gas, LLC ("East Tennessee") pipeline system. PSNC Energy
currently sources gas from Saltville Storage and transports these volumes on the East Tennessee
and Transcontinental Gas Pipeline Company, LLC ("Transco") systems before delivery to PSNC
Energy's distribution system. The Project provides a primary receipt and delivery forward haul
transportation path that offers improved reliability as compared to the secondary -firm backhaul
deliveries PSNC Energy currently receives from Transco.
• The Southgate Project will provide PSNC Energy flexibility with deliveries from the intrastate
Cardinal Pipeline, which should avoid the need for PSNC Energy to acquire additional Cardinal
capacity.
• The Southgate Project allows PSNC Energy to avoid incremental capital investment for system
upgrades. The other pipeline alternatives considered by PSNC Energy would have required
additional system upgrades.
• Mountain Valley and PSNC Energy have agreed to a minimum delivery pressure that is higher than
Transco's existing obligation. This should improve PSNC Energy's ability to conduct system
planning and enhance the operation of its system.
In addition to executing agreements that made PSNC Energy an anchor shipper for the Project, Mountain
Valley conducted an Open Season between April 11, 2018 and May 11, 2018 to determine interest from
additional shippers. Negotiations continue with interested shippers for the remaining capacity of the
Southgate Project.
The Southgate Project is not designed to provide natural gas to any liquefied natural gas export terminal
and has no intention of seeking authorization under Section 3 of the Natural Gas Act to export natural gas,
nor does the contracted shipper have plans to transport gas to a liquefied natural gas terminal. The Project
terminates at an inland location more than 185 miles from the nearest coastal Virginia port, 155 miles from
' In 2013, the North Carolina Utilities Commission recognized the need for competitive interstate pipeline capacity
alternatives in Docket No. G-100, Sub 91, Investigation Regarding Competitive Alternatives for Additional Natural
Gas Service Agreements. The Project will satisfy this need for a new competitive interstate pipeline consistent with
the expressed goal of the North Carolina Utilities Commission.
' Mountain Valley and PSNC Energy also executed binding long-term agreements whereby PSNC Energy became a
shipper on the Mountain Valley Pipeline Project.
2-2 November 2018
M Mountain Valley Joint Permit Application
PIPELINE USACE —Wilmington District and NCDEQ
SAW -2018-008887
the nearest coastal North Carolina port, and even farther from the nearest liquefied natural gas export
terminal. Accordingly, the Southgate Project does not have the physical ability to export natural gas. As
currently designed, gas transported on the Southgate system will be delivered into existing facilities in Eden
and Graham, North Carolina. The Project's anchor shipper, PSNC Energy, has committed to 300 MMcf/d
of firm transportation service and will use the gas it transports to serve its fast growing residential,
commercial and industrial markets in North Carolina.
2.2 LOCATION
The North Carolina portion of the Project includes approximately 47 miles (64 percent) of the proposed
pipeline alignment. It originates at the Virginia/North Carolina state boundary in Rockingham, North
Carolina at milepost ("MP") 26.1 and ends at MP 73.1 in Alamance County, North Carolina, as shown on
Figure 1. The route through North Carolina is described below and is depicted on U.S Geological Society
("USGS") 7.5 -Minute topographic excerpt maps provided in Appendix A.
From the Virginia/North Carolina border, at MP 26.1 in Rockingham County, the 24 -inch -diameter pipeline
extends southwest approximately 4.3 miles to a proposed delivery interconnect (T-15 Dan River
Interconnect) located at approximate MP 30.4. From the T-15 Dan River Interconnect, the pipeline will be
a 16 -inch -diameter pipeline and continue southwest for approximately 2.4 miles. East of the City of Eden,
North Carolina, the pipeline will turn to the southeast near MP 32.8 and continue southeast for
approximately 20 miles into Alamance County at (MP 52.6), east of the town of Wentworth and the City
of Reidsville. From the Alamance County boundary, the pipeline will continue southeasterly to MP 66.3,
where it will turn south and continue for approximately 6.8 miles to its delivery terminus (T-21 Haw River
Interconnect) located at MP 73.1 approximately 2.5 miles southeast of the City of Graham, North Carolina.
The North Carolina portion of the Project is located within the USGS designated 03 -South Atlantic -Gulf
Region (USGS, 2018a). In North Carolina, the Project crosses the Roanoke River Basin and the Cape Fear
River Basin, three sub basins and five watersheds (NCDEQ, 2018b). Table 2-1 (below) identifies these
major regions and their respective sub -basins by 8 -digit HUC and watershed by 10 -digit HUC.
Table 2-1
Major Regions, 8 -digit HUC and 10 -digit HUCs crossed by the Project
Major Region
River Basin
County
Sub -basin
Watershed
(2 -digit HUC)
(8 -digit HUC)
(10 -digit HUC)
Rockingham
Upper Dan
Cascade Creek -Dan River
3010103
301010309
Roanoke
Rockingham
Lower Dan
Hogans Creek -Dan River
03- South Atlantic-
3010104
301010401
Gulf Region
Rockingham/
Headwaters Haw River
Alamance
Haw 3030002
303000202
Cape Fear
Alamance
Haw 3030002
Back Creek -Haw River
303000204
Source: NCDEQ, 2018b
2-3 November 2018
M Mountain Valley
2.3 PROPOSED FACILITIES
Joint Permit Application
USACE -Wilmington District and NCDEQ
SAW -2018-008887
In North Carolina, the Project includes 46 miles of new 24 -inch and 16 -inch diameter pipeline, temporary
construction workspace, new and existing access roads, above ground facilities, cathodic protection and
contractor yards. These are depicted on the Project's alignment sheets (Appendix B) and are described
below. Typical construction details depicting the workspace for the proposed facilities in a variety of work
conditions are provided as Appendix C. Table 2-2 summarizes the facilities by location and land
requirements for construction and operation.
Table 2-2
Proposed Southgate Project Facilities and Land Requirements in North Carolina
Total Land Requirements
Pipeline (acres) c/
County
Facility Length
(miles) Construction Operation e/
d/
H-650 Pipeline Right -of -Way a/ 26.5 304.10 153.30
Additional Temporary Workspace NA 97.70 0.00
Access Roads b/ NA 50.40 4.70
Rockingham
Contractor Yards NA 93.10 0.00
Aboveground Facilities NA 8.70 1.50
Cathodic Protection Ground beds NA 0.60 0.60
Total c/ 26.5 554.6 160.1
Pipeline Right -of -Way 20.5 235.30 119.70
Additional Temporary Workspace NA 72.00 0.00
Access Roads NA 24.70 2.30
Alamance
Contractor Yards NA 8.50 0.00
Aboveground Facilities NA 3.60 0.70
Cathodic Protection Ground beds NA 1.70 1.70
Total 20.5 345.8 124.4
Guilford
Access Roads NA 0.20 0.00
Contractor Yards NA 14.50 0.00
Total NA 14.70 0.00
Project Total in North Carolina 47.0 915.1 284.5
a/ Acreage based on 100 -foot construction right-of-way and 50 -foot operations right-of-way. Impacted acreage
will be less due to avoidance of sensitive resources where practicable.
b/ Acreage assumes a 25 -foot road width for temporary and permanent access roads. Actual road widths may be
less than 25 feet.
c/ Includes uplands and wetlands.
d/ Construction acreage includes the area affected by construction (i.e., temporary and additional temporary
workspace, contractor yards, and access roads) and the area affected by operation of the Southgate Project.
(i.e., facility operation footprint and 50 -foot pipeline permanent right-of-way). The 50 -foot -wide permanent right-
of-way between horizontal directional drill entry and exit points and within railroad rights-of-way are not included
in this acreage.
e/ Operation acreage includes only the operation footprint of the Southgate Project facilities (e.g., the 50 -foot -wide
permanent pipeline right-of-way in uplands and 25 -foot -wide maintenance corridor in wetlands). The 50 -foot -wide
permanent right-of-way between horizontal directional drill entry and exit points and within railroad rights-of-way
are not included in this acreage.
NA = Not Applicable
2-4 November 2018
M Mountain Valley Joint Permit Application
PIPELINE USACE — Wilmington District and NCDEQ
SAW -2018-008887
2.3.1 Pipeline Facilities
The pipeline will generally require a 100 -foot -wide construction right-of-way (limit of disturbance) during
construction consisting of a 50 -foot permanent right-of-way and 50 feet of temporary workspace. The
temporary workspace is necessary for worker safety, the safe travel of construction vehicles and equipment,
stockpiling soil, and installation of erosion and sediment controls. The proposed 100 -foot wide construction
right-of-way is consistent with the Interstate Natural Gas Association of America's ("INGAA")
recommendations for a pipeline diameter of 18 to 24 inches. INGGA recommends the use of a 95 -foot
baseline width and increasing or decreasing this baseline width for special conditions (Gulf Interstate
Engineering, 1999). The necessary construction workspace is largely dictated by the area required for the
safe operation and movement of equipment required to install the pipeline as well as the additional
workspace needed to install and maintain appropriate erosion and sediment controls. These workspace
requirements are not materially different for a 16 inch or 24 inch pipeline. See Appendix C for typical
construction workspace details.
The Southgate Project has reduced the construction right-of-way width at wetland and waterbody crossings
to 75 feet along the construction right-of-way, for a distance of 50 feet on each side of the crossing to
preserve upland and riparian buffer areas. The Project will implement the FERC Upland Erosion Control,
Revegetation, and Maintenance Plan ("Plan") (Appendix D) and the FERC Wetland and Waterbody
Construction and Mitigation Procedures ("Procedures") (2013) (Appendix E), and its Project -specific
Erosion and Sediment Control Plan (`B&SCP") that comply with state -specific regulations to minimize
impacts during construction. The Project is preparing a state -specific E&SCP that will comply with North
Carolina erosion control regulations and will incorporate all relevant substantive provisions of General
Permit — NCGO1000.5 See Appendix C for typical wetland and waterbody crossing details.
The pipeline is located parallel to and adjacent with an existing gas or electric transmission corridor for
approximately 18 miles (37 percent) of the proposed alignment in North Carolina. Where collocation with
existing utility right-of-way occurs, the Project has designed the workspace such that the construction right-
of-way for the new pipeline is located immediately adjacent to or partially within the existing pipeline right-
of-way wherever feasible. The Project is proposing to use up to 25 feet of temporary workspace within the
adjacent utility right-of-way where possible; however, final design and use of workspace within these areas
is dependent on successful negotiation with the easement owner(s). See Appendix C for typical
construction workspace details for construction with collocated facilities.
2.3.2 Additional Temporary Workspace
Additional temporary work space "ATWS" areas will be required for construction activities requiring space
outside the standard 100 -foot construction right-of-way. Construction activities that may require ATWS
include but are not limited to:
• Areas requiring extra depth of cover over the pipeline;
• Timber storage areas;
• Areas with unstable soil;
• Installation of erosion and sediment controls and other stormwater management facilities;
5 The Project is exempted from obtaining coverage under this permit for stormwater discharges by 33 U.S.C. § 1342(1).
2-5 November 2018
M Mountain Valley
Ir PIPELINE
Joint Permit Application
USACE — Wilmington District and NCDEQ
SAW -2018-008887
• Road and railroad crossings;
• Winch hills;
• Wetland and waterbody crossings;
• Conventional bores;
• Horizontal Direction Drills;
• Foreign pipeline crossings and interconnects;
• Foreign utility crossings;
• Areas requiring full -width topsoil segregation;
• Specific request of the landowner;
• Areas with steep side slopes, rock, or other difficult terrain;
• Pipeline access and truck turnarounds;
• Material storage, storage of excess spoil at crossings, parking, vehicle turning radius, or other
worker safety issues;
• Fabrication and staging areas; and
• Hydrostatic test water withdrawal and discharge locations.
The ATWS areas will be limited to the minimum size necessary to safely construct the pipeline and be
protective of the environment with respect to the existing conditions at the time of construction. ATWS is
located near wetlands and waterbodies in accordance with the setback requirements contained in the FERC
Procedures and in consultation with other federal and state agencies. If field conditions do not allow for a
minimum 50 -foot setback from wetlands and/or waterbodies, the Project will request alternative measures
to the FERC Procedures. Proposed ATWS and ancillary sites required for the Project are shown on the
alignment sheets (Appendix B).
2.3.3 Access Roads
New or existing roads will be used to provide access to the pipeline right-of-way during construction and/or
operation of the Project. Access road widths will be the minimum necessary to provide access for
construction equipment while maintaining safe travel conditions. Access will be constructed such that the
length of the road minimizes impacts on waters of the United States and will be maintained as close as
possible to pre -construction contours and elevations. Temporary construction -related wetland or waterbody
impacts are proposed along 11 access roads in Rockingham and two in Alamance Counties. Two of the
permanent access roads in Rockingham County have limited permanent wetland impacts and three will
have permanent culverted waterbody crossings. These impacts are discussed further in Section 4.0. The
locations of proposed temporary and permanent access roads are shown on the 7.5 -Minute topographic
maps (Appendix A) and alignment sheets (Appendix B).
2.3.4 Contractor Yards
The Southgate Project has identified potential contractor staging yards for temporary use during
construction. They will be used to stockpile pipe and fabricate facilities, if needed. Additionally, they will
be used by the construction contractor to stage construction operations, store materials, park equipment,
and set up temporary construction offices. The contractor yards were selected due to their proximity to
existing roads, railways, and rail yards and primary open industrial/commercial land uses. Focus was given
to properties with limited streams, wetlands, and other sensitive habitats. Depending upon the condition of
2-6 November 2018
M Mountain Valley Joint Permit Application
PIPELINE USACE — Wilmington District and NCDEQ
SAW -2018-008887
these yards and their current use, some surface grading, drainage improvements, placement of surface
materials (e.g., crushed rock), and internal roadways may be required.
Seven contractor yards are proposed. Minor construction -related temporary impacts to wetlands and
waterbodies are proposed for contractor yards 5 and 6. Table 2-3 details the land requirements and current
land use for contractor yards, and their locations are shown on the alignment sheets (Appendix B).
Table 2-3
Southgate Project Contractor Yards in North Carolina
Contractor Yard Name
Location/County
Approximate Milepost
Existing
Workspace
Land Use a/
(acres)
CY-04
Eden, Rockingham
2.8 miles West of 28.5
OL
3.8
CY-05
Eden, Rockingham
3.7 miles West of 28.3
Cl, OL, WL
49.9
CY-06
Eden, Rockingham
3 miles West of 28.9
OL, WL
15.9
CY-07
Eden, Rockingham
3.2 miles West of 28.9
OL, FW, Cl
8.8
CY-08
Reidsville, Rockingham
2.9 miles West of 44.6
OL, Cl
14.6
CY-09
McLeansville, Guilford
15.8 miles West of 68.2
OL, FW, RD
14.5
CY-10
Altamahaw-Ossipee,
60.2
OL
8.5
Alamance
a/ Existing Land Use: Cl = Commercial / Industrial; FW = Upland Forest / Woodland; OL = Upland Open Land; RD =
Residential; WL = Wetland
2.3.5 Aboveground Facilities
2.3.5.1 Meter Stations
Two downstream delivery points with the PSNC Energy system are proposed near MP 30 and MP 73. The
Project will install a meter (interconnect) station at both of these locations consisting of but not limited to
custody -transfer flow meter, pressure/flow regulator, over pressure protection, isolation mainline valves,
and associated instrumentation and controls at the proposed gas receipt and delivery points to measure the
flow of natural gas between the Project and the interconnect. Each interconnect will consist of one or more
meter runs located inside a fenced and gated site and will contain flow or pressure control. The metering
sites will be located as close as practicable to the actual intersection of the Project and the receipt / delivery
facilities to keep the length of the interconnecting piping to a minimum. The locations of these facilities
are described in Table 2-4 and are shown on the alignment sheets in Appendix B. The meter stations will
include upstream and downstream piping to connect to the pipeline and third -party pipelines.
2-7 November 2018
M Mountain Valley
Ir PIPELINE
Joint Permit Application
USACE — Wilmington District and NCDEQ
SAW -2018-008887
Table 2-4
Southgate Project Mainline Valve and Meter Station (Interconnect) Locations
Name County Approximate Milepost Location
T-15 Dan River Interconnect / MLV 4 Rockingham 30.4
MLV 5 Rockingham 42.2
MLV 6 Alamance 55.1
MLV 7 Alamance 68.2
T-21 Haw River Interconnect / MLV 8 Alamance 73.1
a/ Mainline Valves ("MLV's") will be 30 feet by 30 feet in area and will be wholly contained within the permanent
right-of-way. Mainline valves at the T-15 Dan River Interconnect and T-21 Haw River Interconnect will be
located within the fence line of those facilities.
2.3.5.2 Mainline Valves
The Project will install mainline valves ("MLVs") at intermediate locations as necessary to meet operational
needs and the design and installation requirements described in 49 CFR 192.179(a) — Transmission Line
Valves that require minimum distances to the nearest valve based on pipeline location class. Table 2-4
identifies the location of MLVs. MLVs will be located within the permanent right-of-way of the pipeline.
With the exception of those located at pig launcher/receiver locations, MLVs will be buried with
aboveground extensions and equipped with valve actuators to allow for local or remote operation. Each
MLV will be contained within a fenced, gated, and locked area. None of the MLVs are located in wetlands
or waterbodies.
2.3.5.3 Pig Launchers and Receivers
The Project has incorporated launching and receiving facilities to accommodate in-line inspection tools
(smart pigs) for periodic internal inspections of the pipeline during operations. A pig launcher is proposed
at the origination point inside the Lambert Compressor Station fence line at MP 0.0 of the pipeline in
Pittsylvania County, Virginia. The corresponding pig receiver will be located at MP 30.4 in Rockingham
County, North Carolina at the T-15 Dan River Interconnect (meter station), and a second pig launcher will
also be located at this site. A second pig receiver will be located at the terminus of the pipeline at
approximate MP 73.1 at the T-21 Haw River Interconnect near Graham, North Carolina. The locations of
these facilities are included on the alignment sheets located in Appendix B. No wetlands or waterbodies
will be affected by the construction or use of these Pig Launchers and Receivers.
2.4 CONSTRUCTION
2.4.1 General Practices
Construction of the Southgate Project will follow industry -accepted practices and procedures and will be
done in accordance with applicable federal and state regulations and guidelines, as well as the specific
requirements of applicable permits. The Project will adopt the FERC Plan (Appendix D) and Procedures
(Appendix E) to minimize impacts on the environment. The Project will develop its own Project -specific
Erosion and Sediment Control Plan (`B&SC") based on field conditions and state requirements that will
outline best management practices (`BMPs") to minimize impacts. The Project will train construction
personnel in the environmental restrictions and/or requirements applicable to their particular duties. The
Project will provide construction management personnel and environmental inspectors ("EIs") with the
2-8 November 2018
M Mountain Valley Joint Permit Application
PIPELINE USACE — Wilmington District and NCDEQ
SAW -2018-008887
appropriate environmental information/materials specific to the Project. The Project will handle any
hazardous materials stored or encountered during construction in accordance with the Project Spill,
Prevention, Control, and Countermeasures Control Plan ("SPCC") (Appendix F). Waste will be disposed
of at an approved, off-site facility.
The pipeline will be buried a minimum of three feet below the ground surface except for locations where
the pipe will be installed within rock. In those instances, the minimum depth of cover will be two feet. The
pipeline will be constructed of high strength carbon steel pipe manufactured in accordance with the
American Petroleum Institute's ("API") specification API 5L PSL2, Specification for Line Pipe. The
Project will protect the pipe from corrosion by a fusion -bonded epoxy coating and an impressed current
cathodic protection system during operation. Weld joints and other piping that are not factory coated will
be field coated per applicable standards.
The Project is proposing to use two spreads to construct the pipeline. Spread 1 includes MP 0 to MP 30.4
and Spread 2 includes MP 30.4 to MP 73.1. Generally, construction of the proposed pipeline within each
spread will follow a set of sequential operations as shown in Figure 2. In this typical pipeline construction
scenario, the construction spread proceeds along the pipeline right-of-way in one continuous operation.
The Project will coordinate the entire process in such a manner as to minimize the total time a tract of land
is disturbed and therefore exposed to erosion and temporarily precluded from normal use. Appendix C
includes typical construction details depicting various construction scenarios. The following sections
provide detailed descriptions of each proposed construction method.
2.4.2 Typical Upland Pipeline Construction Procedures
The majority of the pipeline is in upland terrain and will be crossed via conventional overland construction
techniques for large -diameter pipelines. In this typical pipeline construction scenario (Figure 2), the
construction contractor will construct the pipeline along the construction right-of-way using sequential
pipeline construction techniques, including survey, staking and fence crossing; clearing and grading;
trenching; pipe stringing, bending and welding; lowering -in and backfilling; hydrostatic testing; clean-up
and restoration; and commissioning. Each step is briefly described in the following:
(a) Surveying
The initial step in preparing the right-of-way for construction will be the civil survey. A civil survey crew
will stake the outside limits of the construction right-of-way, the centerline location of the pipeline, highway
and railroad crossings, access roads, and any temporary ATWS, such as laydown areas or at stream
crossings. The Project will contact the North Carolina 811 "One Call" system, and all known underground
utilities (e.g., cables, conduits, and pipelines) will be located and flagged. The Project will notify affected
landowners a minimum of 24 hours prior to surveying and staking of the proposed route, following
applicable state/federal guidelines.
(b) Clearing and Grading, and Fencing
After the right-of-way has been surveyed and easements have been secured (for the permanent and
temporary construction right-of-way, and any existing right-of-way if necessary), the Project will clear the
right-of-way of obstructions (e.g., trees and stumps, brush, logs, and large rocks) according to the FERC
Plan, the Project -specific E&SCP and applicable regulatory approvals. The Project will clear the right-of-
way to the width required for construction, but not more than specified on the pipeline alignment sheets
(Appendix B) and approved by applicable regulatory approvals. Merchantable timber will be stacked
2-9 November 2018
ITI Mountain Valley
P
L f '�
Joint Permit Application
USACE — Wilmington District and NCDEQ
SAW -2018-008887
1) Survey and Staking
2) Clearing
3) Front -End Grading
4) ROW Topsoil Stripping
5) Restaking Centerline of Trench
6) Trenching (wheel ditcher)
7) Trenching (rock)
8) Padding Trench Bottom
Figure 2. Typical Pipeline Construction Sequence
9) Stringing Pipe
10) Field Sending Pipe
11) Line -Up, Initial Weld
12) Fill d Cap, Final Weld
13) T4s -Built Footage
I4) X -Ray Inspection, Weld Repair
15) Coating Field Welds
16) Inspection 6 Repair of Coating
17) Lowering Pipe into Trench
IS)As-Built Survey
19)Pad, Backfitl, Rough Erode
20) Hydrostatic Testing, Final Tie -In
Z1)Replace Topsoil, Final Clean -Up,
Full Restoration
2-10 November 2018
M Mountain Valley Joint Permit Application
T PIPELINE USACE —Wilmington District and NCDEQ
SAW -2018-008887
outside of the work area alongside the edge of the right-of-way or ATWS (outside of jurisdictional wetlands
or waters). The Project will dispose of brush and slash through burning, windrowing, or chipping, in
accordance with applicable approvals and conditions.
(c) Trenching
The Project will excavate the pipeline trench with a track -mounted backhoe or similar equipment and only
use explosives when necessary in areas where rock substrates are at depths that interfere with conventional
excavation or rock -trenching methods. On actively cultivated agricultural tracts, at wetland crossings, and
in residential areas, subsoil will be segregated and stockpiled separately from topsoil per the FERC Plan.
The Project will stockpile excavated soils along the right-of-way on the side of the trench (the "spoil" side)
away from the construction traffic and pipe assembly area (the "working" side). Where the pipeline route
is collocated adjacent to an existing infrastructure, the spoil will generally be placed on the same side of
the trench as the existing infrastructure.
(d) Pipe Stringing and Bending
New steel pipe for the pipeline will be procured and protected with an epoxy coating applied at the factory
or at a coating yard (the beveled ends will be left uncoated for welding) and shipped to strategically located
materials storage areas, contractor yards, or "pipe yards." The Project will transport the individual joints
to the right-of-way by truck and place along the excavated trench in a single, continuous line that is easily
accessible to the construction personnel on the working side of the trench (typically opposite the spoil side).
This will allow the subsequent lineup and welding operations to proceed efficiently.
The Project will deliver the pipe to the Project workspace in straight joints typically 40 to 60 feet in length.
The use of controlled internal diameter fittings, in addition to the bending of pipe, will be required to allow
the pipeline to follow natural grade changes and directional changes of the right-of-way. Prior to welding,
track -mounted hydraulic bending machines will bend selected joints in the field.
(e) Pipe Assembly and Welding
Following stringing and bending, the Project will place the joints of pipe on temporary supports adjacent
to the trench. The ends will be aligned and welded together by qualified personnel using multiple passes
for a full penetration weld. To ensure that the assembled pipe will meet or exceed the design strength
requirements, the completed welds will be visually inspected and tested for integrity using non-destructive
examination methods such as radiography (X-ray), or ultrasound, in accordance with API 1104. Welds
displaying unacceptable slag inclusions, void spaces, or other defects will be repaired or replaced.
Following welding, the Project will sandblast the previously uncoated ends of the pipe at the joints and
cover them in epoxy. The coating on the completed pipe section will be inspected, and damaged areas will
be repaired prior to lowering in accordance with applicable industry standards.
(f) Pipe Lowering
The completed section of pipe will be lifted off temporary supports and lowered into the trench by side -
boom tractors or equivalent equipment. Prior to lowering the pipe, the Project will inspect the trench to
ensure that it is free of rocks and other debris that could damage the pipe or the coating. In rocky areas, if
the bottom is not smooth, a layer of soil or sand may be placed on the bottom of the trench to protect the
pipe using a padding machine or excavator with a "shaker bucket," which separates rocks from satisfactory
2-1 November 2018
M Mountain Valley Joint Permit Application
PIPELINE USACE — Wilmington District and NCDEQ
SAW -2018-008887
padding materials. Concrete -coated pipe or aggregate filled sacks (pipe weights) will be used if necessary
for negative buoyancy in areas prone to flooding or with a high groundwater table.
(g) Padding and Backfilling
After the pipe is lowered into the trench, the Project will backfill the trench. Previously excavated materials
will be pushed back into the trench using equipment or backhoes. Where the previously excavated material
contains large rocks or other materials that could damage the pipe or coating, clean fill will be used to
protect the pipe. Due to concerns about the acidity of fly ash and its potential impacts on cathodic
protection, fly ash will not be used as backfill material. However, limestone dust or sand, which is typically
basic and will often aid in the cathodic protection of the pipeline, may be used as backfill material. The
remaining fill of the trench will be the aggregate of the excavation material removed at the time of the
excavation. If additional fill is required, it will be either flowable fill or clean fill. After the subsoil is
placed in the trench, segregated topsoil will be placed in the trench above the subsoil. Following backfilling
in agricultural land, and open land, a small crown may be left to account for any future soil settling that
might occur. In wetlands, a crown will not be left to ensure restoration of ground and surface water
hydrology to pre-existing conditions. Excess soil will be distributed evenly on the right-of-way in
accordance with landowner and agency requirements, only in upland areas and only to meet the pre -
construction surface elevations.
(h) Hydrostatic Pressure Testing and Final Tie -In
Following backfilling of the trench, the Project will hydrostatically test the pipeline to ensure that it is
capable of safely operating at the design pressure. Test segments of the pipeline will be capped and filled
with water. Test water is anticipated to be procured from municipal sources. The water in the pipe will be
pressurized and held for a minimum of 8 hours in accordance with the U.S. Department of Transportation
("USDOT") Pipeline and Hazardous Materials Safety Administration Office of Pipeline Safety
requirements identified in 49 CFR Part 192 prior to being placed in service. Any loss of pressure that
cannot be attributed to other factors, such as temperature changes, will be investigated. Leaks detected will
be repaired and the segment will be retested.
The total estimated volume of water used for hydrostatic testing is proposed to be approximately 8,500,000
gallons. Each of the construction spreads will likely be broken down into smaller test sections. The
hydrostatic test has been designed such that the water should only need to be drawn from the identified
source once. From there, it will be transferred into the next test section, which has been chosen to be smaller
than the first. By this method, no additional water will be needed within a construction spread, since the
large volume initially drawn will be transferred to increasing smaller sections that require less volume.
Test water will contact only new pipe, and no chemicals will be added to the test water unless otherwise
approved by FERC and applicable federal and/or state regulatory agencies. If a municipal water source
with chlorinated water is used for testing, addition of an approved dechlorinating agent may be required
prior to release depending on the release location. These measures will be implemented to ensure that
hydrostatic test water releases will not have the potential to cause or contribute to an exceedance of any
water quality standards, consistent with 15A NCAC 02H.0106(f). Upon completion of the test, the water
may be pumped to the next segment for testing, or the water may be released. The test water will be released
through an energy -dissipating device to a vegetated upland area. To the extent practicable, the Project will
release test water within the same watershed from which water was withdrawn, to an upland, well vegetated
2-2 November 2018
M Mountain Valley Joint Permit Application
PIPELINE USACE — Wilmington District and NCDEQ
SAW -2018-008887
area, directed through containment structures such as hay bale structures and filter bags. The release will
be monitored and the rate will be regulated using valves and energy dissipation devices to prevent erosion.
Once a segment of pipe has been successfully tested and dried, the test cap and manifold will be removed,
and the pipe will be connected to the remainder of the pipeline. No desiccant or chemical additives will be
used to dry the pipe. The Project will implement Section VII of the FERC Procedures regarding hydrostatic
testing.
(i) Cleanup and Restoration
The Project will conduct post -construction restoration activities in accordance with the measures specified
in the FERC Plan and Procedures as required. After a segment of pipe is installed, backfilled, and
successfully tested, the Project will final -grade the right-of-way, temporary ATWS, and other disturbed
areas, and construction debris will be disposed of properly. The Project will grade the surface of the right-
of-way disturbed by construction activities to match original contours and to be compatible with
surrounding drainage patterns, except at those locations where permanent changes in drainage will be
required to prevent erosion, scour, and possible exposure of the pipeline. The Project will return segregated
topsoil to its original horizons in agricultural areas and install temporary and permanent erosion and
sediment control measures where necessary, including silt fencing, diversion trenches, and vegetation. The
Project will also restore, to original or better condition, all private and public property impacted by the
Project such as fences, gates, driveways, and roads that have been disturbed by the pipeline construction.
2.4.3 Typical Wetland Pipeline Construction
The Southgate Project will cross wetlands in accordance with state and federal permit conditions and the
FERC Procedures. Pending site conditions, the Project may request alternative measures to the FERC
Procedures, and these would require approval by FERC prior to construction in these areas. In accordance
with the FERC Procedures, fuel will not be stored within 100 feet of wetlands.
Hydrological conditions along the construction corridor in areas proposed for open ditch construction will
likely dictate the use of either open ditch lay or open ditch push/pull lay methods. Selection of the most
appropriate method will depend on site-specific weather conditions, inundation, soil saturation, and soil
stability at the time of construction. The conventional open ditch lay method will be the most frequently
used technique for installation of the pipeline in wetlands. The Project will use the push/pull method, as
described in the FERC Procedures, in inundated or saturated wetland areas where groundwater conditions
preclude conventional construction. Selection of the push/pull method will be decided during construction
by the construction manager or Project representative depending on the conditions at the time of
construction. Appendix G (Wetland and Waterbody Crossing Analysis) provides a practicability
assessment for wetland and waterbody crossing methods. Practicable is defined as available and capable of
being done after taking into consideration cost, existing technology, and logistics in light of overall project
purposes. The Southgate Proj ect will continue to consult with the USACE, USFWS, NCDEQ, NCDEMLR,
and NCWRC on the appropriate crossing method for each wetland. If the Project moves forward with an
alternative crossing method that is not practicable, it is due to the request of a regulatory agency that does
not consider practicability. Descriptions of the crossing methods are provided below.
(a) Unsaturated Wetland Crossings
When crossing unsaturated wetlands (wetlands without standing water or saturated soils), construction will
be similar to the typical upland construction described in Typical Upland Pipeline Construction Procedures
2-3 November 2018
M Mountain Valley Joint Permit Application
PIPELINE USACE — Wilmington District and NCDEQ
SAW -2018-008887
above, with some exceptions. Only one traffic lane will be provided for construction equipment. The
Project will use low ground pressure equipment if normal construction equipment causes rutting or mixing
of wetland topsoil and subsoil, or install temporary equipment mats to allow passage of equipment with
minimal disturbance of the surface and vegetation. Trees will be cut to grade, but stumps will only be
removed within 15 feet of the edge of the pipe trench, or where safety concerns dictate otherwise.
The Project will segregate the topsoil from subsoil in wetlands where hydrologic conditions permit this
practice, and all excavated material will be placed in an upland area if possible. All excavated material
stockpiled in wetlands will be placed on filter cloth, mats, or other semipermeable surface to prohibit mixing
with underlying material. Excavated soil material in wetlands will be stabilized with straw bales or filter
cloth to prevent re-entry into wetlands or waterbodies and will not be stored in wetlands for more than 30
days after the pipeline has been laid in the trench without permission from the USACE-Wilmington District.
Segregated topsoil will be placed in the trench following subsoil backfilling to restore the original contour.
The Project will install and maintain erosion control measures to minimize sedimentation within the
wetland. Trench plugs will be installed at the entry and exit points of wetlands and waterbodies to prevent
the modification of subsurface hydrology.
(b) Saturated Wetland Crossings
For the purposes of this report, saturated wetlands include wetlands with standing water, but not those
wetlands that are constantly or regularly completely submerged. Topsoil segregation will not be practical
in saturated wetlands. Otherwise, construction will be similar as described for unsaturated wetlands to
provide for anticipated widths of the pipeline trench and trench spoil areas. The Project will use low ground
pressure equipment (e.g., rubber tire excavator) or timber mats to facilitate equipment movement through,
and work within, the wetland. Equipment not associated with the pipeline construction within the wetland
will be allowed to pass through the wetland when there is no other reasonable access, as provided in the
FERC Procedures. The Project will use the push/pull lay method in inundated or saturated wetland areas
where groundwater conditions preclude conventional construction. Upon completion of construction, the
right-of-way will be restored and revegetated.
2.4.4 Typical Waterbody Crossings
The Southgate Project will conduct construction across waterbodies in accordance with the FERC
Procedures and state and federal permit requirements. In accordance with the FERC Procedures, fuel will
not be stored within 100 feet of waterbodies. Multiple variables were evaluated when determining the
appropriate crossing method (e.g., waterbody width, waterbody depth, riparian impact, available
workspace, sensitive species, duration to complete the crossing, safety, and cost) that would avoid or
minimize impacts to the greatest extent practicable. The normal trenching operations will skip the
waterbody crossing, stopping on each side near the top of bank. The Project will install the waterbody
section of the pipeline by one of the methods described below. In general, pipe will be bent and fabricated
as the work progresses along the right-of-way so that the excavation of the waterbody crossing is completed
prior to pipe installation by the tie-in crew.
Construction methods at each waterbody will vary based upon the characteristics of the waterbody
encountered and applicable regulatory approvals. Conventional crossing methods where there is
discernable flow (wet crossing methods) were not considered for any waterbody crossings because of
potential impacts to aquatic resources and water quality. Dry open cut crossings combine traditional trench
2-4 November 2018
M Mountain Valley Joint Permit Application
PIPELINE USACE — Wilmington District and NCDEQ
SAW -2018-008887
construction techniques with erosion and sediment control best management practices (silt fence, compost
filter socks, turbidity curtains, pumped water filter bags) and water management techniques (damming,
pumping, etc.) to install pipeline across waterways.' The construction manager's decision whether to use a
dam and pump, flume, or cofferdam stream crossing method will be largely dependent upon the following
at the time of construction: width and depth of the stream, flow rate, flow velocity, weather forecast, and
anticipated time required to complete the crossing. As such, this decision is typically made just before the
installation begins with significant consideration given to the above factors.
Based on the data collected to date, trenchless crossing methods (i.e., conventional bore and HDD) have
been selected as the appropriate crossing alternative for a few waterbodies. More detail on trenchless
crossing methods and why these waterbodies were selected are provided below. The planned crossing
method and practicability of the methods for each stream can be found in Appendix G (Wetland and
Waterbody Crossing Analysis). Practicable is defined as available and capable of being done after taking
into consideration cost, existing technology, and logistics in light of overall project purposes. Prior to
construction, any previously identified crossing conditions (mussel relocation or time of year restrictions)
will be satisfied. The Southgate Project will continue to consult with the USACE, USFWS, NCDEQ,
NCDEMLR, and NCWRC on the appropriate crossing method for each waterbody. If the Project moves
forward with an alternative crossing method that is not practicable, it is due to the request of a regulatory
agency that does not consider practicability.
The Project will require construction activities parallel to and within 10 feet of the top of bank of several
waterbodies and also includes some crossings that are not perpendicular (between 75 and 105 degrees)
based on site-specific conditions in Table 2-4. The Project requests authorization from NDEQ to perform
these necessary construction activities.'
(a) Conventional Crossing
The Project will cross intermittent or ephemeral waterbodies with no discernable flow at the time of
construction using the conventional crossing methods, unless otherwise required. Conventional crossing
requires the least amount of time to complete pipeline installation and restore the waterbody, the least
amount of ground disturbance, and is the most cost effective. Minimizing the time in which riparian areas
remain disturbed and the extent of the disturbed area is required in the Jordan Lake buffer rules for utility,
non -electric projects that include non -perpendicular crossings of streams and other surface waters (15A
NCAC OsB.0267(9), n.4). The ability to use conventional crossing methods when there is no discernable
flow would allow the Project to meet this requirement. Materials will be available to implement a dry
crossing method should flow be anticipated due to precipitation events or other conditions.
Trench spoil will be placed on the bank above the high-water mark for use as backfill. A prefabricated
segment of pipeline will be laid horizontally across the waterbody bed past the high banks on each side of
' It is possible to cross streams with discernible flow using a wet open cut method. The primary difference with the
wet open cut method is that the trench is cut through the stream without diverting the flow around the excavation. The
wet open cut method has not been considered for the Project as a crossing method. Reference to "open cut" in this
application refer solely to the dry open cut method.
I Although NDEQ's Water Quality General Certification (No. 4133) does not expressly apply to this application for
an individual 401 Water Quality Certification, the Project is using its conditions as guidance for developing this
application.
2-5 November 2018
M Mountain Valley
Ir PIPELINE
Joint Permit Application
USACE — Wilmington District and NCDEQ
SAW -2018-008887
the waterbody before raising in elevation to the normal trench level. If necessary, the pipeline may be
weighted with concrete weights, and/or aggregate filled sacks to obtain sufficient negative buoyancy.
Compaction percentage of backfill will be equal to or above that of the adjacent undisturbed areas. Trench
plugs consisting of sandbags or foam may also be used to keep backfill from sloughing in toward the center
of the waterbody. The Project will restore waterbody banks to their original grades and remove and dispose
of excavated material not required for backfill at an upland site. The Project will follow the FERC
Procedures to limit water quality and aquatic resource impacts during and following construction. The
Project will schedule construction activities so that the pipeline trench is excavated immediately prior to
pipe laying activities.
2-6 November 2018
M Mountain Valley
Ir PIPELINE
(b) Dam and Pump Crossing Method
Joint Permit Application
USACE — Wilmington District and NCDEQ
SAW -2018-008887
The dam and pump method involves installation of temporary dams upstream and downstream of the
proposed waterbody crossing. The temporary dams will typically be constructed using materials such as
sandbags and synthetic sheeting. Following dam installation, all fishes will be removed from within the
structure prior to completely dewatering, appropriately sized pumps will be used to dewater and transport
the stream flow around the construction work area and trench. Pumps will be placed within secondary
containment. Intake screens will be installed at the pump inlets to prevent entrainment of aquatic life, and
energy dissipating devices will be installed at the pump discharge point to minimize erosion and streambed
scour. See Figure 3 below for a typical dam and pump design. Trench excavation and pipeline installation
will then commence through the dewatered portion of the waterbody. Following completion of pipeline
installation, backfill of the trench, and restoration of stream banks, the temporary dams will be removed,
and flow through the construction work area will be restored. This method is generally only appropriate
for those waterbody crossings where pumps can adequately transfer the stream flow volume around the
work area and there are no concerns about the passage of sensitive aquatic species. This crossing method
generally minimizes the duration of downstream turbidity by allowing excavation of the pipeline trench
under relatively dry conditions.
SILT €13M
("rj
—=%a F
=zL I WN -
PILE
a At
DAM (SANDBAGS, ETC.)
TRENCH
BREAKER.
(TYP.)
PIPELINE
WATER
BAR
AH
TEMP.
CCESS pE
IAD
COMPOST
TER SACK
S&T FEICE I
fT1'P.)
TW !1i
T
SFENZDAR
)
KEATER
EI UTHENT
-E]o—m r1:1;ESS 6
ROAD E;
F
ENERGY
nISSIPATER
Figure 3. Dam and Pump Crossing Method Typical
2-7 November 2018
M Mountain Valley Joint Permit Application
T PIPELINE USACE — Wilmington District and NCDEQ
SAW -2018-008887
(c) Flume Crossing Method
The flume crossing method will consist of temporarily directing the flow of water through one or more
flume pipes placed over the area to be excavated (See Figure 4). This method will allow excavation of the
pipe trench across the waterbody completely underneath the flume pipes without disruption of water flow
in the stream. Stream flow will be diverted through the flumes by constructing two bulkheads and using
sand bags or synthetic dams to direct the stream flow through the flume pipes. If necessary, dewatering
pumps may be used to pump excess water to ensure stream flow is adequately moved past the work area.
If used, dewatering pumps will be placed within secondary containment. Intake screens will be installed at
the pump inlets to prevent entrainment of aquatic life, and energy dissipating devices will be installed at
the pump discharge point to minimize erosion and streambed scour. The Project will remove bulkheads and
flume pipes following completion of pipeline installation, backfill of the trench, and restoration of
waterbody banks. This crossing method generally minimizes the duration of downstream turbidity by
allowing excavation of the pipeline trench under relatively dry conditions.'
a The difference between the dam and pump and flume crossing methods is based on how streamflow is temporarily
diverted around the work area to allow trenching and pipeline installation to occur in dry conditions. Streamflow
conditions at the time of construction generally dictate which method is preferable. However, they are not considered
true crossing "alternatives" because there is no material difference in the relative water quality impacts between the
two methods
2-8 November 2018
M Mountain Valley
Ir PIPELINE
MATER FLIM
FLUME : ! PIPE
---- L_i__--
II
l
A f
ken.—[ I
CREEK. BANK
WhTE:R L FLUME PIPE
WATER�fL�W �+y
CREEK BOTTOM
k
PROPPPIPEUNE
I — EXCAVATED TRENCH
SECTION "A -A"
Joint Permit Application
USACE —Wilmington District and NCDEQ
SAW -2018-008887
EROSION COHTRCL
AAEASLfETES 10 BE
LOCATED BELOW
APPROACH AREAS
FLOW
P4'= a x
EXCAVATED TRENCIN
A
fAEROSION
CONTR OL
EASURES TO BE
OCATED BEI -61w
PPRCA.CH AREAS
CREEK 6ANK CREEK BANK
MCR EGATE
WATER lE�EL
FPIE
PIPE
£
�' \ T � PPEPOSEEC
SECTION "B B"
Figure 4. Flume Crossing Method Typical
2-9 November 2018
M Mountain Valley
Ir PIPELINE
(d) Cofferdam Crossing Method
Joint Permit Application
USACE — Wilmington District and NCDEQ
SAW -2018-008887
The cofferdam crossing method may be used for crossing channels 10 feet or wider where the dam and
pump and flume methods will be inadequate to safely convey the volume of streamflow around the crossing
and will be designed so as not to prevent the flow of the stream. A cofferdam will be constructed within
the construction right-of-way (e.g., using cofferdam products), enclosing approximately half the streambed
in a semi -circle. The cofferdam seals tightly to the streambed to minimize water from entering the
construction area. Pumps are used to remove water from within the cofferdam and to keep water out of
excavations. This water is pumped to the upland area adjacent to the crossing and is released through
pumped water filter bags places behind silt fence or similar devices. All earth disturbance will occur in the
dry area behind the cofferdam. The pipe will be installed, and the disturbed area backfilled and stabilized.
Sediment barriers at the waterline will be installed and functional before the cofferdam is removed.
Following construction, banks will be stabilized with either riprap or vegetation. The cofferdam is then set
up from the opposite bank and extends far enough to include the tie-in point in mid -stream. The remainder
of the pipe is installed, and the tie-in weld is made. Clean up follows the same procedures described above.
See Figure 5 below for an example.
2-10 November 2018
M Mountain Valley
Joint Permit Application
USACE —Wilmington District and NCDEQ
SAW -2018-008887
EXISTING STREAM WIDTH W
1/2 W
(RAIN.
RIPRAP OR OTHER
NON— ERODI6LE
A MATERIAL A
Q
W
(p) TRE14CHLINE o
w
m
AGGREGATE OR
FLOW - SAN D � o
FILTER CLOTH
PLAN DEWATERING DEVICE, SEE STD. do SPEC_ 3.25
PERIMETERw I
rrnnrrRnt c f `
* (ID
MINA
BE 257. OF TOTAL
WIDTH (W) OF THE
STREAM.
PERIMETER
CONTROLS
TRENCHUNE
L ----
SECTION A -A
Figure 5. Cofferdam Crossing Typical
2-11 November 2018
M Mountain Valley
Ir PIPELINE
(e) Conventional Bore Crossing Method
Joint Permit Application
USACE — Wilmington District and NCDEQ
SAW -2018-008887
Some waterbodies crossed by the Southgate Project are directly associated with or adjacent to roads or
railroads. Where these roads or railroads are to be crossed using a horizontal or conventional boring
machine, the waterbody will typically be included within the length of the bore to avoid the need to excavate
a bore bit in the waterbody. Some elevated or channelized waterbodies, such as irrigation ditches, may also
be successfully bored, depending upon the groundwater level in the area. This crossing method avoids
instream disturbance and therefore is proposed for three crossings where consultation with the USFWS and
NCWRC indicated sensitive aquatic species could be present: Cascade Creek, Wolf Island Creek, and Deep
Creek. To complete a horizontal or conventional bore, two pits will be excavated, one on each side of the
feature to be bored. A boring machine will be lowered into one pit, and a horizontal hole will be bored to
a diameter equal to the diameter of the pipe (or casing, if required) at the depth of the pipeline installation.
The pipeline section and/or casing will then be pushed through the bore to the opposite pit (See Figure 4).
If additional pipeline sections are required to span the length of the bore, they will be welded to the first
section of the pipeline in the bore pit before being pushed through the bore.
Issues which must be considered during evaluation of conventional bore for potential use during crossing
of waterways and wetlands include:
• Worker safety, especially when high groundwater poses risk to stability of bore pits.
• Significantly more workspace required due to the boring machines, drill string and pipe storage and
storage of spoil from the bore pits (as much as 900 cubic yards for a 20 -foot deep pit). Topography
in stream valleys significantly reduces (or eliminates) the amount of space available.
• Groundwater must be managed due to proximity of the bore pit to the feature being bored.
• Bore pits situated on a slope, the depth of the upslope wall of the pit will increase quickly creating
the need for additional surface disturbance and associated workspace as the pit walls must be graded
(laid back) for worker safety.
• Geology may hinder or eliminate the potential use of conventional bore due to the hardness of rock
encountered, the presence of varying different materials in the bore path (i.e. large boulders in sand
and gravel) or changes in bedding thickness.
• Disturbance of riparian buffer associated with workspace and excavation of bore pits.
2-12 November 2018
K�mwn���^k���aU&~°" Joint PenndApp|�aton
' ' '''~~-''~~—^ P/��L���. USACE—VVi|mingbznDisthotandNCDEQ
S/VW'2018'008887
IOPSCIL
�2 LIKIM M45EF.RA'R
ON
PCIL
ML
_
I
BEUNCLESORNG SIZE
SOL
�
EMIPMCWT STORAGE AREA
PLAN VIEW
TURNPIKE OCRW:
�K:Uiofz MOLE
MACHINE
Figure 6. Conventional Bore Typical
2-13 November 2018
M Mountain Valley Joint Permit Application
T PIPELINE USACE — Wilmington District and NCDEQ
SAW -2018-008887
(f) Horizontal Directional Drilling Crossing Method
Horizontal directional drilling ("HDD") is a method that allows for trenchless construction across an area
by pre -drilling a hole below the depth of a conventional pipeline lay and then pulling the pipeline through
the pre -drilled borehole (See Figure 5). Currently, the Project is proposing an HDD at the Dan River and
Stony Creek Reservoir crossings. The HDD was selected at the Dan River due to crossing length, depth of
the river, fluctuation of water levels, and threatened and endangered species concerns. The Stony Creek
Reservoir HDD was selected due to the length of crossing, depth of the reservoir, and to limit impact on
the recreational uses of the waterbody. HDD Site-specific Plans are provided in Appendix H.
The HDD method has been in use since the 1970s as a means to install pipelines across rivers and at shore
approaches to mitigate for construction activities within a waterbody. Pipelines up to 60 inches in diameter
have been successfully installed using this method. The length of pipeline that can be installed by HDD
depends upon topography, soil conditions, geology, and pipe diameters and is limited by available
technology and equipment sizes.
Typically for HDD crossings, electric -grid guide wires will be hand -laid across the land surface along the
pipeline right-of-way to help guide the drill bit along the predetermined HDD route. In thickly vegetated
riparian areas, a swath approximately two to three feet wide may be hand -cleared across the land surface
for the placement of guide wires to monitor the track of the drill alignment, resulting in minimal ground
and vegetation disturbance. This may occur over the pipe or temporary access may be utilized if it does
less harm to the vegetation. Following guide wire installation, a directional drilling rig will be set up and a
small -diameter pilot hole will be drilled along a prescribed profile.
Electromagnetic sensors located on the tip of the drill bit will follow an electromagnetic field created by
the guide wires along the prescribed path. Where guide wires cannot be used, bit tip positioning sensors
will be used to guide the drill bit. In either case, once the pilot hole is completed, it will be enlarged, using
reaming tools to provide access for the pipe. The reaming tools will be attached to the drill string at the
exit point of the pilot hole and then rotated and drawn back to the drilling rig, thus progressively enlarging
the pilot hole with each pass.
During this process, drilling fluid consisting of water and bentonite clay (typically a 97:3 mixture) will be
continuously pumped into the hole to remove cuttings and maintain the integrity of the hole. Bentonite clay
is classified as a non-toxic/non-hazardous substance. Due to the unique characteristics of bentonite, the
slurry is capable of absorbing 10 times its own weight in water and swells up to 19 times its dry volume.
The combined bentonite and water mixture serves the following purposes: lubricate and cool the drill head;
seal and fill the porous space on the circumference of the drilled hole; form a cake -like substance to help
prevent the walls of the drill hole from collapsing inward; and suspend the cuttings for removal through the
drilling process. Water for HDDs is anticipated to be obtained from municipal sources. If necessary,
additional potential sources of water for HDDs may include other municipal systems, groundwater supply
wells, and/or approved surface waters. Additional additives that are approved by agencies may be needed
dependent upon viscosity readings. These additives will be determined by a mud engineer on site. The
Project will use additives for HDDs that are certified for conformance with NSF International/American
National Standards Institute Standard 60, which provides assurances that the product is safe for use in
drinking water (NSF International, 2018). These fluids will comply with state and federal requirements.
HDD fluid will be disposed of per the HDD Contingency Plan (Appendix I). Water containing mud, silt,
drilling fluid, or other materials from equipment washing or other activities, will not be allowed to enter
2-14 November 2018
M Mountain Valley Joint Permit Application
PIPELINE USACE — Wilmington District and NCDEQ
SAW -2018-008887
wetlands and waterbodies. The bentonite used in the drilling process will be either disposed of at an
approved disposal facility or recycled in an approved manner. Once the hole has been sufficiently enlarged,
a prefabricated segment of pipe will be attached behind the reaming tool on the exit side of the crossing and
pulled back through the drill hole to the drill rig, completing the crossing. The Project will dispose of all
HDD cuttings and fluids at approved disposal facilities.
The primary advantage of the HDD method is that there is minimal planned disturbance of the surface
between the entry and exit points of the HDD (limited to the temporary deployment of telemetry cable and
water pipe), provided there is reasonable access to the entry and exit points for the drilling rig and fluids
handling equipment. Where the HDD and the adjacent right-of-way are in or near parallel alignment, the
pull section will be pre -fabricated within the construction right-of-way to the greatest extent practical;
minimal ATWS will be required for this pull section. In areas where pullback space is limited due to
topographic constraints, adjacent resources, encroachment, or other utilities, the pullback string may be
broken into several segments for assembly during the pullback activity. However, the process of breaking
an HDD in multiple pullback sequences significantly increases the amount of time the bore pits and
associated disturbance exist due to the time required for welding the seams mid -pull. This in turn can also
increase the potential for failure of the HDD due to pipe failure and borehole caving. Potential failures can
be avoided or mitigated by conducting geotechnical analysis prior to construction or by making appropriate
adjustments during operation of the HDD equipment.
In addition to the potential for an inadvertent return, the minimum bend radius of the pipe must also be
considered in design. Based on the conservative industry practice of calculating a bending radius using the
formula of 100 times the pipe outer diameter for a HDD, for example the allowable bending radius for 24 -
inch steel pipe is 2,400 feet. The bend radius will affect the catenary, or the curve formed where the pipe
is hanging at the pullback point. Topography, bend radius, and entry/exit angles will all be factors in the
catenary height from the ground. A pipeline depth of at least 25 feet below waterbodies for HDD
construction will also be employed based on minimizing the potential for inadvertent returns.
At a minimum, any HDD below a waterbody would be at least 2,400 feet long and therefore require 2,400
feet of straight stringing space without introducing additional risks. Additional factors to consider when
selecting the HDD crossing method practicality include significantly higher costs, duration to complete the
crossing, increased safety concerns, and increased workspace. Because of the complexities and variables
described above, HDD is not an appropriate crossing alternative for all waterbodies.
2-15 November 2018
M Mountain Valley
Joint Permit Application
r PIPELINE
USACE —Wilmington District and NCDEQ
SAW -2018-008887
APMIOOPAiRY 375'
. .WITELT •.
D
„
}
m
F
Q ❑e i t
' j
? 3 1 17 S ____
'
�
IS'll n
n3
acc'
- gar
w�
wh.
EQUIPMENT
E . 1 1•E T.
1. SPOL CONTAIMM 8' X 20'
- IL _CNTNNER: 8' X 20'
2. SH*ER. 8' X 12'
2. SK -IU 8' X 12'
3. CESILIS: 8' X 8'
3. "E LTEF- 8' X 8'
e, VUD RIC: 8' X 25'
4. N ' 1,: 8' X 25'
5. SUPPLY 1RAPM 8' X 25'
S. S� L PALM 8' X 25'
6. ENTRY PR: 8' X 20'
6. E)1T R x 10'
7. SrORAGF 30' X 30'
7. SI - E x 30'
8. VEHICLE PAWK: 15' X 50'
& '.EH LE -4INC: 15' X 50'
9. POWER UNEF 8' X 10'
9. �Ea-TE r 1VE 8' X 20'
10. DRILL PIPE: 30' X 30'
10. NrE T .=1L& 8' X 40'
11. ME: 8'X8'
12. DPoLLMC PIC: 8' X 45'
13. SUFNEY TR.VLER: 8' X 25'
PLAN
E7(IT
EN7RY 3wr
POINT
WATER9COY
POINT
C:.FVCUT, AL J
E:_I-E1, DEPTH
= _�
F -E ...;-FILE
:IRCFILE
Figure 7. Horizontal Directional
Drill Typical.
2-16 November 2018
M Mountain Valle
Ir PIPELINE
2.4.5 Aboveground Facilities
Joint Permit Application
USACE — Wilmington District and NCDEQ
SAW -2018-008887
Construction activities and storage of construction materials and equipment will be confined within the
designated workspace areas associated with the aboveground facilities. Debris and waste generated from
construction will be disposed of as appropriate. Disturbed surface areas will be restored in a timely manner.
The facilities will be constructed in accordance with the Project construction standards and specifications
as more generally described in the paragraphs that follow.
The compression, piping and other equipment will be shipped to the sites by truck. The equipment will be
offloaded using cranes and/or front-end loaders. The equipment will then be positioned on the foundations,
leveled, grouted where necessary, and secured with anchor bolts, as required. Non -screwed piping
associated with the aboveground facilities will be welded, except where connected to flanged components.
Welders and welding procedures will be qualified in accordance with API standards. Welds in gas piping
systems will be examined using radiography, ultrasound, or other approved non-destructive examination
methods to ensure compliance with code requirements. Aboveground piping surfaces will be cleaned and
painted in accordance with the Project construction specifications. Paint inspection and cleanup will be
conducted in accordance with regulatory requirements and best engineering practices.
Components in high-pressure natural gas service will be tested prior to placing in service. Pressure testing
will follow all applicable federal and state requirements. Before being placed in service, controls and safety
equipment and systems including emergency shutdown, relief valves, gas and fire detection, and engine
over speed and vibration protection will be calibrated and tested.
2.4.6 Access Roads
New and existing roads will be used to provide access to the pipeline right-of-way during construction
and/or operation of the Southgate Project. Access road widths will be the minimum necessary to provide
access for construction equipment while maintaining safe travel conditions. Maintenance or upgrades may
be required on some of the existing roads prior to use by construction equipment. Upgrades may include
grading to prevent rutting, widening or placement of additional stabilization means including but not limited
to gravel or crushed stone on the existing surface to ensure safe travel conditions in uplands. Matting or a
similar material would be used for access roads through wetlands.
Existing culverts that are damaged or otherwise not properly functioning will be repaired or replaced with
an in-kind structure to ensure they are functional during construction activities. Permanent culverts or
temporary flumes installed as part of the Project will include measures to promote the safe passage of fish
and other aquatic organisms. The dimension, pattern, and profile of the stream above and below a culvert
will not be modified by altering the width or depth of the stream profile in connection with the construction
activity. The width, height, and gradient of a proposed culvert will be sufficient to pass the average historical
low flow and spring flow without adversely altering flow velocity. Access will be constructed such that
the length of the road minimizes impacts on waters of the United States and will be maintained as close as
possible to pre -construction contours and elevations.
2.5 RESTORATION
Following construction of the Southgate Project, the areas disturbed by construction will be restored to their
original grades, condition, and use, to the greatest extent practicable. The Project will complete restoration
in accordance with the FERC Plan and Procedures, the Project -specific E&SCP, stormwater management
plans (SWMP), applicable regulatory approvals, and landowner agreements. Restoration will be considered
2-17 November 2018
M Mountain Valley Joint Permit Application
T PIPELINE USACE —Wilmington District and NCDEQ
SAW -2018-008887
successful if the disturbed surface condition is similar to adjacent undisturbed lands, construction debris is
removed (unless requested otherwise by the landowner in upland areas), revegetation is successful, proper
drainage has been restored, and the appropriate federal and state agencies approve. The Project will reseed
areas disturbed by construction in accordance with and proposed seed mixes that will be developed for the
Project and provided in an additional submittal.
2.5.1 Pipeline
Upon completion of the pipeline installation, the surface of the right-of-way disturbed during construction
activities will be graded to match original contours and to be compatible with surrounding drainage patterns,
except at those locations where permanent changes in drainage will be required to prevent erosion, scour,
and possible exposure of the pipeline. Segregated topsoil will be replaced, and soils that have been
compacted by construction equipment traffic will be de -compacted. Permanent stormwater management
measures will be installed in accordance with the Project's SWMP. Temporary erosion control measures
may be left in place, where appropriate, until sufficient vegetative cover is re-established to prevent
significant erosion or sedimentation.
2.5.1.1 Uplands
In most upland locations, excluding actively cultivated cropland, herbaceous vegetative cover will be re-
established by spreading a grass seed and hydro or straw -mulch mixture over the disturbed surface. The
type of seed will be selected to match the mix required by applicable regulatory agencies, or as otherwise
requested by the landowner. Depending upon the time of year, a temporary seed mix may be broadcast or
drilled until a more permanent cover can be established. Steep slopes (e.g., stream banks) may require
additional stabilization using erosion control fabric, revetments, or sod. Vegetation success in these areas
will be monitored by the Project, and reseeding, fertilizing, hydroseed (where allowed), or other
supplemental revegetation measures may be implemented until the density and cover of non -nuisance
vegetation is similar in density and cover to adjacent undisturbed lands.
2.5.1.2 Wetlands
Original surface hydrology will be re-established in wetlands by backfilling the pipe trench and grading the
surface to pre -construction contours with equipment operating from timber mats or equivalent or using low -
ground -pressure tracked vehicles working in the spoil pile depending upon degree of soil saturation and the
bearing capacity. Segregated topsoil will be replaced in unsaturated wetlands. Once the trench is backfilled
and ground surface restored to its natural grade, the soils will be mechanically loosened to a depth of 12
inches, if necessary, and allowed to naturally revegetate. In emergent wetlands, the herbaceous vegetation
is expected to regenerate quickly (typically within one growing season). The Project will conduct
restoration and monitoring of wetland crossings in accordance with the FERC Procedures to ensure
successful wetland revegetation. Wetland revegetation will be considered successful when the cover of
herbaceous and/or woody species is at least 80 percent of the type, density, and distribution of the vegetation
in adjacent wetland areas that were not disturbed by construction. Revegetation efforts will continue until
wetland revegetation is successful based on the FERC Procedures and other applicable regulatory
approvals. If revegetation is unsuccessful, the wetlands will be seeded with appropriate native wetland
species in consultation with USACE and NCDEQ.
2-18 November 2018
M Mountain Valley Joint Permit Application
PIPELINE USACE — Wilmington District and NCDEQ
SAW -2018-008887
2.5.1.3 Waterbodies
Cleanup and restoration activities commence as soon as practicable following completion of the waterbody
crossing. Waterbody substrate will be segregated from other soils and will be used to backfill the trench
once the pipeline is laid. Sediments will be placed in uplands to the extent practicable, and where not
practicable will be placed on filter cloth or other semi -impervious surface. Areas disturbed will be restored
to pre -construction or better conditions. Original streambed and bank contours will be re-established for
surface water and groundwater flow, and mulch, jute thatching, or bonded fiber blankets will be installed
on the stream banks, which are preferential to plastic erosion control blankets because they reduce wildlife
entrapment and are biodegradable. Where the flume technique is used, stream banks will be stabilized
before removing the flume pipes and returning flow to the waterbody channel. Additionally, the Project
will conduct a scour analysis on perennial streams 10 -feet wide or greater in width crossed by the pipeline
to ensure that the placement depth is sufficient to prevent erosion by expected high flows. The analysis
will be completed in early 2019 and results will be provided to USACE and NCDEQ for review.
Seeding of disturbed stream approaches will be completed in accordance with the FERC Procedures after
final grading, weather and soil conditions permitting. Other Federal and State permit seeding requirements
will be considered where applicable. Where necessary, slope breakers will be installed adjacent to stream
banks to minimize the potential for erosion. Sediment barriers, such as silt fence and/or straw bales will be
maintained across the right-of-way until permanent vegetation is established. Temporary equipment
bridges will be removed following construction.
2.5.2 Access Roads
Previously existing access roads that were modified and used during construction will be returned to
original or better condition upon completion of the pipeline facilities installation. Temporary access roads
constructed specifically for the Project installation will be removed, the surface graded to original contours,
and the land restored to its original use unless otherwise requested by the landowner. Temporary erosion
control measures will be removed upon final stabilization and approval from applicable regulatory agencies
and installation of permanent erosion control measures, if necessary.
2.5.3 Aboveground Facilities
Aboveground facilities will be fenced. The areas inside the fence at the aboveground facilities will be
permanently converted to industrial use. Most areas in and around the buildings, meters, and associated
piping and equipment will be covered with an approved stabilization method (typically crushed rock or
equivalent) to minimize the amount of maintenance required. Roads and parking areas may be crushed
rock, concrete, or asphalt. Other ground surfaces will be seeded with a grass that is compatible with the
climate and can be easily maintained. Temporary workspace areas outside the fence will be restored as
described above for the pipeline right-of-way.
2.5.4 Contractor Yards
Upon completion of construction, all temporary facilities (e.g., trailers, sheds, latrines, pipe racks, fencing,
and gates) will be removed from the contractor yards. Unless otherwise requested by the landowner, each
site will be graded to original contours and the land restored to its original use, to the greatest extent
possible. The site will be revegetated, permanent erosion control measures will be installed, and temporary
erosion control measures will be removed.
2-19 November 2018
M Mountain Valley Joint Permit Application
PIPELINE USACE — Wilmington District and NCDEQ
SAW -2018-008887
2.6 QUALITY ASSURANCE MEASURES
To ensure that construction of the facilities will comply with measures identified in the FERC Certificate
and applicable regulatory permits and clearances, the Project will include implementation details in its
construction drawings and specifications. Copies of permit requirements, known conditions and related
drawings will be added to the Construction Bid Package.
Consistent with the FERC Plan and Procedures and the Project -specific E&SCP, environmental training
will be given to the Project personnel and to contractor personnel whose activities may impact the
environment during pipeline and aboveground facility construction. The level of training will be
commensurate with the type of duties of the personnel. All construction personnel from the Chief Inspector,
EI, craft inspectors, and contractor job superintendent to clearing crews, welders, equipment operators, and
laborers will be given the appropriate level of environmental training. The training will be given prior to
the start of construction and throughout the construction process, as needed. The training program will
cover job -specific permit conditions (NWP 12, 401 Water Quality Certification, NPDES, etc.),
contaminated sediment and groundwater management, health and safety, company policies, cultural
resource procedures, threatened and endangered species restrictions, the SPCC Plan (Appendix F), HDD
Contingency Plan (Appendix H), and any other pertinent information related to the Project. The Invasive
Species Plan will be provided at a later date. In addition to the EIs, all other construction personnel will
play an important role in maintaining strict compliance with all permit conditions to protect the environment
during construction.
To ensure quality assurance and compliance with mitigation measures, a Chief Inspector will represent the
Project assisted by another Inspector, and one or more craft inspectors. In addition, there will be at least
one EI who will report to the Chief Inspector, who in turn reports to the Construction Manager. The EI's
duties are consistent with those contained in Section II.B (Responsibilities of the Environmental Inspector)
of the FERC Plan; the EI will be:
• Responsible for monitoring and documenting compliance with all mitigation measures required by
the FERC's Order and any other grants, permits, certificates, or other authorizing documents;
• Responsible for evaluating the construction contractor's implementation of the environmental
mitigation measures required in the contract or any other authorizing document;
• Empowered to order correction of acts that violate the environmental conditions of the FERC's
Order, or any other authorizing document (e.g., USACE Section 404 permit), including stop work
authority;
• A full-time position separate from all other activity inspectors; and
• Responsible for maintaining status reports and training records.
Copies of the Construction Drawing Package will be distributed to inspectors and to contractors'
supervisory personnel. If a contractor's performance is unsatisfactory, the terms of the contract will allow
for work stoppage and will require the contractor to begin remedial work.
The Project's engineering and construction departments are responsible for designing and constructing
certificated facilities in compliance with regulatory and contractual requirements and agreements. If
technical or management assistance is required, the responsible Construction Manager and/or Chief
Inspector will request assistance from the appropriate company department. The operations department
2-20 November 2018
M Mountain Valley Joint Permit Application
PIPELINE USACE — Wilmington District and NCDEQ
SAW -2018-008887
will be responsible for long-term Project maintenance and regulatory compliance once the Project is in-
service.
2.7 SCHEDULE
The order in which each facility will be constructed may vary, depending upon numerous factors, including
the receipt of necessary authorizations, the capabilities of each contractor, available work force, and
optimized logistics. The Southgate Project anticipates clearing to start in the first quarter of 2020 contingent
upon receipt of necessary approvals, and pipeline construction will begin in early 2020 to achieve a target
in-service date of December 2020. A preliminary construction schedule is provided below in Table 2-5.
Table 2-5
Construction Schedule for Major Components of the MVP Southgate Project
Component
Commence
Activity
Complete
Activity
Clearing
Q1 2020
Q1 2020
Pipeline Construction
Q1 2020
Q4 2020
Compressor Stations
Q1 2020
Q4 2020
Restoration
Q2 2020
Q4 2022
Hydrostatic Testing
Q4 2020
December 2020
Anticipated full in-service date of December 2020
2.8 OPERATION AND MAINTENANCE
The Southgate Project will be operated and maintained in compliance with Federal regulations provided at
49 CFR Part 192, FERC regulations at 18 CFR § 380.15, and maintenance provisions of the FERC Plan
and Procedures and its Project -specific E&SCP. Operational activity on the pipeline will be limited
primarily to vegetation management within the permanent easement and inspection, repair, and cleaning of
the pipeline. Periodic aerial and ground inspections by the Project will identify:
• soil erosion that may expose the pipe;
• dead vegetation that may indicate a leak in the line;
• conditions of the vegetation cover and erosion control measures;
• unauthorized encroachment on the right-of-way, such as buildings and other substantial structures;
and
• other conditions that could present a safety hazard or require preventive maintenance or repairs.
Following construction, certain areas along the pipeline alignment (and at aboveground facilities) will have
an associated permanent right-of-way or operational area. For pipeline facilities, the Project will maintain
a typical permanent right-of-way of 50 feet in width. Vegetation on the permanent right-of-way will be
maintained by mowing, cutting, and trimming. Herbicide treatment will only be used to control invasive
species, as necessary, and will not be allowed within 100 feet of a waterbody or wetland unless specifically
allowed by the appropriate federal or state agency.
2-21 November 2018
M Mountain Valley Joint Permit Application
PIPELINE USACE — Wilmington District and NCDEQ
SAW -2018-008887
In uplands, routine vegetation mowing or clearing over the full width of the permanent right-of-way will
occur no more than once every three years. However, to facilitate periodic corrosion/leak surveys, the
Project may clear a corridor not exceeding 10 feet in width centered on the pipeline at a frequency necessary
to maintain the 10 -foot corridor in an herbaceous state. See Appendix C for a typical construction detail of
the maintenance corridor.
In wetlands, routine vegetation mowing or clearing over the full width of the permanent right-of-way will
not occur. However, to facilitate periodic corrosion/leak surveys, the Project may clear a corridor centered
on the pipeline up to 10 feet in width at a frequency necessary to maintain the 10 -foot corridor in an
herbaceous state. In addition, trees within 15 feet of the pipeline may be selectively cut and removed from
the permanent right-of-way to ensure that root systems do not affect the exterior coating of the pipeline.
2.9 FUTURE PLANS AND ABANDONMENT
The Project currently has no plans for either future expansion or abandonment of the facilities. Should the
Project propose any future expansion or abandonment of Project facilities, the Project will seek the
appropriate authorizations from FERC and other federal and state agencies as applicable.
2.10 ROUTE ALTERNATIVES ANALYSIS
Due to the linear nature of this Project, there are no practical alternatives that fulfill the project purpose,
while avoiding all impacts to surface waters and wetlands. Impacts have been avoided and minimized to
the extent practicable through the routing alternatives analysis discussed in this section, the right-of-way
area limitations discussed in Section 2.3.1, and the impact avoidance and minimization measures outlined
in Section 4.4.
During development of the Southgate Project, an extensive review of potential routes was evaluated to
identify viable corridors for placement of the pipeline. Potentially viable corridors were reviewed for a
variety of potential constraints including environmental impacts, effects on landowners, and
constructability and further refined to determine the most feasible route within the least impactful corridor.
One of the Project's primary objectives with respect to pipeline routing was to avoid or minimize, to the
extent possible, crossings of major population centers and significant environmental resources, including
waterbodies and wetlands. The Project also attempted to route its pipeline adjacent to existing rights-of-
way, where feasible, to minimize new land impacts. The Project used field reconnaissance, aerial
photography, topographic maps from the U.S. Geological Survey, and National Wetland Inventory maps
during the route identification and evaluation processes. Appendix J is the FERC Environmental Document
that was filed November 7, 2018. Resource Report 10 of the FERC Environmental Report provides an in-
depth discussion of the Project's alternatives analysis. Appendix G provides an analysis of wetland and
waterbody crossing methods.
The Project evaluated four major route alternatives (including the preferred route) as part of the planning
and design process (See Appendix J). The evaluation was based on environmental and land use impacts, as
well as permanent easement acquisitions and overall Project costs. The primary objective of the evaluation
was to develop the most direct route that could connect customers to the available supply system while
avoiding or minimizing potential adverse environmental impacts and engineering constraints to the greatest
extent practicable. The Project evaluated pipeline routing options based on potential adverse environmental
impacts, existing land usage, constructability, safety, and feasibility considerations.
The selection of the major route alternatives involves several steps.
2-22 November 2018
M Mountain Valley
Ir PIPELINE
Joint Permit Application
USACE — Wilmington District and NCDEQ
SAW -2018-008887
• Development of routing criteria;
• Identification of potential routing alternatives;
• Collection of data relative to each alternative;
• Evaluation of potential environmental and land use impacts;
• Evaluation of routing alternatives against routing criteria; and
• Determination of the most cost-effective technical solution
The route best meeting the selection criteria was selected as the preferred route. The preferred route was
selected primarily for these reasons:
• Shortest length and, therefore, least area of land disturbance during construction and operation;
• Greatest percent of route collocated with existing rights -of -ways;
• Least mileage of forested land crossing; and
• Least area of forested land construction or operation impacts.
Minor Route Variations
The Project evaluated a 300 to 400 -foot wide "study area" around the preferred route. The purpose of the
study was to allow for minor route deviations within the corridor to avoid or minimize impacts to sensitive
resources, including wetlands and waterbodies. The Project has currently identified 280 route variations
during preliminary routing, stakeholder outreach efforts, and landowner and/or and agency requested route
deviations. Of these, the Project has incorporated 191 of these into the proposed current preferred route.
Those that are relevant to avoiding or minimizing impacts to wetlands or waterbodies are summarized in
Table 2-6.
Table 2-6
Minor Route Variations to Avoid or Minimize Impacts to Wetlands or Waterways in North Carolina
Reroute Number
Begin
End
Length
Variation Description
Justification
Milepost
Milepost
(miles)
MVP -RA -153-1309
28.3
28.3
0
ATWS adjustment
Wetland avoidance
Avoidance of multiple
MVP -RR -193-1030
34.95
35.35
0.4
Centerline adjustment
stream crossings and
side -slope construction
MVP -RR -193-1501
39.2
39.6
0.4
Centerline adjustment
Avoid wetland / pond
complex
MVP -RA -163-1116
40
40.2
0.2
Centerline adjustment
Avoidance of waterbody
MVP -RA -186-1423
57.35
57.75
0.4
Centerline adjustment
Avoidance of pond
MVP -RA -143-1534
63.1
63.5
0.4
Centerline adjustment
Move point of inflection
out of pond
MVP -RR -186-1407
67.9
68.2
0.3
Centerline adjustment
Avoidance of pond
2-23 November 2018
M Mountain Valle
1W PIPELINE
3.0 EXISTING SITE CONDITIONS
Joint Permit Application
USACE — Wilmington District and NCDEQ
SAW -2018-008887
3.1 WETLAND AND WATERBODY DELINEATION
The Southgate Project performed a wetland and waterway delineation for the Project environmental survey
area that consisted of a typical 300 to 400 -foot -wide corridor along the 47 miles of proposed pipeline. The
survey area included limits of additional temporary workspaces, above ground facilities, construction yards,
staging areas, and access roads. A typical 50 -foot wide corridor centered over the proposed access road was
surveyed for all access roads. Overall, the survey area for the North Carolina portion of the Project
encompasses approximately 2,135 acres.
The wetland and waterbody delineation was conducted using a combination of the desktop and field
surveys. The field surveys covered approximately 78 percent of the North Carolina Project survey area,
where survey access was available. The remaining area where survey access was not available was
evaluated using existing data resources such as National Wetland Inventory ("NWI") maps, National
Hydrography Dataset ("NHD") maps, published US Department of Agriculture- Natural Resources
Conservation Service "USDA-NRCS" Soil Surveys for Rockingham and Alamance Counties, North
Carolina, and site specific aerial photography and Lidar data flown for the Project area in 2018. Project
scientists made observations of the estimated resources from adjacent tracts where survey access was
available, to the extent possible. Wetland and waterbody limits estimated using desktop analysis will be
field delineated when survey access is available. Wetlands and waterbody boundaries were identified based
on the interpretation of this data and typically represent an over -estimation of the extent of jurisdictional
resources. Details of the survey methodology and results, including data forms, wetland and waterway
delineation maps, and photographs, are provided in Appendix K (MVP Southgate Project — North Carolina
Wetland and Waterbody Delineation Report). The areas delineated via desktop methods will be surveyed
in the field when access becomes available.
3.1.1 Wetlands
One hundred thirty-one wetlands were delineated within the North Carolina Project survey area. These
wetlands are identified in Appendix K (Wetland and Waterbody Delineation report — Appendix A-1) by
resource ID, milepost, and type. None of the delineated wetlands are isolated. The wetlands in the survey
area are associated with stream and river floodplains or their headwaters and include a combination of
palustrine forested ("PFO"), palustrine scrub -shrub ("PSS"), and palustrine emergent wetlands ("PEM").
Table 3-1 summarizes the wetlands delineated (in the field and by estimated) in the North Carolina Project
survey area by watershed and Cowardin cover type.
3.1.2 Waterbodies
Within the North Carolina Project survey area, 280 streams and waterbodies were delineated, including 22
ponds and 258 streams. Of the identified streams, 66 were determined to be ephemeral in nature, 101 are
intermittent, and 91 are perennial. None of the delineated resources are isolated waterbodies and none are
classified as Section 10 waterways by the USACE-Wilmington District. Appendix A-2 of the Wetland and
Waterbody Delineation Report (Appendix K) provides a summary of each delineated waterbody, including
resource ID, milepost, stream name, flow type, watershed, and area/linear feet within the North Carolina
Project survey area. Table 3-2 (below) summarizes the waterbodies delineated in the Project survey area.
3-1 November 2018
M Mountain Valley
Joint Permit Application
USACE - Wilmington District and NCDEQ
SAW -2018-008887
Table 3-1
Summary of Wetlands Delineated and Desktop Reviewed in the North Carolina Project Survey Area by Sub -watershed
Milepost (MP) / Watershed
Cowardin
Classification a/
-
Number of
Resources b/
-
Acres of Wetland Type
Delineated within
Survey Area
Approximated Acres
of Wetland within
Survey Area c/
MP: 26.1 - 26.23
HUC 8: Upper Dan (03010103)
HUC 10: Cascade Creek -Dan River (0301010309)
HUC 12: Trotters Creek -Dan River (030101030903)
PEM
1
0.01
0
PSS
0
0
0
PFO
1
0.09
0
Subtotal
2
0.10
0
MP: 26.23 - 28.13
HUC 8: Upper Dan (03010103)
HUC 10: Cascade Creek -Dan River (0301010309)
HUC 12: Cascade Creek (030101030902)
PEM
3
1.72
0.31
PSS
0
0
0
PFO
2
0.11
0
Subtotal
5
1.83
0.31
MP: 28.13 - 36.3
HUC 8: Upper Dan (03010103)
HUC 10: Cascade Creek -Dan River (0301010309)
HUC 12: Town Creek -Dan River (030101030901)
PEM
24
3.60
0.38
PSS
2
1.17
0.01
PFO
10
14.36
0.26
Subtotal
36
19.13
0.65
MP: 36.3 - 39.7
HUC 8: Upper Dan (03010103)
HUC 10: Cascade Creek -Dan River (0301010309)
HUC 12: Upper Wolf Island Creek (030101030904)
PEM
5
2.59
0
PSS
1
0.16
0
PFO
5
1.15
0
Subtotal
11
3.91
0
MP: 39.7 - 42.2
HUC 8: Lower Dan (03010104)
HUC 10: Hogans Creek -Dan River (0301010401)
HUC 12: Lick Fork (030101040103)
PEM
4
0.35
0
PSS
0
0
0
PFO
4
1.46
0.19
Subtotal
8
1.81
0.19
3-2 November 2018
M Mountain Valley
Joint Permit Application
USACE - Wilmington District and NCDEQ
SAW -2018-008887
Table 3-1
Summary of Wetlands Delineated and Desktop Reviewed in the North Carolina Project Survey Area by Sub -watershed
Milepost (MP) / Watershed
Cowardin
Classification a/
-
Number of
Resources b/
-
Acres of Wetland Type
Delineated within
Survey Area
Approximated Acres
of Wetland within
Survey Area c/
PEM
4
0.65
0.03
MP: 42.2 - 48.36
PSS
1
0.04
0
HUC 8: Lower Dan (03010104)
HUC 10: Hogans Creek -Dan River (0301010401)
PFO
2
0.33
0
HUC 12: Upper Hogans Creek (030101040104)
Subtotal
7
1.02
0.03
PEM
3
0.26
0
MP: 48.36 - 49.48
PSS
1
0.53
0
HUC 8: Haw River (03030002)
HUC 10: Headwaters Haw River (0303000202)
PFO
1
0.03
0
HUC 12: Giles Creek -Haw River (030300020206)
Subtotal
5
0.82
0
PEM
7
1.52
0.14
MP: 49.48 - 55.75 & 55.97 - 56.12
PSS
4
0.38
0
HUC 8: Haw River (03030002)
HUC 10: Headwaters Haw River (0303000202)
PFO
6
1.44
0.01
HUC 12: Town of Altamahaw-Haw River (030300020207
Subtotal
17
3.34
0.15
MP: 55.75 - 55.97; 61.12 - 61.49; 62.82 - 65.35
PEM
1
0.02
0
PSS
0
0
0
HUC 8: Haw River (03030002)
HUC 10: Back Creek -Haw River (0303000204)
PFO
7
2.08
0.27
HUC 12: Stony Creek -Stony Creek Reservoir
Subtotal
8
2.10
0.27
(030300020403)
MP: 56.12 - 61.12; 61.49 - 62.82
PEM
12
3.29
0.27
HUC 8: Haw River (03030002)
PSS
2
0.19
0
HUC 10: Back Creek -Haw River (0303000204)
HUC 12: Travis Creek -Haw River (030300020404)
PFO
13
6.56
0
Subtotal
27
10.03
0.27
3-3 November 2018
M Mountain Valley
Joint Permit Application
USACE — Wilmington District and NCDEQ
SAW -2018-008887
Table 3-1
Summary of Wetlands Delineated and Desktop Reviewed in the North Carolina Project Survey Area by Sub -watershed
Milepost (MP) / Watershed
Cowardin
Classification a/
—
Number of
Resources b/
—
Acres of Wetland Type
Delineated within
Survey Area
Approximated Acres
of Wetland within
Survey Area c/
PEM
3
0.33
0
MP: 65.35 - 72.98
PSS
0
0.00
0
HUC 8: Haw River (03030002)
HUC 10: Back Creek -Haw River (0303000204)
PFO
2
0.12
0.01
HUC 12: Boyds Creek -Haw River (030300020408)
Subtotal
5
0.45
0.01
PEM
0
0
0
MP: 72.98 to MP 73.11 (end)
HUC 8: Haw River (03030002)
PSS
0
0
0
HUC 10: Back Creek -Haw River (0303000204)
PFO
0
0
0
HUC 12: Lower Back Creek (030300020407)
Subtotal
0
0
0
PEM
67
14.34
1.13
PSS
11
2.47
0.01
Total
PFO
53
27.73
0.74
Total
131
44.54
1.88
a/ Classification of Wetlands and Deepwater Habitats of the United States (Cowardin, 1979).
b/ Based on field surveys conducted by the Southgate Project from May 2018 to September 2018.
c/ Based on desktop reviews conducted by the Southgate Project during April -May 2018.
PEM=Palustrine Emergent, PSS= Palustrine Scrub -Shrub, PFO=Palustrine Forested
3-4 November 2018
M Mountain Valley
Joint Permit Application
USACE — Wilmington District and NCDEQ
SAW -2018-008887
Table 3-2
Summary of Waterbodies Delineated and Desktop Reviewed in the North Carolina Project Survey Area by Sub -watershed
Milepost (MP) / Watershed
Flow Type
Number of
Resources
Delineated a/
—
Linear Feet in
Survey Area
Delineated
Acres of
Waterbody
Delineated with
Survey Area
Number of
Resources Desktop
Reviewed within
Survey Area c/
Ephemeral
0
0
0
0
MP: 26.1 - 26.23
HUC 8: Upper Dan (03010103)
Intermittent
0
0
0
0
HUC 10: Cascade Creek -Dan River
(0301010309)
Perennial
0
0
0
0
HUC 12: Trotters Creek -Dan River
Pond
0
0
0
0
Subtotal
0
0
0
0
(030101030903)
Ephemeral
0
0
0
0
Intermittent
2
359
0
1
MP: 26.23 - 28.13
HUC 8: Upper Dan (03010103)
HUC 10: Cascade Creek -Dan River
Perennial
1
468
0
2
(0301010309)
HUC 12: Cascade Creek (030101030902)
Pond
1
0
0.13
0
Subtotal
4
827
0.13
3
Ephemeral
16
3,155
0
1
MP: 28.13 - 36.3
Intermittent
23
12,059
0
2
HUC 8: Upper Dan (03010103)
Perennial
21
10,060
0
5
HUC 10: Cascade Creek -Dan River
(0301010309)
Pond
1
0
0.08
0
HUC 12: Town Creek -Dan River
(030101030901)
Subtotal
60
25,274
0.08
8
3-5 November 2018
M Mountain Valley
Joint Permit Application
USACE — Wilmington District and NCDEQ
SAW -2018-008887
Table 3-2
Summary of Waterbodies Delineated and Desktop Reviewed in the North Carolina Project Survey Area by Sub -watershed
Milepost (MP) / Watershed
Flow Type
Number of
Resources
Delineated a/
—
Linear Feet in
Survey Area
Delineated
Acres of
Waterbody
Delineated with
Survey Area
Number of
Resources Desktop
Reviewed within
Survey Area c/
Ephemeral
5
756
0
0
MP: 36.3 - 39.7
HUC 8: Upper Dan (03010103)
Intermittent
3
943
0
0
Perennial
10
7,959
0
3
HUC 10: Cascade Creek -Dan River
(0301010309) HUC 12: Upper Wolf Island
Creek (030101030904)
Pond
2
0
0.28
0
Subtotal
18
9,658
0.28
3
Ephemeral
3
155
0
0
MP: 39.7 - 42.2
HUC 8: Lower Dan (03010104)
Intermittent
5
1,494
0
1
Perennial
7
3,240
0
0
HUC 10: Hogans Creek -Dan River
(0301010401)
HUC 12: Lick Fork (030101040103)
Pond
0
0
0
0
Subtotal
15
4,889
0
1
MP: 42.2 - 48.36
Ephemeral
11
2,437
0
0
Intermittent
8
1,194
0
1
HUC 8: Lower Dan (03010104)
HUC 10: Hogans Creek -Dan River
(0301010401)
Perennial
17
7,695
0
2
Pond
2
0
0.30
0
HUC 12: Upper Hogans Creek
(030101040104)
Subtotal
36
11,326
0.30
3
Ephemeral
0
0
0
0
MP: 48.36 - 49.48
HUC 8: Haw River (03030002)
Intermittent
2
82
0
0
Perennial
2
698
0
0
HUC 10: Headwaters Haw River
(0303000202)
HUC 12: Giles Creek -Haw River
Pond
0
0
0
0
Subtotal
4
780
0
0
(030300020206)
3-6 November 2018
M Mountain Valley
Joint Permit Application
USACE — Wilmington District and NCDEQ
SAW -2018-008887
Table 3-2
Summary of Waterbodies Delineated and Desktop Reviewed in the North Carolina Project Survey Area by Sub -watershed
Milepost (MP) / Watershed
Flow Type
Number of
Resources
Delineated a/
—
Linear Feet in
Survey Area
Delineated
Acres of
Waterbody
Delineated with
Survey Area
Number of
Resources Desktop
Reviewed within
Survey Area c/
Ephemeral
6
998
0
0
MP: 49.48 - 55.75 & 55.97 - 56.12
HUC 8: Haw River (03030002)
Intermittent
13
3,291
0
1
Perennial
13
6,042
0
2
HUC 10: Headwaters Haw River
(0303000202)
HUC 12: Town of Altamahaw-Haw River
Pond
4
0
1.68
0
Subtotal
32
10,331
1.68
3
(030300020207)
MP: 55.75 - 55.97; 61.12 - 61.49; 62.82 -
Ephemeral
5
341
0
0
65.35
HUC 8: Haw River (03030002)
Intermittent
8
1,230
0
2
Perennial
3
1,602
0
2
HUC 10: Back Creek -Haw River
(0303000204)
HUC 12: Stony Creek -Stony Creek
Pond
1
0
0.20
0
Subtotal
16
3,243
0.20
4
Reservoir (030300020403)
MP: 56.12 - 61.12; 61.49 - 62.82
Ephemeral
8
1,071
0
0
Intermittent
20
5,266
0
1
HUC 8: Haw River (03030002)
HUC 10: Back Creek -Haw River
(0303000204)
Perennial
7
4,555
0
0
Pond
6
0
1.41
0
HUC 12: Travis Creek -Haw River
(030300020404)
Subtotal
35
10,892
1.41
1
MP: 65.35 - 72.98
Ephemeral
12
2,285
0
0
Intermittent
17
5,462
0
3
HUC 8: Haw River (03030002)
HUC 10: Back Creek -Haw River
(0303000204)
Perennial
10
5,078
0
4
Pond
5
0
0.53
0
HUC 12: Boyds Creek -Haw River
(030300020408)
Subtotal
39
12,825
0.53
7
3-7 November 2018
M Mountain Valley
Joint Permit Application
USACE — Wilmington District and NCDEQ
SAW -2018-008887
Table 3-2
Summary of Waterbodies Delineated and Desktop Reviewed in the North Carolina Project Survey Area by Sub -watershed
Milepost (MP) / Watershed
Flow Type
Number of
Resources
Delineated a/
—
Linear Feet in
Survey Area
Delineated
Acres of
Waterbody
Delineated with
Survey Area
Number of
Resources Desktop
Reviewed within
Survey Area c/
MP: 72.98 to MP 73.11 (end)
Ephemeral
0
0
0
0
Intermittent
0
0
0
0
HUC 8: Haw River (03030002)
HUC 10: Back Creek -Haw River
(0303000204)
Perennial
0
0
0
0
Pond
0
0
0
0
HUC 12: Lower Back Creek
(030300020407)
Subtotal
0
0
0
0
Ephemeral
66
11,197
0
1
Intermittent
101
31,374
0
12
Perennial
91
47,397
0
20
Total
Pond
22
0
4.61
0
Total
280
89,968
4.61
33
a/ Based on field surveys conducted by the Southgate Project from May 2018 to September 2018.
b/ Classification of Wetlands and Deepwater Habitats of the United States (Cowardin, 1979).
c/ Based on desktop reviews conducted by the Southgate Project during April -May 2018.
PEM=Palustrine Emergent, PSS= Palustrine Scrub -Shrub, PFO=Palustrine Forested
3-8 November 2018
M Mountain Valley Joint Permit Application
PIPELINE USACE — Wilmington District and NCDEQ
SAW -2018-008887
3.1.3 Preliminary Jurisdictional Determination
An application for a preliminary jurisdictional determination ("PJD") was submitted to the USACE-
Wilmington District in August of 2018. The Southgate Project has participated in several field review days
of the delineated resources with USACE and North Carolina Division of Water Resources ("NCDWR')
personnel on September 5', 1 lt' and 251}i, 2018. No additional field reviews with USACE and NCDWR
are anticipated at the time of this Application.
3-9 November 2018
M Mountain Valley
Ir PIPELINE
Joint Permit Application
USACE — Wilmington District and NCDEQ
SAW -2018-008887
4.0 WETLAND AND WATERBODY IMPACT ASSESSMENT
The majority of the wetland and waterbody impacts associated with construction and operation of the
Southgate Project will be temporary. The only permanent impact would be conversion of forested wetland
to non -forested wetland in the permanent maintenance easement and 0.025 acre of fill in non -forested
wetland for a permanent access road at MP 41.8. Temporary impacts in wetlands may include temporary
loss of vegetation; wildlife habitat disruption; soil disturbance associated with grading, trenching, and
stump removal; soil compaction; sedimentation and increased turbidity; and hydrological profile changes.
Impacts to forested wetlands may include conversion to emergent and/or scrub/shrub wetland types
resulting from tree removal within the construction and operational right-of-way.
A summary of the proposed impacts to wetlands and waters is provided in Tables 4-1 and 4-2 respectively,
by resource type and impact type. Details of the proposed impacts for each individual wetland and
waterbody crossing are provided in Appendix L-1 and L-2, respectively, and depicted on the Impact
Drawings in Appendix M. The following sections outline the potential impacts and measures that the
Project will implement to avoid and minimize impacts to the resources to the maximum extent practicable.
4-1 November 2018
M Mountain Valley
Joint Permit Application
USACE - Wilmington District and NCDEQ
SAW -2018-008887
Table 4-1
Summary of Proposed Wetland Impacts in North Carolina
Milepost (MP)/Watershed
Wetland
Type a/
Number of
Affected
Resources
Pipeline
Crossing
Length
(feet) b/
Construction
Workspace
Impacts
(acres) c/
Permanent
PFO
Conversion to
PEM/PSS
(acres) d/
Permanent Fill
for Access
Road (acre) e/
MP: 26.1-39.7
HUC 8: Upper Dan (03010103)
HUC 10: Cascade Creek -Dan River (0301010309)
PEM
55
754
2.136
0
0
PSS
4
154
0.301
0
0
PFO
19
1732
3.222
1.159
0
Subtotal
78
2640
5.66
1.159
0
MP: 39.7 - 48.36
HUC 8: Lower Dan (03010104)
HUC 10: Hogans Creek -Dan River (0301010401)
PEM
4
0
0.055
0
0.025
PSS
0
0
0
0
0
PFO
4
136
0.246
0.107
0
Subtotal
8
136
0.301
0.107
0.025
MP: 48.36 - 56.12
HUC 8: Haw River (03030002)
HUC 10: Headwaters Haw River (0303000202)
PEM
9
186
0.346
0
0
PSS
5
40
0.136
0
0
PFO
5
180
0.297
0.124
0
Subtotal
19
405
0.779
0.124
0
MP: 56.12 - 73.11
HUC 8: Haw River (03030002)
HUC 10: Back Creek -Haw River (0303000204)
PEM
18
146
0.653
0
0
PSS
1
52
0.069
0
0
PFO
19
1571
2.482
1.077
0
Subtotal
38
1769
3.204
1.077
0
Project Total
PEM
86
1086
3.19
0
0.025
PSS
10
245
0.507
0
0
PFO
47
3619
6.247
2.467
0
Total
143
4951
9.944
2.467
0.025
a/ Wetland type based on Classification of Deepwater of Wetlands and Deepwater Habitats of the United States (Cowardin, 1979)
PEM= Palustrine Emergent; PSS=Palustrine Scrub -Shrub; PFO=Palustrine Forested. All wetlands are jurisdictional under Section 404.
4-2 November 2018
M Mountain Valley
Joint Permit Application
USACE — Wilmington District and NCDEQ
SAW -2018-008887
Table 4-1
Summary of Proposed Wetland Impacts in North Carolina
Pipeline Construction Permanent
Wetland
Number of Crossing Workspace PFO Permanent Fill
Milepost (MP)/Watershed Type a/ Affected Length Impacts Conversion to for Access
Resources PEM/PSS Road (acre) e/
(feet) b/ (acres) c/ (acres) d/
b/ Construction impacts based on a 75 -foot wide construction workspace within wetlands. Wetlands crossed by Horizontal Directional Drill and outside of
construction workspace will not have a construction impact.
c/ Permanent impacts include conversion of forested wetland (PFO) to nonforested wetland (PSS/PEM) for 30 foot wide maintenance easement and fill for a
permanent access road. The permanent impacts are a subset of the construction impacts, not an addition to the construction impacts.
4-3 November 2018
M Mountain Valley
Joint Permit Application
USACE — Wilmington District and NCDEQ
SAW -2018-008887
Table 4-2
Summary of Proposed Waterbody Impacts in North Carolina
Watershed
Waterbody Type
a/
Number of
Affected
Resources
Waterbody
Width at
Pipeline
Crossing
(feet) b/
Stream
within
Construction
Workspace
(linear feet)
c/
Permanent
Stream Impact
(linear feet)
Pond withinPermanent
Construction
Workspace
(square feet)
Pond Impact
(square feet)
Ephemeral
37
680
2686
0
0
0
MP: 26.1 — 39.7
Intermittent
26
119
3569
25
0
0
HUC 8: Upper Dan (03010103)
HUC 10: Cascade Creek -Dan
Perennial
15
16
955
0
0
0
Pond
2
0
0
0
1441
0
River (0301010309)
Subtotal
80
814
7211
25
1441
0
Ephemeral
20
263
2115
0
0
0
Intermittent
11
11
653
16
0
0
MP: 39.7-48.36
HUC 8: Lower Dan (03010104)
Perennial
6
12
351
0
0
0
HUC 10: Hogans Creek -Dan
River (0301010401)
Pond
0
0
0
0
0
0
Subtotal
37
286
3119
16
0
0
Ephemeral
17
74
1641
0
0
0
Intermittent
10
11
723
0
0
0
MP: 48.36 - 56.12
Perennial
4
3
129
0
0
0
HUC 8: Haw River (03030002)
HUC 10: Headwaters Haw River
(0303000202)
Pond
1
0
0
0
350
0
Subtotal
32
88
2492
0
350
0
Ephemeral
30
605
2330
0
0
0
Intermittent
35
97
2557
26
0
0
MP: 56.12 — 73.11 (terminus)
Perennial
10
14
636
0
0
0
HUC 8: Haw River (03030002)
HUC 10: Back Creek -Haw River
(0303000204)
Pond
3
25
0
0
1881
11
Subtotal
78
740
5523
26
1881
11
4-4 November 2018
M Mountain Valley
Joint Permit Application
USACE — Wilmington District and NCDEQ
SAW -2018-008887
Table 4-2
Summary of Proposed Waterbody Impacts in North Carolina
Waterbody
Stream
Number of
Width at
within
Permanent
Pond withinPermanent
Watershed
Waterbody Type
Affected
Pipeline
Construction
Stream Impact
Construction
Pond Impact
a/
Resources
Crossing
Workspace
(linear feet)
Workspace
(square feet)
(feet) b/
(linear feet)
(square feet)
c/
Perennial
104
1621
8772
0
0
0
Intermittent
82
237
7501
67
0
0
Total
Ephemeral
35
45
2072
0
0
0
Pond
6
25
0
0
3672
11
Total
227
1928
18345
67
3672
11
a/ Waterbody type: stream classification based on field evaluations using the NCDWQ Stream Identification Form Version 4.11 for delineated resource.
For
approximated waterbodies, flow type was estimated based on aerial imagery unless the approximated stream is directly associated with a delineated waterbody
in which the approximated waterbody was assigned the same flow type as the associated delineated waterbody. All waterbodies are Section 404. None are
Section 10.
b/ Width of the pond or stream channel (at ordinary high water mark) at the intersection of the pipeline. For estimated waterbodies, aerial imagery
was used to
estimate the channel width if wide enough to discern, and defaulted to 5 feet if too narrow to be measured using aerial imagery.
c/ Stream crossings by HDD or conventional bore have "0" linear feet in construction workspace
4-5 November 2018
M Mountain Valley
Ir PIPELINE
4.1 WETLAND IMPACTS
4.1.1 Temporary Construction Impacts
Joint Permit Application
USACE — Wilmington District and NCDEQ
SAW -2018-008887
The Project will temporarily impact approximately 10 acres of wetlands during the construction process
from typical pipeline construction procedures, described in Section 2.4. These temporary impacts will result
from vegetation clearing, stump and root removal above the proposed trench, excavation and stockpiling of
wetland soils, and ground disturbance from construction vehicles. The impacts will temporarily affect 4.8
acres of non -forested wetland and 5.2 acres of forested wetland (Table 4-1).
4.1.2 Permanent Conversion of Forested Wetlands to Nonforested Wetlands
As required by the FERC Procedures, the Southgate Project will maintain no more than a 10 -foot -wide strip
centered over the pipeline in an herbaceous state and will only remove woody vegetation within a 30 -foot -
wide strip centered over the pipeline. This will result in a 10 -foot wide strip of herbaceous vegetation
centered over the pipeline flanked by a potential shrub (PSS wetland type) strip of 10 -foot width on either
side. Woody species removal from the 30 -foot wide maintenance corridor would be performed periodically
as needed and would be done on a selective basis, only removing woody species with potential to
compromise the integrity of the buried pipeline. Maintaining this 30 -wide maintenance corridor is necessary
for the safety and protection of the pipeline in accordance with the applicable federal standards. This
operational requirement would result in the conversion of approximately 2.5 acres of forested wetlands to
emergent and/or scrub/shrub wetland types. Crossing of the pipeline through forested wetlands has been
minimized to the extent practicable through Project siting as described in Section 2.8.
The Southgate Project will provide compensatory mitigation for the conversion of approximately 2.5 acres
of forested wetland to non -forested wetland through purchase of wetland mitigation credits at a 1:1 ratio
from an approved mitigation bank with a service territory covering the watershed where the impacts would
occur.
4.1.2.1 Permanent Fill for Access Road
The Project avoided siting permanent access roads in wetlands to the extent possible. There is one
permanent access road where wetland impacts were not avoidable. This is an existing access road that leads
to a permanent cathodic protection ground bed to be used during operation of the pipeline. Access Road
(PA-RO-113A) at MP 41.8 will permanently fill approximately 0.025 acre of non -forested wetland. The
access road is an existing farm road that crosses a PEM/PSS wetland and will provide access to ground bed
#3. The additional fill is required to improve the road such that equipment can access the ground bed area
during operation of the pipeline. Since the Project will use the existing road, the proposed upgrade will
minimize impacts to wetlands since the alternative would be to develop a new road that would cross a
portion of the wetland that is currently undisturbed. To compensate for the permanent wetland fill
associated with the access road upgrade, the Southgate Project will purchase credits at a 1:1 ratio from an
approved wetland mitigation bank.
4-6 November 2018
M Mountain Valley
Ir PIPELINE
4.2 WATERBODY IMPACTS
4.2.1 Temporary Construction Impacts
Joint Permit Application
USACE — Wilmington District and NCDEQ
SAW -2018-008887
The Project will temporarily impact six ponds (3,672 square feet) and 221 streams (18,345 linear feet) from
typical pipeline construction activities, described in Section 2.4. No single and complete project will exceed
300 linear feet of temporary disturbance. These waterbodies will be restored to their pre -construction
condition, as closely as possible, after construction and will be monitored to ensure they remain stabilized
and restoration is successful per the FERC Procedures.
4.2.2 Permanent Impacts
The Project will result in permanent impacts to four waterbodies. Approximately 11 square feet of WB -
B18 -1, a pond located at MP 68.2, will be permanently filled for a ground bed in Alamance County. The
other permanent waterbody impacts include three permanent culverted stream crossings associated with
permanent access roads. Two of the permanent access roads are within Rockingham County: PA-RO-000
will cross 25 linear feet of AS-NHD-6002, an intermittent tributary to the Dan River and PA-RO-113A will
cross 16 linear feet of S -B 18-32, an intermittent tributary to Lick Fork. In Alamance County, PAR -AL -164
will cross 26 linear feet of AS-NHD-1554, an intermittent tributary to the Haw River.
4.3 RIPARIAN BUFFER IMPACTS
The Jordan Lake impoundment was created in 1983 by damming the Haw River near its confluence with
the Deep River. Jordan Lake spans several county boundaries and supplies drinking water to approximately
500,000 people and offers recreational opportunities (swimming, boating, fishing) to residents (TCH, 2018,
USACE, 2018). In December of 1963, the U.S. Army Corps of Engineers ("USACE") Wilmington District
took stewardship of Jordan Lake, proposing an earthen dam with a multi-level intake tower in the interest
of flood control, water supply, water quality control, recreation and other purposes (USACE, 2018). In a
joint effort to improve the low water quality of Jordan Lake, the Wilmington District and NCDWR have
enacted the Jordan Lake Nutrient Strategy, consisting of the Jordan Lake Rules that are a nutrient
management strategy designed to restore the water quality in the lake by reducing the amount of pollution
entering upstream (15A NCAC 02B .0267). Specific issues addressed by the rules include reducing
pollution from wastewater discharges, stormwater runoff from new and existing development, agricultural
and fertilizer application (NCDWR, 2018). In an effort to further define the Jordan Lake Nutrient Strategy
program, a riparian buffer zone watershed upstream of Jordan Lake was developed which outlines the
stormwater and buffer permit program for the watershed. The Jordan Lake watershed is divided into three
Jordan subsheds, the Lower New Hope, Upper New Hope and the Haw subshed (NCDWR, 2018).
Although Jordan Lake is located approximately 25 miles southeast of the southern extent of the Southgate
Project, the Project crosses the Jordan Lake riparian buffer zone watershed (Jordan Lake watershed),
specifically the Haw subshed, for a total of approximately 24 miles in Rockingham (4 miles) and Alamance
(20 miles) counties. The Southgate Project will abide by state requirements / permit conditions for the
Jordan Lake riparian buffer ("riparian buffer') zone watershed. The riparian buffer applies to intermittent
streams, perennial streams, lakes, ponds, estuaries and modified natural streams within natural
drainageways that are depicted on the most recent published version of the soil survey map prepared by the
Natural Resources Conservation Service or the 1:24,000 scale topographic map prepared by the USGS
(Appendix A).
4-7 November 2018
M Mountain Valley Joint Permit Application
PIPELINE USACE — Wilmington District and NCDEQ
SAW -2018-008887
As outlined in 15A NCAC 02B.0267(7)(a), the Zone One buffer consists of a vegetated area that is
undisturbed except for allowed uses initiating at the bank of a waterbody and extending 30 feet horizontally.
The Zone Two buffer extends from the outer limit of the Zone One buffer and measures 20 feet horizontally,
which comprises the outer portion of the 50 -foot buffer zone for waterbodies that qualify for the riparian
buffer protection within the portion of the Southgate Project area that is inside the Jordan Lake watershed.
The Southgate Project's temporary impacts within the riparian buffer zone are classified as either
"Allowable" or "Allowable with mitigation" uses for non -electric, utility line projects (NCDEQ, 2010a).
Therefore, the Project is seeking a buffer authorization for construction and operation -related impacts
within the Zone One and Zone Two buffers associated with jurisdictional waterbodies. Surface waters that
are exempt from the buffer requirements include man-made ponds and lakes that are not part of a natural
drainage way; ephemeral streams and ditches or other man-made water conveyances (15A NCAC 02B
.0267(5)). Additionally, the Project will continue to consult with NCDWR to identify applicable variances.
Proposed impacts to waterbodies in the Jordan Lake watershed subject to the riparian buffer rules are
summarized in Table 4-3 below and Appendix M (Impact Drawings).
4-8 November 2018
M Mountain Valley
Joint Permit Application
USACE -Wilmington District and NCDEQ
SAW -2018-008887
Table 4-3
North Carolina Riparian Buffer Impacts within the Jordan Watershed
Meets Perpendicular
Workspace within
Workspace within
Area of Wetland
Area of Wetland
Milepost
ID
Flow type
Crossing Standard
Zone 1 Buffer
Zone 2 Buffer
Overlap Zone 1
Overlap Zone 2
Required Mitigation
Additional Information on Non-
(yes/no)
(Square feet)
(Square feet)
Buffer
Buffer
(Square feet)
Perpendicular Crossings
(Square feet)
(Square feet)
Collocated with existing utility corridor
48.7
S -A18-60
Perennial
No
5,224.93
3,343.97
307.05
0.00
14,753.64
Avoids solar farm
Construction workspace reduced to 75 feet
49.3
S -A18-55
Perennial
Yes
4,752.35
3,194.86
0.00
0.00
19,049.35
-
AS -A18-182 /
S -A18-182:
Intermittent &
No
Collocated with existing utility corridor
49'9
S -A18-183:
Perennial
13,797.69
11,256.00
3,347.60
2,367.94
31,350.27
Construction workspace reduced to 75 feet
S -A18-185 Workspace only
S -A18-185
Collocated with existing utility corridor
50.2
S -A18-244
Perennial
No
4,334.94
3,211.68
9.17
0.00
12,977.31
Construction workspace reduced to 75 feet
50.3
S -A18-243
Perennial
Yes
1,165.40
1,202.08
0.00
0.00
5,299.34
-
Estimated waterbody boundary due to lack of
50.8
AS-NHD-305
Perennial
No
6,690.08
8,276.70
0.00
0.00
20,070.24
survey access
Construction workspace reduced to 75 feet
Collocated with existing utility corridor
51.4
S -C18-21
Perennial
No
5,203.08
3,357.32
508.09
884.69
14,084.97
Construction workspace reduced to 75 feet
Yes
S -C18-15
Intermittent
52.1
18, 349.13
9,602.85
0.00
0.00
69,451.67
-
S -A18-217
Perennial
A -A18-217 Workspace only
52.4
S -A18-219
Perennial
Yes
4,702.17
3,134.84
0.00
0.00
18,808.77
-
Waterbody meanders - crosses as
52.7
S-1318-94
Perennial
No
6,918.77
4,208.03
0.00
0.00
20,756.31
perpendicular as possible
Construction workspace reduced to 75 feet
S -A18-84
No
Collocated with existing utility corridor
53.7
Perennial
15,291.21
8,901.46
95.61
108.18
58,776.72
S -A18-87
Yes
Construction workspace reduced to 75 feet
54
S -A18-89
Intermittent
Workspace only
3,392.15
3,677.64
0.00
0.00
15,692.90
-
Collocated with existing utility corridor
54.5
S -C18-63
Perennial
No
8,510.36
5,193.70
0.00
0.00
25,531.08
Construction workspace reduced to 75 feet
S -A18-215
Intermittent &
54.6
S -A18-216
Perennial
Yes
2,310.42
1,071.05
0.00
0.00
8,537.84
-
Collocated with existing utility corridor
54.6
S -C18-62
Perennial
No
6,437.34
3,524.48
0.00
0.00
19,312.02
Construction workspace reduced to 75 feet
S -B18-142
Collocated with existing utility corridor
54.9
S -C18-60
Intermittent
No
10,852.41
7,500.16
0.00
0.00
32,557.23
Construction workspace reduced to 75 feet
S -C18-61
4-9 November 2018
M Mountain Valley
Joint Permit Application
USACE -Wilmington District and NCDEQ
SAW -2018-008887
Table 4-3
North Carolina Riparian Buffer Impacts within the Jordan Watershed
Meets Perpendicular
Workspace within
Workspace within
Area of Wetland
Area of Wetland
Milepost
ID
Flow type
Crossing Standard
Zone 1 Buffer
Zone 2 Buffer
Overlap Zone 1
Overlap Zone 2
Required Mitigation
Additional Information on Non-
(yes/no)
(Square feet)
(Square feet)
Buffer
Buffer
(Square feet)
Perpendicular Crossings
(Square feet)
(Square feet)
AS -1318-59 /
Yes: S-1318-59-2
S-1318-59
meander -crosses as
perpendicular
perpendicular as possible
55.3
S-618-59-2
Perennial
No: AS -1318-59 /
25,054.93
13,021.18
3,132.36
0.09
85,299.35
Collocated with existing utility corridor
S-1318-59
S -B18-59 &
Construction workspace reduced to 75 feet
S -C18-68
S -C18-68
55.6
S -A18-162
Intermittent
Yes
0.00
1,102.50
0.00
0.00
1,653.76
-
S -A18-120
Perennial &
No: S -A18-120
Collocated with existing utility corridor
56.4
10, 256.10
4, 846.71
7, 323.42
0.92
8, 798.04
S-1318-65
Intermittent
Yes: S-1318-65
Construction workspace reduced to 75 feet
S -A18-125-2
S -A18-125-3
Collocated with existing utility corridor
56.6
Perennial
Workspace only
17,204.96
12,813.77
6,472.25
6,010.83
42,402.54
S -A18-125-4
Construction workspace reduced to 75 feet
S -A18-125
S -A18-132
Perennial &
Collocated with existing utility corridor
57.1
No
8,226.69
8,696.42
353.53
941.52
23,619.48
S -A18-136
Intermittent
Construction workspace reduced to 75 feet
S -A18-136
57.2
S -A18-134
Intermittent & Pond
Yes
2,025.57
5,283.58
1,753.80
3,057.88
4,153.86
-
W B -A18-137
57.9
S -C18-2
Intermittent
Yes
5,624.74
3,505.72
352.98
852.66
19,794.87
-
S -C 18-8
58.1
Intermittent
Yes
185.17
1,527.87
0.00
0.00
2,847.32
-
S -C18-9
S -C18-11
No
Waterbodies meander - crosses as
Perennial &
perpendicular as possible
58.7
S -C18-12
Intermittent
11,804.89
3,792.64
0.00
0.00
35,414.67
Collocated with existing utility corridor
S -C18-13
S -C18-12 Workspace only
Construction workspace reduced to 75 feet
AS-NHD-1554:
58.9
I nt.
Intermittent
Yes
1,621.65
1,168.67
0.00
0.00
6,617.96
-
Estimated waterbody boundary due to lack of
59.6
AS-NHD-1549
Intermittent
No
5,701.92
3,767.72
0.00
0.00
17,105.75
survey access
Construction workspace reduced to 75 feet
Waterbodies meander - crosses as
S -C18-28
perpendicular as possible
60.8
S -C18-30
Intermittent
No
13,338.77
8,686.03
9,812.50
4,607.77
10,578.81
Collocated with existing utility corridor
Construction workspace reduced to 75 feet
Waterbody meanders - crosses as
S -A18-78
Intermittent &
perpendicular as possible
61.8
S -A18-76
Perennial
No
6,129.77
8,269.82
157.17
0.00
17,917.80
Collocated with existing utility corridor
Construction workspace reduced to 75 feet
61.9
S -A18-69
Intermittent
Yes
187.96
1,531.48
0.00
0.00
2,861.11
-
4-10 November 2018
M Mountain Valley
Joint Permit Application
USACE -Wilmington District and NCDEQ
SAW -2018-008887
Table 4-3
North Carolina Riparian Buffer Impacts within the Jordan Watershed
Meets Perpendicular
Workspace within
Workspace within
Area of Wetland
Area of Wetland
Milepost
ID
Flow type
Crossing Standard
Zone 1 Buffer
Zone 2 Buffer
Overlap Zone 1
Overlap Zone 2
Required Mitigation
Additional Information on Non-
(yes/no)
(Square feet)
(Square feet)
Buffer
Buffer
(Square feet)
Perpendicular Crossings
(Square feet)
(Square feet)
S -A18-70-2
S -A18-70
62.5
S -A18-72-2
Intermittent &
Yes
18,354.82
7,882.78
855.11
167.43
64,072.16
-
Perennial
S -A18-72
S -A18-71
S-1318-12-2
S-1318-12-3
S-1318-12-4
S-1318-12-5
S-1318-12-6
Intermittent &
63.1
Workspace only
35,454.71
16,924.25
14,083.87
4,880.13
82,178.70
-
S-1318-12
Perennial
S-1318-22-2
S-1318-22
S-1318-24
S-1318-26
63.7
S-1318-137
Intermittent
Workspace only
1,680.94
1,041.91
0.00
0.00
6,605.68
-
Estimated waterbody boundary due to lack of
63.8
AS -1318-20
Intermittent
No
5,754.88
3,739.27
3,510.97
11.49
6,731.73
survey access
63.8
AS -1318-138
Perennial
Yes
1,584.93
1,022.61
0.00
0.00
6,288.71
-
Estimated waterbody boundary due to lack of
64
AS-NHD-1547
Perennial
No
6,979.62
4,574.02
0.00
0.00
20,938.86
survey access
64.5
AS-NHD-3040
Intermittent
Yes
4,763.72
3,149.65
0.00
0.00
19,015.64
-
S -A18-250
Perennial &
Waterbodies meander - crosses as
65.6
No
6,735.42
3,925.67
0.00
0.00
20,206.26
perpendicular as possible
S -A18-251
Intermittent
Construction workspace reduced to 75 feet
66.5
AS-NHD-7000
Intermittent
Yes
1,542.76
1,021.83
0.00
0.00
6,161.03
-
Estimated waterbody boundary due to lack of
66.8
AS-NHD-3025
Intermittent
No
5,401.00
3,645.28
0.00
0.00
16,203.00
survey access
Estimated waterbody boundary due to lack of
67.2
AS -A18-177
Perennial
No
4,713.58
3,066.23
0.00
0.00
14,140.74
survey access
AS -A18-233 /
67.6
S -A18-233
Perennial
Yes
5,543.84
4,838.60
0.00
0.00
23,889.42
Estimated waterbody boundary due to lack of
68.1
AS-NHD-1551
Intermittent
No
5,299.16
3,551.97
0.00
0.00
15,897.48
survey access
68.3
S-1318-3
Intermittent
Yes
604.87
2,071.45
0.00
0.00
4,921.79
-
4-11 November 2018
M Mountain Valley
Joint Permit Application
USACE -Wilmington District and NCDEQ
SAW -2018-008887
Table 4-3
North Carolina Riparian Buffer Impacts within the Jordan Watershed
Meets Perpendicular
Workspace within
Workspace within
Area of Wetland
Area of Wetland
Milepost
ID
Flow type
Crossing Standard
Zone 1 Buffer
Zone 2 Buffer
Overlap Zone 1
Overlap Zone 2
Required Mitigation
Additional Information on Non-
(yes/no)
(Square feet)
(Square feet)
Buffer
Buffer
(Square feet)
Perpendicular Crossings
(Square feet)
(Square feet)
68.4
S-1318-7
Perennial
Yes
4,743.03
3,261.73
0.00
0.00
19,121.69
-
68.5
AS-NHD-1552
Intermittent
Yes
5,598.24
4,631.52
0.00
0.00
23,742.01
-
Waterbody meanders - crosses as
68.8
S-1318-8
Intermittent
No
5,576.86
3,452.70
0.00
0.00
16,730.58
perpendicular as possible
Construction workspace reduced to 75 feet
Waterbody meanders - crosses as
68.9
S-1318-11
Intermittent
No
5,857.99
4,043.59
0.00
0.00
17,573.97
perpendicular as possible
Construction workspace reduced to 75 feet
Maintained field
S -A18-15
69.2
Intermittent & Pond
No
5,065.77
4,244.49
0.00
0.00
15,197.31
Avoids forest impacts
WB -A18-16
Construction workspace reduced to 75 feet
69.4
AS -1318-132
Perennial
Yes
4,775.13
4,149.92
0.00
0.00
20,550.27
-
69.9
AS -A18-115
Perennial
Yes
5,696.99
3,819.38
0.00
0.00
22,820.04
-
S-618-133
Perennial &
Yes
Construction workspace reduced to 75 feet
70.2
S -B18-134
Intermittent
No
8,493.33
7,421.01
0.00
0.00
36,611.51
Avoids parallel impacts
Waterbody meanders - crosses as
70.4
S -C18-82
Intermittent
No
7,176.12
5,109.15
0.00
0.00
21,528.36
perpendicular as possible
Construction workspace reduced to 75 feet
ATWS outside of wetlands and waterbodies
70.7
S -C18-81
Perennial
No
4,974.16
3,310.56
0.00
0.00
14,922.48
Crosses as perpendicular as possible
Construction workspace reduced to 75 feet
Minimizes forested riparian corridor impacts to
S -A18-108
Intermittent &
No
Haw River Nearby S -A-18-109 is crossed
70.9
S -A18-109
Perennial
Yes
12,373.70
9,141.68
0.00
0.00
50,833.62
perpendicular
Construction workspace reduced to 75 feet
Minimizes forested riparian corridor impacts to
Haw River Nearby S -A-18-109 is crossed
71
S -A18-107
Intermittent
No
6,052.88
4,029.82
0.00
0.00
18,158.64
perpendicular
Construction workspace reduced to 75 feet
S -A18 -64S-
Minimizes forested riparian corridor impacts to
71.5
A18-65
Intermittent &
Yes
9,745.68
5,632.31
0.00
0.00
37,685.51
Haw River Construction workspace reduced to
S-1318-58
Perennial
No
75 feet
71.8
S -A18-68
Perennial
Yes
5,495.44
5,201.27
0.43
323.94
23,801.01
-
72.1
AS-NHD-1560
Intermittent
Yes
4,562.87
3,047.54
0.00
0.00
18,259.92
-
72.2
S -A18-207
Intermittent
Workspace Only
141.40
416.42
141.40
3.82
618.90
-
72.2
S -A18-207
Intermittent
Workspace Only
1,705.20
2,896.87
0.00
0.00
9,460.91
-
4-12 November 2018
M Mountain Valley
Joint Permit Application
USACE —Wilmington District and NCDEQ
SAW -2018-008887
Table 4-3
North Carolina Riparian Buffer Impacts within the Jordan Watershed
Meets Perpendicular
Workspace within
Workspace within
Area of Wetland
Area of Wetland
Milepost
ID
Flow type
Crossing Standard
Zone 1 Buffer
Zone 2 Buffer
Overlap Zone 1
Overlap Zone 2
Required Mitigation
Additional Information on Non-
(yes/no)
(Square feet)
(Square feet)
Buffer
Buffer
(Square feet)
Perpendicular Crossings
(Square feet)
(Square feet)
Avoids impacts to Haw River riparian buffer and
72.4
S-618-125
Intermittent
No
6,043.78
4,120.56
0.00
0.00
18,131.34
wetlands
Construction workspace reduced to 75 feet
Avoids impacts to Haw River riparian buffer and
72.5
S-618-127
Intermittent
No
7,060.20
5,099.74
0.00
0.00
21,180.60
wetlands
Construction workspace reduced to 75 feet
72.7
S-1318-58
Perennial
Yes
0.00
13.81
0.00
0.00
20.72
-
Total:
440,848.57
302,170.52
52,217.31
24,219.29
1,380,275.50
4-13 November 2018
M Mountain Valle
PIPELINE
4.3.1.1 Diffuse Flow Requirement
Joint Permit Application
USACE — Wilmington District and NCDEQ
SAW -2018-008887
The Jordan Lake Rules state that `diffuse flow of runoff shall be maintained in the riparian buffer by
dispersing concentrated flow prior to its entry into the buffer and reestablishing vegetation'. To ensure
compliance with this requirement, the Project will implement its E&SCP during construction and adhere to
the FERC Plan and Procedures. Both of these documents provide for stormwater best management
practices during construction and detail post -construction stabilization and revegetation measures. In
addition, the Project will comply with applicable federal and state stormwater management requirements
and approvals.
4.3.1.2 No Practicable Alternatives
Since the use associated with the Project is designated as `allowable' or `allowable with mitigation',
Southgate is including a request for a `no practicable alternatives' determination. The Project is linear in
nature and, as such, cannot completely avoid impacts within the riparian buffer. Since the Project terminus
is located within the Jordan Lake watershed, there is no practical alternative that could avoid activities
within the buffers. As detailed within this narrative, the Southgate Project certifies that the Project meets
the following criteria for a determination of `no practical alternatives':
• The basic project purpose cannot be practically accomplished in a manner that would better
minimize disturbance, preserve aquatic life and habitat, and protect water quality;
• The use cannot practically be reduced in size or density, reconfigured or redesigned to better
minimize disturbance, preserve aquatic life and habitat, and protect water quality; and
• Best management practices shall be used if necessary to minimize disturbance, preserve aquatic
life and habitat, and protect water quality.
4.3.1.3 Impact Mitigation
Based on the table of uses within the Jordan Lake Rules, the Project will be regulated under two uses that
are allowable with mitigation: (1) Utility, non -electric, perpendicular crossing of streams and other surface
waters that disturb greater than 40 linear feet but equal to or less than 150 linear feet of riparian buffer with
a maintenance corridor greater than 10 feet in width (applicable in both Zone 1 and Zone 2); and (2) Utility,
non -electric, other than perpendicular crossings with impacts located within Zone 1. Based on consultation
with NCDEQ, the mitigation ratios for Project -related impacts within Zone 1 are 3 to 1, and 1.5 to 1 in
Zone 2 for (1) Utility, non -electric, perpendicular crossing of streams and other surface waters, and the
mitigation ratios for Project -related impacts within Zone 1 are 3 to 1, and allowable without mitigation in
Zone 2 for (2) Utility, non -electric, other than perpendicular crossings. Riparian buffer impacts and
associated mitigation estimates are provided in Table 4-3. The Project will continue to consult with
NCDEQ regarding the approved form(s) of mitigation for the Project.
4.4 IMPACT AVOIDANCE AND MINIMIZATION MEASURES
Where impacts to wetlands and waterbodies cannot be avoided, the Southgate Project will seek to minimize
impacts through use of the following measures, as applicable:
• Clearly marking wetland and waterbody boundaries with signs and flagging in the field prior to the
start of construction;
4-14 November 2018
M Mountain Valley
Ir PIPELINE
Joint Permit Application
USACE — Wilmington District and NCDEQ
SAW -2018-008887
• Limiting the construction right-of-way width to 75 -feet through wetlands and waterbodies (unless
alternative, site-specific measures are requested by the Project and approved by the FERC and other
applicable agencies) and extending this reduced width 50 feet on each side of the resource;
• Limiting the operation of construction equipment within wetlands to only equipment essential for
clearing, excavation, pipe installation, backfilling, and restoration;
• Cutting trees to grade, and only removing stumps from directly over the trench, or where safety
concerns dictate otherwise, thus allowing existing vegetation to recover more rapidly in the
remainder of the right-of-way once the equipment mats and spoil piles have been removed;
• Installing and maintaining sediment barriers, such as silt fences or other approved barriers
throughout the construction process per the FERC Plan and Procedures and Project -specific
E&SCP;
• Preventing the compaction and rutting of wetland soils by operating equipment off of equipment
mats or equivalent in wetlands that are not excessively saturated;
• Restricting grading in wetlands to the area directly over the trench, except where necessary for
safety concerns;
• Locating ATWS at least 50 feet away from wetland and waterbody boundaries (unless alternative,
site-specific measures are requested by the Project and approved by the FERC and other applicable
agencies);
• Selecting the most appropriate FERC -approved crossing procedure, based on site specific
conditions at the time of crossing;
• Dewatering the trench, if needed, in a manner designed to prevent heavily silt -laden water from
entering a waterbody or undisturbed portions of wetlands within and adjacent to the Project limits;
• Segregating topsoil from the trench in non -saturated wetlands and returning topsoil to its original
location during backfilling to avoid changes in the subsurface hydrology and to promote re-
establishment of the original plant community by replacing the seed bank found in the topsoil;
• Placing excavated soils in wetlands on filter cloth, mats, or similar semi -permeable surface to avoid
mixing of with underlying materials and stabilizing the soils with filter cloth, straw bales or other
appropriate measure to prevent re-entry into adjacent wetlands or waters;
• Limiting storage of excavated soil material in wetlands to no longer than 30 days after the pipe has
been laid in the trench, without prior approval from the USACE;
• Installing trench breakers or trench plugs at the boundaries of wetlands, as needed, to prevent
draining of wetlands;
• Backfilling the ditch with the spoil excavated from the wetland;
• Spreading segregated topsoil over the area from which it was stripped and restoring the ground
surface to approximate pre -construction contour;
• Mechanically loosening the upper 12 inches of soils backfilled in wetlands;
4-15 November 2018
M Mountain Valley
Ir PIPELINE
Joint Permit Application
USACE — Wilmington District and NCDEQ
SAW -2018-008887
• Seeding wetland areas that are not inundated with annual rye to provide soil stabilization while
allowing the natural seedbank to revegetate the wetland area.
• Seeding wetlands with appropriate native wetlands species if natural revegetation is not successful;
• Removing all equipment mats, debris, or other material from the wetlands and waterbodies after
construction;
• Aligning the crossings as close to perpendicular to the axis of the waterbody channel as engineering
and site-specific conditions allow;
• Limiting the operation of construction equipment within waterbodies to only equipment essential
for clearing, excavation, pipe installation, backfilling, and restoration;
• Avoiding the use of riprap for bank stabilization purposes. In the event that riprap is required for
bank stabilization purposes, the Project will adhere to the general conditions;
• Installing temporary bridges for equipment crossings over channels with flowing water and
ensuring they are constructed and maintained to allow unrestricted flow and to prevent soil from
entering the waterbody;
• Limiting crossing of waterbodies to clearing equipment and equipment necessary for installation
of bridges prior to bridge installation;
• Remove temporary equipment bridges as soon as practicable after permanent seeding.
• Aligning culverts to prevent bank erosion or streambed scour. If necessary, install energy
dissipating devices downstream of the culverts;
• Adherence to required time of year construction restrictions. If adherence to time of year
restrictions is not possible, notification will be provided on a case-by-case basis to the applicable
agency with a request for a modification or waiver of the timing restriction;
• Adherence to the FERC Plan and Procedures and applicable permit requirements;
• Adherence to NWP 12 terms and conditions (see Appendix N).
• Developing and adhering to a Project specific SPCC plan; and
• Use of independent qualified EI's through the construction process to ensure construction adhered
to FERC Plan and Procedures and application permit terms and conditions.
• Prohibiting the use of live concrete as a building material such that wet concrete does not come
into contact with water;
• Prohibiting the use herbicides or pesticides within 100 feet of a wetlands or waterbodies, unless
specified or approved by a federal or state agency;
• Prohibiting the storage of chemicals, fuels, hazardous materials, and lubricating oils within 100 feet
of a wetland;
• Prohibiting parking and/or fueling of equipment within 100 feet of a wetland; unless the
Environmental Inspector determines there is no reasonable alternative, and appropriate steps (such
as secondary containment structure) are taken;
4-16 November 2018
M Mountain Valley
Ir PIPELINE
Joint Permit Application
USACE — Wilmington District and NCDEQ
SAW -2018-008887
• Conducting annual monitoring of wetlands and waterbodies and performing maintenance activities,
as needed, until the wetlands and waterbodies are successfully restored;
• Preventing the invasion or spread of undesirable exotic vegetation according to a project -specific
invasive plant species management plan;
• Limiting post -construction maintenance of vegetation to removal of trees with roots that could
compromise the integrity of the pipeline within 15 feet of the pipeline centerline, and the
maintenance of a 10 -foot wide corridor centered over the pipeline as herbaceous vegetation; and
• The Project will conduct pre -construction testing of all private wells located within 150 feet of the
construction workspace. The Project will conduct post -construction tests if requested by a
landowner who had a pre -construction test (See Appendix O — Water Resources Identification and
Testing Plan).
Specific measures to minimize or avoid impacts to waterbodies for the dry or trenchless waterbody crossing
methods proposed include:
Dam and Pump
• Sufficient pumps, including on-site backup pumps, will be used to maintain downstream flows;
• Pumps will be placed in secondary containment and properly aligned to prevent streambed scour
at pump discharge;
• Dams will be constructed with materials that prevent sediment and other pollutants from entering
the waterbody;
• Pump intakes will be screened to minimize entrainment of fish; and
• Dams and pumps will be continuously monitored to ensure proper operation throughout the
waterbody crossing.
Flume
• Sand bags, sand bag and plastic sheeting diversion structures, or the equivalent will be used to
develop an effective seal and to divert stream flow through the flume pipe;
• Flume pipes will be installed after blasting (if necessary), but before trenching;
• Flume pipes will remain in place until trenching, pipe laying, backfilling, and initial streambed
restoration efforts are complete;
• Flume pipes will be properly aligned to prevent bank erosion and streambed scour; and
• All flume pipes and dams that are not part of the equipment bridge will be removed as soon as final
cleanup of the streambed and bank is complete.
Cofferdam
• Hydrographic studies of the waterbody
• Sand bags, sand bag and plastic sheeting diversion structures, or the equivalent will be used to
develop an effective seal
4-17 November 2018
M Mountain Valley
Ir PIPELINE
Conventional Bore
• Desktop analysis of the water table
HDD
• Implementation of HDD Contingency Plan (if needed).
Joint Permit Application
USACE — Wilmington District and NCDEQ
SAW -2018-008887
4.4.1 Stormwater Management and Diffuse Flow Plan
Stormwater permit applications and associated Erosion and Sediment Control plans will be developed by
the Project in winter of 2018, and applications will be submitted in early 2019. The Project team will
develop a diffuse flow plan, where required, as part of the Erosion and Sediment Control plans that will be
submitted to the appropriate local government and NCDWR responsible for review and approval of
construction stormwater permitting.
4.4.1.1 Stormwater Management Plan
Stormwater permit applications and associated Erosion and Sediment Control plans will be developed by
the Project in winter of 2018, and applications will be submitted in early 2019. The Project team will
develop a storm water management plan, where required, as part of the Erosion and Sediment Control plans
that will be submitted to the NCDEMLR, as applicable, who is responsible for review and approval of
construction stormwater permitting.
4.4.1.2 Certified Local Government Stormwater Review
Stormwater permit applications and associated Erosion and Sediment Control plans will be developed by
the Project team in winter of 2018, and applications will be submitted in early 2019. The Project will
develop an Erosion and Sediment Control plan that will be submitted to the appropriate local government
or NCDEMLR, as applicable, responsible for review and approval of construction stormwater permitting.
4-18 November 2018
M Mountain Valle
PIPELINE
Joint Permit Application
USACE — Wilmington District and NCDEQ
SAW -2018-008887
5.0 ADDITIONAL SUPPORTING INFORMATION
5.1 ENVIRONMENTAL DOCUMENTATION
The Project will file an application with FERC for a Certificate of Public Convenience and Necessity under
Section 7(c) of the Natural Gas Act by September 2015. As a part of the FERC filing process Draft and
Final Environmental Impact Statements ("EIS") will be prepared by the FERC for the Southgate Project.
The Environmental Impact Statements will be published for review and comment. (See Appendix J). Any
additional documents will be filed as a supplemental that are required to support this joint permit
application.
5.2 VIOLATIONS
This section is not applicable to the Project as it consists of new construction. See Section F2 of the Joint
Permit Application Form for additional information.
5.3 CUMULATIVE IMPACTS
The Southgate Project has potential to cause cumulative effects to the wetlands or waterbodies from the
incremental consequences of the Project when added to other past, present, and reasonably foreseeable
future actions, regardless of what agency or person undertakes such other actions. The scope of the
cumulative effects analysis in this permit application is limited to direct or indirect effects on wetlands or
waterbodies from projects having potential to affect surface waters within the same HUC 10 or 12 as the
Southgate Project. An environmental impact statement is being prepared by the FERC that will include a
comprehensive cumulative impact statement from the agency.
Projects included in this assessment were limited to those with publicly available information pertaining
the proposed undertaking and potential impacts. Sources of information used to collect data about relevant
projects included federal, state, and local agencies permitting databases or websites. Projects with potential
cumulative impacts on wetlands or waterbodies within the North Carolina portion of the Southgate Project
area are listed in Table 6-1.
The Southgate Project need originated from a forecasted growing demand in the region of the Project in
North Carolina. This is an open access pipeline; therefore, other companies have the option to request gas
service from the pipeline system. An increase in demand beyond the current scope would likely require
modifications to the pipeline and/or its facilities. PSNC Energy solicited interest because it requires
additional pipeline capacity to meet forecasted incremental demand on its distribution system. Over the
past four years, PSNC Energy has experienced a 15 percent increase in peak daily throughput on its system.
This trend will carry forward into the future, as PSNC Energy expects its design day requirements to
increase an additional 11 percent over the next five years. This past, present, and future demand growth on
PSNC Energy's system reflects, at least in part, the substantial population increase in North Carolina. North
Carolina's population is expected to increase by nearly 2 million people between 2020 and 2035. In
Alamance County, where the project terminates, the population is anticipated to grow approximately 11
percent from July 2020 to July 2029.9 Secondary impacts as a result of this Project are currently anticipated
through new developments that will be serviced by PSNC (e.g., residential communities, industrial
9 See North Carolina Office of State Budget and Management population projections, available at:
http s://files. nc. gov/nco sbm/demog/countytotals_populationoverview. html
5-1 November 2018
M Mountain Valley Joint Permit Application
PIPELINE USACE —Wilmington District and NCDEQ
SAW -2018-008887
facilities). Construction of these developments could affect surface waters or wetlands that would not occur
if the Project were not built as the result of a newly available natural gas supply. The potential water quality
impacts from any induced new development in the Roanoke River Basin and Cape Fear River Basin will
be mitigated by federal and state specific permitting requirements, and often including municipal
stormwater management programs. If the Project were not constructed, it is likely that at least some of the
forecasted growth would still occur without a new gas supply. Future expansion plans are not discussed
because Mountain Valley has no plans to expand the pipeline beyond the terminus at the Haw River
Interconnect in Graham, North Carolina.
Cumulative effects on surface water resources affected by the Project would be limited to waterbodies that
are affected by other projects located within the same major watersheds. No permanent diversions or dams
are planned, so any impacts from construction on surface waters would be temporary. The greatest potential
impacts of pipeline construction on surface waters would result from an increase in sediment loading to
surface waters and an increase in internal sediment loading due to channel/floodplain instability as a result
of a change in erosion deposition patterns. Each of the project proponents will minimize these effects by
implementing wetland and waterbody construction and mitigation measures, including erosion control
measures by complying with applicable federal and state permit requirements.
Construction of the Project facilities will result in temporary impacts to wetlands. However, each proponent
for the projects listed in Table 6-1 that affects wetlands will be required, by the terms and conditions of
their respective Section 404 permits, to provide compensatory mitigation for unavoidable wetland impacts.
The cumulative effect on water resources and wetlands will be temporary and minor.
The primary factors associated with the Southgate Project that will minimize its contribution to cumulative
impacts are as follows:
• The impacts resulting from the Project pipeline facilities will primarily be short-term and constitute
temporary impacts associated with construction;
• Approximately 34 percent of the Project pipeline facilities will be parallel to existing utility
corridors and other rights-of-way; thereby minimizing impacts associated with construction; and
• The Project has been designed to avoid and minimize impacts to the extent practicable and will
implement various plans and techniques to ensure potential impacts are further minimized (e.g.,
Project -specific E&SCP and SWMP).
• The Project E&SCP and SWMP will address post -construction stormwater management associated
with the permanent right-of-way.
5-2 November 2018
M Mountain Valley
Joint Permit Application
USACE — Wilmington District and NCDEQ
SAW -2018-008887
Table 5-1
Projects with Potential Cumulative Impacts
Shared
Approximate
Potential/
Project
Description
County
Watershed
(5th Level/
Distance
Direction
Status
Anticipated
Potential
Permits
HUC10)
from Project
Impacts
Transportation Projects
Future 1-73 / North
Construction of a 9.4 -mile, four -
Carolina
lane interstate from Joseph M.
Complete
Wetlands and
State and
Department of
Bryan Boulevard/Airport
Guilford
Reedy Fork
25 miles
West
October 2017
Waterbodies
Local
Transportation
Parkway interchange to U.S.
("NCDOT)
220 near the Haw River
Completion of the Greensboro
Greensboro Urban
Urban Loop to help relieve 1-40
Guilford
Reedy Fork
10 miles
West
Under
Wetlands and
State and
Loop / NCDOT
congestion at 1-85 Business and
Construction
Waterbodies
Local
U.S. routes 29, 70, 220 and 421
No cumulative
Macy Grove Road
Proposed improvements and an
Forsyth/
In
effects given
State and
Improvements /
extension to Macy Grove Road
Guilford
Reedy Fork
32 miles
West
Development
unknown
Local
NCDOT
in Forsyth and Guilford counties
construction
timeframe
Proposed relocation of a portion
No cumulative
NC 119 Relocation
of N.C. 119 in Mebane —from I-
Back Creek-
In
effects givenState
and
/ NCDOT
85 to existing the N.C. 119 near
Alamance
Haw River
5 miles
East
Development
unknown
Local
Mrs. White Lane
construction
timeframe
Proposed widening an
No cumulative
N.C. 62 Widening -
approximately 1 -mile stretch of
Back Creek-
In
effects given
State and
Ramada Road to
N.C. 62 to improve traffic flow
Alamance
Haw Rive
4 miles
West
Development
unknown
Local
U.S. 70 / NCDOT
and safety
construction
timeframe
U.S. 158 (Reidsville
Proposed 18.8 -mile widening of
No cumulative
Road)
U.S. 158 from U.S.
Headwaters
In
effects given
State and
Improvements /
421 /Business 40 in Winston-
Guilford
Haw River
18 miles
West
Development
unknown
Local
NCDOT
Salem to U.S. 220 in Guilford
construction
County
timeframe
5-3 November 2018
M Mountain Valley
Joint Permit Application
USACE — Wilmington District and NCDEQ
SAW -2018-008887
Table 5-1
Projects with Potential Cumulative Impacts
Shared
Approximate
Potential/
Project
Description
County
Watershed
(5th Level/
Distance
Direction
Status
Anticipated
Potential
Permits
HUC10)
from Project
Impacts
Commercial, Industrial, Residential Projects
No cumulative
Oakwood Homes- New construction mobile home Cascade effects given
Under State and
Eden / Oakwood park at S Van Buren Rd. Eden, Rockingham Creek -Dan 2 miles West Construction unknown Local
Homes NC; approx. 18 new homes River construction
timeframe
Clayton Homes-
New construction housing
Burlington /Clayton
development single family
Alamance
Back Creek-
2.5 miles
West
Under
Wetlands and
State and
Homes
homes off S Graham Hopedale
Haw River
Construction
waterbodies
Local
Rd, Burlington
LGI Homes-
New construction housing
Bedford Hills /LGI
development single family
Alamance
Back Creek-
1.5 miles
East
Under
Wetlands and
State and
Homes
homes near 111 Pillow Ln.,
Haw River
Construction
Waterbodies
Local
Burlington, NC
Forest Creek /True
New construction housing
Back Creek-
Under
Wetlands and
State and
Homes
development 5 new homes in
Alamance
Haw River
3.5 miles
Southwest
Construction
Waterbodies
Local
development
5-4 November 2018
M Mountain Valley
Ir PIPELINE
5.4 SEWAGE DISPOSAL
Joint Permit Application
USACE — Wilmington District and NCDEQ
SAW -2018-008887
The Project does not include a wastewater disposal system; therefore, this section is not applicable.
5.5 ENDANGERED SPECIES AND DESIGNATED CRITICAL HABITAT
The Endangered Species Act (ESA) of 1973 (16 United States Code A-1535-1543, P.L. 93-205) provides
for the listing, conservation, and recovery of endangered and threatened species of plants and wildlife.
Under the ESA, plants and animals provide aesthetic, ecological, educational, historic, and scientific value
to the United States. The US Fish and Wildlife Service (USFWS) is mandated to monitor and protect all
federally listed freshwater and terrestrial species, whereas the National Marine Fisheries Service (NMFS)
is responsible for marine species. A federally listed endangered species is any species in danger of
extinction throughout all or a significant portion of its range. A federally listed threatened species is any
species likely to become an endangered species within the foreseeable future throughout all or a significant
portion of its range.
The ESA also provides protection for "critical habitat" that, as defined by the USFWS, are (1) specific areas
within the geographical area occupied by the species, at the time of listing, on which are found those
physical or biological features essential to the conservation of the species and which may require special
management considerations or protections; and (2) specific areas outside the geographical area occupied
by the species at the time it is listed and are determined to be areas essential for the conservation of the
species.
Under provisions of the ESA, all states were granted the authority to enact their own endangered species
protection policies. The North Carolina Endangered Species Act (G.S. 113-331 to 113-337 Act 25) states
that the NCWRC is the regulatory authority over state -listed endangered, threatened, or species of special
of concern. The regulation allows the NCWRC to adopt the federal list of endangered and threatened
species and develop a list of state "protected species." State protected species are separated into three
separate categories; North Carolina Endangered, North Carolina Threatened, and North Carolina Special
Concern. The definitions are as follows:
North Carolina Endangered: "Any native or once -native species of wild animal whose continued existence
as a viable component of the State's fauna is determined by the Wildlife Resources Commission to be in
jeopardy or any wild animal determined to be an "endangered species" pursuant to the Endangered Species
Act."
North Carolina Threatened: "Any native or once -native species of wild animal that is likely to become an
endangered species within the foreseeable future throughout all or a significant portion of its range or one
that is designated as a threatened species pursuant to the Endangered Species Act.
North Carolina Special Concern: "Any species of wild animal native or once native to North Carolina that
is determined by the Wildlife Resources Commission to require monitoring but that may be taken under
regulations adopted under the provisions of Article 25."
5.5.1 Consultation
The Southgate Project reviewed USFWS online Information for Planning and Conservation (IPaC) system
and requested records of any known federally listed, state -listed, rare or special concern species within the
Project area from the United States Fish and Wildlife Service (USFWS), North Carolina Wildlife Resource
5-5 November 2018
M Mountain Valley Joint Permit Application
T PIPELINE USACE —Wilmington District and NCDEQ
SAW -2018-008887
Commission (NCWRC), and North Carolina Natural Heritage Program (NCNHP). The Project submitted
listed bat, plant, and freshwater mussel survey plans detailing locations and methods to the applicable
agencies for approval. Similar study plans for other taxonomic groups may be developed as necessary,
following further coordination with federal and state agencies. Concerns regarding nesting eagle and
colonial nesting birds are also addressed herein.
5.5.2 Findings
Based on initial consultation with the USFWS, NCWRC, and NCNHP and review of spatial data provided
by NCNHP, a total of 10 federally listed (8 endangered and 2 threatened), 14 state listed (4 state endangered,
2 state threatened, and 8 special concern); and 4 state rare species were identified that could potentially
occur within 2 miles of the Project area.
5.5.3 Wildlife Species
Based on coordination with the USFWS Raleigh and Gloucester Field Offices and NCWRC, nine species
of bats are of concern in North Carolina, including three federally endangered bat species: Indiana bat
(Myotis sodalis), gray bat (Myotis grisescens), Virginia big -eared bat (Corynorhinus townsendii
virginianus), and one threatened species, northern long-eared bat (Myotis septentrionalis); one state
threatened species, Rafinesque's big -eared bat (Corynorhinus rafinesquii rafinesquii); and four state special
concern species, including eastern big -eared bat (Corynorhinus rafinesquii macrotis), eastern small -footed
bat (Myotis leibii), Florida yellow bat (Lasiurus intermedius floridanus), and southeastern bat (Myotis
austroriparius). None of these is known to occur in Rockingham or Alamance counties. Based on lack of
bat survey data available within the Project area, the Project proposed targeted mist netting and acoustic
surveys in accordance with 2018 Range -wide Indiana Bat Survey Guidelines (USFWS 2018) as a voluntary
conservation measure. In consultation with USFWS and NCWRC, the Project submitted a revised study
plan detailing survey type, effort, and locations to the USFWS, NCWRC and VDGIF on July 24, 2018 with
a request for concurrence and site-specific authorization. Written study plan concurrence was received
from the USFWS Raleigh Field Office and NCWRC on July 24, 2018 and August 3, 2018, respectively.
Fifty-two mist net sites (minimum of 6 net nights per site) and 11 acoustic survey sites (minimum of 2
detector nights per site) were completed between July 13 and August 14, 2018. Three hundred and twenty
complete and 114 partial net nights resulted in the capture of 551 bats, including 344 eastern red (Lasiurus
borealis), 153 big brown (Eptesicus fuscus), 37 evening (Nycticeius humeralis), 11 Seminole (Lasirus
seminolus), 3 tri -colored (Perimyotis subflavus), 2 hoary (Lasiurus cincereus), and 1 Mexican free -tailed
(Tadarida brasiliensis). Winter habitat (e.g., portals) was assessed concurrently with other environmental
surveys from June 1 through August 7, 2018 and was not found within the Project study corridor. Based
on the lack of species occurrence during summer sampling, all federally listed species are assumed absent
or present in such low density as for impacts to be inconsequential and Federal requirements for the Project
under Section 7(a)(2) of the ESA are met.
The Project is within geographic ranges of the bald eagle (Haliaeetus leucocephalus) and golden eagle
(Aquila chrysaetos), which are protected under the Bald and Golden Eagle Protection Act of 1940 (16 U.S.
Code 668-688d). A review of the North Carolina Natural Heritage Program database for bald and golden
eagles did not identify element occurrences in Rockingham or Alamance counties. Prior to construction,
the Project intends to conduct an aerial survey in the winter of 2019-2020 for nesting eagles and colonial
nesting bird rookeries within 1 mile of the Project. If eagle nests are identified within 0.5 mile of Project
activities, the Project will implement the USFWS Bald Eagle Management Guidelines (USFWS 2007). If
5-6 November 2018
M Mountain Valley Joint Permit Application
PIPELINE USACE —Wilmington District and NCDEQ
SAW -2018-008887
colonial nesting birds are observed during survey, the Project will cease all activities within a buffer of 0.5 -
mile around each rookery between February 15 and July 30. Implementation of these measures will avoid
impacts on eagles and colonial nesting birds.
Two state rare invertebrates were identified by NCNHP, including helicta satyr (Neonympha helicta) and
coppery emerald (Somatochlora georgiana). Surveys for these species were not requested; however,
implementation of the FERC Plan & Procedures and the Project's Invasive Species Control Plan will
minimize impacts to these species.
Five federally listed aquatic species were identified during consultation and review of the NCNHP database,
including the endangered Roanoke logperch (Percina rex), Cape Fear shiner (Notropis mekistocholas), and
James spinymussel (Parvaspina collina) and the threatened yellow lance (Elliptio lanceolata). On October
11, 2018 the Atlantic pigtoe (Fusconaia masoni) was listed as threatened with a 4(d) designation. In
addition, critical habitat for the Atlantic pigtoe was proposed in the Dan River drainage; however, the
Project does not cross the proposed critical habitat.
5.5.4 Aquatic Species
Five state listed species were identified, including four state endangered freshwater mussels: yellow
lampmussel (Lampsilis cariosa), green floater (Lasmigona subviridis), Carolina creekshell (Villosa
vaughaniana), Savannah lilliput (Toxolasma pullus); and one state threatened freshwater mussel: eastern
lampmussel (Lampsilis radiata). Four special concern species include the notched rainbow (Villosa
constricta), Greensboro burrowing crayfish (Cambarus catagius), mole salamander (Ambystoma
talpoideum), and four -toed salamander (Hemidactylium scutatum). Three state rare species include:
riverweed darter (Etheostoma podostemone), eastern creekshell (Villosa delumbi), and Carolina ladle
crayfish (Cambarus davidi).
Early coordination with USFWS and NCWRC identified three waterbodies known or likely to harbor
Roanoke logperch and rare mussel species, including the Dan River, Cascade Creek, and Wolf Island Creek.
The Project is proposing to use HDD or conventional bore methods to cross these waterbodies to avoid
instream impacts on federal and state listed fish and mussel species. During consultation, NCWRC also
requested HDD or conventional bore of Deep Creek to avoid impacts on eastern lampmussel. The Project
is proposing to use of HDD or conventional bore at the Deep Creek crossing.
NCWRC requested surveys for mussel streams and identified 17 streams (21 crossings) for survey.
NCWRC and USFWS reviewed the Project's mussel study plan and provided comments on September 20,
2018. Surveys were authorized to commence as soon as possible; however, surveys were cancelled for the
fall 2018 due to hurricane Florence and restricted access to survey sites. Freshwater mussel surveys are
scheduled for April -May 2019, and results of these surveys will be submitted to USFWS and NCWRC for
review and comment.
The Project will implement and strictly adhere to applicable federal and state erosion and sediment
control/storm water management laws and regulations. If live native freshwater species are observed during
surveys, mussels will be relocated prior to construction in coordination with NCWRC. If federal species
are observed during survey, the Project will notify USFWS and evaluate appropriate avoidance and
minimization measures. Measures taken to avoid and minimize impacts on federal listed species also benefit
state species and unlisted species. The Project is committed to working with the agencies to determine
applicable avoidance, minimization or mitigation strategies to minimize impacts to these species.
5-7 November 2018
M Mountain Valley Joint Permit Application
'T PIPELINE USACE —Wilmington District and NCDEQ
SAW -2018-008887
NCWRC requested surveys for the Greensboro burrowing crayfish within 200 feet of any mapped stream,
both intermittent and perennial in the Haw River basin; and requested surveys for Carolina ladle crayfish
in all first to third order streams in the Dan and Haw river basins. The Project is evaluating potential habitats
and continues to coordinate with NCWRC. Implementation of the FERC Plan & Procedures and strict
adherence to applicable federal and state erosion and sediment control/storm water management laws and
regulations will minimize impacts to these species.
NWCRC requested a desktop habitat evaluation of potential habitats of the four -toed and mole salamanders.
The Project is evaluating potential habitats and continues to coordinate with NCWRC. Implementation of
the FERC Plan & Procedures and strict adherence to applicable federal and state erosion and sediment
control/storm water management laws and regulations will minimize impacts to these species, including
abiding by applicable time of year construction restrictions.
5.5.5 Plant Species
Consultation identified two federally endangered plants, including small whorled pogonia (Isotria
medeoloides) and smooth coneflower (Echinacea laevigata). A study plan was submitted to USFWS and
NCWRC on July 17, 2018, and concurrence was received from USFWS on August 21. A desktop
assessment identified 261 acres of potential habitat of federal listed plants along the Project. Small whorled
pogonia is best surveyed May -July when in flower; smooth coneflower can be surveyed between June -
October. Surveys were conducted between July and September 2018.No individuals of the target species
were observed; but several small whorled pogonia potential habitats were flagged for re -survey in summer
2019. Due to limited access, surveys in 2018 ended before all potential habitats could be completed.
Approximately 47.5 acres of potential small whorled pogonia habitat and 25 acres of potential smooth
coneflower habitat are planned for survey in summer 2019. Upon completion of 2019 field surveys, results
will be submitted to USFWS and NCWRC for review and comment and filed with FERC. If listed species
are identified, the Project will develop a relocation plan in coordination with USFWS Raleigh Field Office
and NCWRC. The final plan will be submitted to USFWS and NCWRC for review and approval. The
Project is committed to working with the agencies to determine applicable avoidance, minimization or
mitigation strategies to minimize impacts to these species.
One additional plant, the state rare cliff stonecrop (Sedum glaucophyllum), was identified during review of
the NCNHP database. Surveys for this species were not requested; however, implementation of the FERC
Plan & Procedures and the Project's Invasive Species Plan will minimize impacts to this species should it
be encountered during construction.
5.5.6 Conclusions
The Project will provide Section 7 clearance as soon as it is obtained.
5-8 November 2018
M Mountain Valley
Ir PIPELINE
5.6 ESSENTIAL FISH HABITAT
Joint Permit Application
USACE — Wilmington District and NCDEQ
SAW -2018-008887
According to the NMFS online Essential Fish Habitat Mapper tool (NMFS, 2017), the Project does not
cross any waterbodies identified as Essential Fish Habitat. Because the Project is located well inland of
saltwater and tidal waters and does not cross known anadromous or diadromous fish migration routes, none
of the waterbodies crossed by the Project contain, or have the potential to support, species managed by the
NMFS.
5.7 CULTURAL RESOURCES INFORMATION
MVP Southgate is currently conducting archaeological surveys of the direct area of potential effect for
Project facilities, including the pipeline corridor and all ancillary facilities such as access roads, contractor
yards, and ATWS. As of September 20, 2018, archaeological survey has been completed for approximately
77.4 percent of the pipeline route. Survey for aboveground historic resources is also being conducted, and
as of September 20, 2018 has been completed for an estimated 90.0 percent of the pipeline route. Detailed
reports on cultural resource surveys were submitted to the North Carolina State Historic Preservation
Office, applicable federally -recognized tribes as requested and the FERC along with the FERC Certificate
Application. The Project is currently assessing avoidance or assessment options for those properties that
may be eligible for the National Register of Historic Places and will develop treatment plans for any such
properties that may be affected by the Project. If necessary, the FERC will develop a Programmatic
Agreement (PA) to provide a process for completing surveys on no access properties and implementation
of the treatment plans, if any. A draft unanticipated cultural resources discovery plan is included in
Appendix P. The Project will provide Section 106 concurrence once it is obtained.
5.8 FLOOD ZONE DESIGNATION
The Southgate Project has reviewed Federal Emergency Management Agency ("FEMA") Flood Insurance
Rate Mapping for areas crossed by the Project and recorded the location of 100 -year flood zones (FEMA,
2018). A summary of 100 -year flood zones crossed by the Project is listed below in Table 5-2, and shown
in the FEMA Figure set in Appendix Q. There are four permanent access roads and two interconnects
located within the FEMA 100 -year flood zone. Temporary access roads located within floodplains may
have a temporary effect on flood storage but will be restored after construction unless requested to be
maintained by the landowner or agency. All applicable floodplain permits will be obtained from the relevant
issuing authorities.
5-9 November 2018
M Mountain Valley
Ir PIPELINE
Joint Permit Application
USACE - Wilmington District and NCDEQ
SAW -2018-008887
5-10 November 2018
Table 5-2
100 -Year Floodplain areas crossed
State/County
Flood Zone a/
Entry Mile Post
Exit Mile Post
Length Crossed (feet)
North Carolina
Rockingham
AE
27.1
27.8
3,665
AE
27.8
27.8
32
AE
27.9
28.0
668
AE
28.0
28.1
97
AE
28.3
28.4
204
AE
29.6
29.6
22
AE
29.6
30.5
4,741
AE
30.5
30.6
315
AE
30.7
30.7
150
AE
30.7
30.9
941
AE
32.1
32.2
37
AE
32.2
32.2
196
AE
32.2
32.2
10
AE
32.6
32.7
526
AE
33.0
33.1
470
AE
33.1
33.1
32
AE
38.6
38.8
886
AE
41.1
41.2
320
AE
43.2
43.3
551
AE
46.4
46.5
88
AE
46.9
47.0
341
AE
48.6
48.7
353
AE
50.8
50.8
95
AE
27.1
27.8
3,665
AE
27.8
27.8
32
Alamance
AE
53.6
53.7
198
AE
54.6
54.6
125
AE
56.4
56.4
26
AE
56.6
56.6
281
AE
57.0
57.0
304
AE
57.9
57.9
8
AE
58.6
58.7
322
AE
60.7
60.7
76
AE
60.7
60.8
47
AE
63.6
63.6
350
AE
63.6
63.6
4
AE
63.8
63.9
100
AE
64.0
64.0
377
AE
65.6
65.6
115
AE
67.6
67.6
153
AE
69.1
69.1
222
AE
69.1
69.3
894
5-10 November 2018
M Mountain Valley
Joint Permit Application
USACE —Wilmington District and NCDEQ
SAW -2018-008887
5-11 November 2018
Table 5-2
100 -Year Floodplain areas crossed
State/County
Flood Zone a/
Entry Mile Post Exit Mile Post
Length Crossed (feet)
AE
70.2 70.3
320
AE
70.7 70.8
254
AE
70.9 70.9
253
AE
70.9 71.0
115
AE
71.3 71.3
328
AE
71.3 71.8
2,536
AE
72.5 72.7
1,279
AE
72.9 73.1
832
AE
69.1 69.3
894
AE
70.2 70.3
320
a/ Flood Zone A — Areas subject to inundation by the 1 -percent annual chance flood event determined using
approximate methodologies.
Flood Zone AE —Areas subject to inundation by the 1 -percent annual chance flood event determined by detailed
methods.
5-11 November 2018
M Mountain Valley Joint Permit Application
PIPELINE USACE — Wilmington District and NCDEQ
SAW -2018-008887
6.0 REFERENCES
Cowardin, L.M., V. Carter V., F.C. Golet, E.T. LaRoe. 1979. Classification of Wetlands and Deepwater
Habitats of the United States. U.S. Fish and Wildlife Service Report No. FWS/OBS/-
79/3 LWashington, D.C.
Environmental Laboratory. 1987. "Corps of Engineers Wetlands Delineation Manual," Technical Report
Y-87-1, U.S. Army Engineer Waterways Experiment Station, Vicksburg, Miss.
Federal Emergency Management Agency (FEMA). 2018. Flood Map Service Center. Available online at:
http://msc.fema.goy/portal. Accessed July 2018.
Federal Energy Regulatory Commission (FERC) 2013. Upland Erosion Control, Revegetation, and
Maintenance Plan. Available online at: http://www.ferc.gov/industries/gas/enviro/2lan.pdf. Accessed
August 2, 2018.
Federal Energy Regulatory Commission (FERC) 2013. Wetland and Waterbody Construction and
Mitigation Procedures. Available online
at: http://www.ferc.gov/industries/gas/enviro/procedures.pdf. Accessed August 2, 2018.
Federal Energy Regulatory Commission (FERC). 2013. Upland Erosion Control, Revegetation and
Maintenance Plan. May 2013.
Federal Energy Regulatory Commission (FERC). 2013. Wetland and Waterbody Construction and
Mitigation Procedures. May 2013.
Federal Energy Regulatory Commission (FERC). 2017. Guidance Manual for Environmental Report
Preparation. February.
Gulf Interstate Engineering. 1999. Temporary Right -of -Way Width Requirements for Pipeline
Construction. Prepared for the INGAA Foundation, Inc. Available online at:
hqp://www.in ag armor File.aspx?id=19105.
National Wild and Scenic Rivers System. 2018. Explore Designated Rivers. Available online at:
http://www.rivers. og v/map.php. Accessed July 2018.
NCWRC. 2018. Response to project review request on the MVP Southgate Project. Letter dated August
10, 2018, addressed to Ms. Megan Stahl of EQT, from Mr. Vann Stancil, of NCWRC.
North Carolina Department of Environment and Natural Resources, Division of Environmental Health
(NCDENR). 1999. Source Water Assessment Program Plan. Available online at:
https://files.nc.gov/ncdeq/Water%20Resources/files/swap/FullText.pdf. Accessed Jules
North Carolina Department of Environmental Quality (NC DEQ). 2018. Reidsville Energy Center Permit
#NC0089699. https://deq.nc.gov/reidsville-energy-center-permit-nc0089699. Accessed October 3,
2018.
North Carolina Division of Environmental Quality (NCDEQ). 2018b. Digital information regarding
watersheds. Available online at: http://data-ncdenr.opendata.arc isg com/. Accessed July 2018.
6-1 November 2018
M Mountain Valley Joint Permit Application
PIPELINE USACE — Wilmington District and NCDEQ
SAW -2018-008887
North Carolina Division of Environmental Quality (NCDEQ). 2018d. Surface Water Classifications.
Available online at: https://deq.nc.gov/about/divisions/water-resources/planning/classification-
standards/classifications#DWRPrimaryClassification. Accessed July 2018.
North Carolina Division of Water Resources (NCDWR). 2018. Jordan lake Nutrient Strategy. Available
online at: https:Hdeq.nc.gov/about/divisions/water-resources/water-plannin nonpoint-source-
planning/jordan-lake-nutrient. Accessed August 2018.
North Carolina Wildlife Resources Commission (NCWRC). 2018. Trout Fishing Maps. Available online
at: http://ncwildlife.org/Fishing/Trout-Fishing-Mqps. Accessed July 2018.
NSF International. 2018. NSF / ANSI 60. Available online at: http://www.nsf.org/services/by-
industry/water-wastewater/water-treatment-chemicals/nsf-ansi-standard-60. Accessed October 2018.
Town of Chapel Hill (TCH). 2018. Jordan Lake Watershed. Available online at:
http://www.townofchgpelhill.orfz/town-hall/departments-services/public-works/stormwater-
management/local-watersheds-water-qualiiy/jordan-lake-watershed. Accessed August 2018.
U.S. Army Corps of Engineers (USACE). 2012. Regional Supplement to the Corps of Engineers Wetland
Delineation Manual: Eastern Mountains and Piedmont Region Version 2.0, ed. J. F. Berkowitz, J. S.
Wakeley, R. W. Lichvar, C. V. Noble. ERDC/EL TR -12-9. Vicksburg, MS: U.S. Army Engineer
Research and Development Center.
U.S. Energy Information Agency (EIA). 2017a. State Profile and Energy Estimates — Virginia. Available
online at: https://www.eia.gov/state/analysis.php?sid=VA Accessed June 3, 2018.
U.S. Energy Information Agency (EIA). 2017b. State Profile and Energy Estimates — North Carolina.
Available online at: https://www.eia.gov/state/analysis.php?sid=NC. Accessed June 3, 2018.
U.S. Fish and Wildlife Service (USFWS). 2009. National Wetlands Inventory website. U.S. Department of
the Interior, Fish and Wildlife Service, Washington, D.C. Available online at:
http://www.fws.gov/wetlands/. Accessed July 2018.
U.S. Fish and Wildlife Service (USFWS). 2018. Critical Habitat Portal. Available online at:
http://ecos.fws.gov/crithab/flex/crithabMapper. Accessed July 2018.
U.S. Fish and Wildlife Service (USFWS). 2018b. Endangered and Threatened Species and Species of
Concern by County for North Carolina. Available online at:
https://www.fws.gov/raleigh/species/cptylist/nc_counties.html Accessed on July 31, 2018.
U.S. Geological Survey (USGS). 2018b. National Hydrography Dataset (NHD). Available online at:
http://nhd.usgs.%zov/data.html. Accessed July 2018.
USFWS. 2007. National Bald Eagle Management Guidelines. Available online at
https://www.fws.gov/northeast/ecological
services/pdf/NationalBaldEagleManagementGuidelines.pdf.
USFWS. 2016. Final rule: Endangered and threatened wildlife and plants: 4(d) Rule for the northern long-
eared bat. Pages 1900-1922 in Federal Register Volume 81, No. 9. U.S. Department of Interior, Fish
and Wildlife Service.
6-2 November 2018
M Mountain Valley
Joint Permit Application
USACE —Wilmington District and NCDEQ
SAW -2018-008887
USFWS. 2018. Range -wide Indiana bat survey guidelines - April 2018. U.S. Department of the Interior,
Fish and Wildlife Service. 61 pp.
6-3 November 2018