HomeMy WebLinkAboutMulti ID#'s_Updated Interim Action Plan Schedules Approval Letter_20160930Enclosure 1 1 Asheville Steam Electric Plant Interim Action Plan Schedule Update to DEQ September 30, 2016  Pump Test Completion October 14, 2016  30% Design Complete November 21, 2016 (incorporate majority of Basis of Design Report components)  NPDES Permit Anticipated February 28, 2017  Issuance for Final Construction April 3, 2017 (incorporate remainder of Basis of Design Report components)  Begin Extraction Well and Treatment System Construction May 15, 2017  Extraction Well and Treatment System Begin Operation July 18, 2017 Note: Asheville Steam Electric Plant has options after treatment of extracted groundwater; NPDES discharge at permitted outfall or discharge to sanitary sewer system. Both options in close proximity to the area of groundwater extraction. Enclosure 1 2 Belews Creek Steam Station Interim Action Plan Schedule Update to DEQ September 30, 2016  Pump Test Completion October 14, 2016  30% Design Complete January 2, 2017 (incorporate majority of Basis of Design Report components)  NPDES Permit Anticipated January 31, 2017  Issuance for Final Construction May 25, 2017 (incorporate remainder of Basis of Design Report components)  Begin Extraction Well and Treatment System Construction July 6, 2017  Extraction Well and Treatment System Begin Operation September 20, 2017 Note: Belews Creek Steam Station only option after treatment of extracted groundwater is to discharge at a NPDES permitted outfall. Permitted outfall is not in close proximity to the area of groundwater extraction. Enclosure 1 3 H.F. Lee Energy Complex Interim Action Plan Schedule Update to DEQ September 30, 2016  Pump Test Completion October 14, 2016  30% Design Complete November 28, 2016 (incorporate majority of Basis of Design Report components)  NPDES Permit Anticipated January 31, 2017  Issuance for Final Construction April 24, 2017 (incorporate remainder of Basis of Design Report components)  Begin Extraction Well and Treatment System Construction June 5, 2017  Extraction Well and Treatment System Begin Operation August 14, 2017 Note: H.F. Lee Energy Complex only option after treatment of extracted groundwater is to discharge at a NPDES permitted outfall. Area to construct treatment system is limited with wetlands surrounding ash basin. Wetlands permitting could significantly impact schedule shown. Enclosure 1 4 L.V. Sutton Energy Complex Interim Action Plan Schedule Update to DEQ September 30, 2016  90% Design Complete October 17, 2016 (incorporate majority of Basis of Design Report components)  Issuance for Final Construction November 21, 2016 (incorporate remainder of Basis of Design Report components)  Begin Extraction Well and Treatment System Construction January 9, 2017  Extraction Well and Treatment System Begin Operation May 5, 2017 Note: L.V. Sutton Energy Complex NPDES permit already includes discharge from treatment of extracted groundwater via NPDES permitted outfall 001.