Asheville Steam Electric Plant
Interim Action Plan Schedule Update to DEQ
September 30, 2016
Pump Test Completion October 14, 2016
30% Design Complete November 21, 2016
(incorporate majority of Basis of Design Report components)
NPDES Permit Anticipated February 28, 2017
Issuance for Final Construction April 3, 2017
(incorporate remainder of Basis of Design Report components)
Begin Extraction Well and Treatment System Construction May 15, 2017
Extraction Well and Treatment System Begin Operation July 18, 2017
Note: Asheville Steam Electric Plant has options after treatment of extracted groundwater; NPDES discharge at permitted
outfall or discharge to sanitary sewer system. Both options in close proximity to the area of groundwater extraction.
Enclosure 1
2
Belews Creek Steam Station
Interim Action Plan Schedule Update to DEQ
September 30, 2016
Pump Test Completion October 14, 2016
30% Design Complete January 2, 2017
(incorporate majority of Basis of Design Report components)
NPDES Permit Anticipated January 31, 2017
Issuance for Final Construction May 25, 2017
(incorporate remainder of Basis of Design Report components)
Begin Extraction Well and Treatment System Construction July 6, 2017
Extraction Well and Treatment System Begin Operation September 20, 2017
Note: Belews Creek Steam Station only option after treatment of extracted groundwater is to discharge at a NPDES permitted
outfall. Permitted outfall is not in close proximity to the area of groundwater extraction.
Enclosure 1
3
H.F. Lee Energy Complex
Interim Action Plan Schedule Update to DEQ
September 30, 2016
Pump Test Completion October 14, 2016
30% Design Complete November 28, 2016
(incorporate majority of Basis of Design Report components)
NPDES Permit Anticipated January 31, 2017
Issuance for Final Construction April 24, 2017
(incorporate remainder of Basis of Design Report components)
Begin Extraction Well and Treatment System Construction June 5, 2017
Extraction Well and Treatment System Begin Operation August 14, 2017
Note: H.F. Lee Energy Complex only option after treatment of extracted groundwater is to discharge at a NPDES permitted
outfall. Area to construct treatment system is limited with wetlands surrounding ash basin. Wetlands permitting could
significantly impact schedule shown.
Enclosure 1
4
L.V. Sutton Energy Complex
Interim Action Plan Schedule Update to DEQ
September 30, 2016
90% Design Complete October 17, 2016
(incorporate majority of Basis of Design Report components)
Issuance for Final Construction November 21, 2016
(incorporate remainder of Basis of Design Report components)
Begin Extraction Well and Treatment System Construction January 9, 2017
Extraction Well and Treatment System Begin Operation May 5, 2017
Note: L.V. Sutton Energy Complex NPDES permit already includes discharge from treatment of extracted groundwater via
NPDES permitted outfall 001.