HomeMy WebLinkAboutMulti ID#'s_DE Letter to DEQ Sept 2016 Updated IAP Schedules_20160930DUKE ENERGY® September 30, 2016 Mr. S. Jay Zimmerman, P.G. Director, Division of Water Resources North Carolina Department of Environmental Quality 1611 Mail Service Center Raleigh, NC 27699-1611 RE: Interim Action Plan Schedule Update for Asheville Steam H.F. Lee Energy Complex and L.V. Sutton Energy Complex Dear Mr. Zimmerman: Plant, Belews Creek Steam Station, Duke Energy, along with our consultants, and Department of Envi nmental Quality (DEQ) staff discussed the Interim Action Plans for the above -referenced facilities during a meeting at the Archdale Building on August 24, 2016. A letter summarizing this meeting was submitted to you on September 9, 2016. During that meeting, Duke Energy stated an updated schedule would be provided for each of these four facilities. Enclosed are those updated schedules. As Duke Energy stated during the August meeting, only Sutto required startup of March 31, 2017. This is because Suttor discharge requirements from the proposed extraction system. recently submitted an NPDES permit modification which includ and Asheville is not expected to make this submittal until the ei permit has been received, a treatment system can not be desigr Duke Energy will request an extension beyond March 31, 2017 d have a better idea at that time of the length of extension require If you have any questions or need any clarification regarding me at iohn.toegfer@duke-enerev.com or at 919-546-7863 at Respectfully submitte 0-;7 John R. Toepfer, P.E. Lead Engineer cc/enc: Mr. Bill Miller — HDR Ms. Kathy Webb — SynTerra Mr. James McNash - Geosyntec Mr. Ryan Czop—Duke Energy Ms. Kim Witt — Duke Energy Mr. Ed Sullivan — Duke Energy had the possibility to meet the DEQ NPDES permit already contains the wo of the other three facilities only discharge from an extraction system of October. Until an updated NPDES I as the discharge limits are unknown. ing February 2017 as Duke Energy will information provided, please contact convenience. Enclosure 1 Asheville Steam Electric Plant Interim Action Plan Schedule Update to DEQ September 30, 2016 Pump Test Completion 30% Design Complete (incorporate majority of Basis of Design Report components) NPDES Permit Anticipated Issuance for Final Construction (incorporate remainder of Basis of Design Report components) Begin Extraction Well and Treatment System Construction Extraction Well and Treatment System Begin Operation October 14, 2016 November 21, 2016 February 28, 2017 April 3, 2017 May 15, 2017 July 18, 2017 Note: Asheville Steam Electric Plant has options after treatment of extracted groundwater; NPDES discharge at permitted outfall or discharge to sanitary sewer system. Both options in close proximity to the area of groundwater extraction. Enclosure 1 Belews Creek Steam Station Interim Action Plan Schedule Update to DEQ September 30, 2016 Pump Test Completion 30% Design Complete (incorporate majority of Basis of Design Report components) NPDES Permit Anticipated Issuance for Final Construction (incorporate remainder of Basis of Design Report components) Begin Extraction Well and Treatment System Construction Extraction Well and Treatment System Begin Operation October 14, 2016 January 2, 2017 January 31, 2017 May 25, 2017 July 6, 2017 September 20, 2017 Note: Belews Creek Steam Station only option after treatment of extracted groundwater is to discharge at a NPDES permitted outfall. Permitted outfall is not in close proximity to the area of groundwater extraction. 2 Enclosure 1 H.F. Lee Energy Complex Interim Action Plan Schedule Update to DEQ September 30, 2016 Pump Test Completion 30% Design Complete (incorporate majority of Basis of Design Report components) NPDES Permit Anticipated Issuance for Final Construction (incorporate remainder of Basis of Design Report components) Begin Extraction Well and Treatment System Construction Extraction Well and Treatment System Begin Operation October 14, 2016 November 28, 2016 January 31, 2017 April 24, 2017 June 5, 2017 August 14, 2017 Note: H.F. Lee Energy Complex only option after treatment of extracted groundwater is to discharge at a NPDES permitted outfall. Area to construct treatment system is limited with wetlands surrounding ash basin. Wetlands permitting could significantly impact schedule shown. 3 Enclosure 1 L.V. Sutton Energy Complex Interim Action Plan Schedule Update to DEQ September 30, 2016 90% Design Complete (incorporate majority of Basis of Design Report components) Issuance for Final Construction (incorporate remainder of Basis of Design Report components) Begin Extraction Well and Treatment System Construction Extraction Well and Treatment System Begin Operation October 17, 2016 November 21, 2016 January 9, 2017 May 5, 2017 Note: L.V. Sutton Energy Complex NPDES permit already includes discharge from treatment of extracted groundwater via NPDES permitted outfall 001. 4