HomeMy WebLinkAbout19980260 Ver 6_R-2247EB sediment losses_20210818
Wanucha, Dave
From:Euliss, Amy
Sent:Wednesday, August 18, 2021 3:58 PM
To:Wanucha, Dave
Cc:Marciniak, Katherine J; Suggs, Phillip H; Jones, Scott A; Swicegood, Dale L; Librandi,
Nicholas C
Subject:R-2247EB sediment losses
We had 6 sediment losses on R-2247EB following rains received between Thursday and this morning. We still have one
culvert underwater and will let you know if there is anything to report when it subsides. The losses are as follows:
Site 9A-III had a loss due to a sliding of the slope and overwhelming the SDO approximately 9 CY
Site 10A-VV had a silt loss due to an SDO failure approximately 20 5 gal buckets.
Site 10B-VV had a silt loss due to failure of inlet protection around a box approximately 2 CY.
Site 13A-DDD had a silt loss due to an SDO failure approximately 20 5 gal buckets.
Site 15B-XX had a silt loss due to SDO failures approximately 1 CY.
Site 15G-XX had a silt loss due to SDO failures approximately 2 CY.
Our apologies for the delay in the inspections. Our prime contractor did not complete the NPDES inspections in the
required time. DOT began the inspection yesterday, and DOT and the prime contractor’s representatives completed the
NPDES inspections today. Our Resident Engineer’s office has shut down the prime contractor’s operations and any
subcontractor operations that disturb the ground until the repairs on the list are completed within the appropriate time
frames. The prime contractor began working on the erosion control measures today. Let me know if you have
questions or need additional information.
Amy Euliss
Division 9 PDEA Engineer
North Carolina Department of Transportation
336 747 7802 office
aeuliss@ncdot.gov
375 Silas Creek Parkway
Winston Salem, NC 27127-7167
Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third parties.
1