HomeMy WebLinkAbout19980260 Ver 6_Re_ U-2579DEF lime spill_Pics_20210701
Wanucha, Dave
From:Euliss, Amy
Sent:Wednesday, June 30, 2021 4:27 PM
To:Wanucha, Dave
Cc:Kiser, Marcus K; Suggs, Phillip H; McLaughlin, Zachery R; Wyrick, Scott D; Tucker,
Mezak
Subject:Re: U-2579DEF lime spill_Pics
I am not sure what happened before. It should be attached correctly this time. The limits of the staining are about a
100’ downstream of the project. We will still plan to install the wattles and take the pH samples.
1
2
Get Outlook for iOS
From: Euliss, Amy <aeuliss@ncdot.gov>
Sent: Wednesday, June 30, 2021 4:21:44 PM
To: Wanucha, Dave <dave.wanucha@ncdenr.gov>
Cc: Kiser, Marcus K <mkkiser@ncdot.gov>; Suggs, Phillip H <psuggs@ncdot.gov>; McLaughlin, Zachery R
<zrmclaughlin@ncdot.gov>; Wyrick, Scott D <sdwyrick@ncdot.gov>; Tucker, Mezak <mtucker@ncdot.gov>
Subject: Re: U-2579DEF lime spill
The
linke
d
imag
e
cann
ot …
I left this photo off of the previous email. My apologies.
Get Outlook for iOS
From: Euliss, Amy
Sent: Wednesday, June 30, 2021 4:14:49 PM
To: Wanucha, Dave <dave.wanucha@ncdenr.gov>
Cc: Kiser, Marcus K <mkkiser@ncdot.gov>; Suggs, Phillip H <psuggs@ncdot.gov>; McLaughlin, Zachery R
<zrmclaughlin@ncdot.gov>; Wyrick, Scott D <sdwyrick@ncdot.gov>; Tucker, Mezak <mtucker@ncdot.gov>
Subject: U-2579DEF lime spill
Good afternoon, Dave. We are currently doing chemical stabilization of the grade on the U-2579DEF project. Our
inspectors discovered a lime slurry spill this afternoon on the grade. We are currently trying to determine what
happened. The lime solution went down the slope and into a basin. There is evidence of slurry in the stream. I have
attached some pictures showing the lime slurry on the grade, in the basin, a film shown in the stream, and clean up
measures underway. DOT has directed Flatiron to cleanup the slurry from the grade, basin, etc. We have instructed
them to obtain pH samples upstream, and downstream at 100’ intervals to determine if the lime had an impact on the
pH of the waters. We have also directed them to install a series of wattles in the stream to the limits of the staining,
and collect any accumulated solids/slurry from the behind the wattles and anywhere along the stream that it has
deposited. We’ll keep you up to date when we receive additional information. Note this is permit site 6 (basin 10.5) on
the project. Let me know if you would like us to do anything additional. Thanks in advance.
Amy Euliss
Division 9 PDEA Engineer
North Carolina Department of Transportation
336 747 7802 office
aeuliss@ncdot.gov
375 Silas Creek Parkway
Winston Salem, NC 27127-7167
Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third parties.