Wanucha, Dave
From:Wanucha, Dave
Sent:Friday, January 8, 2021 10:49 AM
To:Euliss, Amy; Alsmeyer, Eric C CIV USARMY CESAW (USA)
Cc:Miller, Vickie M (Vickie.Miller@hdrinc.com); Kiser, Marcus K; Wyrick, Scott D;
McLaughlin, Zachery R
Subject:RE: \[External\] U-2579DEF - Permit Site 20_DWR approval
Hi Amy,
Barring any concerns/objections of the proposed changes by the Corps, DWR will allow the temporary crossing
as described since the proposed work is within the permitted construction right-of-way. If you do proceed,
please ensure that field crews follow all approved BMP measures as outlined in NCDOT’s Construction and
Maintenance Activities manual and other 401 Certification conditions.
Thanks for the notification of proposed changes.
Dave W.
Division of Water Resources
401 & Buffer Transportation Permitting
NC Department of Environmental Quality
336-776-9703 office
336-403-5655 mobile
Dave.Wanucha@ncdenr.gov
NC DEQ Winston Salem Regional Office
450 West Hanes Mill Road, Suite 300
Winston Salem, NC 27106
Based on the current guidance to minimize the spread of COVID-19, the Department of Environmental Quality has
adjusted operations to protect the health and safety of the staff and public. Many employees are working remotely or
are on staggered shifts. To accommodate these staffing changes, all DEQ office locations are limiting public access to
appointments only. Please check with the appropriate staff before visiting our offices, as we may be able to handle your
requests by phone or email. We appreciate your patience as we continue to serve the public during this challenging
time.
From: Euliss, Amy <aeuliss@ncdot.gov>
Sent: Friday, January 8, 2021 8:13 AM
To: Alsmeyer, Eric C CIV USARMY CESAW (USA) <Eric.C.Alsmeyer@usace.army.mil>; Wanucha, Dave
<dave.wanucha@ncdenr.gov>
Cc: Miller, Vickie M (Vickie.Miller@hdrinc.com) <Vickie.Miller@hdrinc.com>; Kiser, Marcus K <mkkiser@ncdot.gov>;
Wyrick, Scott D <sdwyrick@ncdot.gov>; McLaughlin, Zachery R <zrmclaughlin@ncdot.gov>
Subject: FW: \[External\] U-2579DEF - Permit Site 20 (Mill Creek)
Dave and Eric,
1
Below is an email from Vickie Miller with HDR. They are the Design team on the U-2579DEF project. The contractor
needs to install a temporary crossing to bring a crane to the site. After your review, let me know if you do or do not
have any objections to us proceeding. We no longer need to do the previously permitted work pad (site 20C-165’), but
instead need 60’ of temporary impacts at the same site but at a different location on the stream. The pdf labelled “RW-
21_L-STA+50 Rev.3 markup” is shows the location of the proposed site, and the pdf labelled “Site 20 Permit Sheet
U2579DEF” shows the site as it was permitted.
Give me a call if we need to discuss.
Amy
336-671-2886
From: Miller, Vickie M. (Raleigh) <Vickie.Miller@hdrinc.com>
Sent: Thursday, January 7, 2021 6:39 PM
To: Euliss, Amy <aeuliss@ncdot.gov>
Cc: Yelverton, Wyatt <Wyatt.Yelverton@hdrinc.com>
Subject: \[External\] U-2579DEF - Permit Site 20 (Mill Creek)
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to
Report Spam.
Hi Amy,
I have attached the permit plan sheet, the summary impact table, and a marked up sheet of the location that Flatiron
would like to put a temporary crossing at Mill Creek. You will notice they are not showing the need for a temporary
workpad in the channel but instead a 60’ long pipe in Mill Creek for a crossing to move cranes, etc. The original
permitted length of impact for the temporary work pad (Site 20C) was 165 ft. This would be less impact from that
standpoint. The proposed location for the temporary pipe is in an area where we will have impacts from a ditch tie in
(Site 20A). Site 20 A currently is permitted for 16 lf of permanent impact and 21 lf of temporary impact. We would need
to increase the temporary impact by approximately 44 lf to cover the length requested as well as making sure we have
temporary impacts for dewatering/installation of the pipe (assumed 10 ft downstream and the 11 ft upstream which
was previously permitted).
Please let me know if you have any questions or comments. Thank you for checking on what will be needed for this one.
Thanks,
Vickie