Loading...
HomeMy WebLinkAbout20110136 Ver 1_Information Letter_20100914 North Carolina Department of Transportation Project Development and Environmental Analysis Branch of JAoRT11 ?q CIO 7 m o 0 OF TR Pinehurst, Moore County Widen NC 211 From NC 73 in West End to the traffic circle in Pinehurst TIP PROJECT R-2812 September 14, 2010 Purpose of Meeting The purpose of the meeting is to review and obtain project team concurrence on a proposed alignment shift along TIP project R-2812. The project begins at NC 73 in West End and terminates at the traffic circle in Pinehurst located in Moore County. The length of the proposed project is 7.2 miles. (see Figure 1) Project History The Environmental Assessment (EA) and Finding of No Significant Impact (FONSI ) were completed in October 2005 and August 2006, respectively. Concurrence Point 1 was achieved on August 9, 2001. The purpose of the project is to upgrade NC 211 in order to safely and efficiently accommodate existing and projected traffic volumes.... Concurrence Point 2 was achieved on April 11. 2002. The alternatives carried forward for detailed study were "Best-Fit" Alternative with curb and gutter and "Best-Fit" Alternative with grass shoulder section. Concurrence Points 3 and 4a were achieved on October 26, 2006. The selected LEDPA was the "Best-Fit" Alignment with a combination of Alternative 1 and Alternative 2. A 4B meeting was held on March 12; 2008, and a 4C meeting was held on February 25, 2009. Copies of the signed concurrence forms are located in Appendix D. While preparing the Right of Way plans for the project, NCDOT discovered that an apartment building would be impacted resulting in eight families being relocated at a cost of $1,725,000, not including utilities. Moreover, NCDOT discovered a cost savings of 5150,000 by shifting the alignment to minimize impacts to utilities. The Department has now revised preliminary plans to reflect an alignment shift which would avoid these impacts. The permit drawings displaying the alignment shift is now presented for the project team review. Proposed Alignment Shift In order to minimize impacts to an apartment building and utilities, NCDOT proposes shifting the alignment south between stations -L- 39 + 05.52 and -L- 133 + 16.02,-L- 253 + 34.50 and -L- 317 + 10.00, respectively. The permit drawings and impact tables are located in Appendix A. Environmental Impacts Table 1. Preliminary Hydraulic Design for Stream Crossing of US 21 ?T E' i 4 F. _ AY?(.Zit 'e're4?irr ] -L- 245+95 UT to Joe's Fork 0.5 Sq Mi Remove extension and retain and extend existing RCBC 2 -L- 278+75 Joe's Fork 1.2 Sq Mi Replace with RCBC 3 -L- 340+60 Board Branch 368 Ac 60" RCP nl.nl nemtorcea Concrete box l:ulven RCP Reinforced Concrete Pipe I These clusters did not meet pre-project SMS requirements for the 0.25 mile radius foraging partition. SMS foraging habitat analyses results fro the 0.5 mile radius partition follow. A MOOR 35: The pre-project SMS foraging habitat totals were 1,999.49 sq. ft. of pine BA on 31.56 acres of suitable habitat, 13,489.81 sq. ft of pine BA on 141.56 acres of potentially suitable habitat and 2,022.59 sq. ft. of pine BA on 69.86 acres of future potential habitat. Road improvements will remove 31.14 sq. ft. of pine BA on 0.57 acre of suitable habitat, 366.61 sq. ft. pine BA on 4.52 acres of potentially suitable habitat and 103.10 sq. ft. of pine BA on 3.58 aces of future potential habitat. The post-project SMS foraging habitat totals were 1;968.35 sq. ft. of pine BA on 30.99 acres of suitable habitat; 13,123.21 sq. ft. of pine BA on 137.05 acres of potentially suitable habitat and 1.919.49 sq. ft. Of pine BA on 66.28 acres of future potential habitat. This partition will meet the SMS requirements post-project provided that potentially suitable habitat is made suitable through management. The 2010 revised project design resulted in a decrease in pine BA removed from 704.32 sq. ft. to 500.84 sq. ft. and a decrease in forested habitat removed from 10.07 to 8.67 acres in the MOOR 35 partition i relative to the Concurrence Letter (8 October 2009). SOP] 50: The revised pre-project foraging habitat totals were 1,078.80 sq. ft. of pine BA 1 on 21.12 acres of suitable habitat and 8,729.06 sq. ft. of pine BA on 101.33 acres of potentially suitable habitat and 307.73 sq. ft. of pine BA on 11.75 acres of future potential habitat prior to removing habitat impacted by the highway project. Road construction will remove 63.83 sq. ft. of pine BA on 1.10 acre of suitable habitat. 307.72 sq. fi. of pine BA on 3.41 acres of potentially suitable habitat and 1.57 sq. ft. of pine BA on 0.06 acre of future potential habitat. The post-project SMS foraging habitat totals were 1,414.96 sq. ft. of pine BA on 20.02 acres of suitable habitat, 8,421.34 sq. ft. of pine BA on 97.92 acres of potentially suitable habitat and 306.16 sq. ft. of pine BA on 11.69 acres of future potential habitat. This partition will meet the SMS requirements post-project provided that potentially suitable habitat is made suitable through management. Biological Conclusion: May Affect-Not Likely to Adversely Affect Pine-tvild Community: and Dam The Pinewild Community and Lake Pinewild Dam are located in Pinehurst, NC. The Pinewild property owners association has had a committee in place to monitor progress of the project and ensure that the project does not adversely affect the property owners. Of particular concern is the aligment of the project in the area near the Pinewild dam. The Lake Pinewild Dam is located approximately 3300 feet (0.63 miles) west of the intersection of NC 211 and NC 5 and approximately 500 feet south of existing NC 211; near the eastern most entrance along NC 211 to the Pinewild subdivision. The dam is an earth structure approximately 850 feet long and about 30 feet high at the maximum report concluded "widening NC 211 along the north side of the existing road, as proposed, will have no impact on the structural performance of the dam." ]n 2006, the alignment of the roadwav was finalized. The north side alignment was chosen minimizing the impact to the Pinewild Community. However, the north side alignment would impact an apartment building that was vacant directly across from the dam. Since that time, the apartment building is occupied with plans to build more in the future. NCDOT proposed revising the alignment further south to avoid the apartment building. NCDOT is proposing this change to avoid displacing eight families within the apartment complex at a cost savings of. approximately $1,725,000.00. NCDOT, again, hired Mactec Engineering, to conduct another detail analysis of the Lake Pinewild dam with the re-alignment of the roadwav closer to the dam. A copy of the findings from the Mactec Engineering report is located in Appendix C. The findings of the Mactec Engineering report concluded the following: 1. Significant fill or excavation occurs, including deeper ditching. Fill heights are expected to be less than 15 feet high and will not extend outward far enough to affect the dam. 2. The culvert capacity does not match dam discharge capacih'. NCDOT will evaluate drainage requirements and design accordingly. 3. Pile driving or other equipment that could cause vibrations to be transmitted to the dam is used. Planned widening does not include a bridge or heavy structures where pile driving or heavy equipment would be needed. 4. Any construction, clearing, or ground disturbance is to occur very close to the dam. The grading limit is approximately 220 ft. to more than 400fi. from the toe of the dam: there should be no construction, clearing, or ground disturbance "very close" to the dam. As a result of the proposed re-alignment, the Pinewild Property Owners Association has requested that the NC Department of Environmental and Natural Resources' (NCDENR)- Department of Water Quality (DWQ), review their concerns relative to the dam. A copy of the letter from the Pinewild Property Owners Association to DWQ is attached in Appendix B. Upon approval of the proposed re-alignment, NCDOT will conduct a citizens' informational workshop to present the plan revisions to the public. A copy of the Eddy Engineering report, the Soils and Foundations report, the DLR inspection reports, and the Mactec Engineering report are on file with the NCDOT Project Development and EnAronmental Analysis Branch. 5 ?m 0 a z BEGIN PROJECT NORTH CAROLINA VICINITY MAPS DIVISION OF HIGHWAYS MOORE COUNTY PROJECT: U504.L1 (R-281Z FIGURE-1 OF NORTH CAROLINA I `'I-' wge "'y1[n U95lpn_010809\Permlt 1\1 -2812-hyd.permlt s-tgh.dgn cmyer6 r WBS: 34504.1.1_ TIP PROJECT: R 3A -, O O a n o F? o o ro N A 0 N V O 0 m n 0 v -4 n O C 9 '0 0 o Ot"OO IN ? ? I i o g I I J y3. ?POO'cF ?a IN < -i ? S O 1U IA , ti II II Ib II III II U U Ir d IN IU IW a ? ? ae ? ? Ig j8 a I F ? o 0 'v o? ? C m m c N 47 • a o? •,C 1? a I a; pO N 3' ?Z m r? i 1 I ? 1 O 1 oA 1 I I na 4e I 2 e' e ?I Qg .a A:B S) V SI u k? vi i i 1 I s ' c 1 ? I I I 1 1 i -)7. /N j P/Np rgt<EY -Y8- GLASGOW RD N D J?. vm SR 1291 ARCHIE RD -Y5- r -Ylo_ SR 1276 JUNIPER LAKE RD O, DRIVE STONEYKIRK -YI ? c m O m y_ II 1 x N -Y72_ SR 1270 BEAULAH HILL CHURCH RD i n 50. N 1? I f? n mZ N m ? ]y. O r7 t2: it D O r W ^m z 0 m n N 00 N GUNCLUB DRIVE -Y75- l / Z I 1 I 0 1?-+ I I I? I I I I ? ? I I I I I? I I I la ? INA In w I? I In LI I Ix Ib ? ?? I ? i I 1? I I I I I I I I ?b InI I I I I y I I I? I I Ic I I II ? I ? I I I I I 1 I I 1 1 I i y76 ORIAL pRIVE { `n '1 `I I . I ------------------------------------------------------------------------- ------------------------------------------------------------------------- ------------------------------------------------------------------------- -L- STA 222+85 MATCH LINE SEE SHEET 20 I I Iz?, hl III l,l I I II ill I i I 1 1 I?+ I II I I I I :1 I Q N° I I -1 i 1 r a II I r II III I •' 1 I ?I IIII; 110 _Vl I :IIII I'Iq I s l ' II II17 I. i n I ?I VIII I. it II; II ; I' If'III I ,III ?Il.l.., :fil N 0 I C I I II ? A !I ? I I III ? III hl I I IIII ICI / III I, ^ ? // II II / // II II / /F III i // 1 1 I I /6 I / ,S' / I / I II I ? I ^ 2 Y??'-\ II I II ; fl II Ilp el I II„ ?I I II ? ? I - 1 I- I I ? It ,I 1 I I I I I'? I II IIII I III I I ,„u I I ? IIII I 1 I II H ; I III I 11 I I: 11 I .? I / 71 m0 n z ?I rn O 2 245 RENSIONS ------------- _--------------- _pn.m?en_e23_nocon.dgn MATCH LINE SEE SHEET 22 -L- STA 263+8_ dl III ! _?-sir 265 I r II II I I I I. 1 1111_ 1 I I I I I I I II I 1 1? 11 III i I I ? I; II ?? 1i ;7-_ _ a r o0 n r ?r Q \ \ Q ? \ {tel. \\ \\I _ _ ? ? a en - 9 270 m I N I ' ???:1 I r ?rv I II Ildl rr ?i ?n ??-_`\ ,? lull r I II pd, r / ?' ? 275 I it 11 / / I II IIII~ - ? J i` I II III ?I IIII I \\ ? \ II (RI \ II IUI \ . \ II IIII \ \ III IIII ? a r I III' I.? > 9NOm m III 11?'? o °az z O III N °a? z° 2 1 al r 1 ns '? n3 71 II A. I III tll ° z I • • Y' I a I I 1' ----------------------------------------------------------------------------------------------------------- !3 nocen.dgn ---------------------------------. ----------------------------------------------------------------------------------------------------------- MATCH LINE SEE SHEET 22 -L- STA 263+88 III,I- 1111 1I-, 265 r I I ill III ?II I ' `l"1 1 I ? II 1 I I I I\ VIII II II Iii! ?I II r I r? I r \ I ? / I ' \?? ? _ es uaeY / iL-. 1 'r ?? III I I e > II ¦' hi J ?Y TOE . 270 ti ?r I l ? I m ' ? f N I lit I III - I ? 1 I , T I I. r II II I I II I I I ? If l' I ? ry i ? 27 II, III,. I ? III I IIII I \. \ ano c II i?lll •i ? \? \' III I^ o _ o YII III! o °NOm m II III ° m III ? YI _, I: rn' -am 8n Z I ? a9 ? II ? I _ 1 1 \ r 1 ?\ Z 1 1 II I I ? MATCH LINE SEE SHEET 27 -L- STA 331+92 vI ? yCy; da w sa F $ ?9? "o ?I I I I I I ' 1. ?I ^I I I I I.i I II II LII CsIII 0 I I I f L i 0 t II w „\/i I ww g? w : 4 N U 0 o I ?, II' I 11 I I I I zl I. 30- $ ail V A / o?p T O . F Q . °z s O el Z k ? ?UZ / T a I n J ? 1 A I U \ \ 9 1 Ia 1 , 1 7` n 0 SHEEP 20 -L- STA 222+85 MATCH UNE SEE g?F$ `mm II iiii ?, ? 4 a4 \ I 1nl !? '' _O?M? ? gppf ywb T y / I L n Z C z m 0 2 24? MATCH LINE SEE SHEET 22 -L- STA 263+88 I n; 10 ? R \ A \ g?mq a \, get N 1 bhv I rj ? 1 :r" I'I1\S??a {:,?.;r? ggy ?¢^ NJ "ids F•- / ;'i I I II i I ?i II I1' Ijl a'i I'Ij Ili ;,j III ,II III II Ij I;I P, 4 1 It h m r a? C N Yr l 0 . j b I"??; n O o 0 l 0 s i `? ? ; q II ?n I d ? I II a l k ??I I17 ? IE ? ? I„ I ;? ?n l T I.I ?. n ? xp o " 265 gY ". 3 ? w lr }} a o FF 7^• b w ?r rv/ _ g Eq ? d V C , m d a \ 0 pp G ?F j.. _ 27( ?. } p t t' x \ ap 1 N y ? ? k4 1 T I?t o 1 .,r"r ro _?- 1 P' ,t r I I> p 1 S ,? d ?$o( a 6 n I j I I 1 , '.J 1Y ` / I u f % I f' -? 2 s11?`i Ell r- 0 oao o c ?I ^^ °nm iN m T n= ?£ III 0 REVISIONS i t 8 1 P i I ? v ? 8 8 'I `?3 i I I . I MATCH LINE , SEE SHEET 27 -L- STA 331192 II + I _ 7 I ---------- - ----- t ? p N ? e 4 0 •' la i? yp C ? Y /(:. k k 4 ? Os µ N R ?` M M k k k 4 4 ? y 4 I M ? k ..j 4 y 4 µ k lll/ I y i n91 ??s ? T I ti I x II ?: ?c I yam` l ? ? \ n u p y. / O .I I it m 1 t s 7FP/? g r I . I 1If1 ._- ..? a I I a {{{ I vyl: ? (}?rf ?\\ ^? I I ?i JY i ._. r J I A r o ? \ ' / 1 l k\ ` 340 I I ? I N e ? 4 ?O a 0 ?I k k ? d r 1 7:17-11 11 I. F m E c ' z mc m o 0 0 0 0 0 0 0 ? ? zn z N D y c S N b V W C U a O a C ? Z m m aE? o o ; O o 0 o z ='"i z z w U E~ ? 4 o m ="'o a e U ? C ? ^ L- = ? o N u z u aC C U C• n O E U O » W Q m •? •^ m 0 0 O N O ? P N 1? W L-` (( -.. ? y U f C ?- E n ?' y a W U E- < ? O N y cv (0 .. W w z F d U 3 U O M '- O O O o M O O z E m N m o m o 0 0 o p m - } F E O N V O O 0 0 N V G m ?" C U 3 O O N t7 ? y Et n E`° o d o 0 0 °° o m m d F- - a U Q v a m a 'as c a 13 c m m ' - o 0 00 00 °0 0 0 o 0 N F m m d d d m m d ci d a ? 3 a LLI D m N a c a 0 m m 0 0 0 0 O O O O N m Z L m m m 3 O O d C o d 0 d Q m U Y ~ ? c m W d c ? D c iO ° o 0 0 o 0 o N o > c m o o ci o 0 o tO Z d o h o d d d d - m X 3 W n _ ` m N (7 D C C 0 0 0 O O 0 0 p m E= m m E o 0 0 0 0 0 0 0 - Fii m d d d d o d o d m C 0 C b m D N C n m m N m 0 O h W m m _ m O O O t O N m m ji m O d d G O 0 0 d ? a ? Y 9 m a m U U c m U ma > ^ Z4 ? `m ? a s a U X X N C - D m N N W W C m b m O m y D m a m m U c ° m c ` o K m X W x W a W v m a E Of J 0? J J J 9 O O O O O p p O O O O + t N ,0 ' O + U ? ? - m P N P N P N N m N P M P O N v N m N m A m C !n m to m fn rn fn `° X J J J J J ? J J - W ( n m o N M J F c m E f!1 Z P m ? a l? Q APPENDIX B Pinewild Property Owners Association letter to DWQ TIP Project No. R-2812 I ROADWAY DUSIGN UNIT JUN 0 7 2010 Pinewild Property Owners Assoc iation PO Box 3975, Pinehurst, NC 28374 Office: 910-215-0531, Fax: 9 0-2Y?'W36 - 'i`f*;UN ML'MFORD SYIM.e _ June 04, 2010 ,13R, xrxnrar B. - J. MOORE HGGCR `BEER vii. L..d Freeman, Secretary _ _ TKYLOR NC Department of Environmental and Natural Resources, - _ THO" WALLS WALLS 1601 Mail Service Center, F.Y.1, - Raleigh, NC 27699-1601 _PREPA.REREPLYFOR _ S Wt1URE Dear Sir: We understand the NC Department of Transportation will soon be sending your department a request for approval to revise their plans for the widening of NC Highway 211 (project R-2812). Their request will ask for approval to move the new roadway closer to the Pinewild dam in Pinehurst, NC. The purpose of this letter is to recommend that DOT's request be denied. First, some background: DOT's project R-2812 has been in the planning stages for several years. Ovr property owners association has had a committee in place during. all this time to monitor progress and ensure that the roadway expansion does not adversely affect our property owners. Of particular concern to us is the alignment of the project in the area near the Pinewild dam, which has been categorized by the NC Department of the Environment & Natural Resources as a "high hazard" dam. In 2006, the alignment of the roadway was finalized and reviewed with the public. The plan called for the widening of the highway in our area to take place on the north side of the existing roadway, which we found to be satisfactory. However in the past year, DOT has decided to revise the alignment in the area immediately adjacent to the Pinewild dam, moving the new roadway closer to the dam. DOT is making this change to avoid buying an apartment building on the north side of the highway, for which they have identified possible savings of $2 million. Ten years ago, an engineering study on the Pinewild dam was done by Eddy Engineering, P.C., which identified several areas of concern with the proposed highway construction. A copy of their report is enclosed for your information. Recently, DOT commissioned another study, by MACTEC Engineering & Consulting, Inc. The report issued as a result of that study attempts to dismiss the issues raised by Eddy Engineering. On'the basis of that study, DOT now plans to ask for NCDENR approval to move the roadway expansion to the south, closer to the dam. At its nearest point, the current roadway is approximately 220 feet from the toe of the dam. The planned expansion will move it 50 feet closer. Our concern is that the construction project and increased traffic on the new road could threaten the stability of the dam. As you probably know, this earthen dam is more than 80 years old and was built with no pre-construction engineering comprehending the stability of its soil structure. We can understand DOT's interest in the possibility of saving $2 million by not having to buy the apartment building. However, if the dam were to fail, those savings would be dwarfed by the property damage that would result. Our understanding is that the "high hazard" classification of the dam is a reflection of the seriousness of those risks. Specifically: • The potential exists for significant property damage and/or loss of life downstream of the dam if it were to fail. The apartment building DOT wants to avoid buying is the first property that would be flooded. B-1 Pinewild Property Owners Association PO Box 3975, Pinehurst, NC 28374 Office: 910-2155-0531, Fax: 910-215-9736 NC Highway 211 (project R-2812) Project Concerns - Page 2 • The town of Taylortown, NC gets its drinking water from Lake Pinewild and this source of water would be lost if the dam were to fail. • The revised project will encroach upon a wetlands area which exists between the highway and the dam. In the past, the Army Corps of Engineers expressed serious concerns about this encroachment. • Forty-four Pinewild property owners own lots and homes with frontage on the lake. The typical value of these lots is $250,000 and the some of the homes are valued at more than $1 i million. The value of these properties would be seriously affected by failure of the dam. • There are 1,000 additional property owners and homes in the Pinewild development whose properties are not on the lake but whose property values would also be diminished. All of these issues can be avoided if the alignment stays as previously planned and approved; on the north side of the road. Keep in mind that two conflicting engineering studies have been done on the dam; one identifying potential problems and the other minimizing those same problems. DOT is assuming their study is the correct one. However, if they are wrong, the damages would greatly exceed their anticipated cost savings. We believe the risks outweigh the potential savings. For these reasons, we recommend that NCDOT's request be denied. If you have any questions, please let us know. Sincerely, Mr. Charles Mills President, Pinewild Property Owners Association u: Mr. Hams Blake Mr. Jamie Boles Mr. Terry Gibson Mr. Jimmy Goodnight Mr. Tim Johnson B-2 Copy EDDY ENGINEERING, P.C. Apn17, 2000 Project 2000-011 Mr. Mice King General Manager Pinew lei Property Owners Association VIA Facsimile 910-215-9736 Re: Dam Observations and NC 211 Widening Dear Mr. King: The purpose of this letter is to present our observations of Pinewild Lake Dam during our site visit of March 2, 2000, and to comrnent on the possible ramifications of the proposed NC 211 widening with respect to the dam The dam appears to be little changed since our previous site visit in 1996. The seepage collection system installed in 1996 bppears to be functioning as intended. The slope sun`ace above this seepage collection system remains stable and not excessively wet. Discharge from the drain outlet was clear and at approximately the same rate observed after completion of construction. Other drain systems within the dam also appear to be functioning. The outlets for other drain systean, recognizable by the black corrugated plastic pips used in the drains, had become covered, but were still flowing water. No. excessively wet anew were observed on the embankment above the older drain areas Downstream of the dam there continues to be seepage through the foundation of the dam reaching the ground surface. Although many areas below the dam have water ponding at the surface of the ground, no strong or concentrated flow was observed. The emergency spillway has been partially landscaped and may be part of an adjoining lot. Flow area does not appear to be restricted at this time, but any fimae activity in the emergency spillway should be avoided. Confirmation that the emergency spillway danensions have not been altered is recommended. The record drawings for the work done to the dam in the late 199(Ys should be consulted fbT the appropriate elevations and widths. One manhole song the sewer line near the toe of the dam was observed to be leaking. This should be repaired as soon a possible. 4416 LonrtDarg xoaq Sucre IUY (919) 954-1802 RaIdA Noah CvWino 21661 F= (919) 934-1804 B-3 We have been receiving regular pierometer readings since the construction work in 1996. Because there is little evidence of fluctuation in pieaometer levels over time, we recommend that the pienometer readings be taken on an annual basis in the future. Monthly readings should be taken, if there arc any change in the picometet readings from one year another, or if any construction work is commenced in the vicinity of the dam Ail readings should be transmitted to us immediately for review. We understand that the Pbwwild Owners Association (POA) is concerned about the possible ranllfmations of the proposed NC 211 widening project. NCDOT is in the preliminary stages of locating and planting improvements or relocation of NC 211. Widening along the current or similar alignment is the alternative of most concern to the POA. It is our opinion that widening along the current alignment could adversely affect the dam if, 1. Signffimm fill or excavation occur, including deeper ditching. 2. The culvert capacity does not match dam discharge capacity 3. Pile driving or other equipment that could cause vibrations to be transmitted to the dam are used. 4. Any construction, clearing, or ground disturbance is to occur very close the dam Frill and excavation both have the potential to alter groundwater flow regimes through and below the dam Fill could consolidate soils or cover seeps, causing soil pore water pressures to rise. Bemuse soil strength is a function of effective stress, bwrtascd pore water pressures could reduce dam stability. Excavation could create a preferred path for foundation seepage. This could result in an increase in an apparent increase in seepage discharge. If not properly filtered, such seepage could lead to a piping f LDure. If excavation is conducted close enough to the embankment, stability of the dam could be reduced by an increase in the effective height of the embankment. If culvert capacity is such that the spillway outlet becomes submerged, spillway capacity will be reduced. Submergence of the spillway outlet is currently limited to an insignificant level by the top of road elevation. If the top of road elevation were increased without an increase in the culvert capacity, a significant loss of spillway capacity could occur. If pile driving or the use of other vibratory equipment occurs, the potential exists for these vibrations to be transmitted to the dam and its foundation. Because the dam and its foundation ate, prvnarily sandy soils and are generally saturated, the potential for densilication or liquefaction of soils should be considered. and monitored Densification by vibration is a commonly used practice where loose, saturated sands are present. Ikmi6cation of soils in the dam foundation or within the dam itself could lead to settlement and damage to existing drainage piping or spillway conduit. Liquefaction on a large scale is unlikely to result from construction activities. 4418 Louisburg Rood Suitt 209 (919) 954-1801 Rdelgh, Nonh Carolina 27661 Far (919) 954-1804 B-4 Mr Mike King Page 3 April 7, 2000 Any construction of land disturbing activity in the i mnediete vicinity of the dam could darnage subsurface drain or change surface flow patterns in areas wet by seepage flows. Existing subsurface drains arc obscured by vegetation and ground litter. They arc not readily recognizable by untrained personnel and could be damaged by construction traffic in the irnmediste vicinity of the dam. Where seepage is ponding downstream of the dent, construction traffic, cleerung, or other work could change surface flow patterns, increasing the apparent rate of seepage. 'Ilse potential of these four groups of activities to adversely affect the dam is a function of the proximity of the activities to the dam and the extent of the activities. As such, we recommend that proposed activities be rrviewed by us in more devil when the scope of the proposed activities is known. If possible, consideration for potential negative effects on the dam should be considered in the proposed roadway design Again, when construction is commenced, we recommend taking monthly piezometer reading so that any changes in seepage conditions can be documented and evaluated. Thank you for giving Eddy Engineering, P.C., the opportunity to provide professional services on this project. If you have any questions on this report, or if we may be of further service, please ' contact us at your convenience. 4428 Louisburg Racer( Suite 209 (919) 934-1802 , B-5 Raleigh, North Carolina 27661 Far (919) 954-1804 APPENDIX C Supplemental Evaluation from MACTEC Engineering and Consulting TIP Project No. R-2812 i BEVERLY EAVES PERDUE GOVERNOR STATE OF NORTttCAROLINA DEPARTMENT OF TRANSPORTATION May 10, 2010 MEMORANDUM TO: ATTENTION: FROM: Jay A. Bennett, P.E. State Roadway Design Engineer Tim Goins, P.E. Project Design Engineer NJo M 'M roge ainaina, P.E. State Geotechnical Engineer ROADWAYDESt NG 01ITITT MAY 1 4 2010 -BENt?TT -STEFNENSON -L R" -VIES -LO&RING "NnHT N _B.AIOORF SF= EIRMW A. CONrr? SECRETARY -TAYLOR THOMAS _F FX.L WALLS _F?dIRY,?'!S?LCe LLRTY STATE PROJECT: 34504.1.1 (R-2812) FEDERAL PROJECT: STP-211(5) COUNTY: Moore DESCRIPTION: NC 211 from NC 73 in West End to the Traffic Circle in Pinehu st SUBJECT: Report of 2"d Supplemental Evaluation In response to the Request for Lake Pinewild Dam Investigation (March 15, 2010), the Geotechnical Engineering Unit's Contracts Investigation group asked MACTEC Engineering and Consulting, Inc., to evaluate the potential for the proposed alignment changes to impact the existing Lake Pinewild Dam. MACTEC completed the two previous investigations at the dam. See the attached Report of 2nd Supplemental Evaluation. Please call Brad Worley, L.G. or Kevin Miller, L.G. at (919) 250-4088 if there are any questions concerning this memorandum. NWW/bdw Attachment MAILING ADDRESS: NC DEPART EW OF TRANSPORTAT1 GEOTECHNICALENGINEERING UW 1589 MAIL SERVICE CENTER RALEIGH NC 276991589 TEIEPHOHE: 919250-4088 Fat: 919-2594237 ~ ncdotgovkblVpeEOnsfttmOrahwaylgeotmh LOCATION: CENTURY CENTER C9wpP ENTRANCE &2 1020 BIRCH RIoGE DRIVE RALEIGH NC 27810 C-1 O MACTEC - „engineering and constructing a better tomorrow May 4, 2010 Mr. Njoroge Wainaina, P.E. State Geotechnical Engineer NCDOT Geotechnical Engineering Unit 1589 Mail Service Center Raleigh, North Carolina 27699-1589 Subject: Report of 2od Supplemental Evaluation: Lake Pinewild Dam Assessment for Proposed Roadway Alignment Shift NC 211 from NC 73 in West End to the Traffic Circle in Pinehurst Project No.: 34504.1.1 TIP No.: R-2812 Federal Aid No.: STP-211(5) County: Moore MACTEC Project 6468100094 Dear Mr. Wainaina: MACTEC Engineering and Consulting, Inc. (MACTEC), is pleased to submit this report of our geotechnical services for the above-referenced project. This report reviews our understanding of the project information, presents our observations from a field reconnaissance visit and provides our evaluation of the potential for the proposed new alignment of NC 211 to impact the existing Lake Pinewild dam. In summary it is our opinion that widening NC 211 as shown on the current plans (March, 2010) will have no impact on the structural performance of the dam. NCDOT should confine that the hydrologic/hydraulic design for the culvert and extension will provide suitable flow capacity so the lake discharge from its design flood will not cause water to impound against the toe of the dam. PROJECT INFORMATION Our understanding of this project comes from NCDOT's letter titled "Request for Lake Pinewild Dam Investigation" dated March 15, 2010, which was received by MACTEC on April 6, 2010 along with two other NCDOT letters and a Pinewild Property Owners Association (PPOA) letter, all from 2002 and regarding work on the project prior to 2002; electronic files of drawings of the project site; previous work by MACTEC and others; and conversations with personnel of the Geotechnical Engineering Unit. The Lake Pinewild dam is an earth structure approximately 850 feet long and about 30 feet high at the maximum section, reportedly constructed in the early 1940's. The dam is presently owned by Tohato Realty, USA, and they are responsible for maintenance. The lake itself is owned by the PPOA, and the area immediately downstream of the dam is owned by the Pinewild Project Limited Partnership. The dam impounds an approximate 40-acre lake that serves as a source for irrigation water for the- Pinewild golf course and as drinking water for the Town of Taylortown. The lake outlet works consist of a vertical 21-inch diameter corrugated metal pipe connected to an 18-inch diameter corrugated metal pipe through the dam leading to a concrete end wall and directing the outflow into a channel leading into a wetland area. MACTEC Engineering and Consulting, Inc. NC License F-0653 C_2 3301 Atlantic Avenue - Raleigh, NC 27604 • Phone: 919.876.0416 • Fax: 919.831.8136 w .nviclec.com .NC: Department of Transportation May 4, 2010 Lake Pinewild Dam Assessment MAMC Project No. 6468-10-0094 Paget The existing NC 211 below the dam is on a low-height (-5 feet) fill. The current widening plans call for constructing an additional fill section of similar height on the south side of the existing road embankment. Filling will be done into an existing jurisdictional wetland in some areas. A culvert presently carves surface runoff and outflow from the dam underneath NC 211. We understand the existing culvert will be i extended under the new embankment. MACTEC reviewed the dam conditions relative to two previous alignments planned for NC 211 and issued reports dated January, 20, 2004 and September 29, 2006 that concluded that neither of the proposed alignments would impact the dam provided the new culvert maintained capacity suitable for flood flows from the lake. The information provided by NCDOT in March, 2010 shows a further alignment change that would move the new embankment closer to the dam. MACTEC was asked to evaluate the new alignment for potential to cause impacts to the dam. NEW ALIGNMENT Attached is a copy of the topographic survey of the dam and immediate surrounding area adapted from our 2004 report. On this drawing we have highlighted the new proposed NC 211 alignment. The current plan shows the southern edge of the proposed roadway approximately 50 feet south of the southern edge of the existing roadway. The southern limit of proposed grading is approximately 220 from the toe of the dam at the closest approach near the west end of the dam. FIELD RECONNAISSANCE A reconnaissance of the dam was made on April 27, 2010 by Mr. AI Tire, P. E.. There were no observable changes in the dam crest, downstream slope or outlet works from observations made during reconnaissances in 2003 and 2006. The crest and slopes are grass covered and continue to be well maintained. Two wet areas indicating possible seepage were noted near the toe near the center of the dam. These possible seepage areas were noted during the previous reconnaissances. No flow was noted during past or current reconnaissanres. In 1996, a blanket drain and trench drains weir added to the dam to address seepage problems. The outlet of the drainage collector pipes is at the lake discharge pipe, beside the concrete etidwall of the culvert. These drainage collector pipes were flowing clear water at estimated rates of 2 to 3 gallons per minute. While the water was clear, there was accumulated sediment in the pipe outlets and on the ground below the pipe outlets. The sediment has become slighfly cemented by iron oxides in the water, a common observation for dams. Mr. John Robertson, director of maintenance for Tohato Realty, reported that the drain pipes were cleaned using a plumber's snake tool last summer. The lake drainage pipe was flowing freely. The outflow from the lake drainage pipe and the seepage drains is directed down a narrow swale with some rip rap. The swale leads into a low, wet, wooded area. This area is drained by poorly defined channels that cross the nearby Progress Energy power line right of way and then lead to the culvert under NC 211. No blockages to the lake outflow prior to its reaching the low, wet area were seen. Natural blockages in the low, wet area are present, causing meandering of the swales. The toe of the dam fill is at the edge of woods or within woods from the lake discharge pipe outlet west to the end of the dam. This area was walked to check for possible seepage. No seepage from the slope or at the toe of the fill was observed. The natural topography north of the dam leads down toward the low, wet ArMACTEC C_3 N. C-. Department of Transportation take Pinewitd Dam Assessment May 4, 2010 _ MACTEC Project No. 6468-10-0054 Page 3 area. Two locations about 20 to 25 feet north of the toe of the dam in the wooded area near the west end of the dam were seen where water was emerging from the ground and feeding into natural swales (Photograph 1). The water was barely moving. No boils or other signs of underflow piping conditions were seen. These areas are interpreted as possible groundwater discharges, but they could represent water moving through the natural ground underneath the dam in response to the head in the lake. Blockage of these exit points by filling could cause elevated pore water pressures to develop in the dam. These points; however, are over 200 feet from any planned construction associated with the NC 211 relocation, and no filling would be occurring over the points. The area between the dam and the proposed new alignment is wooded. The natural topography has a high point on the west end of the area, slopes down to a low flat bottom that is about 500 feet wide west to east and then rises to the east. Progress Energy maintains a 100-foot power line right of way that is roughly parallel to NC 211 and angles northeast away from the dam. About half of thew right of way is cleared. Photographs 2 through 4 show the topographic setting along the power line right of way. Standing water and small swales with slowly moving water draining toward the existing NC 211 culvert are present in the central low area along the power line right of way. The planned new fill limits are approximately 40 to fro feet north of the power line right of way. The most recent inspection of the dam by the North Carolina Department of Environment and Natural Resources Division of Land Resources was performed on December 9, 2009. Their report dated December, 10, 2009 did not indicate any apparent problems. A copy of their inspection report is attached. EVALUATION In our 2004 report, we addressed four concerns presented by Mr. John Eddy of Eddy Engineering, P.C. in a letter to the Pinewild Property Owners Association dated April 7, 2000. The concerns Mr. Eddy has identifted are possible areas of concern for construction near any existing dam. Based on the proposed 2010 alignment and the dam location as illustrated on Drawing No. 1 (attached) and normal roadway construction, our evaluation of the 2010 proposed alignment of NC 211 relative to Mr. Eddy's concerns is given below for each concern. 1. Significant fill or excavation, including deeper ditching could alter groundwater flow, causing soil pore water pressures to rise. There will be some excavation to clear trees and near surface organic materials on the south side of the existing roadway prior to placement of roadway embankment fill material. The southern limit of grading at the closest point to the toe of the dam (near the west end) as taken from Drawing I is approximately 220 feet. The distance between the toe of the dam and the south edge of the roadway embankment fill increases to the east to more than 400 feet. As Mr. Eddy points out, fill placement can result in increased pore water pressures and reduced effective soil strengths. These effects are limited to the areas affected by the stress increase of the fill. Stress increases due to a fill are minimal at a lateral distance beyond the toe of the fill equal to about half the fill height. Since the new fill is expected to be less than 15 feet high, stress increases and related pore water pressure increases from the new fill construction will not extend outward far enough to affect the dam. Also it should be noted that the subsurface soils are very sandy. In granular soils pore water pressure increases dissipate very rapidly, typically as embankment fill is placed. AMACTEC C_4 KC. Department of Transportation Lake Pinewild Dam Assessment May 4, 2010 MACTEC Project No. 6468-10-0094 Page 4 We anticipate that only limited shallow ditching will be required through the highway improvement area. The areas where possible ditching might be used are the low, wet areas. Ditches with gravity inflow are not very efficient for lowering the groundwater table except in the immediate vicinity of the ditch. There is a significant recharge in the wetland area that will inhibit the lateral extent of drawdown due of ditching. Because the groundwater table at the dam will be outside the influence zone of ditches, excavated ditches will have no influence on the phreatic surface through the dam. Also, because the low areas needing drainage are already several feet below the base of the dam, any further lowering of groundwater by ditching in the low areas would only cause drops in groundwater levels near the dam, not increases, if any effect were noted at all. As described earlier, possible groundwater or dam underseepage is emerging from the natural ground in spots west of the lake drain outlet. These areas may represent mechanisms for natural dissipation of pore water pressures through normal movement of water through a dam. The areas are over 200 feet from the planned construction. The planned 2010 NC 211 alignment does not call for any fill over these areas, thus blockage of these natural drainage features would not occur due to the road construction. 2. If the culvert capacity does not match dam discharge capacity, the dam could be affected. As Mr. Eddy points out in his letter, if the culvert beneath the highway can not pass flood flows through the culvert rapidly enough, backwater flooding could result in submergence of the dam outlet, reduction in spillway capacity and potential adverse effects on the performance of the dam. Hydraulic evaluation was not within our scope; we understand the NCDOT hydraulics section will evaluate drainage requirements. 3. If pile driving or other equipment that could cause vibrations to be transmitted to the dam were used,. the dam could be affected. The planned widening does not include a bridge or other heavy structures; we are not aware of any pile driving requirements for the portion of NC 211 to be constructed adjacent to the dam. The only equipment required will probably be earthmoving and compaction equipment. Vibrations from such equipment are low to begin with and dissipate with increasing distance from the work on a logarithmic scale. Based on published studies and our experience with monitoring construction vibrations, with approximately 220 to more than 400 feet from the southern limit of the construction area to the toe of the dam, vibrations from normal earthmoving and compacting equipment should be at levels nearly non- detectable on monitoring equipment. 4. If construction, clearing or ground disturbance is very close to the dam, the dam might be affected. The limit of grading is approximately 220 to more than 400 feet from the toe of the dam; therefore there should be no construction, clearing or ground disturbance "very close" to the dam. Within the limit of grading, work will include clearing and grubbing, and placement and compaction of embankment fill. As noted above, the distance from the dam is such that vibrations from equipment for these operations should have no adverse affects on the dam. JMACTEC C-s . NC: Department of Transporiation May 4, 2010 Lake Pinewild Dam Assessment MAMC Project No. 6468-10-0094 Page 5 MACTEC appreciates working with you on this project. Please call us if you have any questions. JAT/jat Attachments: Drawing 1 Photograph Sheets (2) NCDENR Notice of Inspection 10 December 2009 Very truly yours, MACTEC Engineering and Consulting, Inc. ??roR H CArRpp G% J. llan Tice, P.E. (Engines of !d 'fl James E. Veith, P. E. (Reviewer) Senior Principal Geotechni-Cal gine AL Principal Geotechnical Engineer % Registered NC 6428 _ 911" Registered North Carolina 023232 rMACTEC C-6 North Carolina Department: of Environment and Natural Resources 0 ?? verly Eaves Perdue, Governor r tee Freeman, Secretary NCDENR i ' James D. Simons, P.G., P.E. Director and State Geologist Division of Land Resources ll NOTICE OF INSPECTION DIVISION OF LAND RESOURCES LAND QUALITY SECTION 10 December 2009 Pinewild Projects Limited Parterslrip ATTN: Koichi Sato P.O. Box 3087 Pinehurst, NC 28374 RE: Pinewild Lake Dam Moore-143 Moore County, North Carolina Cape Fear River Basin Dear Mr. Sato: The Dam Safety Law of 1967, as amended, provides for the certification and inspection of dams in the interest of public health, safety, and welfare, in order to reduce the risk of failure of such dams; to prevent injuries to persons, damage to property; and to insure the maintenance of stream flows. Our records indicate you are the owner of the referenced dam, whichis located off NC Hwy 211. This dam was inspected on 9 December 2009 by personnel of the Land Quality Section. This inspection revealed no apparent problems with the dam. However, the following items perti nent to maintenance and operation of the dam are recommended. 1. Maintain a ground cover sufficient to restrain accelerated erosion on all earthen portions of the structure. 2. Periodically remove trees less than about six inches in diameter and thick undergrowth from the slopes and crest of the dam. This will serve to (A) prevent the formation of a root system which might significantly increase seepage through the dam which could ultimately result in failure of the structure, (B) reduce the possibility of damage to the darn due to the uprooting of trees by wind or other natural causes. and (C) facilitate ease of inspection and increase the likelihood of early detection of more serious problems connected with the dam. C-7 Pinewild Lake D_ ern MORE-143 Periodically remove all trees from the emergency spillway. This will reduce the possibility of its capacity being reduced by the entrapment of debris, should it become active. 4. Periodically check the operation of all drain valve facilities. This will insure satisfactory operation of the drains should an emergency situation arise. 5. Periodically monitor the subject dam and appurtenant works with respect to elements affecting its safety. This is in light of the legal duties, obligations, and liabilities arising from the ownership and/or operation of.a dam. During this inspection we also investigated thepotential forproperty damage and loss of life in the event that your dam fails. This investigation determined that failure of your dam could result in severe property damage and/or possible loss of life downstream. Therefore, we are listing your dam in the "High Hazard" category. Also be advised that this Office must approve any excavations in this dam or major repair work to this dam before any work is done. Also, note that this dam may not be breached; meaning the dam may not be drained by cutting a notch in the dam, without prior engineered breach plans being submitted to and approved by this Department. Please be advised that though we make every reasonable effort to determine the safety ofyour dam, our resources limit us to surficial inspection. There is no certainty regarding the internal stability of the dam. Dams, and especially their spillways and conduits, deteriorate with age. Therefore, you are advised to keep a close watch on your dam and to notify us if you detect any changes, especially cracks, ground movements, or changes in seepage rate or color. Your cooperation and consideration in maintaining a safe dam is appreciated. If ownership of the dam has changed, or if you are not responsible for the dam, please notify us so that we can update our records. Should you have any questions concerning our inspection, please contact meat (910) 433-3300. Sincerely, M. Stepp , Cook, C. E.S.C. Regional Engineer Land Quality Section `J MSC\joh cc: State Dam Safety Engineer (electronic copy) cc: Fayetteville Regional Office File C-8 Section 404/NEPA Merger Project Team Meeting Agreement -rte Concurrence Point 1: Purpose and Need. Project Name/Description: Widen NC 211 from NC 73 in West End to east of SR 1208 (Page Road) in Pinehurst, Moore County, TIP R-2812, Fed. Proj. STP-191(1) Purpose of the Proposed Project (August 9, 20011 The purpose of the project is to upgrade NC 211 in order to safely and efficiently accommodate existing and projected traffic volumes. The Project Team members concur with the purpose and need stated above , as indicated by signature below: USACE el Date OJ NCDOT ??. Date 8I?Iol USEPA Date USFWS Date o f9 fvi NCDWQ.?? . (?ctrt Qi ft)?p?Qo Date O/ NCWRC Date FHWA ?Tc Lit %e - Date F/910) D-1 SECTION 404 / NEPA Merger Project Team Meeting Agreement Concurrence Point No. 3 - Least Environmentally Damaging Practicable Alternative (LEDPA) Proiect No./TIP No /NamPm riation State Project Number: 8.1560601 Federal Aid Number: STP-211(5) TIP Number: R-2812 TIP Description: Widen NC 211 to a multilane facility from NC 73 in West End to the traffic circle in Pinehurst Recommended alternative: The "Best-fit" Alignment is a combination of Alternative 1 and Alternative 2. A four-lane divided facility with curb and gutter will begin.at the traffic circle in Pinehurst and wili extend along existing NC 211 to terminate at SR 1291 (Archie Road) (Alternative 1)..A four-lane divided facility with grass shoulders will begin at SR 1291 (Archie Road) and will extend along existing NC 211 to the project terminus at NC 73 in West End (Alternative 2). The Project Team has concurred on this date of October 2006 with the selection of the "Best fit" as the Least Environmentally Damaging Practicable Alternative (LEDPA) for TIP Project No. 9-2812 as stated above U. S. Army Corps of Engineers i L I J.S. Environmental Protection Agency I U.S. Fish and Wildlife Services N.C. Wildlife Resource Commission N!C. Department of Cultural Resources N.C. DENR-DWQ Federal Highway Administration " N. C. Department of Transportation _ D-2 >r ? r Section 404/NEPA Merger Project Team Meeting Agreement ConcurreumPoini-No-2 - Alternatives to be studied in detail . in the NEPA document. Project No./TIP No./Name/Description: State Project No. 8.1560601 Federal Aid No. STP-211(5) TIP. No_R2812 Widen NC 211 to a multilane facility from NE 73 in West End to the traffic circle in Pinehurst Alternatives to be stud in detail in the. NE A-document: 1.) "Best-Fit" Alternative with curb and gutter Widen NC 211 to a multi-lane facility, from NC 73 in West End to the traffic circle in Pinehurst_ utilizing a combination of North-side South side, and symmetrical widening in order to minimize impacts to the natural and human environments. 2.) "Best-Fit" Alternative with grass shoulder section Widen NC 211 to a mul i-lane facility, from NC 73 in West End to the traffic circle in Pinehurst, utilizing a combination of North-side South- side, and symmetrical widening in order to minimize impacts to the natural and human environments. The Project Team has concurred on this date of April 11, 2002 with the "alternatives.tabe-.studied_in-detaiP in-the-NEPA-document as stated absove with the stipulation that the "Best Fit" alignment will be determined during Concurrence.-Paint 3. USACE u USEPA- c.r / Y6 NCDCR NCDOT USFWS NCWRC FHWA - ?,?-> D-3 SECTION 404 / NEPA Merger Project Team Meeting Agreement Concurrence Point No. 4A - Avoidance and Minimization Project No./TIP No./Name/Description: State Project Number: 8.1560601 Federal Aid Number: STP-211(5) TIP Number: R-2812 TIP Description: Widen NC 211 to a multilane facility from NC 73 in West End to the traffic circle in Pinehurst Avoidance and Minimization: Minimization efforts have taken place continually throughout the planning process. NCDOT studied various widening scenarios that achieved the purpose of the proposed project and minimized impacts to the environment. NCDOT developed the "Best Fit" alignment with the Merger Team in order to minimize impacts to the human and natural environment. The Merger Team reviewed the preliminary plans on December 11, 2002 and concurred that the "Best Fit" alternative was the preferred. See attached sheet for continued Avoidance and Minimization Efforts. The Project Team concurred on this date of October 26. 2006 with the avoidance and minimization measures for TIP Project No. R-2812 as stated above. U. S. Army Corps of Engineers U.S. Environmental Protection Agency U.S. Fish and Wildlife Services- N.C. Wildlife Resource Commission N.C. Department of Cultural Resources N.C. DENR-DWQ Federal Highway Administration N. C. Department of Transportation 4t/U t - D-4 October 26, 2006 R-2812 Concurrence Point 4A-Avoidance and Minimization Efforts to date 1. -Leave current drainage structures in place and accommodate widening by extending the two existing culverts 2. -The NCDOT preferred alternative would use a curb and gutter typical section for a portion of the project which narrows the project footprint. 3. -The NCDOT preferred alternative would reduce the typical section by using the curb and gutter instead of a shoulder section along a portion of the project. 4. -Steeper fill slopes (2:1) were used along the curb and gutter section, reducing the project footprint. 5. -A 23-foot raised island, the narrowest acceptable median width, is recommended. This median width will reduce the project's footprint. a S z v p c ? r F ? Z i`. 2 N F ?_ f ? N N F N G 6 ? N 4 3 3 z o < = z z U - O F a a O O ° ? Z U tt O O O F S a o 6 ? ? c p r ? e ? p r z O z F F V e w m 0 m N m co O W N m M N V5 N m C m m ` o N a c n E J J J J of W' m ? C N t U m N w C N C E ?nEc ? ? r o 0 0 0 0 0 0 0 0 ? z f/J ? m N C C U 4 'y n E s o :1 0 0 0 0 0 m E ~ w u N y OI 41 c c u c . Z N? Q E W O O O m N ? N ? w U E v a ri ?„ o n ? o 0 0 0 ? ? W '? o N 0 0 0 0 o W Y F E 0 0 N ? Q c C C rC ? V O f?J O O Ol N N V O ? 1p3 n? °o ? °o vNi o o °o 0 1O ? " 0 0 0 ° F ? E 0 0 0 0 0 U a d rn " m c- o 0 0 0 0 0 0 0 ? V m U_ 3 0 0 0 0 0 0 0 0 ° N 1 ?? N C '- !a U W W N O O d < N yy O? yy W 1D ?O ? Q N N 0 0 0 O O O y ry " O O ° Q ? U 3 0 0 0 0 0 0 0 0 F ? c W c 3 N s ' ? N 0 0 0 O 0 0 O O N ? c 0 ?p 0 O 0 O 0 O O O O O O O O O O O x 0 0 01 0 0 0 0 0 ° J w N d c?? 0 0 0 O O O O O O E=!0 m 8 °o o °o °o °o °o °o O F LL " 0 0 0 0 0 0 0 0 O 3 C N ? c C ,.., W N O m W ? N O W `' o 0 0 0 vLL3 0 0 0 0 0 a a s ? U U U U c c !0 m U m U ° n n ? v N m m a d c F ? w w 2 3 n n U m U ? a o o ? `- H W W c m O O N .O ? W W m U v y d m y w w a w w O O O 0 0 0 O O O O N O t N N ul O O . N Q N N N ry a N N N m LL A A A 'u A ? A m N ? ? m N m m cn J J J J J J J J J W O 2 to N O M « O 16 0 F a c E c ? ? O o O ? " jp d O O N F z M Z U) ?¢., ti w x N ? ? o r m m 01 « a ¢ ?' [.1 a F - 'y c'°E= N U I ¢z¢s z zz O O Q E W U E~ K ?.' _ o n U p c U ? !z ? W C C U C. °? O m N I? U (.Z] O n O 0 x r E E ?' M o g > F W U_ ? c? a '. F Q a . O . 6 .. ? a W U x U w ? z LL E m m m z F ? m E`° N N ` ? r F Q « U M > N U m O O O O } y E N E m > o 0 0 0 0 F U a - a D. N m a U . _ O F U ? cc W m W o IL - m C G ` v N v v v J ? r0 N N N N O O O M O Q N ? >? >> O O O ?. J F U g ° W a o ? ? C c m m N o M O o m '- mm -- 0 0 ci Z U > w g W N 3 a E M 4 ° O l >d F C (? m a C C C t0 = t0 U O] V O 0) Ol C? M O T ELL y i6 O O O O '_ a U O C O C O m a N c o m m m H rv F 3 U = a U = U N O m W Q N N W C 0 X V O n m U) a 0 -p O Y O Y c U c ? c c 0 x 0 a ? m ? m w F F F F O CL J O J O J O O O O 0 + 0 0 N + O i `O N 0 O + N W M V t0 O ? N N b N ? M Nw in A m N A m J ? m J m J N J J J J J N U N M M V V F mZ O H