HomeMy WebLinkAbout20021016 Ver 1_Complete File_20020611BRIDGE PROJECT SCOPING SHEET 11-2-98 TIP PROJECT: B-3497 DIVISION: 7 F.A. PROJECT: BRZ-1517(2) COUNTY: Orange STATE PROJECT: 8.2501501 ROUTE: SR 1517 DESCRIPTION: Replace Bridge No. 26 on SR 1517 over North Fork Little River PROJECT PURPOSE: Replace Obsolete Bridge PROJECT U.S.G.S. QUAD SHEET(S): Caldwell ROADWAY CLASSIFICATION: Rural Local TIP CONSTRUCTION COST ....................................................... $ 300,000 TIP RIGHT OF WAY COST ....................................................... $ 30,000 PRIOR YEARS COST ............................................................... TIP TOTAL COST ................................................................... $ 330,000 TRAFFIC: CURRENT: 500 VPD; DESIGN YEAR (2025): 800 VPD DUALS : 2 % TTST : 1 % EXISTING ROADWAY TYPICAL SECTION:: Two-lane, 18 foot, paved roadway with grassed shoulders/ditches. EXISTING STRUCTURE: LENGTH 23 METERS WIDTH 6.1 METERS 75 FEET 20.1 FEET COMMENTS: Gordonton 1 1 1 1 ---•• n 1 107 ` - - J - 1134 ! -' 1. 3 1 N 1106 1.4 c ,4 .2 , 8 CfK' " ! 1181 i 1 135 -' W m 7 Hurdle v9mills > 1.7 6 1 FOfk•' - 1113 % 1114 - y 120 ?' - 1 108 y1? t0 ? 1001 1208 i 102 ? 4 103 2 ' 1915 12 1119 120 09 1.5 1119 3 1.3 - 2 1 1 105 S S ?. _ ._......... 01 0 i O - 1001 1117 o 5 fQ5 :_ .? i ' 1 18 8 1 18 e? o &l` 1 121 1 n ?D 1122 1123 N 7 3 N 1515 ' ?•?: 1527 i 9 1 /? 51 A G 4 N-•' 6 U N T - 1 r 526 p i - `?^ ',1001 N l 1507 1578 2 Bridge No 26 1512 . 14 . ? i • e n , ?,9 i OR J f ? 152$ 1 ro W 1512 • 1516 I CO ' `S 1511 O 1.6 1 . 1 1510 1510 1517 1.0 0 1522 ' 9 .7 ! 1517 1509 ^ ??'? 9r ti • O 1 ? I •) • 6 '?•.` 1518 ? . OD N ` 1508 ' 1519 1520 i 57 157 1.9 1507 •.` ` 1546 inn ?. i >1T 1508 i Caldwell V 1543 2. 1 1 1.0 1581 ?• ,639 p 154 ' 5 2 S 1545 i P 1520 1.1 1507 _ _,. 3. 3 1544 162 121 ' 2 1579 W S I l i1/,Sv? FC)/-k- L4? OR 11 1rlft F F??R?aF NORty-G t• North Carolina Department of Transportation Division of Highways ?. si° ? Planning & Environmental Branch OA TRAT? Orange County Replace Bridge No. 26 on SR 1517 Over North Fork Little River W497 FIGURE 1 V tb t1 ,r ? - - _ 00 Lim;,,, 1?;. . _ _ L fir `__ \ - _?_ _?__ •A62 - \ :6__ 4, L "..Berm Grove hF .00 -I em "Mll, a?M isville Grov 650\? ?• z 1, ?/ 616 ??9 it ( c6 Littl -41 II 01 (F f f57 10 633 - --- -.i •662 ? ^ _ O ' 0 L JO \ \) '__ ? i % 67 , n \ JL_' J 640 ?p ( '•62 // ?i 650 f --? = S i d o O 0 0 9 ? o °4 v v ? 0 oil> °i e 0 e e ?e Mrao? p 2101 ?? ? 4 STATE OF NORTH CAROLINA 4-W DEPARTMENT OF TRANSPORTATION`„,? MICHAEL F. EASLEY LYNDO L?fr' f t GOVERNOR SECRETARY U.S. Army Corps Raleigh Field Office Falls of the Neuse Suite 120 Raleigh, NC 27 ce Road 615-6814 ATTENTION: Mrs. Jean Manuele May 21, 2002 of Engineers NCDOT Coordinator SUBJECT: Orange County, Proposed Replacement of Bridge No. 26 on SR 1517 over North Fork Little River. Federal Aid Project No. BRZ-1517(2), State Project No. 8.2501501, TIP No. B-3497. Dear Sir: As you are aware, the North Carolina Department of Transportation (NCDOT) has requested authorization from the U.S. Army Corps of Engineers (USACE) under a Section 404 Nationwide (NWP) 23 on September 14, 2001 to replace Bridge No. 26 on SR 1517, over the North Fork Little River, in Orange County. The purpose of this letter is to request authorization under Section 404 NWP 33 to place impervious dikes in the stream in order to dewater the site and divert flow around the site during construction of the culvert. The project has a let date of January 2003. NCDOT will replace Bridge No. 26 on SR 1517, over the North Fork Little River, in Orange County. Replacement will be at approximately the same location with a double barrel 13'x 10" reinforced concrete box culvert (RCBC). The culvert travelway will be 22 wI e wI oot-grasse ou der width will be increased by at least 3 feet where guardrail is warranted. Project length is approximately 400 feet. Traffic will be detoured along existing secondary roads. The existing bridge will be demolished. The existing bridge is composed of an asphalt overlay surface on a timber deck, with timber joists and steel I-beams. The substructure is made up of timber except for concrete encasements at the pile footings. The bridge is 75 feet long and 20 feet wide. The asphalt wearing surface and bridge rails MAILING ADDRESS: TELEPHONE: 919-733-3141 LOCATION: NC DEPARTMENT OF TRANSPORTATION FAX: 919-733-9794 TRANSPORTATION BUILDING PROJECT DEVELOPMENT AND ENVIRONMENTAL ANALYSIS 1 SOUTH WILMINGTON STREET 1548 MAIL SERVICE CENTER WEBSITE. WWW.DOH.DOT.STATE.NC.US RALEIGH NC RALEIGH NC 27699-1548 will be removed prior to demolition, without dropping it into the water. There is the potential for parts of the bridge to fall into the water; the calculated maximum potential fill in the water resulting from bridge demolition is 17 yd3 of material. All temporary fill material will be removed from the river as soon as possible as part of the bridge removal process. During construction, Best Management Practices for Bridge Demolition and Removal will be followed. Replacing the bridge with a culvert will result in temporary and permanent impacts to waters of the United States. There are 0.05 acres of fill and 0.03 acres of mechanized clearing impacts anticipated to jurisdictional wetlands by the construction of the proposed project. However, construction will also, result in 0.07 acres of surface water impacts to North Fork Little River. There will be 87 linear feet of surface water impacts by the construction of the project. The temporary impacts will result from the placement of a cofferdam or impervious dike (riprap or a less intrusive device) and a diversion pipe within the channel during the operation. Sandbags are recommended as the temporary fill to be used as impervious dikes. Temporary impacts from dewatering structures will extend a maximum of 40 feet per end beyond the footprint of the proposed structure giving a total temporary impact of 80 feet. Temporary impacts to the stream in area caused by the placement of cofferdam or impervious dikes is (0.06 ac.). A temporary stone silt screen is proposed as an in-stream sedimentation erosion control device. The temporary impacts associated with installing the stone silt screen are (0.006ac.). Within 15 working days of the culvert installation, all dewatering structures will be entirely removed, and the natural stream and contours restored and seeded. Culvert Construction Sequence: 1) Install a stilling basin or special stilling basin (e.g., silt bag) as directed by the NCDOT representative. 2) Stilling basins will be placed through the scour area and around the construction area. 3) Divert flow around the cofferdam or impervious dike. 4) Dewater the culvert construction area with discharge through the stilling basin or special stilling basin. 5) Construct the box culvert. 6) Upon completion of the culvert, divert flow into the culvert and fill scour area. 7) Within 15 working days of the culvert installation, all dewatering structures will be entirely removed, and the natural stream and contours restored and reseeded. 8) Care should be taken to maintain aquatic life movement throughout the project. Written concurrence for 401 Water Quality Certification (WQC) from the N.C. Division of Water Quality (NCDWQ) is not required for the Section 404 NWP 33, however, NCDOT will adhere to all conditions of the general certification for Section 404 NWP 23 and 33. The NCDWQ is provided written notification of the proposed action by copy of this Section 404 NWP 33 application. In summary, the NCDOT has requested authorization from USACE, under Section 404 NWP 23, to replace Bridge No. 26 over North Fork Little River on SR 1517 with a culvert. NCDOT also requests authorization under Section 404 NWP 33 to place cofferdams or impervious dikes in the stream in order to dewater the site and divert flow around the site during construction of the culvert. If you have any questions or need any additional information concerning the project please contact Mr. Jared Gray at (919) 733-7844 ext. 331. Sincerely, William D. Gilmore, P.E., Manager Project Development and Environmental Analysis Branch VCB/jg cc: w/attachment Mr. David Franklin, USACE, Wilmington Field Office I/Nft. John Dorney, DWQ Mr. David Cox, NCWRC Mr. Jay Bennett, P.E., Roadway Design Mr. Burt Tasaico, P.E., Program Development Mrs. Debbie Barbour, P.E., Design Services Mr. David Chang, P.E., Hydraulics Mr. Tim Rountree, P.E., Structure Design Mr. Mike Mills, P.E., Division 7 Engineer Mr. Len Smith, DEO, Division 7 Mr. Dennis Pipkin, NCDOT Project Engineer Mr. Ken Pace, NCDOT Roadside Environmental Unit, Raleigh M . z \ W \ J co 0. T 9 ? J t lS? a S' J I LL. W t1 a 0 n N z 0 z J 7 I'r'e c- t Form Version April 2001 Office Use Only' ®? ®16 USACE Action ID No. DWQ No. If any particular item is not applicable to this project, please enter "Not Applicable" or "N/A" rather than leaving the space blank. 1. Processing Check all of the approval(s) requested for this project: ® Section 404 Permit Section 10 Permit ® 401 Water Quality Certification ® Riparian or Watershed Buffer Rules 2. Nationwide, Regional or General Permit Number(s) Requested: NW 23 & NW 33 3. If this notification is solely a courtesy copy because written approval for the 401 Certification is not required, check here: 4. If payment into the North Carolina Wetlands Restoration Program (NCWRP) is proposed for mitigation of impacts (see section VIII - Mitigation), check here: II. Applicant Information Owner/Applicant Information Name: North Carolina Department of Transportation Mailing Address: Project Development & Environmental Analysis Branch 1548 Mail Service Center Raleigh NC 27699-1548 Telephone Number: 919-733-3141 Fax Number: 919-733-9794 E-mail Address: b ilmore dot state nc us 2. Agent Information (A signed and dated copy of the Agent Authorization letter must be attached if the Agent has signatory authority for the owner/applicant.) Name: Company Affiliation: Mailing Address: Telephone Number: Fax Number: E-mail Address: Page 1 of 10 III. Project Information Attach a vicinity map clearly showing the location of the property with respect to local landmarks such as towns, rivers, and roads. Also provide a detailed site plan showing property boundaries and development plans in relation to surrounding properties. Both the vicinity map and site plan must include a scale and north arrow. The specific footprints of all buildings, impervious surfaces, or other facilities must be included. If possible, the maps and plans should include the appropriate USGS Topographic Quad Map and NRCS Soil Survey with the property boundaries outlined. Plan drawings, or other maps may be included at the applicant's discretion, so long as the property is clearly defined. For administrative and distribution purposes, the USACE requires information to be submitted on sheets no larger than 11 by 17-inch format; however, DWQ may accept paperwork of any size. DWQ prefers full-size construction drawings rather than a sequential sheet version of the full-size plans. If full-size plans are reduced to a small scale such that the final version is illegible, the applicant will be informed that the project has been placed on hold until decipherable maps are provided. 1. Name of project: Bridge Replacement over North Fork Little River 2. T.I.P. Project Number (NCDOT Only): B-3497 3. Property Identification Number (Tax PIN): 4. Location County: Orange Nearest Town: Caldwell Subdivision name (include phase/lot number): Directions to site (include road numbers, landmarks, etc.): Bridge No.26 over North Fork Little River on SR 1517 approximately 1.75 miles west of NC 157, approximately 3.2 miles northwest of Caldwell. 5. Site coordinates, if available (UTM or Lat/Long): see attached application (Note - If project is linear, such as a road or utility line, attach a sheet that separately lists the coordinates for each crossing of a distinct waterbody.) 6. Describe the existing land use or condition of the site at the time of this application: Rural 7. Property size (acres): 8. Nearest body of water (stream/river/sound/ocean/lake): North Fork Little River 9. River Basin: Neuse (Note - this must be one of North Carolina's seventeen designated major river basins. The River Basin map is available at hqp://h2o.enr.state.nc.us/admin/mUs/.) Page 2 of 10 10. Describe the purpose of the proposed work: Replacement of the bridge with a double barrel 13' X 10' reinforced concrete box culvert 11. List the type of equipment to be used to construct the project: 12. Describe the land use in the vicinity of this project: rural IV. Prior Project History If jurisdictional determinations and/or permits have been requested and/or obtained for this project (including all prior phases of the same subdivision) in the past, please explain. Include the USACE Action ID Number, DWQ Project Number, application date, and date permits and certifications were issued or withdrawn. Provide photocopies of previously issued permits, certifications or other useful information. Describe previously approved wetland, stream and buffer impacts, along with associated mitigation (where applicable). If this is a NCDOT project, list and describe permits issued for prior segments of the same T.I.P. project, along with construction schedules. V. Future Project Plans Are any additional permit requests anticipated for this project in the future? If so, describe the anticipated work, and provide justification for the exclusion of this work from the current application: No VI. Proposed Impacts to Waters of the United States/Waters of the State It is the applicant's (or agent's) responsibility to determine, delineate and map all impacts to wetlands, open water, and stream channels associated with the project. The applicant must also provide justification for these impacts in Section VII below. All proposed impacts, permanent and temporary, must be listed herein, and must be clearly identifiable on an accompanying site plan. All wetlands and waters, and all streams (intermittent and perennial) must be shown on a delineation map, whether or not impacts are proposed to these systems. Wetland and stream evaluation and delineation forms should be included as appropriate. Photographs may be included at the applicant's discretion. If this proposed impact is strictly for wetland or stream Page 3 of 10 mitigation, list and describe the impact in Section VIII below. If additional space is needed for listing or description, please attach a separate sheet. 1. Wetland Impacts Wetland Impact Site Number (indicate on map) Type of Impact* Area of Impact (acres) Located within 100-year Floodplain** (yes/no) Distance to Nearest Stream (linear feet) Type of Wetland*** 15+60 to 18+47 - L-LT fill & mechanized clearing 0.08 10 linear ft. PEN/SS * List each impact separately and identify temporary impacts. impacts include, but are not limited to: mecnanized ciearmg, grading, nu, excavation, flooding, ditching/drainage, etc. For dams, separately. list impacts due to both structure and flooding. * * 100-Year floodplains are identified through the Federal Emergency Management Agency's (FEMA) Flood Insurance Rate Maps (FIRM), or FEMA-approved local floodplain maps. Maps are available through the FEMA Map Service Center at 1-800-358-9616, or online at http://www.fema.pov. *** List a wetland type that best describes wetland to be impacted (e.g., freshwater/saltwater marsh, forested wetland, beaver pond, Carolina Bay, bog, etc.) List the total acreage (estimated) of existing wetlands on the property: Total area of wetland impact proposed: 0.08 2. Stream Impacts, including all intermittent and perennial streams Stream Impact Site Number (indicate on map) Type of Impact* Length of Impact (linear feet) Stream Name** Average Width of Stream Before Impact Perennial or Intermittent? (please specify) 15+60 to 18+47 L-LT culvert 87 North Fork Little River 20 ft. Perennial * List each impact separately and identify temporary impacts. impacts include, but are not limited to: culverts and associated rip-rap, dams (separately list impacts due to both structure and flooding), relocation (include linear feet before and after, and net loss/gain), stabilization activities (cement wall, rip-rap, crib wall, gabions, etc.), excavation, ditching/straightening, etc. If stream relocation is proposed, plans and profiles showing the linear footprint for both the original and relocated streams must be included. ** Stream names can be found on USGS topographic maps. If a stream has no name, list as UT (unnamed tributary) to the nearest downstream named stream into which it flows. USGS maps are available through the USGS at 1-800-358-9616, or online at www.usgs.gov. Several internet sites also allow direct download and printing of USGS maps (e.g., www.topozone.com, www.mai)quest.com, etc.). Page 4 of 10 Cumulative impacts (linear distance in feet) to all streams on site: 87 linear feet 3. Open Water Impacts, including Lakes, Ponds, Estuaries, Sounds, Atlantic Ocean and any other Water of the U.S. Open Water Impact Site Number (indicate on map) Type of Impact* Area of Impact (acres) Name of Waterbody (if applicable) Type of Waterbody (lake, pond, estuary, sound, bay, ocean, etc.) * List each impact separately and identify temporary impacts. impacts include, but are not limited to: fill, excavation, dredging, flooding, drainage, bulkheads, etc. 4. Pond Creation If construction of a pond is proposed, associated wetland and stream impacts should be included above in the wetland and stream impact sections. Also, the proposed pond should be described here and illustrated on any maps included with this application. Pond to be created in (check all that apply): E] uplands E] stream ? wetlands Describe the method of construction (e.g., dam/embankment, excavation, installation of draw-down valve or spillway, etc.): Proposed use or purpose of pond (e.g., livestock watering, irrigation, aesthetic, trout pond, local stormwater requirement, etc.): Size of watershed draining to pond: Expected pond surface area: VII. Impact Justification (Avoidance and Minimization) Specifically describe measures taken to avoid the proposed impacts. It may be useful to provide information related to site constraints such as topography, building ordinances, accessibility, and financial viability of the project. The applicant may attach drawings of alternative, lower-impact site layouts, and explain why these design options were not feasible. Also discuss how impacts were minimized once the desired site plan was developed. If applicable, discuss construction techniques to be followed during construction to reduce impacts. The other alternative called for an on-site detour, which would have added an additional 60 linear feet of stream impact This design calls for an off-site detour so that the stream impacts are minimized This project is located in the Neuse River Basin: therefore the regulations pertaining to the Neuse Buffer Rules will apply. There are 0.05 acres of impacts in Buffer Zone 1, and 0.01 acres of impact to Buffer Zone 2 Page 5 of 10 VIII. Mitigation DWQ - In accordance with 15A NCAC 2H .0500, mitigation may be required by the NC Division of Water Quality for projects involving greater than or equal to one acre of impacts to freshwater wetlands or greater than or equal to 150 linear feet of total impacts to perennial streams. USACE - In accordance with the Final Notice of Issuance and Modification of Nationwide Permits, published in the Federal Register on March 9, 2000, mitigation will be required when necessary to ensure that adverse effects to the aquatic environment are minimal. Factors including size and type of proposed impact and function and relative value of the impacted aquatic resource will be considered in determining acceptability of appropriate and practicable mitigation as proposed. Examples of mitigation that may be appropriate and practicable include, but are not limited to: reducing the size of the project; establishing and maintaining wetland and/or upland vegetated buffers to protect open waters such as streams; and replacing losses of aquatic resource functions and values by creating, restoring, enhancing, or preserving similar functions and values, preferable in the same watershed. If mitigation is required for this project, a copy of the mitigation plan must be attached in order for USACE or DWQ to consider the application complete for processing. Any application lacking a required mitigation plan or NCWRP concurrence shall be placed on hold as incomplete. An applicant may also choose to review the current guidelines for stream restoration in DWQ's Draft Technical Guide for Stream Work in North Carolina, available at http://h2o.enr.state.nc.us/ncwetlands/stn-ngide.html. 1. Provide a brief description of the proposed mitigation plan. The description should provide as much information as possible, including, but not limited to: site location (attach directions and/or map, if offsite), affected stream and river basin, type and amount (acreage/linear feet) of mitigation proposed (restoration, enhancement, creation, or preservation), a plan view, preservation mechanism (e.g., deed restrictions, conservation easement, etc.), and a description of the current site conditions and proposed method of construction. Please attach a separate sheet if more space is needed. No proposed mitigation 2. Mitigation may also be made by payment into the North Carolina Wetlands Restoration Program (NCWRP) with the NCWRP's written agreement. Check the box indicating that you would like to pay into the NCWRP. Please note that payment into the NCWRP must be reviewed and approved before it can be used to satisfy mitigation requirements. Applicants will be notified early in the review process by the 401/Wetlands Unit if payment into the NCWRP is available as an option. For additional- information regarding the application process for the NCWRP, check the NCWRP website at httn://h2o.enr.state.nc.us/Wrn/index.htm. If Page 6 of 10 use of the NCWRP is proposed, please check the appropriate box on page three and provide the following information: Amount of stream mitigation requested (linear feet): zero Amount of buffer mitigation requested (square feet): zero Amount of Riparian wetland mitigation requested (acres): zero Amount of Non-riparian wetland mitigation requested (acres): zero Amount of Coastal wetland mitigation requested (acres): zero IX. Environmental Documentation (DWQ Only) Does the project involve an expenditure of public funds or the use of public (federal/state/local) land? Yes ® No ? If yes, does the project require preparation of an environmental document pursuant to the requirements of the National or North Carolina Environmental Policy Act (NEPA/SEPA)? Note: If you are not sure whether a NEPA/SEPA document is required, call the SEPA coordinator at (919) 733-5083 to review current thresholds for environmental documentation. Yes ® No ? If yes, has the document review been finalized by the State Clearinghouse? If so, please attach a copy of the NEPA or SEPA final approval letter. Yes ® No ? X. Proposed Impacts on Riparian and Watershed Buffers (DWQ Only) It is the applicant's (or agent's) responsibility to determine, delineate and map all impacts to required state and local buffers associated with the project. The applicant must also provide justification for these impacts in Section VII above. All proposed impacts must be listed herein, and must be clearly identifiable on the accompanying site plan. All buffers must be shown on a map, whether or not impacts are proposed to the buffers. Correspondence from the DWQ Regional Office may be included as appropriate. Photographs may also be included at the applicant's discretion. Will the project impact protected riparian buffers identified within 15A NCAC 2B .0233 (Meuse), 15A NCAC 2B .0259 (Tar-Pamlico), 15A NCAC 2B .0250 (Randleman Rules and Water Supply Buffer Requirements), or other (please identify )? Yes ® No ? If you answered "yes", provide the following information: Page 7 of 10 Identify the square feet and acreage of impact to each zone of the riparian buffers. If buffer mitigation is required calculate the required amount of mitigation by applying the buffer multipliers. Zone* Impact (square feet) Multiplier Required Mitigation 1 0.05 3 2 0.01 1.5 Total 0.06 Lone 1 extenas out su teet perpenatcuiar rrom near oanx or cnannei; cone Z extenas an additional 20 feet from the edge of Zone 1. If buffer mitigation is required, please discuss what type of mitigation is proposed (i.e., Donation of Property, Conservation Easement, Riparian Buffer Restoration / Enhancement, Preservation or Payment into the Riparian Buffer Restoration Fund). Please attach all appropriate information as identified within 15A NCAC 2B .0242 or .0260. Not required XI. Stormwater (DWQ Only) Describe impervious acreage (both existing and proposed) versus total acreage on the site. Discuss stormwater controls proposed in order to protect surface waters and wetlands downstream from the property. XII. Sewage Disposal (DWQ Only) Clearly detail the ultimate treatment methods and disposition (non-discharge or discharge) of wastewater generated from the proposed project, or available capacity of the subject facility. XIII. Violations (DWQ Only) Is this site in violation of DWQ Wetland Rules (I 5A NCAC 2H .0500) or any Buffer Rules? Yes E] No Is this an after-the-fact permit application? Yes ? No Page 8 of 10 XIV. Other Circumstances (Optional): It is the applicant's responsibility to submit the application sufficiently in advance of desired construction dates to allow processing time for these permits. However, an applicant may choose to list constraints associated with construction or sequencing that may impose limits on work schedules (e.g., draw-down schedules for lakes, dates associated with Endangered and Threatened Species, accessibility problems, or other issues outside of the applicant's control). Applicant/Agent's Signature Date (Agent's signature is valid only if an authorization letter from the applicant is provided.) US Army Corps Of Engineers Field Offices and County Coverage Asheville Regulatory Field Office Alexander Cherokee Iredell Mitchell US Army Corps of Engineers Avery Clay Jackson Polk 151 Patton Avenue Buncombe Cleveland Lincoln Rowan Room 208 Burke Gaston Macon Rutherford Asheville, NC 28801-5006 Cabarrus Graham Madison Stanley Telephone: (828) 271-4854 Caldwell Haywood McDowell Swain Fax: (828) 271-4858 Catawba Henderson Mecklenburg Transylvania Raleigh Regulatory Field Office Alamance Durham Johnston Rockingham US Army Corps Of Engineers Alleghany Edgecombe Lee Stokes 6508 Falls of the Neuse Road Ashe Franklin Nash Surry Suite 120 Caswell Forsyth Northampton Vance Raleigh, NC 27615 Chatham Granville Orange Wake Telephone: (919) 876-8441 Davidson Guilford Person Warren Fax: (919) 876-5283 Davie Halifax Randolph Wilkes Washington Regulatory Field Office Beaufort Currituck Jones US Army Corps Of Engineers Bertie Dare Lenoir Post Office Box 1000 Camden Gates Martin Washington, NC 27889-1000 Carteret* Green Pamlico Telephone: (252) 975-1616 Chowan Hertford Pasquotank Fax: (252) 975-1399 Craven Hyde Perquimans Wilmington Regulatory Field Office Anson Duplin Onslow US Army Corps Of Engineers Bladen Harnett Pender Post Office Box 1890 Brunswick Hoke Richmond Wilmington, NC 28402-1890 Carteret Montgomery Robeson Telephone: (910) 251-4511 Columbus Moore Sampson Fax: (910) 251-4025 Cumberland New Hanover Scotland Pitt Tyrrell Washington Wayne Union Watauga Yancey Wilson Yadkin *Croatan National Forest Only Page 9 of 10 US Fis US Fish and Wildlife Service Raleigh Field Office Post Office Box 33726 Raleigh, NC 27636-3726 Telephone: (919) 856-4520 h and Wildlife Service / National M US Fish and Wildlife Service Asheville Field Office 160 Zillicoa Street Asheville, NC 28801 Telephone: (828) 665-1195 [arine Fisheries Service National Marine Fisheries Service Habitat Conservation Division Pivers Island Beaufort, NC 28516 Telephone: (252) 728-5090 North Carolina State Agencies Division of Water Quality 401 Wetlands Unit 1650 Mail Service Center Raleigh, NC 27699-1650 Telephone: (919) 733-1786 Fax: (919) 733-9959 Division of Water Quality Wetlands Restoration Program 1619 Mail Service Center Raleigh, NC 27699-1619 Telephone: (919) 733-5208 Fax: (919) 733-5321 CAMA and NC Coastal Counties State Historic Preservation Office Department Of Cultural Resources 4617 Mail Service Center Raleigh, NC 27699-4617 Telephone: (919) 733-4763 Fax: (919) 715-2671 Division of Coastal Management Beaufort Chowan Hertford Pasquotank 1638 Mail Service Center Bertie Craven Hyde Pender Raleigh, NC 27699-1638 Brunswick Currituck New Hanover Perquimans Telephone: (919) 733-2293 Camden Dare Onslow Tyrrell Fax: (919) 733-1495 Carteret Gates Pamlico Washington NCWRC and NC Trout Counties Western Piedmont Region Coordinator Alleghany Caldwell Watauga 3855 Idlewild Road Ashe Mitchell Wilkes Kernersville, NC 27284-9180 Avery Stokes Telephone: (336) 769-9453 Burke Surry Mountain Region Coordinator Buncombe Henderson Polk 20830 Great Smoky Mtn. Expressway Cherokee Jackson Rutherford Waynesville, NC 28786 Clay Macon Swain Telephone: (828) 452-2546 Graham Madison Transylvania Fax: (828) 506-1754 Haywood McDowell Yancey Page 10 of 10