HomeMy WebLinkAbout20100015 Ver 1_Email_20070813Me: U-470 Timber Drive East Extension
Subject: Re: U-4703 Timber Drive East Extension
From: Rob Ridings <rob.ridings@ncmail.net>
Date: Mon, 13 Aug 2007 12:58:36 -0400
To: Drew Joyner <djoyner@dot.state.nc.us>
Drew,
If no other agencies request a meeting, then I'll go with DOT's recommendation of Alternative 4. It does
seem to be the best. (Hopefully, as we move along in the design process, some tweaking can further
minimize impacts to Tributary 3 if possible.)
Provided no one wants a formal merger meeting, I'll sign off for Alt 4.
-Rob Ridings, DWQ
Drew Joyner wrote:
Merger Team Members:
A Merger Team meeting for U-4703 was held on February 13, 2007. At that meeting, the team
discussed looking at a shorter bridge alternatives. Information concerning those alternatives,
including NCDOT's recommended alternative, is attached. It is my hope that the Merger Team can
come to agreement without having to hold another meeting. Please review the attached
information. If you agree with NCDOT's recommendation, please "reply all." If you have questions
or concerns, please let me know (you can "reply all," for that, as well). If any team member thinks
we need a meeting, please let me know and we'll schedule one. If all the Merger Team members
agree with the recommendation, I will collect signatures over the next few weeks. I would
appreciate a response to this email by August 24th.
Attached in this email are updated impact summary sheets (two spreadsheets in one excel
workbook) for each alternative and an information sheet explaining why NCDOT is recommending
Alternative 4. Also attached are the minutes from the Merger Team meeting for U-4703 held on
February 13, 2007 (which you received earlier).
Due to the size of the figures, I will send them in subsequent emails.
Drew Joyner, P. E.
Project Engineer
Project Development and Environmental Analysis Branch
North Carolina Department of Transportation
Phone: (919) 733-7844 ext. 268
Fax: (919) 733-9794
1 of 1 8/13/2007 12:59 PM