Loading...
HomeMy WebLinkAboutNC0003417_HF Lee Basis of Design Report_20161123526 South Church Street Charlotte, NC 28202 Mailing Address: PO Box 1006 Mail Code EC13K Charlotte, NC 28201-1006 980 373 2779 704 382 6240 fax November 23, 2016 Mr. David May North Carolina Department of Environmental Quality Washington Regional Office 943 Washington Square Mall Washington, NC 27889 Subject: H.F. Lee Energy Complex Interim Action Plan - Basis of Design Report - First Submittal Dear Mr. May: Enclosed is the first submittal of the Interim Action Plan Basis of Design Report for the H.F. Lee Energy Complex. This submittal incorporates the 30% design drawings and supporting documents. The next Basis of Design submittal is expected January 27, 2017. If you have any questions on the enclosed information, please contact me at ryan.czop@duke- energy.com or at 980-373-2779. Respectfully submitted, Ryan Czop Engineer I Waste and Groundwater Programs Cc/enc: Mr. Steve Lanter, NCDEQ 1636 Mail Service Center Raleigh, NC 27699 - 1636 ecc: Mr. Kevin Kirkley, Duke Energy Mr. Mike Graham, Duke Energy Mr. Ed Sullivan, Duke Energy Mr. John Toepfer, Duke Energy Mr. Will Hart, NCDEQ 4CT synTerra BASIS OF DESIGN REPORT (30% SUBMITTAL) H.F. LEE ENERGY COMPLEX 1199 BLACKJACK CHURCH ROAD GOLDSBORO,, NORTH CAROLINA 27530 NOVEMBER 2016 PREPARED FOR DUKE ENERGY PROGRESS,, LLC. 410 S. WILMINGTON STREET/NCIS RALEIGHj, NORTH CAROLINA 27601 �� DUKE ENERGY PROGRESS William La tz, NC PE 44301 Senior Project Engineer ts a," Justi Mahan, NC LG 2026 Project Manager INNOVATE 148 River Street, Suite 220 Greenville, SC 29601 (864)421-9999 Fax (864)421-9909 www.synterracorp.com Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra Page i P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx TABLE OF CONTENTS (Gray highlights indicate work in progress) SECTION PAGE 1.0 INTRODUCTION AND BACKGROUND .............................................................. 1-1 1.1 Project Background ................................................................................................... 1-1 1.1.1 Settlement Agreement ........................................................................................ 1-1 1.1.2 Interim Action Plan ............................................................................................. 1-2 1.1.3 Purpose of Basis of Design ................................................................................ 1-2 1.1.4 Scope and Objectives of the Interim Action .................................................... 1-3 1.2 Interim Action Alternative Evaluation .................................................................. 1-3 1.3 Report Organization ................................................................................................. 1-4 2.0 REFINED SITE CONCEPTUAL MODEL ................................................................. 2-1 2.1 Geology and Hydrogeology .................................................................................... 2-2 2.2 Summary of Baseline Site Conditions .................................................................... 2-3 2.3 Summary of Aquifer Characteristics ...................................................................... 2-3 3.0 INTERIM ACTION DESIGN CONSIDERATIONS .............................................. 3-1 3.1 Preliminary Design Criteria and Layout ............................................................... 3-1 3.2 Groundwater Extraction System Design ............................................................... 3-1 3.3 Evaluation of Alternative Technologies ................................................................ 3-1 3.4 Groundwater Flow Modeling ................................................................................. 3-2 3.4.1 Groundwater Flow Model Conceptualization Design .................................. 3-2 3.4.2 Groundwater Flow Model Calibration ............................................................ 3-2 3.5 Groundwater Extraction System Design ............................................................... 3-2 3.5.1 Current Conditions ............................................................................................. 3-2 3.5.2 Post-Basin Closure Conditions .......................................................................... 3-3 3.6 Groundwater Fate and Transport Modeling ........................................................ 3-3 3.6.1 Groundwater Fate and Transport Model Calibration ................................... 3-3 3.6.2 Predictive Results ................................................................................................ 3-3 3.6.3 Implications of Remedy on Geochemical Conditions and Plume Stability 3-3 3.7 Groundwater Extraction System Design Limitations .......................................... 3-4 Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra Page ii P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx 4.0 WELL DESIGN .............................................................................................................. 4-1 4.1 Overview of Extraction Well Network .................................................................. 4-1 4.2 Well Construction ..................................................................................................... 4-1 4.3 Groundwater Extraction Rates ................................................................................ 4-2 5.0 GROUNDWATER EXTRACTION SYSTEM PIPELINE AND PUMP STATION DESIGN ........................................................................................................................... 5-1 5.1 Overall Pipeline Design Basis ................................................................................. 5-1 5.1.1 Well Pumps .......................................................................................................... 5-1 5.1.2 Well Discharge Piping ........................................................................................ 5-1 5.1.3 Well Head Configuration................................................................................... 5-2 5.2 Extraction Well Pipeline ........................................................................................... 5-2 5.2.1 Pipe Pressure ....................................................................................................... 5-2 5.2.2 Pipe Flow .............................................................................................................. 5-3 5.2.3 Pipe Insulation ..................................................................................................... 5-4 5.2.4 Pipe Expansion/Contraction .............................................................................. 5-5 6.0 ELECTRICAL AND INSTRUMENTATION DESIGN .......................................... 6-1 6.1 Piping and Instrumentation Diagram .................................................................... 6-1 6.2 Pump Controls .......................................................................................................... 6-1 6.3 Emergency System Shutdown ................................................................................ 6-1 7.0 DESIGN DOCUMENTS .............................................................................................. 7-1 7.1 Design Drawings ....................................................................................................... 7-1 7.2 Specifications ............................................................................................................. 7-1 8.0 GROUNDWATER EXTRACTION SYSTEM OPERATION ................................ 8-1 8.1 System Performance Metrics ................................................................................... 8-1 8.2 Permits ........................................................................................................................ 8-1 8.3 Institutional Controls ................................................................................................ 8-1 8.4 Contingency Plans .................................................................................................... 8-1 8.5 Construction and Monitoring Schedules ............................................................... 8-1 Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra Page iii P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx LIST OF FIGURES Figure 1-1 Site Location Map Figure 1-2 Conceptual Remediation System Figure 4-1 Extraction Well Schematic Figure 5-1 Well Head Enclosure LIST OF TABLES Table 4-1 Target Extraction Well Screen Intervals LIST OF APPENDICES Appendix A Pilot Test Report Appendix B Evaluation of Alternative Remedial Technologies Appendix C Groundwater Flow Model Report Appendix D Geochemical Model Report Appendix E Pipe and Pump Selection Package Appendix F Design Drawings Appendix G Technical Specifications Appendix H Permits Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra Page iv P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx LIST OF ACRONYMS BGS Below Existing Ground Surface CAMA Coal Ash Management Act CAP 1 Corrective Action Plan Part 1 CAP 2 Corrective Action Plan Part 2 Constituent Constituent of Interest CSA Comprehensive Site Assessment CSA SUP CSA Supplemental Report CSM Conceptual Site Model DEP Duke Energy Progress, LLC. DEQ North Carolina Department of Environment Quality Eh Reduction Potential ft Feet gpm Gallons per Minute HDPE High-Density Polyethylene HMI Human Machine Interface Hp Horsepower IAP Interim Action Plan IMAC Interim Maximum Allowable Concentrations MW Monitoring Well NCAC North Carolina Administrative Code NPDES National Pollution Discharge Elimination System Plant H. F. Lee Energy Complex psig Per Square Inch Gauge ROI Radius of Influence USACE United States Army Corps of Engineers USEPA United States Environmental Protection Agency VFD Variable Frequency Drive 2L NCDEQ/DWR Title 15, Subchapter 2L. Groundwater Quality Standards Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra Page 1-1 P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx 1.0 INTRODUCTION AND BACKGROUND Duke Energy Progress, LLC (Duke Energy) owns and operates the H.F. Lee Energy Complex (H.F. Lee, Lee Plant or Site) located at 1199 Black Jack Church Road, Goldsboro, North Carolina. The property encompasses approximately 2,100 acres, including the ash basins (171-acre inactive ash basins and 143-acre active ash basin), cooling pond and plant operations area. A Site Location Map is included as Figure 1-1. The Neuse River (a main stem river) flows through the property. The Lee Plant began operation as a coal-fired electricity-generating facility in 1951. From 1967 through 1971 four oil-fueled combustion turbine units were added. In 2000, five simple-cycle dual fuel (oil and natural gas) units were built. The three coal-fired units were retired in September 2012, followed by the four oil-fueled combustion turbine units in October 2012. The new combined-cycle plant was brought on line in 2012. 1.1 Project Background In order to satisfy requirements of the North Carolina Coal Ash Management Act (NC CAMA), a Comprehensive Site Assessment (CSA), Corrective Action Plan (CAP) Parts 1 and 2, Interim Action Plan (IAP) and the CSA Supplemental Report (CSA SUP) were prepared and submitted to the North Carolina Department of Environmental Quality (DEQ). The most recent document, the CSA SUP, was submitted to DEQ on September 15, 2016. The CAP (Parts 1 and 2) was designed to describe means to restore groundwater quality to the level of the standards, or as close as is economically and technologically feasible in accordance with T15A NCAC 02L.0106. Exceedances of numerical values contained in Subchapter 2L and Appendix 1 Subchapter 02L (IMACs) at or beyond the compliance boundary were determined to be the basis for corrective action with the exception of parameters for which naturally occurring background concentrations are greater than the standards. 1.1.1 Settlement Agreement A Settlement Agreement between DEQ and Duke Energy signed on September 29, 2015, requires accelerated remediation to be implemented at sites that demonstrate off-site groundwater impacts. Historical and CSA assessment indicates the potential for off-site impact east of the active ash basin at H.F. Lee. Figure 1-2 illustrates the general area to be addressed for accelerated remediation. Arsenic and boron have been identified as constituents which occur at levels above 2L and greater than proposed background concentrations. Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra Page 1-2 P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx Arsenic and boron impact which has the potential to migrate beyond the compliance boundary and off site, will be the focus of the accelerated remediation plan. Duke Energy provided an Accelerated Remediation Summary to DEQ on February 17, 2016 which supplemented and updated information included with the CAP Part 2. In correspondence dated March 28, 2016, DEQ acknowledged receipt of the Remediation Summary and requested additional information. DEQ conditionally approved the IAP(s) in a letter dated July 22, 2016 with the condition (among others) that a Basis of Design Report be submitted for review. 1.1.2 Interim Action Plan The IAP, submitted to DEQ in April 2016, provided an update on planned additional assessment and remedial activities at the site. Interim action activities conducted in 2016 which pertain to the east side of the active ash basin are summarized as follows: Background monitoring wells AMW-16BC, AMW-17S and AMW-17BC were installed north of the active basin to increase the available background data set. Monitoring wells AMW-18S and AMW-18BC were installed to further delineate potential ash basin influence east of the active basin (Figure 1-2). A pilot test was conducted in the area proposed for accelerated remediation. The pilot test included the installation of a six inch diameter extraction well (PTW-1) and five observation wells (PTW-2 through PTW-6). Two step drawdown tests and one 36-hour constant rate pumping test were completed in July and August 2016. 1.1.3 Purpose of Basis of Design The purpose of this Basis of Design Report is to provide a system layout and sizing of system components including wells, piping, pumps, and discharge system. It also serves to provide control system capabilities and power requirements. This report also includes evaluation of fate and transport of constituents, potential changes to site geochemistry as a result of remedial efforts and evaluation of remedial alternatives. Key elements include: Refined site conceptual model which incorporates aquifer test results Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra Page 1-3 P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx Groundwater extraction system design Groundwater fate and transport modeling with an emphasis on boron mobility through 2117 Geochemical modeling to address constituent mobility and potential geochemical changes related to remediation 1.1.4 Scope and Objectives of the Interim Action Constituents associated with coal ash pore water migration have been identified within groundwater in the surficial flow zone at the compliance boundary east of the active ash basin. Arsenic and boron are the primary constituents greater than 2L in groundwater. Results from monitoring wells northeast of the active basin have not indicated arsenic and boron concentrations greater than 2L. This indicates that constituent migration is east from the active ash basin and then south and southeast toward the Neuse River. This is consistent with radial groundwater flow for short distances away from the basin. Groundwater monitoring wells indicating constituent concentrations above 2L adjacent to the active basin are on Duke Energy property. The primary objective of the groundwater extraction system is to accelerate the reduction of constituent concentrations in groundwater to below 2L at and beyond the compliance boundary and limit further migration of constituents. 1.2 Interim Action Alternative Evaluation The CAP Part 2 and IAP evaluated groundwater extraction by (1) a network of conventional vertical wells and, (2) an interceptor trench, as part of the remedy for the active ash basin. The IAP proposed completion of a groundwater extraction pilot test to determine expected flow rates and an effective radius of influence for extraction wells. To conduct this test, United States Army Corps of Engineers (USACE) permitting for installation of the test wells was necessary because the well locations are in potential wetland areas. Through the permitting effort, it became clear that disturbance of wetlands could be a significant issue in implementing the proposed interim actions. Ground surface disturbance was determined to be less with a conventional extraction well network than with installation of an interceptor trench. As a result, groundwater extraction along the eastern edge of the active basin is proposed to be accomplished with a network of conventional vertical wells. This approach was evaluated in the CAP and determined to be feasible and effective. Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra Page 1-4 P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx In addition to less surface disturbance, this approach will also provide more operational flexibility. With a network of wells, spatial and temporal variations in the response of the aquifer can be addressed through operational cycling and pumping rate adjustment to individual wells, or by adding wells. Details of alternative remediation technologies were presented in Section 6.0 of the CAP Part 2 (SynTerra, February 2016). The pilot test conducted at H.F. Lee in August 2016 confirmed the feasibility of implementation of extraction wells east of the active ash basin. 1.3 Report Organization The initial 30% submittal provides enough detail of the groundwater extraction design to conceptualize system components, performance, and initiate evaluation of site specific considerations. Provided herein are conceptual layout drawings, preliminary pump and piping specifications. Findings from the aquifer pumping test which determined potential extraction system yield and area of influence are summarized in Section 2.3 and the pilot test report is provided as Appendix A. Sections three through eight will continue to be developed and incorporated into 60% and 90% design packages prior to the final (100%) submittal. Appendices including Focused Evaluation of Alternative Remedial Technologies, Updated Groundwater Fate and Transport Modeling Report, and Updated Geochemical Modeling Report will be provided as interim submittals at time of completion. Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra Page 2-1 P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx 2.0 REFINED SITE CONCEPTUAL MODEL The site conceptual model (SCM) is an interpretation of processes and characteristics associated with hydrogeologic conditions and constituent interactions at the Lee Plant site. The purpose of the SCM is to evaluate areal distribution and flow pattern of constituents with regard to site-specific geological/hydrogeological and geochemical properties at the site relative to the source, potential receptors and natural control mechanisms. The SCM was developed using data and analysis from the CSA (SynTerra, August 2015) and was further refined in the Corrective Action Plan Part 2 (SynTerra, February 2016). This discussion incorporates additional assessment conducted between June and August 2016. Key components of the H.F. Lee SCM are as follows: The ash basins, surficial deposits, the Black Creek and the Cape Fear deposits make up distinct hydrogeologic layers at the H.F. Lee site. Unconsolidated saprolite and/or metamorphic bedrock underlie the sedimentary deposits. Where unconsolidated saprolitic material underlies or is laterally contiguous with either Black Creek or Cape Fear deposits it is considered a component of that hydrogeologic layer. Groundwater in the surficial deposits under the ash basins flows horizontally to the east and south and discharges into the Neuse River or Halfmile Branch. Water within the active ash basin and inactive ash basin 1 is hydraulically higher (upgradient) than the surrounding land surface. Pore water drains through the underlying soil to the groundwater. Groundwater flow is toward the Neuse River (south for the active basin, east to southeast for the inactive basins). This flow direction is away from upgradient receptors. The Neuse River is the hydraulic boundary for constituent migration. Groundwater and seeps are the primary mechanisms for migration of ash-related constituents to the environment. Both flow toward the Neuse River. Boron and arsenic are constituents associated with the ash basins and generally are not found at comparable levels in background wells. Cobalt, iron, vanadium and manganese are ubiquitous in groundwater samples including background locations. Provisional background values have been used to interpret how much of each constituent is background or from basin influence. Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra Page 2-2 P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx Results from sorption studies on site specific soils indicate that iron and manganese leach from naturally occurring materials. While it is known that these metals leach from coal ash, occurrences in background areas limit their use as indicators of groundwater contamination. The primary geochemical factors that affect groundwater quality in the surficial aquifer in the vicinity of the active ash basin are variations in pH and redox potential (Eh). In background areas upgradient from the active basin pH is generally low (4.2 to 4.5) and Eh is high. In contrast, pH values are higher (6.0 to 6.5) and Eh values are lower in groundwater beneath and immediately downgradient from the ash basin. Flow rates observed during the August 2016 pumping test for the surficial hydrogeologic unit at the east side of the active ash basin indicated higher hydraulic conductivity (136 ft/day) than previously estimated based on slug tests from assessment wells (geometric mean for surficial unit of 4.85 ft/day). The duration of pumping tests is longer than slug tests and affects a larger formation volume. Due to scale dependence, pumping tests often result in greater estimates of hydraulic conductivity (Butler and Healey, 1998). The difference in results illustrates the importance of pumping tests for extraction system design purposes. Slug test results are useful data for comparison purposes but may be heavily influenced by near-well conditions. Field observations from well installations indicate the surficial deposits east of the active basin are characterized by thick (15 feet or greater) layers of medium to coarse grained sand which appear to be contiguous across the area. Downward vertical migration of constituents is restricted due to the clay and silt layers beneath the ash basins that act as confining layers over the deeper aquifers in the area. 2.1 Geology and Hydrogeology Assessment activities conducted as part of the CSA in 2015 indicate that the lithology beneath the site generally consists of a layer of silty to clayey surficial deposits underlain by interbedded clay and sand of the Cape Fear and Black Creek deposits. The Cape Fear is present beneath surficial deposits in areas on the west side of the active ash basin. The Black Creek deposits are present beneath the active basin and in areas to the east. Field observations indicate that a confining clay layer at the top of the Black Creek deposits is present under the active basin and to the east. Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra Page 2-3 P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx Pertinent aspects of the hydrogeology east of the active basin are summarized as follow: Boron and arsenic are present in the surficial hydrogeologic unit east of the active basin at concentrations above 2L. Monitoring results from below the underlying Black Creek confining clay do not indicate elevated boron and arsenic concentrations. Depth to groundwater varies from one to five feet in the area. Surficial deposits in the area consist primarily of medium grained sand with minor clay lenses. The surficial hydrogeologic unit thickens from the north (20 feet) to the south (40 feet) toward the Neuse River. 2.2 Summary of Baseline Site Conditions Based on groundwater monitoring results from wells east of the active basin, arsenic (AMW-18S, CMW-6 and CMW-6R) and boron (AMW-18S, CMW-6, CMW-6R and CMW-5) are present at concentrations above 2L in the surficial aquifer. Constituent concentrations at AMW-18S in July 2016 were greater than 2L standards for arsenic and boron and were similar to June 2016 results from CMW-6R for those constituents. Results from shallow monitoring wells to the north (AMW-17S and BGMW-10) and on the northeastern side of the active basin (AMW-14S and AMW-15S) have not indicated arsenic and boron exceedances. This is consistent with constituent migration towards the CMW-6R and AMW-18S areas. Monitoring well CMW-6R is located at the compliance boundary. Monitoring well AMW-18S is located southeast of CMW-6R, just outside of the compliance boundary. Preliminary groundwater fate and transport modeling included in the CAP Part 2 indicated that removing constituent mass from this area will accelerate reduction of groundwater constituents at the compliance boundary. 2.3 Summary of Aquifer Characteristics Aquifer testing east of the active basin consisted of two step-drawdown tests and a pumping test in late July and early August 2016. Approximately 10,000 gallons of water was extracted during the two step-drawdown tests. On August 2, 2016, a 36-hour constant rate pumping test was initiated at pilot test well PTW-1. The volume of water extracted during the 36-hour pumping test was approximately 63,500 gallons. The extracted groundwater was pumped into the active ash basin. Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra Page 2-4 P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx Results from step-drawdown tests and pumping test indicate the following: Average sustainable yields (over the course of the test) were at least 30 gallons per minute. The radius of influence is approximately 300 feet from the extraction well. Hydraulic conductivity of approximately 136 ft/day with an assumed average aquifer thickness of about 20 feet. Specific yield and hydraulic conductivity are constant throughout the target area, confirming low heterogeneity of the unconfined aquifer flow system. Hydraulic conductivity calculated from step-drawdown and pumping tests exceeded predicted hydraulic conductivities from well development logs. Using graphical calculation methods and AQTESOLV Pro.4.5, the geometric mean of the transmissivity in the surficial unit is 2,970 ft2/day. This value is representative of medium to coarse sand. Aquifer data in the vicinity of PTW-1 indicate conditions at this location would support viable extraction wells under current site conditions. There was no measurable water level drawdown of the hydrogeologic unit below the Black Creek clay unit from pumping the surficial aquifer system. Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra Page 3-1 P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx 3.0 INTERIM ACTION DESIGN CONSIDERATIONS This section addresses the identification and evaluation of possible corrective measures applicable to the restoration of groundwater quality in the area of interest to the east of the active basin. 3.1 Preliminary Design Criteria and Layout Groundwater extraction along the eastern edge of the active basin is proposed to be accomplished with a network of conventional extraction wells. Results from aquifer testing indicate that groundwater extraction is feasible given site conditions. 3.2 Groundwater Extraction System Design The groundwater extraction system design is based on effective and efficient capture and conveyance of groundwater for treatment and discharge. Groundwater extraction was evaluated in the CAP Part 2 (SynTerra, February 2016) and IAP as part of the remedy for the area east of the active ash basin. The IAP proposed completion of aquifer testing to evaluate the feasibility of groundwater extraction within this area. Results of the aquifer testing indicated groundwater extraction could be a viable remedial alternative. Criteria for the design of groundwater extraction at the Lee Plant include: Installation of extraction wells with sufficient capacity to efficiently extract groundwater and constituent mass from the surficial hydrogeologic flow system; Well placement within the area of highest concentrations (east of the active ash basin) as determined by extensive groundwater sampling and assessment; and Adequate treatment of extracted groundwater to meet potential limits required by selected discharge option. Extracted groundwater is anticipated to be pumped to a permitted National Pollutant Discharge Elimination System (NPDES) outfall, possibly with treatment prior to the outfall. A conceptual layout of the remediation system is shown on Figure 1-2. The system layout and the location of the treatment system and control panel will be further evaluated through the 60% design submittal. The final location of the treatment system and control panel will be coordinated with basin closure activities. 3.3 Evaluation of Alternative Technologies Collection of groundwater can be accomplished with extraction wells or collection trenches. For this facility, groundwater will be extracted primarily from the surficial Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra Page 3-2 P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx groundwater zone. Conventional vertical extraction wells are an effective method of groundwater capture and will provide much more operational flexibility and less ground disturbance than a trench. With a series of wells, spatial and temporal variations in the response of the aquifer can be addressed through operational cycling and pumping rate adjustment to individual wells or by adding wells. For the purpose of accelerated groundwater remediation in the area of interest, this is the most viable approach for ease of design and implementation. A focused evaluation of alternative remedial technologies will be provided in Appendix B. 3.4 Groundwater Flow Modeling An initial Groundwater Flow and Transport Modeling Report was developed and submitted with the CAP Part 1 on November 2, 2015. This model will be updated with information obtained from the installation of data gap wells and the recently completed aquifer pumping test. The updated groundwater flow model will be included in Appendix C and prepared to inform the 60% design level. 3.4.1 Groundwater Flow Model Conceptualization Design Discussion of Groundwater Flow Model Conceptualization Design will be included in the final Basis of Design Report submittal. 3.4.2 Groundwater Flow Model Calibration Discussion of Groundwater Flow Model Calibration will be included in the final Basis of Design Report submittal. 3.5 Groundwater Extraction System Design The groundwater extraction system design is based on effective and efficient capture and conveyance of groundwater for treatment and discharge. 3.5.1 Current Conditions The step-drawdown test and extended pumping test data were used to calculate a hydraulic conductivity of approximately 136 feet per day (ft/day) with an assumed average aquifer thickness of about 20 feet for the surficial aquifer east of the active basin. Aquifer data in the vicinity of PTW-1 indicate conditions at this location could support viable extraction wells under current site conditions. Radius of Influence (ROI) was calculated to be at least 300 feet. Average sustainable yields were at least 30 gallons per minute (gpm). The 30 gpm flow rate yielded a 3-foot drawdown. Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra Page 3-3 P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx 3.5.2 Post-Basin Closure Conditions Source control measures are being addressed separately but are assumed to occur in addition to the groundwater corrective action alternatives discussed in this submittal. The closure scenario at H.F. Lee is anticipated to involve excavation to a lined solution. The hydraulic head currently associated with the active basin is expected to be lowered in this closure scenario which will lessen or remove the component of groundwater flow to the east of the basin. 3.6 Groundwater Fate and Transport Modeling An initial Groundwater Flow and Transport Modeling Report was developed and submitted with the CAP Part 1 on November 2, 2015. This model will be updated with information obtained from the installation of data gap wells and the recently completed aquifer pumping tests and groundwater analysis. The updated groundwater fate and transport model will predict how long boron concentrations will remain above the 2L at the offsite property boundary (compliance boundary), and at least through the year 2117. This model will be included in Appendix C and prepared to inform the 60% design level. 3.6.1 Groundwater Fate and Transport Model Calibration Discussion of Groundwater Fate and Transport Model Calibration will be included in the final Basis of Design Report submittal. 3.6.2 Predictive Results Discussion of predictive results will be included in the final Basis of Design Report submittal. 3.6.3 Implications of Remedy on Geochemical Conditions and Plume Stability Implementation of the remedial strategy (groundwater extraction) is anticipated to drive subsurface geochemical conditions toward more natural background conditions. This is likely to result in a localized decrease in pH and increase in Eh. A decrease in pH will generally cause a decrease in the mobility of anions and an increase in the mobility of cations. Anions will have a greater electrostatic attraction and cations will have a lesser electrostatic attraction towards the sorptive medium as mineral surfaces transition from a net negative to a net positive surface charge. In general, the expected decrease in pH toward background conditions may result in sustained concentrations of soluble Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra Page 3-4 P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx groundwater cationic species such as manganese, and a decrease in groundwater concentrations of anionic species such as arsenic. Changes in geochemistry near the ash basin as a result of groundwater extraction, such as a return to more natural Eh-pH conditions, are not expected to change the mobility of boron. 3.7 Groundwater Extraction System Design Limitations Discussion of groundwater extraction system design limitations will be included in the final Basis of Design Report submittal. Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra Page 4-1 P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx 4.0 WELL DESIGN The well system design is intended to provide drawdown and capture groundwater flow to the east of the active basin. 4.1 Overview of Extraction Well Network Based on this objective and results from the pumping test, design spacing between extraction wells is estimated at 300 feet along the eastern edge of the basin. The expected width of the plume at the base of the basin is approximately 2,700 feet so nine wells are anticipated. At 30 gpm per well, the total flow rate for the proposed extraction system would be 270 gpm. At some point greater pumping rates and drawdown levels may be desirable so, for planning purposes, a maximum design flow rate of 540 gpm is used. The nine extraction wells will be located approximately adjacent to the existing monitoring well access path to minimize disturbance of wetland areas during drilling and installation and to provide access for operations and maintenance (O&M) of the extraction system. 4.2 Well Construction The extraction wells will be installed by a North Carolina licensed well driller in accordance with North Carolina Administrative Code Title 15A, Subchapter 2C – Well Construction Standards, Rule 108 Standards of Construction: Wells Other Than Water Supply (15A NCAC 02C .0108). The wells are planned to be drilled using 12-inch hollow stem auger drilling methods to allow for a 3-inch annular space around the 6- inch casing and screen. The well casing will extend approximately one foot above ground surface. The top of the sand pack (Gravel Pack #3) will extend to two feet above the top of the well screen. The bentonite well seal will be at least one foot thick. Neat cement grout with 5% bentonite will be placed to within three feet of the ground surface. Concrete grout will be placed in the top three feet of the annular space. Due to difficult access in some areas, well construction methods and specifications may be modified for site specific conditions. All materials and installations will be in accordance with 15A NCAC 02C. Groundwater modeling will aid in the determination of minimum yield requirements to achieve the objective of accelerated remediation. A schematic diagram of an extraction well is included as Figure 4-1. The wells will be drilled and installed to approximate depths between 25 and 40 feet, corresponding to the shallow aquifer thickness, to enable recovery through the entire shallow aquifer water column. The depth of each well will correspond to the shallow aquifer thickness at that location. The exact depths will be determined based on Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra Page 4-2 P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx observations in the field during drilling. The expected depths, based on previous drilling data, are provided in Table 4-1. The wells will not penetrate the underlying clay layer. The well screens will be installed near the bottom of the permeable formation to reduce premature oxidation of iron during extraction, which could cause extraction and pumping system fouling and loss of efficiency. Wound wire screens will be used to reduce loss of efficiency over time and to facilitate rehabilitation if necessary. The extraction wells will be 6-inch diameter wells with Schedule 40 PVC casings. At a maximum depth of 40 feet, the worst case scenario collapse pressure will be 17.3 psi. 𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃 (𝑝𝑝𝑃𝑃𝑝𝑝)=𝐷𝐷𝑃𝑃𝑝𝑝𝐷𝐷ℎ 𝑜𝑜𝑜𝑜 𝐶𝐶𝐶𝐶𝑃𝑃𝑝𝑝𝐶𝐶𝐶𝐶 (𝑜𝑜𝑃𝑃𝑃𝑃𝐷𝐷) × 𝑊𝑊𝐶𝐶𝐷𝐷𝑃𝑃𝑃𝑃 𝑊𝑊𝑃𝑃𝑝𝑝𝐶𝐶ℎ𝐷𝐷 (𝑙𝑙𝑙𝑙𝑃𝑃 𝑝𝑝𝑃𝑃𝑃𝑃 𝑐𝑐𝑃𝑃𝑙𝑙𝑝𝑝𝑐𝑐 𝑜𝑜𝑜𝑜𝑜𝑜𝐷𝐷) 𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃 (𝑝𝑝𝑃𝑃𝑝𝑝)=40 𝑜𝑜𝑃𝑃𝑃𝑃𝐷𝐷 × 62.4 𝑙𝑙𝑙𝑙𝑃𝑃𝑜𝑜𝐷𝐷3 × 1 𝑜𝑜𝐷𝐷2144 𝑝𝑝𝐶𝐶2 =17.3 𝑝𝑝𝑃𝑃𝑝𝑝 The collapse pressure for 6-inch Schedule 40 PVC is 77 psi. Six-inch diameter PVC casing installations are allowed to depths of 130 feet in accordance with 15A NCAC 02C. The well screens will be 0.010-inch (10-slot) Johnson Screen® Free-Flow® 304 stainless steel wound wedge (or comparable) wire screens. These screens have a collapse pressure of 87 psi. The well screens will be 10 feet long which will provide for a minimum flow capacity of 108 gpm which is significantly greater than the maximum design flow of 60 gpm. 𝐶𝐶𝐶𝐶𝑝𝑝𝐶𝐶𝑐𝑐𝑝𝑝𝐷𝐷𝐶𝐶 (𝐶𝐶𝑝𝑝𝑔𝑔)=𝑂𝑂𝑝𝑝𝑃𝑃𝐶𝐶 𝐴𝐴𝑃𝑃𝑃𝑃𝐶𝐶 × 0.31 @ 0.1 𝑜𝑜𝐷𝐷/𝑃𝑃𝑃𝑃𝑐𝑐 × 𝑆𝑆𝑐𝑐𝑃𝑃𝑃𝑃𝑃𝑃𝐶𝐶 𝐿𝐿𝑃𝑃𝐶𝐶𝐶𝐶𝐷𝐷ℎ (𝑜𝑜𝑃𝑃𝑃𝑃𝐷𝐷) 𝑄𝑄=35 × 0.31 × 10 =108.5 𝐶𝐶𝑝𝑝𝑔𝑔 4.3 Groundwater Extraction Rates Results of the pilot test activities in July and August 2016 indicate a hydraulic conductivity of approximately 136 feet per day (ft/day) with an assumed average aquifer thickness of about 20 feet for the surficial aquifer east of the active basin. Radius of influence (ROI) was calculated to be at least 300 feet. Average sustainable yields were at least 30 gallons per minute (gpm). The 30 gpm flow rate yielded a 3-foot drawdown. Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra Page 5-1 P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx 5.0 GROUNDWATER EXTRACTION SYSTEM PIPELINE AND PUMP STATION DESIGN 5.1 Overall Pipeline Design Basis The anticipated flow rate for the system is 270 gpm. The pipeline design basis is 540 gpm to allow for increased pumping rates if that becomes necessary. The piping system will be constructed either aboveground or below grade with high density polyethylene (HDPE). Above grade installation would be adequately insulated to protect from freezing conditions. 5.1.1 Well Pumps The extraction wells will be equipped with a Grundfos 62S75-14 (or equal) submersible electric pumps. Each pump will be equipped with variable frequency drive (VFD) motor control and electrical and thermal motor protection. Assuming similar conditions and flow rates as indicated during the pumping test, the pumps provide 285 feet of nominal head, operate on 230 or 460 volt 3-phase power and have a 7.5 horsepower (Hp) motor. The pump diameter is four inches with a 2-inch discharge. At 30 gpm, the pump provides 375 feet of head and operates at 55% efficiency. At 60 gpm, the pump provides 305 feet of head and operates at 70% efficiency. The minimum 305 feet of head is sufficient to provide the necessary flow rates for the system. The expected head requirement assumes 45 feet from the well water column, 195 feet for piping losses, 30 feet for fittings loss, and an estimated 20 feet to reach treatment system headworks. This pump provides the greatest efficiency over the design flow rate range. Use of a VFD will provide the capability to operate the pump at lower flow rates, if necessary, while not significantly sacrificing efficiency or subjecting the pump to unnecessary working pressure. The control system will include water level and flow monitoring and feedback to the VFD and will allow for efficient, timely and effective operation of the pumps. 5.1.2 Well Discharge Piping It is anticipated that the well pump will discharge through a 2-inch diameter discharge pipe to the surface. The pipe will be secured in the center of the well with Simmons (or equal) top guides. Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra Page 5-2 P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx 5.1.3 Well Head Configuration Well boxes will be finished above or below grade and insulated to simplify O&M (Figure 5-1 provides an above grade example). Well box piping and fittings may be 304 stainless steel to reduce risk of damage due to O&M. The piping will transition to HDPE fusion-welded pipe. The well seal will be Simmons Model 316 (or equal) cast solid plate, 4-bolt seal with threaded openings for the pump power cable, level monitor and well vent. The piping will be fitted with a Simmons Model 516SS (or equal) check valve. Flow monitoring at the well head will be accomplished with a Sparling Tigermag EP FM656 (or equal) electromagnetic flow meter with direct read and transmitter. Well water level will be monitored with a Solinist Levelogger (or equal) transducer. This feature will allow level control of the pumping system. The piping will be fitted with a one-half inch sampling port ball valve. The well head piping train will include a ball valve for isolation of the well head from the header and pipe unions for maintenance access. The well head will be enclosed within a Virtual Polymer Compounds (or equal) 6- foot by 3-foot by 30-inch high insulated fiberglass aboveground vault with full top access and locking cover. The vault will be attached to a poured-in-place concrete foundation. 5.2 Extraction Well Pipeline The extraction well header pipe will connect all of the well discharges to the treatment system. It will be constructed of polyurethane pre-insulated 6-inch diameter DR-11 HDPE. 5.2.1 Pipe Pressure The maximum pressure of the system will be less than 150 psi. Manufacturers’ pressure rating for DR-11 HDPE pipe is 200 psi. DR-11 pipe also meets long term pressure performance criteria. Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra Page 5-3 P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx PR =2(HDS) 𝑜𝑜𝐸𝐸 𝑜𝑜𝑇𝑇𝐷𝐷𝐷𝐷−1 PR: pressure rating, psi HDS: hydrostatic design stress, psi; 800 @ 73 degrees Fahrenheit (oF) fE: environmental design factor; 1.00 for water fT; operating temperature multiplier; 1.11 @ 73 oF DR: pipe dimension ratio, DR=D/t; D: diameter, t: thickness 150 =2(800)(1.00)(1.11)𝐷𝐷𝐷𝐷−1 DR = 11.8; 11.8 > 11, so DR-11 is acceptable 5.2.2 Pipe Flow Flow velocities for the extraction well and header piping were estimated using the Hazen Williams formula with US units. S = 𝑃𝑃𝑑𝑑𝐿𝐿=4.52 𝑄𝑄1.852 𝐶𝐶1.852 𝑑𝑑4.8704 where: S = frictional resistance (pressure drop per foot of pipe) in psig/ft (psi gauge pressure per foot) Pd = pressure drop over the length of pipe in psig L = length of pipe in feet Q = flow, gpm C = pipe roughness coefficient d = inside pipe diameter, in At the assumed header pipe operating flow rate of 270 gpm, the water velocity in the pipe would be 3.85 feet per second (fps) and the head loss would be 0.010 feet of water per foot of pipe length (ft/ft). At the design flow rate of 540 gpm the velocity would be 7.71 fps and the head loss would be 0.036 ft/ft. Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra Page 5-4 P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx Piping from the well boxes to the header is anticipated to be pre-insulated 2-inch diameter DR-11 HDPE. At the expected well line operating flow rate of 30 gpm, the water velocity in the pipe will be 3.32 fps and the head loss will be 0.025 ft/ft. At the design flow rate of 60 gpm the velocity will be 6.65 fps and the head loss will be 0.089 ft/ft. These fluid velocities and head losses are within acceptable ranges given the fluid and piping material characteristics. Installation of the pipe will be completed with heat fused joints and insulating collars will be installed over the joints after welding and pressure testing. 5.2.3 Pipe Insulation To prevent freezing, the header and well extraction piping will be factory-insulated with 1-1/2 inches thick polyurethane foam and polyurethane polymer coating. Temperature loss over the length of the header piping under average conditions is estimated to be 0.13 oF. This assumes a groundwater extraction temperature of 60.8 oF and the historical lowest monthly average low ambient air temperature of 34 oF. Conductive Heat Flow = Overall Temperature Difference / Summation of Thermal Resistance's 𝑞𝑞=2𝜋𝜋𝐿𝐿 (𝑇𝑇1 −𝑇𝑇3 )�1k𝑎𝑎�ln 𝑃𝑃2𝑃𝑃1 +�1𝑘𝑘𝑏𝑏�ln 𝑃𝑃3𝑃𝑃2 𝑞𝑞=𝑐𝑐𝑜𝑜𝐶𝐶𝑑𝑑𝑃𝑃𝑐𝑐𝐷𝐷𝑝𝑝𝑜𝑜𝐶𝐶 𝐵𝐵𝑇𝑇𝐵𝐵ℎ𝑃𝑃= 𝑙𝑙𝑙𝑙 ∙ ℉ℎ𝑃𝑃 𝐿𝐿=2700 𝑜𝑜𝐷𝐷 × 12 𝑝𝑝𝐶𝐶𝑜𝑜𝐷𝐷=32,400 𝑝𝑝𝐶𝐶 𝑇𝑇1 =𝐺𝐺𝑃𝑃𝑜𝑜𝑃𝑃𝐶𝐶𝑑𝑑𝐺𝐺𝐶𝐶𝐷𝐷𝑃𝑃𝑃𝑃 𝐷𝐷𝑃𝑃𝑔𝑔𝑝𝑝𝑃𝑃𝑃𝑃𝐶𝐶𝐷𝐷𝑃𝑃𝑃𝑃𝑃𝑃,𝐶𝐶𝑎𝑎𝑃𝑃𝑃𝑃𝐶𝐶𝐶𝐶𝑃𝑃 60.8 ℉; 𝑙𝑙𝑜𝑜𝐺𝐺𝑃𝑃𝑃𝑃𝐷𝐷 46.4 ℉ (𝐶𝐶𝑆𝑆𝐴𝐴 𝑑𝑑𝐶𝐶𝐷𝐷𝐶𝐶) 𝑇𝑇3 =𝐴𝐴𝑔𝑔𝑙𝑙𝑝𝑝𝑃𝑃𝐶𝐶𝐷𝐷 𝐶𝐶𝑝𝑝𝑃𝑃 𝐷𝐷𝑃𝑃𝑔𝑔𝑝𝑝𝑃𝑃𝑃𝑃𝐶𝐶𝐷𝐷𝑃𝑃𝑃𝑃𝑃𝑃,𝑙𝑙𝑜𝑜𝐺𝐺𝑃𝑃𝑃𝑃𝐷𝐷 𝑔𝑔𝑜𝑜𝐶𝐶𝐷𝐷ℎ𝑙𝑙𝐶𝐶 𝐶𝐶𝑎𝑎𝑃𝑃𝑃𝑃𝐶𝐶𝐶𝐶𝑃𝑃 𝑙𝑙𝑜𝑜𝐺𝐺 34 ℉; 𝑙𝑙𝑜𝑜𝐺𝐺 𝑃𝑃𝑃𝑃𝑐𝑐𝑜𝑜𝑃𝑃𝑑𝑑𝑃𝑃𝑑𝑑−1 ℉ 𝑘𝑘𝑎𝑎=𝑝𝑝𝑝𝑝𝑝𝑝𝑃𝑃 𝑐𝑐𝑜𝑜𝐶𝐶𝑑𝑑𝑃𝑃𝑐𝑐𝐷𝐷𝑝𝑝𝑎𝑎𝑝𝑝𝐷𝐷𝐶𝐶=2.86 𝐵𝐵𝑇𝑇𝐵𝐵∙𝑝𝑝𝐶𝐶𝑜𝑜𝐷𝐷2 ∙ℎ𝑃𝑃∙℉ × 1 𝑜𝑜𝐷𝐷2144 𝑝𝑝𝐶𝐶2=0.1986 𝐵𝐵𝑇𝑇𝐵𝐵𝑝𝑝𝐶𝐶∙ℎ𝑃𝑃∙℉ Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra Page 5-5 P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx 𝑘𝑘𝑏𝑏=𝑝𝑝𝐶𝐶𝑃𝑃𝑃𝑃𝑙𝑙𝐶𝐶𝐷𝐷𝑝𝑝𝑜𝑜𝐶𝐶 𝑐𝑐𝑜𝑜𝐶𝐶𝑑𝑑𝑃𝑃𝑐𝑐𝐷𝐷𝑝𝑝𝑎𝑎𝑝𝑝𝐷𝐷𝐶𝐶=0.19 𝐵𝐵𝑇𝑇𝐵𝐵∙𝑝𝑝𝐶𝐶𝑜𝑜𝐷𝐷2 ∙ℎ𝑃𝑃∙℉ × 1 𝑜𝑜𝐷𝐷2144 𝑝𝑝𝐶𝐶2=0.0013 𝐵𝐵𝑇𝑇𝐵𝐵𝑝𝑝𝐶𝐶∙ℎ𝑃𝑃∙℉ 𝑃𝑃1 =𝑝𝑝𝑝𝑝𝑝𝑝𝑃𝑃 𝑝𝑝𝐶𝐶𝑃𝑃𝑝𝑝𝑑𝑑𝑃𝑃 𝑃𝑃𝐶𝐶𝑑𝑑𝑝𝑝𝑃𝑃𝑃𝑃=2.675 𝑝𝑝𝐶𝐶 𝑃𝑃2 =𝑝𝑝𝑝𝑝𝑝𝑝𝑃𝑃 𝑜𝑜𝑃𝑃𝐷𝐷𝑃𝑃𝑝𝑝𝑑𝑑𝑃𝑃 𝑃𝑃𝐶𝐶𝑑𝑑𝑝𝑝𝑃𝑃𝑃𝑃=3.277 𝑝𝑝𝐶𝐶 𝑃𝑃3 =𝑝𝑝𝐶𝐶𝑃𝑃𝑃𝑃𝑙𝑙𝐶𝐶𝐷𝐷𝑝𝑝𝑜𝑜𝐶𝐶 𝑜𝑜𝑃𝑃𝐷𝐷𝑃𝑃𝑝𝑝𝑑𝑑𝑃𝑃 𝑃𝑃𝐶𝐶𝑑𝑑𝑝𝑝𝑃𝑃𝑃𝑃=4.875 𝑝𝑝𝐶𝐶 𝑞𝑞=2𝜋𝜋(32400)(60.8 −34)�10.1986�ln 3.2772.675 +�10.0013�ln 4.8753.277 𝑞𝑞=1.78 × 104 𝑙𝑙𝑙𝑙 ∙ ℉ℎ𝑃𝑃 ∆𝑇𝑇=𝐷𝐷𝑃𝑃𝑔𝑔𝑝𝑝𝑃𝑃𝑃𝑃𝐶𝐶𝐷𝐷𝑃𝑃𝑃𝑃𝑃𝑃 𝑑𝑑𝑃𝑃𝑜𝑜𝑝𝑝= 1.78 × 104 𝑙𝑙𝑙𝑙 ∙ ℉ℎ𝑃𝑃270 galmin ∙8.34 𝑙𝑙𝑏𝑏𝑙𝑙𝑔𝑔𝑎𝑎𝑙𝑙 ∙60 𝑚𝑚𝑚𝑚𝑚𝑚ℎ𝑟𝑟=0.13 ℉ The temperature drop using the more extreme temperature conditions and assuming only one well is running at 30 gpm is 2.1 oF. This is also low heat loss. Freezing should not occur under these conditions. 5.2.4 Pipe Expansion/Contraction HDPE pipe has a thermal expansion coefficient of 67.0 × 10−6 in/in ℉. Using the average groundwater temperature, 60.8 oF, as the starting point, the largest dimension change would be during the record low temperature of -1 ℉. ∆𝑇𝑇=65.8 − −1 =66.8 ℉ ∆𝐿𝐿=100 𝑜𝑜𝐷𝐷 × 12 𝑝𝑝𝐶𝐶𝑜𝑜𝐷𝐷× 67.0 × 10−6 in℉ in × 66.8 ℉.=5.4 𝑝𝑝𝐶𝐶 Pipe expansion loops or curvature will be included in the detailed pipe layout to accommodate approximately 5.4 inches of expansion/contraction per 100 feet of pipe. Due to the thermal capacity of the pipe contents and the pipe insulation, this will be a conservative approach. Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra Page 5-6 P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx To ensure that the piping will not float due to buoyancy during flood events if the piping system is placed aboveground, the piping will be anchored with percussion driven or drilled helical anchors installed 5 to 10 feet deep, spaced approximately 50 feet apart, and adjacent to connection points between the header pipe and individual well discharge pipes. The buoyancy force will be equal to the weight of the volume of water displaced by the piping minus the weight of the pipe material. The 6-inch pipe has a 9.75-inch OD and weighs 6.01 lbs/foot. Buoyant Force = Water Weight – Pipe Weight 𝑃𝑃𝑝𝑝𝑝𝑝𝑃𝑃 𝑉𝑉𝑜𝑜𝑙𝑙𝑃𝑃𝑔𝑔𝑃𝑃=𝜋𝜋𝑃𝑃2 𝐿𝐿= 𝜋𝜋�9.75 𝑝𝑝𝐶𝐶2 �2 × 50 𝑜𝑜𝐷𝐷 × 1144 𝑜𝑜𝐷𝐷2𝑝𝑝𝐶𝐶2 =25.9 𝑜𝑜𝐷𝐷3 𝑊𝑊𝐶𝐶𝐷𝐷𝑃𝑃𝑃𝑃 𝑊𝑊𝑃𝑃𝑝𝑝𝐶𝐶ℎ𝐷𝐷= 25.9 𝑜𝑜𝐷𝐷3 × 62.43 𝑙𝑙𝑙𝑙𝑃𝑃𝑜𝑜𝐷𝐷3 =1618 𝑙𝑙𝑙𝑙𝑃𝑃 𝑃𝑃𝑝𝑝𝑝𝑝𝑃𝑃 𝑊𝑊𝑃𝑃𝑝𝑝𝐶𝐶ℎ𝐷𝐷= 50 𝑜𝑜𝐷𝐷 × 6.01 𝑙𝑙𝑙𝑙𝑃𝑃𝑜𝑜𝐷𝐷=301 𝑙𝑙𝑙𝑙𝑃𝑃 𝐵𝐵𝑃𝑃𝑜𝑜𝐶𝐶𝐶𝐶𝐶𝐶𝐷𝐷 𝐹𝐹𝑜𝑜𝑃𝑃𝑐𝑐𝑃𝑃= 1618 𝑙𝑙𝑙𝑙𝑃𝑃− 301 𝑙𝑙𝑙𝑙𝑃𝑃=1317 𝑙𝑙𝑙𝑙𝑃𝑃 𝑜𝑜𝑜𝑜𝑃𝑃 50 𝑜𝑜𝑃𝑃𝑃𝑃𝐷𝐷 𝑜𝑜𝑜𝑜 𝑝𝑝𝑝𝑝𝑝𝑝𝑃𝑃 The anchors will be installed to at least a factor of safety of two, or in excess of 2,600 lbs at each location. Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra Page 6-1 P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx 6.0 ELECTRICAL AND INSTRUMENTATION DESIGN It is anticipated that three-phase, 460-Volt, 200-Amp electrical service will be provided to the system from a power drop located near the system outfall. Planning at this stage assumes the control panel for the system will be located near the proposed treatment facility near the top of the active basin. Power to the well pumps, through the VFDs, as well as the pumping system controls will be provided from this panel. The final location of the system components will depend upon, and be coordinated with, basin closure activities. 6.1 Piping and Instrumentation Diagram The Piping and Instrumentation Diagram (P&ID) will be completed as part of the 60% design package once the conceptual design and complete design objectives are determined. 6.2 Pump Controls The pumps will be controlled with individual Grundfos CUE (or equal) VFDs which adjust the power frequency to vary the motor speed to control the pumping rate. The pumping rate can be adjusted manually or based on set points for flow rate or water level in the well from flow or level sensor signals. The VFDs allow for soft starts of the motor and allow the motors to operate efficiently by only drawing the necessary amperage to provide the desired pumping rate. It is assumed that control of the system will be accomplished through a Human Machine Interface (HMI) screen for ease of operation. 6.3 Emergency System Shutdown The pump motors have internal shutdown systems if the motors start to draw excessive power indicative of pump problems. The motors also have internal shutdown systems for motor overheating. In addition to these safeguards, high pressure conditions or other treatment system malfunctions will also trigger complete system shutdown. These safeguards will be programmed into the pumping control system once the treatment system design is completed. The control system will also be equipped with an auto-dialer to notify operations staff immediately of a system shutdown condition. Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra Page 7-1 P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx 7.0 DESIGN DOCUMENTS This 30% design package includes preliminary site layout drawings and conceptual details for the wells and well head configurations. Additional details and specifications will be provided at the 60% design level and finalized for the 90% and 100% design packages. 7.1 Design Drawings The complete design package will include site layout plans and profiles, process flow diagrams, P&ID diagrams, construction details, electrical and control drawings, and indices and notes. 7.2 Specifications Complete equipment, materials and construction specifications will be incorporated into the final design package. Supporting equipment performance data, calculations, and significant equipment and materials cut-sheets will also be included. The P&ID will be completed as part of the 60% design package once the conceptual design and complete design objectives are determined. Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra Page 8-1 P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx 8.0 GROUNDWATER EXTRACTION SYSTEM OPERATION The groundwater extraction system will be operated to achieve the objectives of this accelerated remediation effort. An anticipated initial drawdown of three feet is expected to meet this objective. Modeling may result in adjustments to this preliminary system layout and assumptions. The system is designed to handle significantly lower or higher pumping rates to achieve the desired results. 8.1 System Performance Metrics System performance metrics will be addressed as part of the 60% design submittal. 8.2 Permits 8.3 Institutional Controls 8.4 Contingency Plans 8.5 Construction and Monitoring Schedules Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx Figures P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis Of Design Report\Design Report (30)\Figures\DE HF LEE FIG 1-1 (SITE LOCATION MAP).dwg PR O J E C T M A N A G E R : LA Y O U T : DR A W N B Y : JU D D M A H A N DA T E : J. C H A S T A I N FI G 1 - 1 ( S I T E L O C A T I O N M A P ) FI G U R E 1 - 1 SI T E L O C A T I O N M A P H. F . L E E E N E R G Y C O M P L E X 11 9 9 B L A C K J A C K C H U R C H R O A D GO L D S B O R O , N O R T H C A R O L I N A SO U T H W E S T A N D N O R T H W E S T GO L D S B O R O , N C Q U A D R A N G L E S CO N T O U R I N T E R V A L : MA P D A T E : 5 FEET 20 1 3 14 8 R I V E R S T R E E T , S U I T E 2 2 0 GR E E N V I L L E , S O U T H C A R O L I N A PH O N E 8 6 4 - 4 2 1 - 9 9 9 9 ww w . s y n t e r r a c o r p . c o m RA L E I G H WI L M I N G T O N GR E E N V I L L E GR E E N S B O R O AC T I V E A S H B A S I N 11 / 1 4 / 2 0 1 6 H. F . L E E E N E R G Y C O M P L E X PR O P E R T Y B O U N D A R Y CC R S U R F A C E I M P O U N D M E N T CO O L I N G P O N D SO U R C E : US G S T O P O G R A P H I C M A P O B T A I N E D F R O M T H E U S G S S T O R E A T ht t p : / / s t o r e . u s g s . g o v / b 2 c _ u s g s / b 2 c / s t a r t / % % % 2 8 x c m = r 3 s t a n d a r d p i t r e x _ p r d % % % 2 9 / . d o 1000 0 1 0 0 0 2 0 0 0 GRAPHIC SCALE IN FEETREMEDIATION SYSTEM CM W - 6 R AM W - 1 5 S AM W - 1 5 B C AM W - 6 R B C CM W - 6 CM W - 5 CT M W - 1 PO W E R L I N E R O W N E U S E R I V E R AC T I V E A S H B A S I N FI G U R E 1 - 2 CO N C E P T U A L R E M E D I A T I O N S Y S T E M DU K E E N E R G Y P R O G R E S S H. F . L E E E N E R G Y C O M P L E X 11 9 9 B L A C K J A C K C H U R C H R D GO L D S B O R O , N O R T H C A R O L I N A AM W - 1 8 B C PU M P T E S T W E L L PT W - 6 PT W - 4 PT W - 3 PT W - 2 PT W - 1 PT W - 4 AM W - 1 8 S SG - 8 PT W - 5 AP R I L 1 7 , 2 0 1 4 A E R I A L P H O T O G R A P H O B T A I N E D F R O M W S P SO U R C E : 14 8 R I V E R S T R E E T , S U I T E 2 2 0 GR E E N V I L L E , S O U T H C A R O L I N A 2 9 6 0 1 PH O N E 8 6 4 - 4 2 1 - 9 9 9 9 ww w . s y n t e r r a c o r p . c o m PR O J E C T M A N A G E R : LA Y O U T : DR A W N B Y : JU D D M A H A N DA T E : JO H N C H A S T A I N FI G 1 - 2 ( C O N C E P R E M D S Y S T E M ) 11 / 0 9 / 2 0 1 6 11 / 1 4 / 2 0 1 6 1 1 : 2 4 A M P: \ D u k e E n e r g y P r o g r e s s . 1 0 2 6 \ 0 4 . L E E P L A N T \ 2 2 . B a s i s O f D e s i g n R e p o r t \ D e s i g n R e p o r t ( 3 0 ) \ F i g u r e s \ D E H F L E E F I G 1 - 2 ( C O N C E P R E M S Y ST E M ) . d w g DA T E P R I N T E D : CW - 1 CO M P L I A N C E M O N I T O R I N G W E L L (S U R V E Y E D ) AB M W - 2 CS A M O N I T O R I N G W E L L ( S U R V E Y E D ) MW - 2 MO N I T O R I N G W E L L ( S U R V E Y E D ) CC R S U R F A C E I M P O U N D M E N T DU K E E N E R G Y P R O G R E S S P A R C E L L I N E CC R S U R F A C E I M P O U N D M E N T CO M P L I A N C E B O U N D A R Y 10 0 0 1 0 0 2 0 0 GR A P H I C S C A L E IN F E E T FLOW DITCH F L O W FLOW DITCH CO N C E P T U A L G R O U N D W A T E R E X T R A C T I O N S Y S T E M 9 W E L L S - 3 0 0 F O O T S P A C I N G LE G E N D PR O P O S E D E X T R A C T I O N W E L L PR O P O S E D EL E C T R I C A L S E R V I C E CO N C E P T U A L T R E A T M E N T S Y S T E M A N D CO N T R O L P A N E L L O C A T I O N . FI N A L L O C A T I O N W I L L B E C O O R D I N A T E D WI T H B A S I N C L O S U R E A C T I V I T I E S . DI S C H A R G E T H R O U G H EX I S T I N G O U T F A L L S T R U C T U R E CO O L I N G P O N D EW - 1 EW - 2 EW - 3 EW - 4 EW - 5 EW - 6 EW - 7 EW - 8 EW - 9 GRAVE L R O A D SAND CEMENT WITH 5 % BENTONITE 12" BOREHOLE &21&5(7(*5287723“)((7 BENTONITE SEAL (MINIMUM 1 FOOT THICK) WELL PUMP 1 FOOT FROM BOTTOM OF BOREHOLEDEPTH OF OPEN BOREHOLE APPROXIMATELY 40' TO THE CONFINING LAYER 6" WELL CASING DISCHARGE PIPE SUBMERSIBLE WELL PUMP HIGH LEVEL CONTROL SENSOR WELL PUMP POWER CABLE CASING CENTRALIZER (MINIMUM OF 2) WELL PIPE GUIDES (MINIMUM OF 2) WELL SEAL LEVEL CONTROL SENSOR CABLES CONFINING LAYER FLOW 148 RIVER STREET, SUITE 220 GREENVILLE, SOUTH CAROLINA 29601 PHONE 864-421-9999 www.synterracorp.com PROJECT MANAGER: LAYOUT: DRAWN BY: W. LANTZ DATE:JOHN CHASTAIN FIG 4-1 WELL SCHEMATIC 11/08/2016 11/10/2016 10:29 AM P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis Of Design Report\Design Report (30)\Figures\DE HF LEE FIG 4-1 WELL SCHEMATIC.dwg FIGURE 4-1 EXTRACTION WELL SCHEMATIC H.F. LEE ENERGY COMPLEX 1199 BLACK JACK CHURCH RD GOLDSBORO, NORTH CAROLINA NOT TO SCALE LOW LEVEL CONTROL SENSOR APPROXIMATE WATER TABLE WATER LEVEL PRESSURE TRANSDUCER LEVEL CONTROL SENSOR CABLES WELL PUMP POWER CABLE PRESSURE TRANSDUCER CABLE PRESSURE TRANSDUCER CABLE 6" WELL SREEN T H R E A D E D U N I O N ( T Y P . ) D I S C H A R G E P I P E B A L L V A L V E P R E S S U R E G A U G E W E L L H E A D E N C L O S U R E I N S U L A T E D F I B E R G L A S S W I T H F U L L Y L O C K I N G E N C L O S U R E D O O R S E L E C T R O M A G N E T I C F L O W M E T E R S A M P L E P O R T CHE C K V A L V E WELL SEAL W E L L P U M P P O W E R C A B L E C O N T R O L S E N S O R C A B L E S WELL CASING F L O W D I S C H A R G E P I P E I N S U L A T I O N F I G U R E 5 - 1 A B O V E G R A D E W E L L H E A D E N C L O S U R E E X A M P L E H . F . L E E E N E R G Y C O M P L E X 1 1 9 9 B L A C K J A C K C H U R C H R D G O L D S B O R O , N O R T H C A R O L I N A 1 1 / 1 0 / 2 0 1 6 1 0 : 3 1 A M P : \ D u k e E n e r g y P r o g r e s s . 1 0 2 6 \ 0 4 . L E E P L A N T \ 2 2 . B a s i s O f D e s i g n R e p o r t \ D e s i g n R e p o r t ( 3 0 ) \ F i g u r e s \ D E H F L E E F I G 5 - 1 ( W E L L H E A D ) . d w g 1 4 8 R I V E R S T R E E T , S U I T E 2 2 0 G R E E N V I L L E , S O U T H C A R O L I N A 2 9 6 0 1 P H O N E 8 6 4 - 4 2 1 - 9 9 9 9 w w w . s y n t e r r a c o r p . c o m P R O J E C T M A N A G E R : L A Y O U T : D R A W N B Y : W . L A N T Z D A T E : J O H N C H A S T A I N F I G 5 - 1 W E L L H E A D E N C L O S U R E 1 1 / 0 2 / 2 0 1 6 N O T T O S C A L E Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx Tables TABLE 4-1 TARGET EXTRACTION WELL SCREEN INTERVALS H.F. LEE ENERGY COMPLEX DUKE ENERGY PROGRESS, LLC, GOLDSBORO, NC Well ID *Depth to Clay Unit (feet)*Depth to Water Target Screen Interval (feet) EW-1 22 1.50 13 - 23 EW-2 22 1.50 13 - 23 EW-3 22 2.00 13 - 23 EW-4 20 4.00 11 - 21 EW-5 25 4.00 16 - 26 EW-6 38 5.00 29 - 39 EW-7 42 6.00 33 - 43 EW-8 42 4.00 33 - 43 EW-9 42 4.00 33 - 43 Prepared by: JDM Checked by: TCP * Estimated based on observations from 2015 - 2016 groundwater assessment data P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Tables\Target Extraction Well Screen Intervals.xlsx Page 1 of 1 Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx APPENDIX A Pilot Test Report tip synTerra TECHNICAL MEMORANDUM CA Date: August 22, 2016 File: 1026.'��°�rv' To: Ryan Czop, Duke Energy Progress aP' Cc: Kathy Webb, From: Judd Mahan Subject: Pilot Test Report — H.F. Lee Energy Complex �Z '-. _1 z� A groundwater extraction pilot test was conducted at the H.F. Lee Energy Complex (Site) located in Goldsboro, North Carolina (Figure 1). Comprehensive Site Assessment (CSA) and historical groundwater monitoring results indicate that areas to the east and north of the active ash basin have potential to have constituent concentrations greater than 2L beyond the compliance and property boundaries. The pilot test was conducted in the area east of the active ash basin to determine aquifer characteristics needed to evaluate and design a remedial action strategy in the area (Figure 2). This report describes the activities, methods and findings for the pilot test which included step- drawdown and pumping test components. 1.0 SITE GEOLOGY AND HYDROGEOLOGY The Site is located in the Atlantic Coastal plain. The Coastal Plain consists of a sequence of stratified marine and non -marine sedimentary rocks deposited on crystalline basement rocks. Surficial soils at the site are comprised of Quaternary alluvial deposits associated with the adjacent Neuse River, consisting primarily of silty and clayey sands with interbedded clay, which contain the surficial aquifer. Underlying these deposits, at depths of around 20-feet below grade in the area of the active ash basin, is the Black Creek Formation, the upper portion of which consists of a dark, carbonaceous -rich, laterally continuous clay unit. The Black Creek clay unit confines the lower boundary of the surficial aquifer. Depths to groundwater in the area of the active ash basin are generally two to five feet below grade. Overall groundwater flow in the area of the active ash basin is southerly toward the Neuse River. 2.0 PILOT TEST WELL INSTALLATION Pilot test wells PTW-01 through PTW-06 were installed between July 12 and July 14, 2016 using a GeoprobeTM rig capable of both direct -push and hollow -stem auger drilling. In order to characterize the local hydrogeology, continuous coring was conducted at the locations of PTW-01, PTW-04, PTW-05 and PTW-06. Macro -core P:\Duke Energy Progress.1026 \ 04.LEE PLANT\ 20. Accelerated Remediation \ Pilot Test \ PDF \ Tech Memo Pilot Test August 2016.docx Step-Drawdown and Pumping Test Findings August 22, 2016 HF Lee Energy Complex Page 2 P:\Duke Energy Progress.1026\04.LEE PLANT\20. Accelerated Remediation\Pilot Test\PDF\Tech Memo Pilot Test August 2016.docx samples were collected into 5-foot vinyl sleeves measuring approximately 1.5 inches in diameter. Borings were advanced at each location until the upper portion of the Black Creek clay unit was identified. The upper contact of the Black Creek clay varied from approximately 19 feet below ground surface (bgs) at PTW-05 to 25 bgs at PTW-06. In general, the soil profile encountered above the Black Creek clay unit consisted of a thin sandy clay layer from ground surface to approximately 5 feet bgs followed by medium to coarse grained sands to approximately 20 to 25 feet bgs. Cores were described and photo-documented in the field. Boring logs and well construction records are provided in Attachment 1. Well PTW-01 was designed as a 6-inch diameter extraction well. PTW-02 through PTW- 06 were designed as 2-inch diameter observation wells. Wells PTW-01 through PTW-04 were installed with screen intervals from 10 to 20 feet bgs. Wells PTW-05 and PTW-06 were installed with screen intervals of 9 to 19 feet and 8 to 18 feet bgs, respectively. Wells PTW-02 through PTW-06 were installed with 10-ft lengths of 0.010-inch slotted PVC screens. Well PTW-01 was constructed with a 10-ft length of 0.010-inch slotted stainless steel V-wire screen. As shown on Figure 1, the observation wells (PTW-02 through PTW-06) were installed at varying directions and distances which ranged from 15 feet to 150 feet from extraction well PTW-1. The extraction well permit is included with Attachment 1. Well development was conducted to establish communication with the surrounding formation and until the water was generally free of turbidity. Wells were surveyed for coordinates on the North Carolina State Plane NAD88 system and to determine top of casing (TOC) elevations. A well construction table is provided as Table 1. 3.0 STEP DRAWDOWN TESTS 3.1 Procedure Two step-drawdown tests were conducted, one on July 27, 2016 and one on July 28, 2016. The starting flow rate for the initial step-drawdown test was determined based on results of slug tests from nearby assessment wells and pilot test well development results. A Grundfos 10 Redi-Flo 3 pump with a maximum flow rate of about 15 gpm was used for the initial step-drawdown test on July 27, 2016. Due to flow rates greater than the predicted estimate, a second step-drawdown test was conducted on July 28, 2016 using a Grundfos 22 Redi-Flo 3 pump, which has a maximum flow rate of approximately 34 gpm. Prior to beginning the step-drawdown tests on July 27, 2016 and July 28, 2016, data level loggers were installed in pilot test wells (PTW-1 and PTW-2) and water level Step-Drawdown and Pumping Test Findings August 22, 2016 HF Lee Energy Complex Page 3 P:\Duke Energy Progress.1026\04.LEE PLANT\20. Accelerated Remediation\Pilot Test\PDF\Tech Memo Pilot Test August 2016.docx measurements were recorded prior to step-drawdown testing. Data loggers were programed to collect water level measurements at a frequency of one per second. Step-drawdown tests were conducted using pilot test well PTW-01 as the extraction well. Water level measurements were collected prior to step-drawdown testing, during the test and at the end of the test. Data for each step-drawdown test was recorded using a Solinst Levelogger data logger, which was programmed to start before pumping began. The data logger was lowered into both wells to approximately 0.5 feet from the bottom of the well. A direct read cable was attached to the data logger installed in well PTW-1, which allowed for real-time viewing of water level drawdown as the well was being pumped. Once the data loggers were installed for the initial step-drawdown test, the pump was installed into the well approximately one-foot above the data logger. Once the water level stabilized based on the direct readings from the data logger, the pump was started and the start time noted. Flow rates were calculated by measuring the time to fill a 100 mL (milliliter) cylinder, a 1000 mL cylinder, or a 5 gallon bucket. Flow measurements were made several times during a given step interval and adjustments were made to the flow valve to maintain a steady flow rate. Periodic water level measurements were also collected to confirm the water level data was being accurately measured and collected with the data logger. A summary of the pumping rates and step intervals for the step-drawdown tests are described below: July 27th Step-Drawdown Test @ PTW-1 initial 0.5 gpm 60 minutes 1 gpm 120 minutes 2.5 gpm 180 minutes 5 gpm 240 minutes 10 gpm 300 minutes 14 gpm Step-Drawdown and Pumping Test Findings August 22, 2016 HF Lee Energy Complex Page 4 P:\Duke Energy Progress.1026\04.LEE PLANT\20. Accelerated Remediation\Pilot Test\PDF\Tech Memo Pilot Test August 2016.docx July 28th Step-Drawdown Test @ PTW-1 initial 15 gpm 60 minutes 20 gpm 120 minutes 25 gpm 180 minutes 30 gpm 240 minutes 33 gpm At the conclusion of each step-drawdown test, the pump was shut off and the data logger was allowed to continue taking readings as the water level recovered in each well. Recovery was measured for one hour and the pump and data logger were removed from the well. Data from the data logger was downloaded to a computer for data evaluation. The data logger was then reset to read data at one second intervals for the next step-drawdown test. 3.2 Data Evaluation Data from the data loggers was imported into AQTESOLV Pro.4.0. The Theis step- drawdown solution was used to analyze the data from the step-drawdown tests. The solution uses curve matching to determine the aquifer transmissivity (T) and storage coefficient (S). Hydraulic conductivity was calculated using an aquifer thickness of 19.75 feet (Table 2). The outputs from the step-drawdown evaluation are included as Attachment 2. TABLE 2 SURFICIAL AQUIFER CHARACTERISTICS STEP-DRAWDOWN TEST H.F. LEE ENERGY COMPLEX DUKE ENERGY PROGRESS, LLC, GOLDSBORO, NC Well ID Transmissivity (ft2/day) Storativity (unitless) Hydraulic Conductivity (ft/day) PTW-1 2.68 x 10+03 1.76 x 10-05 1.36 x 10+02 Prepared by: RAG Checked by: HJF Notes: ft2 - square feet ft - feet *hydraulic conductivity was based on theoretical aquifer thickness of 20 feet. Step-Drawdown and Pumping Test Findings August 22, 2016 HF Lee Energy Complex Page 5 P:\Duke Energy Progress.1026\04.LEE PLANT\20. Accelerated Remediation\Pilot Test\PDF\Tech Memo Pilot Test August 2016.docx 4.0 PUMPING TEST 4.1 Procedure On August 2, 2016, a 36-hour constant rate pumping test was conducted at PTW-1. Data loggers were programmed and installed 0.5 feet from the bottom of wells PTW-1, PTW- 2, PTW-3, PTW-4, PTW-5, PTW-6, CMW-6, and CMW-6R; however, level loggers did not read throughout the pumping test. Manual water levels were collected every hour from wells with data loggers and water levels were collected periodically during the test from monitoring wells AMW-06BC, AMW-14S, AMW-14BC, CCR-103S, AMW-18S, and AMW-18BC to determine radial extent of drawdown influence (Table 3, Figure 2). Note that “PMW”, “CMW”, and “S” wells are screened in surficial deposits and “BC” wells are screened below a laterally continuous clay unit associated with the Black Creek deposits. Several weather systems passed through during the pumping test. The site gauged about 1.13’’ of rain on Tuesday, August 2nd and 0.18’’ of rain on Wednesday, August 3rd. The Seymour Johnson Air Force Base, which is about 4.75 miles east-southeast of the site, had an average daily barometric pressure of 29.98 to 30.06 inches of mercury. The submersible pump in pilot test well PMW-1 was operated at a constant rate of 30 gpm for 36 hours. A flow meter was used to determine the flow rate during the pump test and was recorded every hour. The extracted water was transferred to the active basin. The total volume of water extracted during the 36-hour pumping test was approximately 63,500 gallons. 4.2 Data Evaluation Depth-to-water measurements were recorded during every hour during the 36-hour pumping test and were analyzed using the Cooper-Jacob (1946) straight line method (Figures 3-7) for observation wells PTW-2, PTW-3, PTW-4, and PTW-5. Head levels from extraction well PTW-1 were imported into AQTESOLV Pro.4.0 and analyzed using the Moench solution for unconfined aquifers (Attachment 3). CMW-6 was not analyzed because the well was influenced by the rain events and drawdown was minimal. In addition, the water level differences were near the error tolerance for manual level measurements. The Cooper-Jacob method is a solution created for confined aquifers, however since the surficial unconfined aquifer behaves similar to a confined aquifer by the head draining as a result of dewatering and there were no delayed yield effects observed, the confined solutions were applied towards the end of the drawdown data. Step-Drawdown and Pumping Test Findings August 22, 2016 HF Lee Energy Complex Page 6 P:\Duke Energy Progress.1026\04.LEE PLANT\20. Accelerated Remediation\Pilot Test\PDF\Tech Memo Pilot Test August 2016.docx The assumptions for applying the Cooper-Jacob method are as follows: The aquifer is homogenous, isotropic and of uniform thickness All layers are horizontal and extend infinitely in the radial direction Groundwater flow is horizontal and directed radially towards the well Pumping rate is constant Water is released instantaneously from storage with decline of hydraulic head Head losses through the well screen and pump intake are negligible The Cooper-Jacob solution is plotted on a drawdown versus log time scale to calculate transmissivity (T): T = 2.3𝑄𝑄4𝜋𝜋∆(ℎ𝑜𝑜−ℎ) Note: Q is the flow rate ∆(ℎ𝑜𝑜−ℎ) is the slope of the fitted line By using an estimated aquifer thickness (b) based on boring logs, hydraulic conductivity can be calculated. K = 𝑇𝑇𝑏𝑏 The Moench solution is plotted on a log drawdown versus log time scale to calculate transmissivity (T), specific yield (Sy), and vertical hydraulic conductivity (𝐾𝐾𝑧𝑧). The assumptions for applying the Moench solution are as followed: The aquifer has infinite areal extent Aquifer is homogeneous, isotropic, unconfined and of uniform thickness Aquifer is unsteady Step-Drawdown and Pumping Test Findings August 22, 2016 HF Lee Energy Complex Page 7 P:\Duke Energy Progress.1026\04.LEE PLANT\20. Accelerated Remediation\Pilot Test\PDF\Tech Memo Pilot Test August 2016.docx TABLE 4 PUMPING TEST RESULTS H.F. LEE ENERGY COMPLEX DUKE ENERGY PROGRESS, LLC, GOLDSBORO, NC Well ID Transmissivity (ft2/day) Hydraulic Conductivity (ft/day) PTW-1 3.92 x 10+03 1.98 x 10+02 PTW-2 2.30 x 10+03 1.16 x 10+02 PTW-3 2.35 x 10+03 1.19 x 10+02 PTW-4 2.52 x 10+03 1.12 x 10+02 PTW-5 3.02 x 10+03 1.59 x 10+02 PTW-6 4.23 x 10+03 1.69 x 10+02 Geometric Mean 2.97 x 10+03 1.42 x 10+02 Prepared by: RAG Checked by: HJF The radius of influence (ROI) was determined by graphing the drawdown versus distance plots after pumping 2170 minutes; 𝑑𝑑𝑜𝑜 was estimated to be about 300 feet (Figure 8). 5.0 RESULTS AND RECOMMENDATIONS Step-drawdown tests and the pumping test results conclude the surficial aquifer east of the active basin was calculated to have a hydraulic conductivity of approximately 136 ft/day with an assumed average aquifer thickness of about 20 feet. Aquifer data in the vicinity of PTW-1 indicate conditions at this location could support a viable extraction well under current site conditions. A ROI calculation is shown on Figure 8 with a result of 300 feet. In addition, there was no measurable water level drawdown of the hydrogeologic unit below the Black Creek clay unit from pumping the surficial aquifer system. Using graphical calculation methods and AQTESOLV Pro.4.5, the geometric mean of the transmissivity in the surficial unit is 2,970 𝑓𝑓𝑓𝑓2𝑑𝑑𝑑𝑑𝑑𝑑 . This value is representative of medium to coarse sand. Precipitation during the pump test had little effect on groundwater levels in the surficial aquifer; however CMW-6 did see a 0.2 ft increase in head after the August 2nd rain event which had about 1.12 inches of rain. Step-Drawdown and Pumping Test Findings August 22, 2016 HF Lee Energy Complex Page 8 P:\Duke Energy Progress.1026\04.LEE PLANT\20. Accelerated Remediation\Pilot Test\PDF\Tech Memo Pilot Test August 2016.docx Recharge boundaries were not observed (positive or negative) and recovery occurred faster than drawdown. Results from step-drawdown tests and pumping test indicate the following: Average sustainable yields (over the course of the test) were at least 30 gallons per minute. The radius of influence is approximately 300 feet from the extraction well. Specific yield and hydraulic conductivity are constant throughout the target area, confirming low heterogeneity of the unconfined aquifer flow system. Hydraulic conductivity calculated from step-drawdown and pumping tests exceeded predicted hydraulic conductivities from well development logs. SynTerra recommends initially installing a line of nine six-inch extraction wells along a 2,700 foot transect (Figure 9). Step-Drawdown and Pumping Test Findings August 22, 2016 HF Lee Energy Complex Page 9 P:\Duke Energy Progress.1026\04.LEE PLANT\20. Accelerated Remediation\Pilot Test\PDF\Tech Memo Pilot Test August 2016.docx 6.0 REFERENCES Cooper, H. H., Jr. and C. E. Jacob. 1946. A Generalized Graphical Method for Evaluating Formation Constants and Summarizing Well-Field History. Transaction, American Geophysical Union, Vol. 27, No. 4, pp. 5226 – 534. Duffield, G.M. 2007. AQTESOLV for Windows Version 4.5 User’s Guide. HydroSOLVE Inc., Reston, VA. Johnson, A.J., 1967, Specific yield, Compilation of specific yields for various materials. U.S. Geologic Survey Water Supply Paper. 1662-D, pp. 74. Kruseman, G.P. and N.A. de Ridder, 1994, Analysis and Evaluation of Pumping Test Data. International Institute for Land Reclamation and Improvement. Wageningen, The Netherlands, pp. 23 – 24. Moench, A.F., 1997. Flow to a well of finite diameter in a homogeneous, anisotropic water table aquifer, Water Resources Research, vol. 33, no. 6, pp. 1397-1407. Step-Drawdown and Pumping Test Findings August 22, 2016 HF Lee Energy Complex SynTerra P:\Duke Energy Progress.1026\04.LEE PLANT\20. Accelerated Remediation\Pilot Test\PDF\Tech Memo Pilot Test August 2016.docx FIGURES PR O J E C T M A N A G E R : LA Y O U T : DR A W N B Y : JU D D M A H A N DA T E : J. C H A S T A I N FI G 1 ( S I T E L O C A T I O N M A P ) FI G U R E 1 SI T E L O C A T I O N M A P H. F . L E E E N E R G Y C O M P L E X 11 9 9 B L A C K J A C K C H U R C H R O A D GO L D S B O R O , N O R T H C A R O L I N A SO U T H W E S T A N D N O R T H W E S T GO L D S B O R O , N C Q U A D R A N G L E S CO N T O U R I N T E R V A L : MA P D A T E : 5 FEET 20 1 3 14 8 R I V E R S T R E E T , S U I T E 2 2 0 GR E E N V I L L E , S O U T H C A R O L I N A PH O N E 8 6 4 - 4 2 1 - 9 9 9 9 ww w . s y n t e r r a c o r p . c o m RA L E I G H WI L M I N G T O N GR E E N V I L L E GR E E N S B O R O AC T I V E A S H B A S I N 08 / 1 8 / 2 0 1 6 H. F . L E E E N E R G Y C O M P L E X PUMP TEST IN A C T I V E AS H B A S I N 2 IN A C T I V E AS H B A S I N 1 IN A C T I V E AS H B A S I N 3 LA Y D O W N A R E A PR O P E R T Y B O U N D A R Y CCR SURFACE IMPOUNDMENT COMPLIANCE BOUNDARY CC R S U R F A C E IM P O U N D M E N T B O U N D A R Y CC R S U R F A C E IM P O U N D M E N T BO U N D A R Y CO O L I N G P O N D CC R S U R F A C E IM P O U N D M E N T CO M P L I A N C E BO U N D A R Y SO U R C E : US G S T O P O G R A P H I C M A P O B T A I N E D F R O M T H E U S G S S T O R E A T ht t p : / / s t o r e . u s g s . g o v / b 2 c _ u s g s / b 2 c / s t a r t / % % % 2 8 x c m = r 3 s t a n d a r d p i t r e x _ p r d % % % 2 9 / . d o P : \ D u k e E n e r g y P r o g r e s s . 1 0 2 6 \ 0 4 . L E E P L A N T \ 2 0 . A c c e l e r a t e d R e m e d i a t i o n \ P i l o t T e s t \ D W G \ D E H F L E E F I G 1 - 1 ( S I T E L O C A T I O N M A P ) . d w g 1000 0 1 0 0 0 2 0 0 0 GRAPHIC SCALE IN FEET CM W - 6 R AM W - 1 4 B C AM W - 1 4 S AM W - 1 5 S AM W - 1 5 B C AM W - 6 R B C CM W - 6 CM W - 5 CT M W - 1 PO W E R L I N E R O W N E U S E R I V E R AC T I V E A S H B A S I N FI G U R E 2 PU M P T E S T W E L L L O C A T I O N M A P DU K E E N E R G Y P R O G R E S S H. F . L E E E N E R G Y C O M P L E X 11 9 9 B L A C K J A C K C H U R C H R D GO L D S B O R O , N O R T H C A R O L I N A AM W - 1 8 B C PU M P T E S T W E L L PT W - 6 PT W - 4 PT W - 3 PT W - 2 PT W - 1 PT W - 4 AM W - 1 8 S SG - 6 SG - 8 PT W - 5 GRAVE L R O A D AP R I L 1 7 , 2 0 1 4 A E R I A L P H O T O G R A P H O B T A I N E D F R O M W S P SO U R C E : 14 8 R I V E R S T R E E T , S U I T E 2 2 0 GR E E N V I L L E , S O U T H C A R O L I N A 2 9 6 0 1 PH O N E 8 6 4 - 4 2 1 - 9 9 9 9 ww w . s y n t e r r a c o r p . c o m PR O J E C T M A N A G E R : LA Y O U T : DR A W N B Y : JU D D M A H A N DA T E : JO H N C H A S T A I N FI G 2 ( P U M P T E S T W E L L M A P ) 08 / 1 8 / 2 0 1 6 08 / 2 2 / 2 0 1 6 1 : 3 7 P M P: \ D u k e E n e r g y P r o g r e s s . 1 0 2 6 \ 0 4 . L E E P L A N T \ 2 0 . A c c e l e r a t e d R e m e d i a t i o n \ P i l o t T e s t \ D W G \ D E H F L E E E X T R A C T I O N W E L L S . d w g DA T E P R I N T E D : CW - 1 LE G E N D CO M P L I A N C E M O N I T O R I N G W E L L (S U R V E Y E D ) AB M W - 2 CS A M O N I T O R I N G W E L L ( S U R V E Y E D ) MW - 2 MO N I T O R I N G W E L L ( S U R V E Y E D ) CC R S U R F A C E I M P O U N D M E N T DU K E E N E R G Y P R O G R E S S P A R C E L L I N E CC R S U R F A C E I M P O U N D M E N T CO M P L I A N C E B O U N D A R Y 10 0 0 1 0 0 2 0 0 GR A P H I C S C A L E IN F E E T FLOW F L O W DITCH F L O W FLOW DITCH HI G H P O I N T I N D I T C H D I T C H 14 8 R I V E R S T R E E T , S U I T E 2 2 0 GR E E N V I L L E , S O U T H C A R O L I N A 2 9 6 0 1 PH O N E 8 6 4 - 4 2 1 - 9 9 9 9 ww w . s y n t e r r a c o r p . c o m DR A W N B Y : J . G I L M E R PR O J E C T M A N A G E R : J M A H A N LA Y O U T : DA T E : J U N E 2 0 1 5 FI G U R E 3 PT W - 2 D R A W D O W N V S . L O G T I M E H. F . L E E E N E R G Y C O M P L E X GO L D S B O R O , N O R T H C A R O L I N A P: \ D u k e E n e r g y P r o g r e s s . 1 0 2 6 \ 0 4 . L E E P L A N T \ 2 0 . A c c e l e r a t e d R e m e d i at i o n \ P i l o t T e s t \ P i l o t T e s t R e p o r t _ A u g 2 0 1 6 \ G r a p h s 14 8 R I V E R S T R E E T , S U I T E 2 2 0 GR E E N V I L L E , S O U T H C A R O L I N A 2 9 6 0 1 PH O N E 8 6 4 - 4 2 1 - 9 9 9 9 ww w . s y n t e r r a c o r p . c o m DR A W N B Y : J . G I L M E R PR O J E C T M A N A G E R : J M A H A N LA Y O U T : DA T E : J U N E 2 0 1 5 FI G U R E 4 PT W - 3 D R A W D O W N V S . L O G T I M E H. F . L E E E N E R G Y C O M P L E X GO L D S B O R O , N O R T H C A R O L I N A P: \ D u k e E n e r g y P r o g r e s s . 1 0 2 6 \ 0 4 . L E E P L A N T \ 2 0 . A c c e l e r a t e d R e m e d i at i o n \ P i l o t T e s t \ P i l o t T e s t R e p o r t _ A u g 2 0 1 6 \ G r a p h s 14 8 R I V E R S T R E E T , S U I T E 2 2 0 GR E E N V I L L E , S O U T H C A R O L I N A 2 9 6 0 1 PH O N E 8 6 4 - 4 2 1 - 9 9 9 9 ww w . s y n t e r r a c o r p . c o m DR A W N B Y : J . G I L M E R PR O J E C T M A N A G E R : J M A H A N LA Y O U T : DA T E : J U N E 2 0 1 5 FI G U R E 5 PT W - 4 D R A W D O W N V S . L O G T I M E H. F . L E E E N E R G Y C O M P L E X GO L D S B O R O , N O R T H C A R O L I N A P: \ D u k e E n e r g y P r o g r e s s . 1 0 2 6 \ 0 4 . L E E P L A N T \ 2 0 . A c c e l e r a t e d R e m e d i at i o n \ P i l o t T e s t \ P i l o t T e s t R e p o r t _ A u g 2 0 1 6 \ G r a p h s 14 8 R I V E R S T R E E T , S U I T E 2 2 0 GR E E N V I L L E , S O U T H C A R O L I N A 2 9 6 0 1 PH O N E 8 6 4 - 4 2 1 - 9 9 9 9 ww w . s y n t e r r a c o r p . c o m DR A W N B Y : J . G I L M E R PR O J E C T M A N A G E R : J M A H A N LA Y O U T : DA T E : J U N E 2 0 1 5 FI G U R E 6 PT W - 5 D R A W D O W N V S . L O G T I M E H. F . L E E E N E R G Y C O M P L E X GO L D S B O R O , N O R T H C A R O L I N A P: \ D u k e E n e r g y P r o g r e s s . 1 0 2 6 \ 0 4 . L E E P L A N T \ 2 0 . A c c e l e r a t e d R e m e d i at i o n \ P i l o t T e s t \ P i l o t T e s t R e p o r t _ A u g 2 0 1 6 \ G r a p h s 14 8 R I V E R S T R E E T , S U I T E 2 2 0 GR E E N V I L L E , S O U T H C A R O L I N A 2 9 6 0 1 PH O N E 8 6 4 - 4 2 1 - 9 9 9 9 ww w . s y n t e r r a c o r p . c o m DR A W N B Y : J . G I L M E R PR O J E C T M A N A G E R : J M A H A N LA Y O U T : DA T E : J U N E 2 0 1 5 FI G U R E 7 PT W - 6 D R A W D O W N V S . L O G T I M E H. F . L E E E N E R G Y C O M P L E X GO L D S B O R O , N O R T H C A R O L I N A P: \ D u k e E n e r g y P r o g r e s s . 1 0 2 6 \ 0 4 . L E E P L A N T \ 2 0 . A c c e l e r a t e d R e m e d i at i o n \ P i l o t T e s t \ P i l o t T e s t R e p o r t _ A u g 2 0 1 6 \ G r a p h s 14 8 R I V E R S T R E E T , S U I T E 2 2 0 GR E E N V I L L E , S O U T H C A R O L I N A 2 9 6 0 1 PH O N E 8 6 4 - 4 2 1 - 9 9 9 9 ww w . s y n t e r r a c o r p . c o m DR A W N B Y : J . G I L M E R PR O J E C T M A N A G E R : J M A H A N LA Y O U T : DA T E : J U N E 2 0 1 5 FI G U R E 8 DR A W D O W N V S . L O G DI S T A N C E A T T I M E = 2 1 7 0 M I N H. F . L E E E N E R G Y C O M P L E X GO L D S B O R O , N O R T H C A R O L I N A P: \ D u k e E n e r g y P r o g r e s s . 1 0 2 6 \ 0 4 . L E E P L A N T \ 2 0 . A c c e l e r a t e d R e m e d i at i o n \ P i l o t T e s t \ P i l o t T e s t R e p o r t _ A u g 2 0 1 6 \ G r a p h s CM W - 6 R AM W - 1 4 B C AM W - 1 4 S AM W - 1 5 S AM W - 1 5 B C AM W - 6 R B C CM W - 6 CM W - 5 CT M W - 1 PO W E R L I N E R O W N E U S E R I V E R AC T I V E A S H B A S I N FI G U R E 9 EX T R A C T I O N W E L L L O C A T I O N M A P DU K E E N E R G Y P R O G R E S S H. F . L E E E N E R G Y C O M P L E X 11 9 9 B L A C K J A C K C H U R C H R D GO L D S B O R O , N O R T H C A R O L I N A AM W - 1 8 B C PU M P T E S T W E L L PT W - 6 PT W - 4 PT W - 3 PT W - 2 PT W - 1 PT W - 4 AM W - 1 8 S SG - 6 SG - 8 PT W - 5 GRAVE L R O A D AP R I L 1 7 , 2 0 1 4 A E R I A L P H O T O G R A P H O B T A I N E D F R O M W S P SO U R C E : 14 8 R I V E R S T R E E T , S U I T E 2 2 0 GR E E N V I L L E , S O U T H C A R O L I N A 2 9 6 0 1 PH O N E 8 6 4 - 4 2 1 - 9 9 9 9 ww w . s y n t e r r a c o r p . c o m PR O J E C T M A N A G E R : LA Y O U T : DR A W N B Y : JU D D M A H A N DA T E : JO H N C H A S T A I N FI G 9 ( E X T R A C T I O N W E L L ) 08 / 1 8 / 2 0 1 6 08 / 2 2 / 2 0 1 6 1 : 3 8 P M P: \ D u k e E n e r g y P r o g r e s s . 1 0 2 6 \ 0 4 . L E E P L A N T \ 2 0 . A c c e l e r a t e d R e m e d i a t i o n \ P i l o t T e s t \ D W G \ D E H F L E E E X T R A C T I O N W E L L S . d w g DA T E P R I N T E D : CW - 1 CO M P L I A N C E M O N I T O R I N G W E L L (S U R V E Y E D ) AB M W - 2 CS A M O N I T O R I N G W E L L ( S U R V E Y E D ) MW - 2 MO N I T O R I N G W E L L ( S U R V E Y E D ) CC R S U R F A C E I M P O U N D M E N T DU K E E N E R G Y P R O G R E S S P A R C E L L I N E CC R S U R F A C E I M P O U N D M E N T CO M P L I A N C E B O U N D A R Y 10 0 0 1 0 0 2 0 0 GR A P H I C S C A L E IN F E E T FLOW F L O W DITCH F L O W FLOW DITCH HI G H P O I N T I N D I T C H D I T C H CO N C E P T U A L G R O U N D W A T E R E X T R A C T I O N S Y S T E M 9 W E L L S - 3 0 0 F O O T S P A C I N G LE G E N D PR O P O S E D E X T R A C T I O N W E L L Step-Drawdown and Pumping Test Findings August 22, 2016 HF Lee Energy Complex SynTerra P:\Duke Energy Progress.1026\04.LEE PLANT\20. Accelerated Remediation\Pilot Test\PDF\Tech Memo Pilot Test August 2016.docx TABLES TA B L E 1 WE L L C O N S T R U C T I O N D A T A H. F . L E E E N E R G Y C O M P L E X DU K E E N E R G Y P R O G R E S S , I N C . , G O L D S B O R O , N C Mo n i t o r i n g We l l I D Da t e In s t a l l e d Ma t e r i a l Di a m e t e r (i n c h e s ) Su r f a c e Ca s i n g (F e e t - B G S ) La t i t u d e L o n g i t u d e Me a s u r i n g Po i n t T O C El e v a t i o n (F e e t - M S L ) Gr o u n d Su r f a c e El e v a t i o n (F e e t - M S L ) Total Well Depth (Feet-BGS)Screened Interval (Feet-BGS) PT W - 0 1 0 7 / 1 4 / 1 6 S S 6 N A 3 5 . 3 8 3 1 9 7 8 . 0 6 9 4 1 7 6 . 2 4 9 7 3 . 1 8 8 2 0 1 0 - 2 0 PT W - 0 2 0 7 / 1 4 / 1 6 P V C 2 N A 3 5 . 3 8 3 1 7 7 8 . 0 6 9 4 5 7 6 . 3 7 7 3 . 3 1 2 2 0 1 0 - 2 0 PT W - 0 3 0 7 / 1 3 / 1 6 P V C 2 N A 3 5 . 3 8 3 2 7 7 8 . 0 6 9 4 4 7 6 . 1 4 7 3 . 0 2 1 2 0 1 0 - 2 0 PT W - 0 4 0 7 / 1 3 / 1 6 P V C 2 N A 3 5 . 3 8 3 2 9 7 8 . 0 6 9 1 5 7 5 . 9 6 2 7 2 . 7 1 1 2 0 1 0 - 2 0 PT W - 0 5 0 7 / 1 3 / 1 6 P V C 2 N A 3 5 . 3 8 3 2 4 7 8 . 0 6 9 7 1 7 6 . 4 1 1 7 3 . 2 3 3 1 9 9 - 1 9 PT W - 0 6 0 7 / 1 2 / 1 6 P V C 2 N A 3 5 . 3 8 2 7 4 7 8 . 0 6 9 3 6 7 8 . 4 3 9 7 5 . 3 1 5 1 8 8 - 1 8 AM W - 1 4 S 0 4 / 2 8 / 1 5 P V C 2 N A 3 5 . 3 8 7 1 6 7 8 . 0 7 0 6 9 7 8 . 0 8 7 5 . 2 1 2 1 . 4 1 1 . 4 - 2 1 . 4 AM W - 1 4 B C 0 4 / 2 3 / 1 5 P V C 2 0 - 2 5 3 5 . 3 8 7 1 4 7 8 . 0 7 0 7 1 7 7 . 4 3 7 4 . 6 9 4 5 4 0 - 4 5 AM W - 1 8 S 0 5 / 2 5 / 1 6 P V C 2 N A 3 5 . 3 8 2 0 5 7 8 . 0 6 7 2 0 7 8 . 2 8 74 . 1 4 31 21-31 AM W - 1 8 B C 0 6 / 2 7 / 1 6 P V C 2 0- 4 3 3 5 . 3 8 2 0 4 7 8 . 0 6 7 2 0 77 . 5 4 7 3 . 3 8 66 56-66 CM W - 6 0 7 / 2 9 / 1 0 P V C 2 NA 3 5 . 3 8 3 2 0 7 8 . 0 6 9 8 0 7 6 . 2 5 NM 12 2-12 CM W - 6 R 0 9 / 1 1 / 1 2 P V C 2 NA 3 5 . 3 8 3 1 8 7 8 . 0 6 8 1 0 7 5 . 3 7 73 . 1 6 15 5-15 AM W - 0 6 R B C 0 5 / 0 1 / 1 5 P V C 2 0 - 2 2 . 5 3 5 . 3 8 3 1 9 7 8 . 0 6 8 1 7 7 6 . 1 0 73 . 0 3 50 45-50 No t e s : Prepared by: TCP Checked by: JDM BG S = B e l o w g r o u n d s u r f a c e NF = N o F l o w MS L = M e a n s e a l e v e l TO C = T o p o f c a s i n g NM = N o t M e a s u r e d SS = S t a i n l e s s S t e e l P: \ D u k e E n e r g y P r o g r e s s . 1 0 2 6 \ 0 4 . L E E P L A N T \ 2 0 . A c c e l e r a t e d R e m e d i a t i o n \ P i l o t T e s t \ P i l o t T e s t R e p o r t _ A u g 2 0 1 6 \ T a b l e s \ P i l o t T e s t W e ll C o n s t r u c t i o n D e t a i l s . x l s x P a g e 1 o f 1 TABLE 3 PILOT TEST WATER LEVEL DATA H.F. LEE ENERGY COMPLEX DUKE ENERGY PROGRESS, LLC, GOLDSBORO, NC DATE TIME DTW DATE TIME DTW DATE TIME DTW 8/2/2016 8:45:00 7.07 8/2/2016 8:39:00 7.18 8/2/2016 8:37:00 6.93 8/2/2016 8:58:00 11.22 8/2/2016 9:31:00 8.14 8/2/2016 9:32:00 7.90 8/2/2016 9:02:00 11.35 8/2/2016 11:39:00 8.44 8/2/2016 10:28:00 7.95 8/2/2016 9:28:00 11.43 8/2/2016 12:17:00 8.45 8/2/2016 11:40:00 7.91 8/2/2016 9:48:00 11.45 8/2/2016 13:27:00 8.47 8/2/2016 12:21:00 7.92 8/2/2016 10:27:00 11.50 8/2/2016 14:27:00 8.49 8/2/2016 13:29:00 7.95 8/2/2016 11:37:00 11.47 8/2/2016 15:29:00 8.50 8/2/2016 14:29:00 8.01 8/2/2016 12:07:00 11.49 8/2/2016 16:19:00 8.53 8/2/2016 15:31:00 8.01 8/2/2016 13:27:00 11.50 8/2/2016 17:33:00 8.54 8/2/2016 16:20:00 8.02 8/2/2016 14:27:00 11.53 8/2/2016 20:01:00 8.53 8/2/2016 17:34:00 8.03 8/2/2016 15:29:00 11.55 8/2/2016 20:59:00 8.52 8/2/2016 20:02:00 8.00 8/2/2016 16:19:00 11.56 8/2/2016 21:58:00 8.52 8/2/2016 21:03:00 7.99 8/2/2016 17:32:00 11.59 8/2/2016 22:57:00 8.52 8/2/2016 21:59:00 8.00 8/2/2016 19:58:00 11.55 8/2/2016 23:58:00 8.52 8/2/2016 22:59:00 8.00 8/2/2016 21:05:00 11.56 8/3/2016 0:55:00 8.53 8/2/2016 23:59:00 8.02 8/2/2016 21:58:00 11.57 8/3/2016 1:57:00 8.54 8/3/2016 0:56:00 8.02 8/2/2016 22:58:00 11.58 8/3/2016 2:58:00 8.54 8/3/2016 1:59:00 8.02 8/2/2016 23:59:00 11.58 8/3/2016 3:58:00 8.55 8/3/2016 3:00:00 8.03 8/3/2016 0:55:00 11.58 8/3/2016 4:57:00 8.55 8/3/2016 4:00:00 8.03 8/3/2016 1:58:00 11.59 8/3/2016 5:56:00 8.56 8/3/2016 4:58:00 8.04 8/3/2016 2:59:00 11.60 8/3/2016 6:56:00 8.56 8/3/2016 5:57:00 8.05 8/3/2016 3:59:00 11.60 8/3/2016 7:56:00 8.56 8/3/2016 6:58:00 8.05 8/3/2016 4:58:00 11.60 8/3/2016 9:17:00 8.56 8/3/2016 7:57:00 8.06 8/3/2016 5:57:00 11.60 8/3/2016 10:05:00 8.56 8/3/2016 9:18:00 8.06 8/3/2016 6:57:00 11.61 8/3/2016 11:18:00 8.57 8/3/2016 10:07:00 8.06 8/3/2016 7:56:00 11.62 8/3/2016 12:06:00 8.59 8/3/2016 11:19:00 8.08 8/3/2016 9:15:00 11.62 8/3/2016 13:09:00 8.60 8/3/2016 12:08:00 8.08 8/3/2016 10:04:00 11.63 8/3/2016 14:04:00 8.60 8/3/2016 13:10:00 8.09 8/3/2016 11:17:00 11.64 8/3/2016 15:20:00 8.61 8/3/2016 14:05:00 8.10 8/3/2016 12:05:00 11.65 8/3/2016 16:08:00 8.62 8/3/2016 15:22:00 8.11 8/3/2016 13:08:00 11.66 8/3/2016 17:05:00 8.62 8/3/2016 16:08:00 8.12 8/3/2016 14:03:00 11.66 8/3/2016 18:10:00 8.62 8/3/2016 17:06:00 8.12 8/3/2016 15:19:00 11.67 8/3/2016 18:56:00 8.62 8/3/2016 18:11:00 8.13 8/3/2016 16:07:00 11.68 8/3/2016 19:59:00 8.63 8/3/2016 18:57:00 8.14 8/3/2016 17:04:00 11.69 8/3/2016 20:55:00 8.63 8/3/2016 19:59:00 8.14 8/3/2016 18:08:00 11.69 8/3/2016 20:56:00 8.14 8/3/2016 18:57:00 11.70 8/3/2016 19:58:00 11.70 8/3/2016 20:56:00 11.70 PTW-1 PTW-2 PTW-3 P:\Duke Energy Progress.1026\04.LEE PLANT\20. Accelerated Remediation\Pilot Test\Pilot Test Report_Aug2016\Tables\Pilot Test WL Data.xlsx Page 1 of 4 TABLE 3 PILOT TEST WATER LEVEL DATA H.F. LEE ENERGY COMPLEX DUKE ENERGY PROGRESS, LLC, GOLDSBORO, NC DATE TIME DTW DATE TIME DTW DATE TIME DTW 8/2/2016 8:35:00 6.79 8/2/2016 8:15:00 7.06 8/2/2016 8:18:00 9.33 8/2/2016 9:32:00 7.24 8/2/2016 9:39:00 7.36 8/2/2016 9:36:00 9.44 8/2/2016 10:40:00 7.29 8/2/2016 10:21:00 7.40 8/2/2016 10:24:00 9.49 8/2/2016 11:42:00 7.24 8/2/2016 11:30:00 7.35 8/2/2016 11:30:00 9.50 8/2/2016 12:19:00 7.24 8/2/2016 12:12:00 7.35 8/2/2016 12:15:00 9.51 8/2/2016 13:31:00 7.27 8/2/2016 13:36:00 7.38 8/2/2016 13:38:00 9.53 8/2/2016 14:31:00 7.30 8/2/2016 14:36:00 7.41 8/2/2016 14:38:00 9.54 8/2/2016 15:32:00 7.33 8/2/2016 15:36:00 7.43 8/2/2016 15:38:00 9.55 8/2/2016 16:23:00 7.34 8/2/2016 16:25:00 7.44 8/2/2016 16:28:00 9.57 8/2/2016 17:35:00 7.36 8/2/2016 17:38:00 7.46 8/2/2016 17:40:00 9.58 8/2/2016 20:04:00 7.31 8/2/2016 20:05:00 7.43 8/2/2016 20:10:00 9.57 8/2/2016 21:04:00 7.30 8/2/2016 21:06:00 7.41 8/2/2016 21:10:00 9.58 8/2/2016 22:00:00 7.31 8/2/2016 22:01:00 7.42 8/2/2016 22:04:00 9.58 8/2/2016 23:00:00 7.32 8/2/2016 23:01:00 7.43 8/2/2016 23:04:00 9.58 8/3/2016 0:00:00 7.32 8/3/2016 0:01:00 7.43 8/3/2016 0:05:00 9.59 8/3/2016 0:57:00 7.33 8/3/2016 0:58:00 7.43 8/3/2016 1:01:00 9.59 8/3/2016 2:00:00 7.34 8/3/2016 2:01:00 7.44 8/3/2016 2:04:00 9.60 8/3/2016 3:01:00 7.34 8/3/2016 3:05:00 7.44 8/3/2016 3:04:00 9.59 8/3/2016 4:01:00 7.34 8/3/2016 4:02:00 7.45 8/3/2016 4:05:00 9.60 8/3/2016 4:59:00 7.35 8/3/2016 5:01:00 7.46 8/3/2016 5:03:00 9.60 8/3/2016 5:58:00 7.35 8/3/2016 6:00:00 7.46 8/3/2016 6:02:00 9.60 8/3/2016 6:59:00 7.36 8/3/2016 7:00:00 7.46 8/3/2016 7:03:00 9.60 8/3/2016 7:58:00 7.36 8/3/2016 7:59:00 7.47 8/3/2016 8:02:00 9.61 8/3/2016 9:21:00 7.38 8/3/2016 9:25:00 7.48 8/3/2016 9:28:00 9.61 8/3/2016 10:08:00 7.38 8/3/2016 10:12:00 7.48 8/3/2016 10:16:00 9.61 8/3/2016 11:21:00 7.39 8/3/2016 11:27:00 7.49 8/3/2016 11:29:00 9.62 8/3/2016 12:09:00 7.40 8/3/2016 12:11:00 7.49 8/3/2016 12:15:00 9.63 8/3/2016 13:11:00 7.41 8/3/2016 13:13:00 7.50 8/3/2016 13:17:00 9.63 8/3/2016 14:06:00 7.42 8/3/2016 14:08:00 7.51 8/3/2016 14:12:00 9.63 8/3/2016 15:22:00 7.43 8/3/2016 15:25:00 7.52 8/3/2016 15:28:00 9.64 8/3/2016 16:10:00 7.44 8/3/2016 16:12:00 7.53 8/3/2016 16:15:00 9.64 8/3/2016 17:06:00 7.44 8/3/2016 17:07:00 7.52 8/3/2016 17:10:00 9.64 8/3/2016 18:13:00 7.45 8/3/2016 18:16:00 7.53 8/3/2016 18:19:00 9.65 8/3/2016 18:59:00 7.45 8/3/2016 19:00:00 7.53 8/3/2016 19:02:00 9.65 8/3/2016 19:59:00 7.46 8/3/2016 20:00:00 7.53 8/3/2016 20:03:00 9.65 8/3/2016 20:58:00 7.45 8/3/2016 20:58:00 7.54 8/3/2016 21:02:00 9.65 PTW-6PTW-4 PTW-5 P:\Duke Energy Progress.1026\04.LEE PLANT\20. Accelerated Remediation\Pilot Test\Pilot Test Report_Aug2016\Tables\Pilot Test WL Data.xlsx Page 2 of 4 TABLE 3 PILOT TEST WATER LEVEL DATA H.F. LEE ENERGY COMPLEX DUKE ENERGY PROGRESS, LLC, GOLDSBORO, NC DATE TIME DTW DATE TIME DTW 8/2/2016 8:13:00 5.93 8/2/2016 8:25:00 6.27 8/2/2016 9:42:00 6.02 8/2/2016 14:43:00 6.29 8/2/2016 10:13:00 6.02 8/2/2016 20:14:00 6.31 8/2/2016 11:27:00 5.85 8/3/2016 0:09:00 6.32 8/2/2016 12:11:00 5.82 8/3/2016 8:06:00 6.37 8/2/2016 13:33:00 5.87 8/3/2016 12:19:00 6.40 8/2/2016 14:33:00 5.90 8/3/2016 17:18:00 6.44 8/2/2016 15:34:00 5.94 8/3/2016 20:05:00 6.45 8/2/2016 16:24:00 5.96 8/4/2016 9:58:00 6.32 8/2/2016 17:36:00 5.98 8/2/2016 20:07:00 5.86 8/2/2016 21:13:00 5.86 8/2/2016 22:02:00 5.88 8/2/2016 23:02:00 5.89 8/3/2016 0:03:00 5.90 8/3/2016 1:00:00 5.90 8/3/2016 2:02:00 5.92 8/3/2016 3:06:00 5.93 8/3/2016 4:03:00 5.93 8/3/2016 5:02:00 5.95 8/3/2016 6:01:00 5.95 8/3/2016 7:01:00 5.96 8/3/2016 8:00:00 5.98 8/3/2016 9:23:00 5.99 8/3/2016 10:11:00 5.99 8/3/2016 11:24:00 6.00 8/3/2016 12:13:00 6.01 8/3/2016 13:15:00 6.02 8/3/2016 14:09:00 6.03 8/3/2016 15:26:00 6.06 8/3/2016 16:13:00 6.06 8/3/2016 17:08:00 6.06 8/3/2016 18:17:00 6.07 8/3/2016 19:01:00 6.07 8/3/2016 20:01:00 6.08 8/3/2016 21:02:00 6.09 CMW-6 CMW-6R P:\Duke Energy Progress.1026\04.LEE PLANT\20. Accelerated Remediation\Pilot Test\Pilot Test Report_Aug2016\Tables\Pilot Test WL Data.xlsx Page 3 of 4 TABLE 3 PILOT TEST WATER LEVEL DATA H.F. LEE ENERGY COMPLEX DUKE ENERGY PROGRESS, LLC, GOLDSBORO, NC DATE TIME DTW DATE TIME DTW 8/2/2016 8:23:00 6.36 8/2/2016 8:02:00 4.87 8/2/2016 14:41:00 6.34 8/2/2016 20:38:00 4.52 8/2/2016 20:13:00 6.31 8/3/2016 2:16:00 4.54 8/3/2016 0:09:00 6.31 8/3/2016 10:25:00 4.53 8/3/2016 8:05:00 6.31 8/3/2016 20:24:00 4.55 8/3/2016 12:18:00 6.32 8/4/2016 15:08:00 4.58 8/3/2016 17:20:00 6.31 8/3/2016 20:05:00 6.30 8/4/2016 9:57:00 6.31 DATE TIME DTW DATE TIME DTW 8/2/2016 8:03:00 5.89 8/2/2016 8:30:00 59.98 8/2/2016 20:39:00 5.83 8/2/2016 14:47:00 59.85 8/3/2016 2:17:00 5.83 8/2/2016 20:17:00 59.72 8/3/2016 10:26:00 5.82 8/3/2016 12:23:00 58.98 8/3/2016 20:25:00 5.81 8/3/2016 20:09:00 58.60 8/4/2016 15:10:00 5.82 DATE TIME DTW DATE TIME DTW 8/2/2016 8:09:00 8.25 8/2/2016 8:28:00 10.65 8/2/2016 20:45:00 8.19 8/2/2016 14:46:00 10.61 8/3/2016 2:23:00 8.18 8/2/2016 20:24:00 10.59 8/3/2016 10:32:00 8.18 8/3/2016 12:22:00 10.58 8/3/2016 20:18:00 8.20 8/3/2016 20:08:00 10.60 8/4/2016 10:00:00 10.59 Prepared by: RHJ Checked by: SRW Notes: DTW = Depth to Water CCR-103S AMW-18S AMW-6RBC AMW-14S AMW-14BC AMW-18BC P:\Duke Energy Progress.1026\04.LEE PLANT\20. Accelerated Remediation\Pilot Test\Pilot Test Report_Aug2016\Tables\Pilot Test WL Data.xlsx Page 4 of 4 Step-Drawdown and Pumping Test Findings August 22, 2016 HF Lee Energy Complex SynTerra P:\Duke Energy Progress.1026\04.LEE PLANT\20. Accelerated Remediation\Pilot Test\PDF\Tech Memo Pilot Test August 2016.docx ATTACHMENT 1 BORING LOGS, WELL CONSTRUCTION RECORDS, WELL PERMIT CLAY, tan with orange mottling, sandy and silty, damp. Upper 4" dark brown topsoil. SAND, light gray, clayey and wet. SAND, light gray, fine to medium with dm-scale bedding, wet. Varies from clean to clayey and silty. Contains layers of sand (coarse) with angular to subangular quartz gravel (fine). SAND, light gray, medium to coarse, clean. Coarsens with depth. SAND, light gray, gravelly (quartzose and angular to rounded) with clay/ silt. SAND, tan to light gray, predominantly medium to coarse with varying silt/ clay and gravel content. Contains cm-bedding 17.5'-20' bgs. CLAY containing mm-scale lignite fragments. CL SP SC SP SM SP SP SP SM CH 6" Sch. 40 threaded PVC riser Grout Bentonite Sand Pack 6" stainless steel well screen 90 60 50 90 SA M P L E DESCRIPTION BL O W CO U N T S PTW-01 5 10 15 20 25 30 35 GR A P H I C LO G US C S DE P T H (f t ) PAGE 1 OF 1 7/14/16 DRILLING COMPANY: DRILLING METHOD: BOREHOLE DIAMETER: NOTES: COMPLETED:7/14/16 CLIENT: Duke Progress Energy PROJECT: PROJECT NO: PROJECT LOCATION: Goldsboro, NC H. F. Lee Energy Complex 1026.04.20 WELL CONSTRUCTIONPI D (p p m ) WELL / BORING NO: STARTED: RE C O V . (% ) SynTerra 148 River Street, Suite 220 Greenville, South Carolina 29601 Phone: 864-421-9999 Logged from 5' DPT sleeves. 2277368.622 76.249 ft MSL 20.0 ft BGS J. Gilmer 595688.044 73.188 ft MSL 7.07 ft TOC J. Mahan Parratt - Wolff Inc. Hollow Stem Augers 12 IN NORTHING: G.S. ELEV: DEPTH TO WATER: LOGGED BY: EASTING: M.P. ELEV: TOTAL DEPTH: CHECKED BY: LO G A E W N N 0 4 D E P L E E . G P J G I N T S T D A 4 A S T M L A B . G D T 8 / 1 7 / 1 6 CLAY, tan with orange mottling, sandy and silty, damp. Upper 4" dark brown topsoil. SAND, light gray, clayey and wet. SAND, light gray, fine to medium with dm-scale bedding, wet. Varies from clean to clayey and silty. Contains layers of sand (coarse) with angular to subangular quartz gravel (fine). SAND, light gray, medium to coarse, clean. Coarsens with depth. SAND, light gray, gravelly (quartzose and angular to rounded) with clay/ silt. SAND, tan to light gray, predominantly medium to coarse with varying silt/ clay and gravel content. Contains cm-bedding 17.5'-20' bgs. CLAY containing mm-scale lignite fragments. CL SP SC SP SM SP SP SP SM CH 2" Sch. 40 threaded PVC riser Bentonite Sand Pack 2" pre-packed well screen SA M P L E DESCRIPTION BL O W CO U N T S PTW-02 5 10 15 20 25 30 35 GR A P H I C LO G US C S DE P T H (f t ) PAGE 1 OF 1 7/14/16 DRILLING COMPANY: DRILLING METHOD: BOREHOLE DIAMETER: NOTES: COMPLETED:7/14/16 CLIENT: Duke Progress Energy PROJECT: PROJECT NO: PROJECT LOCATION: Goldsboro, NC H. F. Lee Energy Complex 1026.04.20 WELL CONSTRUCTIONPI D (p p m ) WELL / BORING NO: STARTED: RE C O V . (% ) SynTerra 148 River Street, Suite 220 Greenville, South Carolina 29601 Phone: 864-421-9999 Logged from 5' DPT sleeves. 2277355.488 76.37 ft MSL 20.0 ft BGS J. Gilmer 595681.105 73.312 ft MSL 7.18 ft TOC J. Mahan Parratt - Wolff Inc. Hollow Stem Augers 12 IN NORTHING: G.S. ELEV: DEPTH TO WATER: LOGGED BY: EASTING: M.P. ELEV: TOTAL DEPTH: CHECKED BY: LO G A E W N N 0 4 D E P L E E . G P J G I N T S T D A 4 A S T M L A B . G D T 8 / 1 7 / 1 6 CLAY, tan with orange mottling, sandy and silty, damp. Upper 4" dark brown topsoil. SAND, light gray, clayey and wet. SAND, light gray, fine to medium with dm-scale bedding, wet. Varies from clean to clayey and silty. Contains layers of sand (coarse) with angular to subangular quartz gravel (fine). SAND, light gray, medium to coarse, clean. Coarsens with depth. SAND, light gray, gravelly (quartzose and angular to rounded) with clay/ silt. SAND, tan to light gray, predominantly medium to coarse with varying silt/ clay and gravel content. Contains cm-bedding 17.5'-20' bgs. CLAY containing mm-scale lignite fragments. CL SP SC SP SM SP SP SP SM CH 2" Sch. 40 threaded PVC riser Bentonite Sand Pack 2" pre-packed well screen SA M P L E DESCRIPTION BL O W CO U N T S PTW-03 5 10 15 20 25 30 35 GR A P H I C LO G US C S DE P T H (f t ) PAGE 1 OF 1 7/13/16 DRILLING COMPANY: DRILLING METHOD: BOREHOLE DIAMETER: NOTES: COMPLETED:7/13/16 CLIENT: Duke Progress Energy PROJECT: PROJECT NO: PROJECT LOCATION: Goldsboro, NC H. F. Lee Energy Complex 1026.04.20 WELL CONSTRUCTIONPI D (p p m ) WELL / BORING NO: STARTED: RE C O V . (% ) SynTerra 148 River Street, Suite 220 Greenville, South Carolina 29601 Phone: 864-421-9999 Logged from 5' DPT sleeves. 2277358.902 76.14 ft MSL 20.0 ft BGS J. Gilmer 595718.876 73.021 ft MSL 6.93 ft TOC J. Mahan Parratt - Wolff Inc. Hollow Stem Augers 12 IN NORTHING: G.S. ELEV: DEPTH TO WATER: LOGGED BY: EASTING: M.P. ELEV: TOTAL DEPTH: CHECKED BY: LO G A E W N N 0 4 D E P L E E . G P J G I N T S T D A 4 A S T M L A B . G D T 8 / 1 7 / 1 6 CLAY, light gray to tan with orange mottling, sandy, damp. Upper 6" rooted topsoil. SAND, light gray, medium to coarse. 4" zone near bottom of interval dominated by coarse grains. SAND, tan to light gray and poorly sorted with angular to subangular quartz gravel (fine) ~12.5' bgs. SAND, medium to coarse and clean. Bottom 2" subangular quartz gravel (fine). SAND, medium to coarse with fines. CLAY, dark to light gray, plastic with disseminated pyrite often occurring as sub-vertical stringers at mm-scale thickness. CLS SP SW SP SP SM CH Bentonite 2" Sch. 40 threaded PVC riser Sand Pack 2" pre-packed well screen 50 50 50 50 60 SA M P L E DESCRIPTION BL O W CO U N T S PTW-04 5 10 15 20 25 30 35 GR A P H I C LO G US C S DE P T H (f t ) PAGE 1 OF 1 7/13/16 DRILLING COMPANY: DRILLING METHOD: BOREHOLE DIAMETER: NOTES: COMPLETED:7/13/16 CLIENT: Duke Progress Energy PROJECT: PROJECT NO: PROJECT LOCATION: Goldsboro, NC H. F. Lee Energy Complex 1026.04.20 WELL CONSTRUCTIONPI D (p p m ) WELL / BORING NO: STARTED: RE C O V . (% ) SynTerra 148 River Street, Suite 220 Greenville, South Carolina 29601 Phone: 864-421-9999 Logged from 5' DPT sleeves. 2277445.308 75.962 ft MSL 25.0 ft BGS J. Gilmer 595727.013 72.711 ft MSL 6.79 ft TOC J. Mahan Parratt - Wolff Inc. Hollow Stem Augers 8 IN NORTHING: G.S. ELEV: DEPTH TO WATER: LOGGED BY: EASTING: M.P. ELEV: TOTAL DEPTH: CHECKED BY: LO G A E W N N 0 4 D E P L E E . G P J G I N T S T D A 4 A S T M L A B . G D T 8 / 1 7 / 1 6 CLAY, tan with yellow-orange mottling, silty and sandy (fine to coarse). Grades into sand ~4' bgs. Upper 4" dark brown organic rich soil. SAND, gray to tan, medium with some subrounded quartz gravel (fine), wet. Fining to 10' bgs. SAND, light gray with gravel (coarse). SAND, light gray, fine, graded. SAND, light gray, clayey, poorly sorted with 4" zone of clean sand (fine to medium). CLAY, silty, contains lignite fragments (<10 mm) and sand (coarse). CLAY, thinly bedded (mm-scale) with minor lenses of light gray sand (fine). CL SPG SPG SP SP SC CL ML CH Bentonite 2" Sch. 40 threaded PVC riser Sand Pack 2" pre-packed well screen 90 30 50 100 SA M P L E DESCRIPTION BL O W CO U N T S PTW-05 5 10 15 20 25 30 35 GR A P H I C LO G US C S DE P T H (f t ) PAGE 1 OF 1 7/13/16 DRILLING COMPANY: DRILLING METHOD: BOREHOLE DIAMETER: NOTES: COMPLETED:7/13/16 CLIENT: Duke Progress Energy PROJECT: PROJECT NO: PROJECT LOCATION: Goldsboro, NC H. F. Lee Energy Complex 1026.04.20 WELL CONSTRUCTIONPI D (p p m ) WELL / BORING NO: STARTED: RE C O V . (% ) SynTerra 148 River Street, Suite 220 Greenville, South Carolina 29601 Phone: 864-421-9999 Logged from 5' DPT sleeves. 2277280.518 76.411 ft MSL 20.0 ft BGS J. Gilmer 595706.473 73.233 ft MSL 7.06 ft TOC J. Mahan Parratt - Wolff Inc. Hollow Stem Augers 8 IN NORTHING: G.S. ELEV: DEPTH TO WATER: LOGGED BY: EASTING: M.P. ELEV: TOTAL DEPTH: CHECKED BY: LO G A E W N N 0 4 D E P L E E . G P J G I N T S T D A 4 A S T M L A B . G D T 8 / 1 7 / 1 6 SILT, yellow-orange, clayey. Upper portion of interval rooted. SAND, yellow-orange, fine to medium, contains cm-scale lenses of sand (medium to coarse) mid-interval. Sand coarsens towards 10' bgs with gravel (fine) in matrix of sand (medium). Wet ~8' bgs. SAND, light gray, medium-grained with sand (coarse) and gravel (fine), wet. SAND, light gray, medium-grained and wet. Contains cm-scale repeating succession of sand (coarse) to gravel (fine) to silty, clayey sand (fine). SAND, light gray, clayey with dm-scale interbeds of sand (medium)/ silts to olive gray clay, wet. cm-scale mud nodules occur in light gray sand (fine) matrix. Mud contains dark brown to black lignitic material. Transitions to sand (coarse) in mud/ clay matrix with mud nodules ~24' bgs. CLAY, olive gray, minor silt, plastic and wet. Contains occasional mm-scale light gray sand (fine) lenses, mm-scale fragments of dark organic material, and very fine dissemenated pyrite(?) grains. Bedding massive to lenticular. ML SW SPG SWG SP SC CH Bentonite 2" Sch. 40 threaded PVC riser Sand Pack 2" pre-packed well screen 100 100 30 50 100 100 SA M P L E DESCRIPTION BL O W CO U N T S PTW-06 5 10 15 20 25 30 35 GR A P H I C LO G US C S DE P T H (f t ) PAGE 1 OF 1 7/12/16 DRILLING COMPANY: DRILLING METHOD: BOREHOLE DIAMETER: NOTES: COMPLETED:7/12/16 CLIENT: Duke Progress Energy PROJECT: PROJECT NO: PROJECT LOCATION: Goldsboro, NC H. F. Lee Energy Complex 1026.04.20 WELL CONSTRUCTIONPI D (p p m ) WELL / BORING NO: STARTED: RE C O V . (% ) SynTerra 148 River Street, Suite 220 Greenville, South Carolina 29601 Phone: 864-421-9999 Logged from 5' DPT sleeves. 2277386.3 78.439 ft MSL 30.0 ft BGS J. Gilmer 595526.558 75.315 ft MSL 9.33 ft TOC J. Mahan Parratt - Wolff Inc. Hollow Stem Augers 8 IN NORTHING: G.S. ELEV: DEPTH TO WATER: LOGGED BY: EASTING: M.P. ELEV: TOTAL DEPTH: CHECKED BY: LO G A E W N N 0 4 D E P L E E . G P J G I N T S T D A 4 A S T M L A B . G D T 8 / 1 7 / 1 6 WELL CONSTRUCTION RECORD This loi an can be used for single or multiple %%ells Fur IntemalI:se0\LY I. Well Contractor Information: Lewis LeFever \\-ell Conuactor Came 2480-A Nt Well Conuacloi Ceinlicauon Number Parratt-Wolff Ct n1pam \ame -. 2. Well Construction Permit#;: Lm all ❑pplaahle hell pcnnils (i r Cahill, suNc, l inial,r, hryrcnon, en l 3. Well Use (check well use): Water Supply Well: ❑Agricultural ❑Geothermal (Heating/Cooling Supply) ❑ Ind ustrial/Commerc I'll ❑Municipal/Public ❑Residential Water Supply (single) [-]Residential Water Supply' (shared) ❑Irrigation Non-Al'atet- Supply Well: ❑ Monitoring 0 RecoveiA ❑Aquirer Recharge ❑Aquifer Storage and Recovery ❑Aqua Fer Test ❑Experimental Technology ❑Geothermal (Closed Loop) ❑Geothermal (Heating/Cooling Return) ❑Groundwater Remediation ❑Salinity Barrier ❑S(ormw-ater Drainage ❑Subsidence Control ❑ Tracer ❑Other (explain under #21 1 4. Date Well(s) Completed: 71141201 Well ID# PTW-1 5a. Well Location: Duke Energy HF Lee Station Facility/Owner Name Ficdtly ID- (ifapplicable) 1622 Old Smithfield Rd. Physical Address. City. and Zip Wayne Couuly Parcel Identification No (PIN) 5b, Latitude and Longitude in degrees/minutes/seconds or decimal degrees: Iif %velI field, one laelong is sufficient) 35.384815 N-78.069778 N 6. Is (are) the well(s): OPermanent or ❑Temporary 7. Is this a repair to an existing well: ❑Ves or 7INo tf this is a repair, fill out kit m n hell t onstr fie flan iolo Ovation and rsplain drr nanny ul the repair under "'I winca ks in lion or on fhc• hark o/ this /fri ar S. Number of wells constructed: 1 For antlriple irliecfinn or eon -Water atppll' reel/s OVLY a ah the .came construction. wit ,at submit are /;trim 20.0 9. Total well depth below land surface: (ft.) For rrudliple a ells list all depths ildiherenf (ayample- 3p 200' arc/ 2'a /00') 8.0 10. Static water level below top of casing; (ft.) Il n lei• rail is abm•c Cavil;;, use ' 12.0 11. Borehole diameter: (in.) Ii. WATER ZONES - -- FRONT TO DESCRIPTION 8.0 fr. 15.0 rr. Wet 15.0 rr• 20.0 fry Moist 15. OUTER CASING (fur multi -cased weltsl OR LINER lif a ilicable) FRONT TO I DIAMETER I THR KNESS NI ITERIAL ft. ft. I 16. INNER CASING OR TUBING € eothermal closed -too FRONT TO DIAMETER T€€R KNFSS NI\TERIA1. 0 fr' 10.0 fry 6.0 in. Sch.40 PVC ft. ft. in- 1". of REEK FROM TO DIAMETER SLOT SIZE THICKNESS ;MATERIAL 10.0 IT. 20.0 fry 6.0 in. 0.01" SS W ft. in. IS. GROUT FROM 0 ft. TO 5.0 fr' MATERIAI Bent./Port. EMPI.ACFMFNT METHOD & AAf OVNT Tremied 5.0 fr. 7.0 ft. Bentonite Poured ft. ft. 19. SAND/GRAVEL PACK ifa iicable FROM I TO MATERIAL ENIPLACFNIEN'r METHOD 7.0 fry 20.0 rr• #2 1 Poured it. I 20. DRILLING LOG attach additional sheets if necessa FROM TO DESCRIPTION lcolua.hacdaess, soiVrock. 1. e, raw.si-re. 0 fry 5.0 rr• Brown, Moist, SILT and Clay 5.0 rr• 10.0 fry Tan, Wet Fine SAND and Silt 10.0 fry 15.0 fr, Tan, Wet Fine SAND and Silt 15.0 fry 20.0 fry Dark Gray, Moist, CLAY and Silt ft. ft. ft. ft. ft. ft. 21. REMARKS Installed 8" Stick -Up Cover 22. (Arti ealion: 8i9/2016 ­'t1fi{,�.tt��.�� Si}nature of Crte4d 11e l i ctor r Date B±-.ir\;i`to 1, this fare rhv tu•rtili' that the nell(s) nna (rrc're) cournrrctcd in acrordanr n ith 1 i.4-\'C:aC 02C 0/00 of 1 iA AVAC02C.0'110 Well Construt rant Siandnrzlq and that it c npr of this record has been provider/ to the hull oa neh. 23, Site diagram or additional well details: You may use the back of this page to provide additional well site details of well construction details You inay also attach additional pages if necessaR SUBMITTAL INSTUCTIONS 24a. For .all Wells: Submit this rorm within all days of completion of well construction to the Following Division of Water Resources, Information Processing Unit, 1617 Mail Service Center, Raleigh, NC 27699-1617 24b. For Infection Wells ONLY: In addition to sending the form to the address in 2daabove. also submit a copy of this Fora within �0 days of completion of \\ell 12. Well construction method: Auger construction to the following (r e auger, room, cable, direct push, etc I Division of Water Resources, Underground Injection Control Program, FOR WATER SUPPLY WELLS ONLA : 1636 Mail Service Center, Raleigh, NC 27699-1636 13a. field (gpm) Method of test: 24c. Foryy'ater Supply & Injection Wells: Also submit one copy (it form within 30 dacsofcompletionof 13b. Disinfection type: amount: well construction to the county health department or the count\ where constl ucted Foi nt G\\ - I Not th Carolina Depar orient of Envu tBtntenr and \attual Resoui ces - Dis ismn of \\ alei Resource., Res iced August '0 1", WELL CONSTRUCTION RECORD This trim can be used IN single ai nndI iple meils Fur Inteinal ('se ONLY I. Well Contractor Information: Lewis LeFever Well Contiactw Name 2480-A NC Well C'ontiactoi Certtlication Number Parratt-Wolff Compam Aante 2. Well Construction Permit #: Lau all applicable a 'Il pdrnnits (i e County, Slott. [ iu iunt Milt lion. ell 1 3. Well I -se (check well use): Water Supply Well: ❑Agricultural ❑Munk Ipal/Public ❑Geothermal (Heating/Cooling Supply) ❑Residential Watei Supply (single) ❑Industrial/Commercial ❑Residential Water Supply (shared) ❑Irrigation Non-11'ater Supply Well: ❑O Monitoring ❑ Recover Injection N ell: ❑Ayuifel Recharge ❑Groundwater Remediation ❑Ayuifet Storage and Recovery ❑Salinity Barrier ❑Ayuifel Test ❑Stormwater Drainage ❑Experimental Technology ❑Subsidence Control ❑Geothermal (Closed Loop) ❑Tracer ❑Geotheinmal (Heating/Cooling Rewrn) ❑Other (ex lain under #21 Remarks) 4. Date Well(s) Completed: 7/14/2016Well ID# PTW-2 5a. Well Location: Duke Energy Facility/Owner Name 1622 Old Smithfield Rd. Physical .Address. City and Zip Wayne County HF Lee Station Facthw ID-1 (if applicable) Pai cel Identification No (PIN) 5b. Latitude and Longitude in degrees/minutes/seconds or decimal degrees: (it well field, one lat'long is sufficient) 35.384789 N-78.069847 N 6. Is (are) the well(s): (OPermanent or ❑Temporary 7. Is this a repair to an existing well: ❑Yes or ZINo It' this is a repuir, Jill out know n hell ron.ctrmPin I inlnrnaaimp and explain the name of tad repair under �1I remarks wi,fion or on the hark o/(this loran 8. Number of wells constructed: 1 For midtiple inje, Lion or pion -water cupplr n ells OVLY a ith the same construction, row c an submit n,te log it, 20.0 9. Total well depth below land surface: Ift.) Fnr- rnultilrlr hells list all depths if dilleient (example- 3:ra 200 and 21ia /00') 8.0 10. Static water level below top of casing: (ft.) 11 hater level is mho-e easing, arm° `� 11. Borehole diameter: 8.0 lin.1 la. WATER ZONES FROM TO DESCRIPTION 8.0 fr• 20.0 ft• wet ft, ft. 15.011'F;R CASING [fur multi-m" welLe OR [.1'F.R ifo tieablc FROM Tir Dl vo l"t'17 'f1f1f'tiNF�S M m,TERL%t. ft. I ft. I in. I(,. INNER C tSING Olt TI'Rllf: trEa thermal elm ed-)tat r FROM TO DI\METER I inuk P:Ss vi%,I rRI 11 0 ff 10.0 fL 2.0 In. Sch.40 PVC ft. ft. in. _ 17. SC'REEN FROM TO DIAME'I ER SLOT SIZE THICKNESS MATERIAL 10.0 f" 20.0 D. 2.0 in. 0.01" Sch.40 PVC ft. ft, in, 18. GROUT FROM TO MATFRIAI EMPI ACF,MENTNIF.THQDXANIOI'NT 0 fr. 4.0 ft- Bent./Port. Tremied 4-0 ft- 7.0 ft. Bentonite Poured ft. ft. 19. SANDLGRAVEL PACK if a iicalde FROM I TO I MATERI tt. I FMPt %1CFVFNT MF.TIIOD 7.0 ft- 20.0 ft- #2 Poured ft. fL 20. DRILLING LOG (attach additional sheets if necessary) FROM TO DESCRIPTION Icolot. hardness. soil/rock Ivne. etain size. ergs ft. ft. No Samples ft. ft. fr. ft. fr. ft. ft. ft. ft. ft. ft. fr. 21. RI NTARFiS Installed 4" Stick -Up Cover 22. C` rti cation: r�N 8/9/2016 SI-n I w Unliticcl TftrV/11 nnrlb(cn Date Rr igning this lnrm, I co-li/i that the wc•ll(c) nos- (nerd/ conitruc•ted III I,, ordancc ,vita I ?A \'CAC 02C 0100 or 15A \'CAC 02C 0200 IYe// Copwort tiun ,Standmds and that a cnpr of this record has been provided to the nrll mind•, 23. Site diagram or additional well details: You may use the back of this page to pro%ide additional well site details of well construction details You mayalso attach additional pages, ifnecessar SUBMITTAL INSTUCTIONS 24a. For ,all Wells: Submit this form within 30 days of completion of well construction to the following Division of Water Resources, Information Processing Unit, 1617 Mail Service Center, Raleigh, NC 27699-1617 24b. For Infection Wells ONLY: In addition to sending the form to the address in Auger 2daaboe- also submit a coPe of this form vSithrn 30 days of completion of vNell 12. Well construction method: construction to the following: (i a sues, nxan•, gable, direct push, etc I Division of Water Resources, Underground Injection Control Program, FOR WATER SUPPLY WELLS ONLY: 1636 flail Service Center, Raleigh, NC 27699-1636 13a. Yield (gpm) Methud of test: lac. For N ater Supply & Injection Wells: Also submit one copy of this form within 30 daNsofcompletionof 13b. Disinfection type: Amount: well construction to the county health department of the count) where constructed Foim G\S - I Notch Cmolina Department of Environment and \af ual Resouices- Di\ision of W;trei Resources Re\Ised -\ugusl'_01", WELL CONSTRUCTION RECORD TlLis form can be used for sin wle of multiple vcells I. Well (-(infractor Information: Lewis LeFever Well Conuactol Name 2480-A NC Well C uuoactor Coulicauon Number Parratt-Wolff ( ompan Name 2. Well Construction Permit #: Lwall applicahlc ndl penmitc (i (main, ,Stale Ilaiamre, Imjrcnon. ere I 3. Well t'se (check well use): Water Supply Well: ❑Agricultural ❑Municipal/Public ❑Geothermal (Heating/Cooling Supply) ❑Residential Water Supply (single) ❑Industrial/Commercial ❑Residential Water SupPIN (shared) ❑ Itt i 4at man Non -Water Supply Well: ❑O Monitol Ing ❑ Recover ❑Aquifer Recharge ❑Aquifer Storage and Recovery ❑ Aqul ter Test ❑Experimental Technology ❑Geothermal (Closed Loop) ❑Geothermal (Heat ill g/Cooling ❑Goundwater Remediation ❑Salinity Barrier ❑Stornl\cater Drainage [-]Subsidence Control ❑Tracer Return) ❑other (explain under 421 4. Date Well(s) Completed: 7/13/2016Well ID# PTW-3 5a. Well Location: Duke Energy HF Lee Station Facility/Ocvnei Name Facdiq, ID- (iFapplicable) 1622 Old Smithfield Rd. Physical -\ddress City. and Zip Wayne county Parcel Identification No (PIN) 5b. Latitude and Longitude in degrees/minutes/seconds or decimal degrees: (iflcell field, one fat toms is sti icientl 35.384838 N-78.069786 6. is (are) the well(s): OPermanent or ❑Temporary 7. Is this a repair to an existing well: ❑l•es or DNo 1l lire, i, a repair-, /ill oa) knoua url/ cons) acliom folio rmfitiom find ecplaim der matra-r of the wimih under 4_'1 remarks cretins wore the hot k o/ Ilni /dent S. Number of wells constructed: 1 For matlriple Injection or mom-u (it", capplr n el/c OVLY n idr tire Conte ranstrodion, r ore r am uthmrit rue limn 9. Total well depth below land surface: 20.0 (ft.) Far multiple cells list all deplhc il-diperem (evample- 3'u 100' cord 1'd Wet') 10. Static water level below top of casing: 8.0 (ft.) l/ water level is ahorr ,Icier,;,. it,,, ..- 11. Borehole diameter: 8.0 fill.) Foi Inteinal Use ONLI 14. WATER ZONES FROM TO DESCRIPTION 8.0 120.0 ft wet ft. ft. 15. OUTER CASING (for multi -cased wells) OR LINER fif aoDlicahlel FROM TO I 111011F.TER THICKNESS I MATFRIAI. Fr. fr. I in, 16. INNER CASING OR TUBING (geothermal closed-looDl FROM TO mAMFTFR THUKNI'SS MATFRI.\F 0 f6 10.0 ft- 2.0 in. Sch.40 PVC ft. ff. In. 17.SCREEN FROM TO DLIMFTFR SLOT SIZF THICKNESS MATERIAL 10.0 "' 20.0 ft' 2.0 in. 0.01" Sch.40 PVC ft. ft. in, 19. GROUT FROM TO MATERIAL EMPLACEMENT ]IET IOD & AMOUNT 0 ft. 4.0 ft- Bent./Port. Tremied 4.0 ft. 7.0 ft- Bentonite Poured I'L ft. 19. SAND/GRAVEL PACK (if aoDlicahlel FROM TO MATFRI aI I'MPIAC-EMENTMETHOD 7.0 ft- 20.0 rt #2 Poured ft. ft. 20. DRILLING LOG (attach additional sheets if necessary) FROM To DFtii-HtP'rIl7N Imlru. Its rslnns,xuiLru.k lv n•, rain sine, rtr.I ft. fr. No Samples ft. ft. rr. ft. - - rt. ft. ft. fr. ft. ft. fr. ft. 21. REMARKS Installed 4" Stick -Up Cover 22. Cer If ation: - r`18/9/2016 Signarum irI era}red \Nell Cr.. iraelnr Date 81 si;;rrin;; ilii.v jnrm, 1 /Jeer.• re,ii ji• that the ur//(c) nay mere) con.cu,uered Ili accordanu, nilln 15A .\-CAC 03C.0100 or lSd \'C'a(' O1C 0200 If"ell Congrtwtiurr Stawlanele and that u colt ,I the, rervl'd due hcem prorrelyd Io Ilrr well au net. 23. Site diagram or additional well details: You may use the back or this page to provide additional well site details of well construction details You ma\ also attach additional pages if necessan SUBMITTAL INSTUCTIONS 24a. For .all Wells: Submit this Corm within 30 daNs or completion of Well construction to the following Division of Water Resources, Information Processing t nit, 1617 flail Service Center, Raleigh, NC 27699-1617 tab. For Infection Wells ONLY: In addition to sending the form to the address In Auger ? la above, also submit a cop\ of this form within 3(1 days of completion of v\ell 12. Well construction method: construction to the following: (i a auger, rota-\, cable, direct push. ere 1 Division of Rater Resources, Underground Injection Control Program, FOR WATER SUPPLY WELLS ONL) : 1636 flail Service Center, Raleigh, NC 27699-1636 24c. For Water Supple & Injection Wells: 13a. field (gpm) Method of test: Also submit one copy of this roam within 30 days of completion of 13b. Disinfection type: _ Amount: well cans0u01011 to the county health department of the count\ where constllicted Foim G\\-I Nnuh Carolina Depaimtent ofEnvuonnrenl and Naum:d Resotuces- Division of\\atei Resnurca; Revised-\uausl 2011 WELL CONSTRUCTION RECORD This Ibon can be used fur single of multiple shells Rn Internal Use 0\I.l' I. Well Contractor Information: Lewis LeFever VNell Cnnuactcn Name 2480-A NC \VelI C•onuactor Cei tiicanon Number Parratt-Wolff Compam \amc 2. Well Construction Permit #t Listallapplhahl, Oil, if., Cmrnh.State, lamnae.lnjretinn,rt, 3. Well Use (check well use): Water Supply Well: ❑Agricultural ❑Municipal/Public ❑Geothenmal (Heating/Cooling Supply) ❑Residential Water Supply (single) ❑ Industrial/C•ommei vial ❑Residential Water Supply (shared) ❑ Irnuation Non -Water Suppl} Well: ❑, Monitorma El Recover ❑Aquifer Recharge ❑Aquifer Storage and Recovery ❑Aqulter Test ❑Experimental Technology ❑Geothermal (Closed Loop) ❑Geothermal (Heating/Cooling ❑Gnutndwater Reinedlation ❑Salinity Barrier ❑Stormwater Drainage ❑Subsidence Control ❑Tracer Return) ❑Other (explain under #21 Remarks 4. Date Well(s) Completed: 7/13/2016Well ID# PTW-4 5a. Well Location: Duke Energy Facdny/Owner Name 1622 Old Smithfield Rd, Physical Address City_ and Zip Wayne HF Lee Station Facility ID, (rfapplicable) Count} Parcel Identification No (PIA) 5b. Latitude and Longitude in degrees/minutes/seconds or decimal degrees: lif>sell field, one Iat.long is suflicientl 35.384895 N-78.069649 W. 6. Is (are) the well(s): OPermanent or ❑Temporary 7, Is this a repair to an existing well: ❑I es or 91No If thk ie n repair•, lill ,in bmun uell cnrr.enuchnn inlbrrnurinn nerd explain fire nature of (Ile repair rnr(rr #11 veonurkc vrcnirn nr (in the hark of this /area S. Number of wells constructed: 1 For multiple injec rinn nr non -nee capph• a ells OVLY mith the sumoenn.struetion, i not can vohnrit note In, no. 9. Total well depth below land surface: 20.0 Fnr undtiple r,el/s lisr all depth- ifdilloenr le.rample- 3yi,200'and 2si I00') 10. Static water level below top of casing: 8'0 11 tinter lerel i.c abm e casing, loci - 11. Borehole diameter: 8.0 (in.) I;, WATER ZONES FRO71,1 TO DE.SL I[tl'I LOV 8.0 r` 20.0 ft• Wet 20.0 f` 25.0 f` Moist 15. OUTER LASING for vtellt) OR LINFR 1f a licablc FROM - TO T!glt-cased DIAMETER 'rHCC':ii:NEtiS NIATERIAL ft. . 16. INNER CASING OR TUBING t enthprTal clawd-lnn FRONT TO M\NI FTFR THI(KSFSS M%TFRI\I 0 f` 10.0 f`• 2.0 In' Sch.40 PVC ft. ft. in, 17• SCR FEN FROM TO D1VIIM- R SI_f17 Silt: fit I( talcs M Ct 1'RI %I 10.0 f`- 20.0 f`• 2.0 in. 0.01" Sch.40 PVC ft. ft. in. IS. GROUT FROM TO MATERIAL Bent./Port. FMPI ACFM_FNT NILTHOD & _AMO1 NT 0 ft' 4.0 t• Tremied 4.0 f`• 7.0 rt• Bentonite Poured fr. ff. 19. SAND/GRAVEL PACK lif aunlicablel FROM TO MATERIAL EMPLACENIFN'TMETHOD 7.0 f`• 25.0 f`• #2 Poured ft. ft. 20. DRILLING LOG attach additional sheers if necessary) FRONT TO DESCRIPTION trnlnry hardness, snillrnck rune. main Sip, rr r.l 0 ft- 5.0 ft. Red/Brown, Moist, SILT and Clay 5.0 t• 10.0 0. Tan, Wet Fine SAND and Silt 10.0 t• 15.0 f`• Tan. Wet Fine SAND and Silt 15.0 f`• 20.0 f`• 20.0 t• Tan, Wet, Course SAND and Gravel Dark Gray, Moist, CLAY 25.0 f`• ft. ft. ft. ft. 21. REMARKS Installed 4" Stick -Up Cover 22.I'c t1i alion: rAt 8I9I2016 S qndlw:e ul tniliat ell Corl.u•tur - Date - .._ ... t Br cigring E Jnrnr, / hrrrlru rplr that 1/1e urll(s) nnc (rrre) CO11MUcfed in au'nrdanu• airh / iA ACAC 02C-0100 nr 15/1 ,AVAC 02C 0200 It'eh' Cnnsu•urlinn Sfandaid.c and than a ru/n• Of this rccnrd hue been /n mired on the ❑ell metier 23. Site diagram or additional iiell details: You may use the back of this page to pioN ide additional well site details or well construction details You may also attach additional pages ifnecessan SUBMITTAL INSTUCTIONS 24a. For ,all Wells: Submit this form within 30 days of completion of well construction to the following DiNisiou of Water Resources, Information Processing Unit, 1617 Mail Service Center, Raleigh, NC 27699-1617 24b. For Infection Wells ONLI : In addition to sending the fo1Tn to the address In Auger 24aabove, also submit a copy of this form v\ithin 30 days of completion of well 12. Well construction method: construction to the following: 0 a auger, rotary cable, direct push, etc I Division of Water Resources, Underground injection Control Program, FOR WATER SUPPLY WELLS ONLY: 1636 Mail Service Center, Raleigh, NC 27699-1636 133. Yield (gpm) Method of test:. 24c. For Water Supply & Injection Wells: Also submit one copy of this form within 30 da\ s of completion of 13b. Disinfection type: Amount: well construction to the County health department of the ctnlntV Where constructed Poi it CA\ - I \cu llr Cal olina Department of Envitonmenl and Vann at Resources- Division ot'W.uei Resum ces Re\ised \u�us12013 WELL CONSTRUCTION RECORD This t6i nt can be used for single of out luple swells For Internal UseONLY I. Well Contractor Information: Lewis LeFever Well Colloacto, Name 2480-A NC Well Contractor Ceintication \umbel Parratt-Wolff Compam Naive 2. Well Construction Permit #: Lisl all applaahlc hell pennirs lie Countr, Stale, f aliancr, Injection, etc.) 3. Well Use (check well use): Water Supply Well: ❑Agricultural ❑Municipal/Public ❑Geothermal (Heating/Cooling Supply) ❑Residential Water Supply (single) ❑industrial/Commercial ❑Residential Water Supplv (shared) ❑irrigation Von-NN'atei- Supply Well: M Monitorine ❑Recover ❑Aquifer Recharge ❑Aquifer Storage and Recovery ❑Aquifer Test ❑ENperinlcmal Technology ❑Geothermal (Closed Loop) ❑Gcothennal (Heating/Cooling Return ❑Groundwater Remediation ❑Salinity Barrier ❑Swrmwater Drainage ❑Subsidence Control ❑ Tracer ❑Other (explain under 421 1 4. Date Well(s) Completed: 7/1 3/201 6Well ID# PTW-5 5a. Well Location: Duke Energy HF Lee Station Facility/Owner Name Facility ID4 (ifapplicabhe) 1622 Old Smithfield Rd. Physical Address City. and Zip Wayne County Paicel Identification No (PIN) 5b. Latitude and Longitude in degrees/minutes/seconds or decimal degrees: (ifwell field. one lattong is sutlicient) 35.384659 N-78.07019 N 6. Is (are) the well(s): OPermanent or ❑Temporary 7. Is this a repair to An existing well: ON -es or E]No 1/ this is a repair, fill oul kmmn red/ construction information and explain the nanae of the repair under 411 rernca•ks section or on the hack of this tone S. Number of wells constructed; 1 Fob multiple injee lion or rron-u ater supply wells ONL 1' a-ith the same construction, ran can ❑rhmir one lorm 9. Total well depth below land surface: 19.0 (ft.) For multiple hells list all depth• ifdifferent (evmnple- 3:11200' mid 21,u 100') 10. Static water level below top of casing: 8.0 (ft.) /l n-ater- level is above casing. h(se ' + I I. Borehole diameter: 8.0 (in.) 14. WATER ZONES FROM TO DESCRIPTION 8.0 er. 15.0 e. Wet 15.0 ft• 19.0 ft. Moist 1S OUTER CASfNG Irar mnitFcased wells) OR LINER Ka t licablr FROM TII Mi,,, ETER 'Pit'FNF,ti;i MM:..AI- ft. ft. in. Ib, INNER f %NING OR I 'ItI\G(Stathertnnl closed­hmpli FROM TO m%MtJVR II -lit KR'.Fti:S M#TI'RI:M 0 ft. 9.0 ft. 2.0 'n' I SCh.40 PVC ft. I in. 17. SCREEN FROM TO DIAMETER 5LOTSl211' THICKNESS MATERIAL 9.0 f` 19.0 ft. 2.0 '°' 0.01" Sch.40 PVC f[. ft. in. 19. GROUT- _ FROM TO 3.0 et. MATERIAL Bent./Port. _ EMPL %CE.MENT METHOD & AMOI'NT Tremied 0 ft. 3.0 fr• 6.0 fr• Bentonite Poured fr. fr. 19. SANDlGRAF Fl, P.#C'ii (If a Iiealde} FROM TO MATERIAL - FMPI I.t FMFNT it ETHOD 6.0 ft. 19.0 fr. #2 Poured ft. ft. 20. DRILLING LOG lattach additional sheen • if necessary.) FROM TO DFtiC-KIPTIUN cnln r. lrarslnr�s..+nit:'rvck t. - sYln.4im, Nc.t 0 ft. 5.0 fr• Red/Brown, Moist, SILT and Clay 5.0 f`' 10.0 f` Tan, Wet Fine SAND and Silt MO ft. 15.0 f` Tan, Moist Fine SAND and Silt 15.0 fr• 19.0 f`• Dark Gray, Moist, CLAY rt. er. ft. ft. ft. ft. 2 L. RENO ARKS Installed 4" Stick -Up Cover 22. crl fication: n 8/9/2016 signatwe +f Merl+tied\let t.•OHIHAtIM - Date B+ g"'11mg dui ("ro) �1fo, e.r L,rr that the urIlls) rims (mere) constructed in accordance with 15.4 XCAC 02C 0/00 oh hA ,AVAC 02C'.0200 Well C'onsbmction Standards and that a cope of this record has been provider/ to the cell ouner 23. Site diagram or additional well details: You may use the back of this page to provide additional well site details or well construction details You may also attach additional pages if necessar SUBMITTAL INSTUCTIONS 24a. For All Wells: Submit this form within 30 days of completion of well construction to the following Division of Water Resources, Information Processing Unit, 1617 Mail Service Center, Raleigh, NC 27699-1617 24b. For Infection Wells ONLY: In addition to sending the form to the address in Auger 24a above. also submit a copy of this fonn within 3D days of completion of well 12. Well construction method: construction to the following: (i a auger, roiarv_ cable, ditect push, etc ) Division of Water Resources, Underground Injection Control Program, FOR W aTER SUPPLY WELLS ONLY: 1636 Mail Service Center, Raleigh, NC 27699-1636 13a. field (gpm) Method of test: 24c. For Water Supply & Injection Wells: Also submit one copy of this form within 30 days of completion of 13b. Disinfection type: _ amount: Well construction to die county health department of the count) where constructed Foist Gw-I \'oath Carolina Department of Environment and Natutal Resources- Dkision of Water Resources Res ised August 1013 WELL CONSTRUCTION RECORD This firm call be used for single or multiple e\clIs For Internal Use ONLY: I. Well Contractor Information: Lewis LeFever Aq ell ('untiactor Name 2480-A NC AVell ( ontiactoi Certification Nuniher Parratt-Wolff Compare Nitric 2, Well Construction Permit #: Lrcfall opplicuhk aell Iwo unit., (i e Counli, S'tul,% Iill iall, , bli-lion, "I") 3. Well Use (check well use): Water Supply Well: ❑Agricultural ❑Geothermal (Heating/Cooling Supply) ❑Industrial/C•ommeicial M ❑Municipal/Public ❑Residential Water Supply (single) ❑Residential Water Supply (shared) Non -Water Supply Well: ❑✓ Monitoring ❑Recovere ❑Aquifer Recharge ❑Atluifer Storage and Recovery El Aquifer Test ❑Experimental Technology ❑Geothermal (Closed Loop) ❑Geothermal (Heating/Cooling Return) ❑Groundwater Remedianon ❑Salinity Barrier ❑Stonnwater Drainage ❑Subsidence Control ❑Tracer ❑Other (explain under #21 1 4. Date Well(s) Completed: 7/12/2016Well ID# PTW-6 5a. Well Location: Duke Energy Facility/Owner Name 1622 Old Smithfield Rd. Physical Address City and Zip Wayne County HF Lee Station Facility IDr (ifapplicable) Parcel Identification No (PiN) 5b. Latitude and Longitude in degrees/minutes/seconds or decimal degrees: (it %%ell lield_ onelat long is sufficient) 35.384228-78.069878 W 6. is (are) the w'ell(s): OPermanent or ❑Temporary 7. Is this a repair to an existing well: ❑Yes or ONo /1 this is it rrpuir, fill out knann itch' consu trction inlnrrnanbn and cecphain the nawrr of the repair under ri_'l rerwrks'ection or on Ille hack of this /o nr 8. Number of wells constructed: 1 h'or rnulliple inie'lion oI nun-w(jAli supph cell, ONLY with tire same construction, toil call minprit one for"? 9. Total well depth below land surface: 18.0 Far nnrbiplr wills list all depths i/di/11 rrnr (cccnnrplr- 3'a 200' and 2:u l00') 10. Static water level below top of casing: 8•0 l/ uarrr level is shore casingn rise 11. Borehole diameter: 8.0 (i11.1 la. WATER ZONES FROM TO DE-ScRiPTION 8.0 fr. 20.0 fr. Wet 20.0 ft• 3C ft• Moist 15. OUTER CASING Ifor multi -cased wells) OR LINER (if anolicablel FROM TO DIAMETER TiIR KNESS I \I STFRI At. ft. ff. in. 16. INNER (' VNING OR TURING Igeothertrud closed-Inapi FRO\i '1.41 Ot.%MF'7VIA i 111H K%F'Ss \I ■I Fill\t 0 ff• 8.0 ft. 2.0 in. Sch.40 PVC ft. ft. in. 17. SCREEN FROM TO OIA \tFTFR,_ SLOTS17F THICKNESS \I,\TFRI-11 8.0 ft- 18.0 ft. 2.0 in. 0.011, Sch. 40 PVC ft. ft. in,. 1R, C.ROTIT FROM1fT 0 rt• TO_ _ 2.0 ft• MATERIAL Bent./Port. F.11Pi�'10EM1lES"1 : ETI1011& %NTOtNI Tremied 2.0 ft. 5.0 ft. Bentonite Poured ft. ft. l'l, S.►N-W(:RAN'EL P-A(.:K (if a licablel FROM TO \t:1TF.RL%I. E\fPLUF\IENTMIET1101) 5.0 ft• 30.0 ff. #2 Poured ft. ft. 20. URILLIN(G LOG altaeh additional sheets ifneerssa FROM TO _ _ IIFSURIP-1 ION I-Ni. hardue6s.jAlJrvrk Ir U . rrnin siae. kml 0 ft. 5.0 ft. Red/Brown, Moist, SILT and Clay 5.0 ft. 10.0 ft. Tan, Wet Fine SAND and Silt 10.0 ft• 15.0 ft• Tan, Wet Fine SAND and Silt 15.0 ft. 19.0 ft. Tan, Wet Fine SAND and Silt 20.0 ft• 25.0 ft, Gray, Moist, CLAY 25.0 ft. 30.0 ft. Dark Gray, Moist, CLAY ft. ft. 21. REMARKS Installed 4" Stick -Up Cover 22. Celcalion: cl- 8/9/2016 Signature ot erldied %Velj Ft itractm Date RV slk'niri:_*clr[:c %nrnr, / hrV4n n' (L'Tih' that the err//(cl u'n., (inert) eoncnvete•d ill arcoodnncr with 15A :AV4C 02C .0/00 or 15.A NC. -IC 02C0100 It'rlh Cnnslrvc lion Srandardl urrd that it c opt of this record has been provided to Ill,, rvrll owner 23. Site diagram or additional well details: You may use the back of this page to pro\ ide additional well site details or well construction details You nlaA also attach additional pages ifnecessan SUBMITTAL INSTUCTiONS ft.) 24a. For ,all Wells: Submit this form within 30 days of completion of well construction to the following (ft.) Division of Water Resources, Information Processing Lnit, 1617 Mail Service Center, Raleigh, NC 27699-1617 24b. For Infection Wells ONLY: in addition to sending the form to the address in Auger 24a above, also submit a cop} of this form wrthm 30 days of completion of ever) 12. Well construction method: construction to the following: (r a auger, rotary, cable, direct push, ere ) Division of Wafer Resources, Underground injection Control Program, FOR WATER SUPPLI WELLSONLY- 1636 Nlail Service Center, Raleigh, NC 27699-1636 13a. Yield (gpm) Method of test: 24c. For Water Supply & Injection Wells: Also submit one copy or this form %vithin 30 dmsofcompleuonor 13b. Disinfection type: ,Amount: well construction to the county health department of the countN where constructed Form GAF -I North Carolina Department of Em ironment and Natural Resources- Die isimr or Water Resources Re\iced August '_011 I -Al 1VICCKOKY Govemor DONALD R. VAN DER VAART Water Resources E. VIRORMENTAL OUAL17Y May 2, 2U 16 Mr. Ryan Czop Duke Energy Progress; LLC 526 South Church Street Mail Code EL;-13K Charlotte, North Carolina SUBJECT: Well Con3ts uctiou Pus m;t No. NM0700820 H. V. Lee Energy Complex -- rormer Lee Steam Station Wayne County, North Carolina Dear Mr. Clop: S—�, ter..,—y S. jAY ZIMMERMAN Director In accordance with your application received April zu, zu 16; we are forwarding herewith Well Construction Permit No. WR0700820, dated May 2, 2016, issued to Duke Energy Progress, LLC (DEP), for the construction of 1 recovery well located at on property owned by ijtF as indicated on the figures accompanying the application, in Wayne County, North Carolina. Thin Pe111r11 will be etfecdve trom the date of its issuance until May z, 2U17, and shall be subject to the conditions and limitations as specived therein. It any pans, requirements, or limitations contained in this Permit are unacceptable to you, you have the right to an adjudicatory hearing before a healing office, upolr written demand to the Director within 30 days following receipt of this Permit, identifying the specitied issues to be contended. unless such demand is made, this Permit shall be final and binding. A well Construction xecord (uw-1) must be filled out by the driller and submitted to Divijivlr of Water Quality, Arm: Lrfo11ua1iou Management, 1617 Mail Service Center, Raleigh, NC 27699-1617 within 3U days upon completion of the well construction. It additional intormation or clarification is required, please contact will Hart at 252-948-3918. Sincerely, Robert Ta11ka1d, Assisian Regional Supervisor Water Quality Regional uperations Section Division of Water Resources, NCDEQ cc: Cascade Drillurg, LLC 1393 CU1uWbia Hwy N, A1KCu, Sl; LYSU1 Duke Energy Progress, LLC 410 S. Wilmington St., Raleigh, NC 27601 wdRuS — Central uffice WQROS - WaRO State of North Carolina I Environmental tlualsy Water KoSOZ7—S war- Vcaacty K,.o.-.at 0t,.rax.ons-Wasmngton Regtonat C]mce 943 Wasn.ngto-. Sgz—mr i, w. Win.-gto.-., LNC Ztaay 252-946-6481 — NORTH UAKULINA DEPARTMEx1' ur' ENVIRONMEIv i, AND NATURAL RESuujKuES DIVISION OF WAXER QUALITY —AQuwta PROTECTION Sl UTIUN .PERMIT FOR TnE UUNSTRUCTION Or' A F mcuVERY WELL in accordan.,c with the provisions of Arti�lc 7, Chapter 87, North Caiulina General Statutes, aiid other applii,ablc Laws, Rules and Regulations. PERMnSluly 1S HEREBY GxAlv'1'Eju '1'O Duke Energy Progress, LLC (DEr) FOR l tth CONSTRUCTION ur A xhC;U VERY WELL S Y S I hNl consisting of mane well owned by DEF located at the Fortner Lee Steam Station, ill Goldsboro, North Caiulilla. 1 fie well will be located on the property owned by DEP lu%ated at 1 199 black Jack Church Road, in cioldsburu, NC in Wayne County. This Permit is issued in accordance with the application received on April 2U, 2016 in conformity with specifications and supporting data, aai of whi.;h are filed with the Department of Envirotttnent and Natural Rz;soulucs aitd are considered integral parts of this Permit. 1 his -Permit is for w ell cunstruetiun only, and does not waive any provision or requiictnent of any other applicable law of regulation. C;onstru.,tion of any well under this Pcltnit shall be in strict ,umpliaancu with the North Carolina Wcll Construction Regulations and Standards (15A NCAC 02C .uIuu), and other State and Leal Laws and regulations pertaining to well construction. If any requirements or limitations speclfled in this Permit are unacceptable, you have a right to an adj udicatory hcaiing upon written request within 3u days of receipt of this Permit. l he request must be in the full,, of a written petition %,unfurming to Chapter 150B of the North Carolina General Statutes and filed with the Offic;c of Administrative Hearings, 6714 mail Service Center, Raleigh, North Carolina 27699-6714. Unless such a demand is trade, this -Permit is final Gild binding. This Peltnit will be effective fur one year from the date of its issuance and shall be subject to other spccifled conditions, limitations, or exceptions as follows: 1. Issuance of this Permit does not obligate reimbulsemcnt from State trust funds, ifthcse wells are being installed as part of an investigation for contamination from an utldcrground storage tank or dry cleaner incident. 2. lssuaill,c of this Permit does not superscdc any other agreameut, puiluit, or requirement issued by another agency. J. The well(s) shall be located and joust, uctcd as shown on the attachments submitted as part of the Permit application. 4. Each well shNh have a Well Contractor ldentitication Plate in accordance with 15A NCAC 02C .0 I u8(o). ttcvised July 2011 S. Well construction records ((iW-1) tor each well shall be submitted to the Division or Water Quality's Infurrnatiun Processing Unit within 30 daps uf the wall c;umpletiun. 6. When the well is discontinued or abandoned. it shall be abandoned in accordance with 1 SA NCAC 02C .0113 mda well abandonment reVord (GW-30) shall be submitted tu thu Division or Water QuN ity7s infurinatlun Yruuessing Umt within iu days of the well abandonment. 7. Groundwater extracted dming the test shall be played into the Active Ash Basin, as &sciibcd in the application. Permit issued the Jeuond day or May, lu 15 FUR THE NUKI'H UAKULINA EN VIKUNAMNTAL MANAGEMENT UUMM1aalUN Kober l ankard, Assistant egional Supervisor Division of Water RGSVU1cGS Water Quality Kegiunei Uperations Sectiun Washington Regional Office By Authority or the hnvironmentNI Management Commission Permit No. # WR0700820 KLv6ed jury 2ui i Step-Drawdown and Pumping Test Findings August 22, 2016 HF Lee Energy Complex SynTerra P:\Duke Energy Progress.1026\04.LEE PLANT\20. Accelerated Remediation\Pilot Test\PDF\Tech Memo Pilot Test August 2016.docx ATTACHMENT 2 AQTESOLV OUTPUT FROM STEP-DRAWDOWN TESTS 1. 10.100. 1000. 1.0E+4 1.0E+5 0.001 0.01 0.1 1. 10. Time (sec) Di s p l a c e m e n t ( f t ) STEP-DRAW DOWN TEST PTW-1 Data Set: S:\...\Step-DrawdownTest_PTW-1.aqt Date: 08/18/16 Time: 17:18:59 PROJECT INFORMATION Company: SynTerra Corp Client: DEP HF Lee Project: 1026.104 Test Well: PTW-1 Test Date: August 2016 AQUIFER DATA Saturated Thickness: 19.75 ft Anisotropy Ratio (Kz/Kr): 1. SOLUTION Aquifer Model: Confined Solution Method: Theis (Step Test) T = 2679. ft2/day S = 1.759E-5 Sw = 0.C = 0. sec2/ft5 P = 2. Step Test Model: Jacob-Rorabaugh Time (t) = 1. sec Rate (Q) in cu. ft/sec s(t) = 40.23Q + 0.Q2. W.E. = 100.% (Q from last step) Step-Drawdown and Pumping Test Findings August 22, 2016 HF Lee Energy Complex SynTerra P:\Duke Energy Progress.1026\04.LEE PLANT\20. Accelerated Remediation\Pilot Test\PDF\Tech Memo Pilot Test August 2016.docx ATTACHMENT 3 AQTESOLV OUTPUT FROM PUMPING TEST 1. 10.100. 1000. 1.0E+4 1.0E+5 1.0E+6 1.0E-4 0.001 0.01 0.1 1. 10. Time (sec) Di s p l a c e m e n t ( f t ) WELL TEST ANALYSIS Data Set: S:\...\PTW-1_PumpingTest_RealTime.aqt Date: 08/18/16 Time: 17:20:21 PROJECT INFORMATION Company: SynTerra Corp Client: DEP HF Lee Project: 1026.104 Test Well: PTW-1 Test Date: August 2016 AQUIFER DATA Saturated Thickness: 40. ft Anisotropy Ratio (Kz/Kr): 0.256 SOLUTION Aquifer Model: Unconfined Solution Method: Moench T = 3917.6 ft2/day S = 7.302E-23 Sy = 0.001 ß = 1.0E-5 Sw = 0.r(w) = 0.25 ft r(c) = 0.25 ft alpha = 1.0E+30 sec-1 Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx APPENDIX B EVALUATION OF ALTERNATIVE REMEDIAL TECHNOLOGIES Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx APPENDIX C GROUNDWATER FLOW MODEL REPORT Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx APPENDIX D GEOCHEMICAL MODEL REPORT Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx APPENDIX E PIPE AND PUMP SELECTION PACKAGE Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx APPENDIX F DESIGN DRAWINGS Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx APPENDIX G TECHNICAL SPECIFICATIONS Basis of Design Report – 30% Submittal November 2016 H.F. Lee Energy Complex SynTerra P:\Duke Energy Progress.1026\04.LEE PLANT\22.Basis of Design Report\Design Report (30)\Report text\HF Lee Basis of Design Report.docx APPENDIX H PERMITS