HomeMy WebLinkAbout20111003_CAMA approval geotech work_20141107
Ward, Garcy
From:Lane, Stephen
Sent:Friday, November 07, 2014 9:59 AM
To:Stanton, Tyler P; Tom Steffens (Thomas.A.Steffens@usace.army.mil); Ward, Garcy
Cc:Sollod, Steve
Subject:RE: R-3307 Geotech Research
Hi Tyler,
The proposed geotechnical work will not require any additional approval from NCDCM. Let me know if I can be of any
further assistance. Hope you have a great weekend!
Thanks,
Stephen
From: Stanton, Tyler P
Sent: Friday, November 07, 2014 9:56 AM
To: Tom Steffens (Thomas.A.Steffens@usace.army.mil); Ward, Garcy; Lane, Stephen
Subject: R-3307 Geotech Research
Geotech is hoping to get started next week, so if you could let us know asap, that would be appreciated.
Geotech is planning to conduct research around the test pile that will require them to spud a barge. The work should
only take a day or two, but could potentially last up to a week depending on the weather; however, once it is set it will
not move until they are finished. Do we need any additional approvals or refinements?
Thanks,
Tyler
Tyler Stanton
Environmental Program Consultant
NCDOT, Natural Environment Section
Direct 919.707.6156
Fax 919.212.5785
tstanton@ncdot.gov
Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third parties.
1