HomeMy WebLinkAbout20081268 Ver 3_Mitigation Information_20210922fires
July 23, 2021
Kyle Barnes
U.S. Army Corps of Engineers
Regulatory Division
69 Darlington Ave
Wilmington, NC 28403
Subject: NeuCon UMBI Tull Wooten III (SAW-2017-00847) As -Built Baseline Report Submittal
Mr. Barnes:
360o Glenwood Avenue, Suite ioo
Raleigh, NC 27612
Corporate Headquarters
6575 West Loop South, Suite 300
Bellaire, TX 77401
Main: 713.520.5400
On behalf of EBX Neuse I, LLC, a wholly owned subsidiary of Resource Environmental Solutions (RES), I am pleased to submit
the NeuCon UMBI Tull Wooten III As -Built Baseline Report. Construction and planting for this project were completed in
March 2021 and invasives treatment was completed in July 2021. The site was built to design and guidelines with only minor
adjustments.
RES set up cross sections, vegetation plots, and stream monitoring devices in March 2021. Monitoring data of the vegetation
indicates that all plots are exceeding the interim success criteria of 320 planted stems per acre. The average stem height in
the plots was 1.5 feet.
Per the approved mitigation plan and as referenced in the as -built report, RES is requesting to perform supplemental
planting and livestaking on TW1 and TW4 to fulfill the adaptive crediting strategy in the upcoming dormant season of winter
2021/spring 2022. The livestaking would include shade tolerant species (buttonbush and silky dogwood) and occur every
four feet along the bottom of both banks on both reaches. The supplemental planting would be performed in areas of low
stem density/heavy invasive treatment and include shade tolerant species such as flowering dogwood, eastern redbud,
persimmon, blackgum, sugarberry, and laurel oak. The additional work would take place during this upcoming dormant
season and would change the credit ratios for TW1 and TW4 from 10:1 to 5:1.
Upon approval of this as -built report and the adaptive crediting strategy, RES is requesting a 15% stream credit release
based on the approved mitigation plan. This is a total as -built release of 531 SMUs. All wetland credits for this bank are
preservation and were released in the initial Task 1 release. Please see the enclosed credit release timeline and updated
credit ledgers.
Thank you for all of your time and consideration and we look forward to continuing to work with you all as this Project
progresses. Please contact me if you have any questions or require any additional information.
Thank you,
Katie Webber, Project Manager
kwebber@res.us 1 (984) 275-3483
res.us
From: Davis. Erin B
To: Baker, Caroline D
Subject: FW: [External] Notice of As -Built Review/ RES Neu -Con UMBI - Tull Wooten III Mitigation Site/ SAW-2017-00847/
Lenoir County
Date: Monday, November 1, 2021 2:06:39 PM
Attachments: Cover Letter TWIII MYO.odf
Laserfiche Upload: Email & Attachment
DWR#: 20081268 v.3
Doc Type: Mitigation Information
From: Browning, Kimberly D CIV USARMY CESAW (USA)
[mailto: Kimberly. D.Browning@usace.army.mil]
Sent: Wednesday, September 22, 20214:38 PM
To: Tugwell, Todd J CIV USARMY CESAW (US)<Todd.J.Tugwell@usace.army.mil>; Haywood, Casey M
CIV (USA) <Casey.M.Haywood@usace.army.mil>; Davis, Erin B <erin.davis@ncdenr.gov>; Wilson,
Travis W. <travis.wilson@ncwildlife.org>; Merritt, Katie <katie.merritt@ncdenr.gov>;
kathryn_matthews@fws.gov; Bowers, Todd <bowers.todd@epa.gov>
Cc: Barnes, Kyle W CIV USARMY CESAW (USA) <Kyle.W.Barnes@usace.army.mil>; Katie Webber
<kwebber@res.us>; Lekson, David M CIV USARMY CESAW (USA)
<David.M.Lekson@usace.army.mil>; Lastinger, James C CIV USARMY CESAW (USA)
<James.C.Lastinger@usace.army.mil>; Crumbley, Tyler A CIV USARMY CESAW (USA)
<Tyler.A.Crumbley2@usace.army.mil>
Subject: [External] Notice of As -Built Review/ RES Neu -Con UMBI - Tull Wooten III Mitigation Site/
SAW-2017-00847/ Lenoir County
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an
attachment to Report Spam.
Hello IRT,
The FINAL As -Built Report review has been requested by RES for the Tull Wooten III Mitigation Bank
Site. Per Section 332.8(o)(9) of the 2008 Mitigation Rule, this review follows the streamlined review
process, which requires an IRT review period of 15 calendar days from this email notification. Please
provide any comments by 5 PM on October 8, 2021. Comments provided after the 15-day
comment deadline may not be considered. The As-Built/MYO Report and associated credit ledgers
can be found on RIBITS:
https://ribits.ops.usace.army.mil/ords/f?p=107:278:14858358587016:::RP.278:P278_BANK_ID:5913
RES provided linked drone footage, in -lieu of an IRT site visit. We will plan to visit the site in 2022.
TW2-A https://vimeo.com/610440910/e3dO922a4e
<Blockedhttps:Hvimeo.com/610440910/e3dO922a4e>
TW3 https:,//vimeo.com/610517675/22d6503d75
<Blockedhttps://vimeo.com/610517675/22d6503d75>
Site Overview httr)s://vimeo.com/610530374/9bdO698bce
<Blockedhttps:Hvimeo.com/610530374/9bdO698bce>
15-Day Comment Start Date: September 22, 2021
15-Day Comment End Date: October 8, 2021
45 Day DE Decision: November 7, 2021
At the conclusion of this comment period, a copy of all comments will be provided to RES and the
NCIRT along with District Engineer's intent to approve or disapprove this Final As -Built and 2nd credit
release.
Kyle Barnes is the bank manager for this project. Please copy Kyle on all correspondence.
Regards,
Kim
Kim Browning
Mitigation Project Manager, Regulatory Division I U.S. Army Corps of Engineers