HomeMy WebLinkAbout20001195 Ver 17_Preconstruction Meeting Minutes_20210215Meeting Minutes Project: SCF - Earthwork and Utilities � 1 CHARLOTTE DOUGLAS" INTERNATIONAL AIRPORT Subject: SCF PKG #1 - Earthwork and Utilities Pre -Construction Construction Meeting Meeting Type: Project Kickoff Meeting Number: 1 Start Date: 2/2/2021 10:30:00 AM End Date: 2/2/2021 12:00:00 PM Location: Eagle Conference Room Description: 1. INTRODUCTION OF TEAM & ROLES A. OWNER City of Charlotte, Aviation Department B. ENGINEER WSP USA Inc. C. CONTRACTOR Thalle Construction Company D. OTHER PARTIES 2. ORGANIZATIONAL CHART a. CLT Organizational Chart 3. HOUSEKEEPING a. Contract Update • Administrative Notice to Proceed —November 10, 2020 • Construction Notice to Proceed — March 1, 2021 b. Insurance —All is in order c. Compliance Requirements i. DBE Participation Goal —18% d. Thalle Subcontractor Status e. Security/Operations i. Authorized Signers, Badge Application & Procedures ii. Driver Training Program f. Fence Amendment — 45 Day Notice i. Amendment for first fence move is in place ii. TSA/ASP Coordination for future moves SCF - Earthwork and Utilities 10:19:53 AM, 2/15/2021 4. PROJECT REVIEW a. Scope of Work b. Phasing Plan c. Project Performance Period i. Final Completion - 580 Calendar Days from NTP d. Permit Status i. USACE IP ii. NC DEQ— North Carolina Department of Environmental Quality iii. City of Charlotte — Land Development iv. Flood Management —CLOMR v. Dam Safety vi. Byrum Driveway vii. Others (Contractor Responsibility) e. IFC Contract Document Set (Plans/Specs), Current Construction Drawings, Design Changes f. Contractor Construction Schedule g. Contractor Submittal Schedule (Shop Drawings & Materials) 5. GENERAL- LOGISTICS a. Site Access / Parking / Staging Area i. Storage of Materials ii. Temporary Facilities/ Job Trailer b. Working Hours c. Deliveries d. 7460 Update e. Earthwork Management Plan f. Site Cleanliness i. FOD ii. Roads iii. Jobsite g. Adjacent Projects h. Existing Utilities i. Safety Plan Compliance Document i. Emergency Contact List j. Security/ SIDA Fence / Badging 6. GENERAL- ADMINISTRATIVE a. Project Correspondence CDIA's address is: Leslie Jo Hurwitz 5601 Wilkinson Blvd Charlotte, NC 28208 LeslieJo.Hurwitz@cltairport.com WSP USA address is: Matt DuBose WSP USA Inc. 1001 Morehead Square Drive #610 Charlotte, NC 28203 Matthew.dubose@wsp.com a. eBuilder • Correspondence, Submittals, RFls, CORs, Pay Applications, Testing Reports b. Progress/OAC Meeting (Weekly/Monthly) ■ Proposed Meeting Days ■ Weekly progress meetings for every Tuesday @ 2 pm (2/9 Start?) ■ Monthly OAC meeting for third Wednesday of each month @ 2 pm c. Project Control Items d. Schedule of Values/Progress Payments e. As -Built Drawings & Documents f. Liquidated Damages g. Closeout 7. OPEN DISCUSSION Published By: Herold, Blake Attendees Name Company Email Attended brian.fuerst@wsp.com Yes Ifantozzi@thalle.com Yes sue.homewood@ncdenr.gov Yes skohler@thalle.com Yes phi llip.owens@anseradvisory .com Yes alan.johnson@ncdenr.gov Yes Duane.lohnson@faa.gov Yes cbacchi@trimattesting.com Yes jeffrey.chandler@ncdenr.gov Yes Jon.Manke@terracon.com Yes bryan.k.rodenreynolds@usac e.army.mil No david.I.shaeffer@usace.army .mil Yes james.moore@ncdenr.gov No kthomas@thalle.com Yes io.castro@terracon.com Yes Archer, Wright THALLE CONSTRUCTION CO INC WArcher@thalle.com Yes Bowen, Ken THALLE CONSTRUCTION CO INC KBowen@thalle.com Yes Choi, Marcus CLT Aviation Marcus.Choi@cltairport.com Yes DuBose, Matt WSP matthew.dubose@wsp.com Yes Ellis, Tom Thalle Construction tellis@thalle.com Yes Fairchild, Ryan CLT Aviation Ryan. Fairchild@cltairport.co Yes m Fox, Craig CLT Aviation Craig.Fox@cltairport.com No Freeman, Matthew CLT Aviation Matthew. Freeman @cltairport Yes .com Geiger, Ron HDR ENGINEERING Ron.geiger@hdrinc.com Yes INC OF THE CAROLINA'S Heaton, Sierra CLT Aviation Sierra. Heaton@cltairport.co Yes m Herold, Blake WSP Blake. Herold@wsp.com Yes Hurwitz, Leslie Jo CLT Aviation LeslieJo.Hurwitz@cltairport.c Yes om Kondratyk, Alexis CLT Aviation alexis.kondratyk@cltairport. Yes com McIntosh, Buddy THALLE bmcintosh@thalle.com Yes CONSTRUCTION CO INC McMahan, Brian CLT Aviation bmcmahan@cltairport.com Yes McSwain, Jeff CLT Aviation jmcswain@cltairport.com No Miller, Bill THALLE BMiller@thalle.com Yes CONSTRUCTION CO INC Moran, Logan CLT Aviation logan.moran@cltairport.com Yes Murray, John THALLE jmurray@thalle.com Yes CONSTRUCTION CO INC Overcash, Justin ANSER ADVISORY Justin.Overcash@anseradvis Yes ory.com Owens, Phillip ANSER ADVISORY Phillip.Owens@cltairport.co Yes m Peeples, Gary CLT Aviation ghpeeples@cltairport.com No Perry, Jeffrey CLT Aviation jperry@cltairport.com Yes Picerno, Christopher CLT Aviation ctpicerno@cltairport.com No Pierce, Jim THALLE jpierce@thalle.com No CONSTRUCTION CO INC Radcliff, Chelsea CLT Aviation Chelsea. Radcliff@cltairport.c Yes om R sdon, Eric HDR eric.rysdon@hdrinc.com Yes Scherrer, Tammy WSP USA INC T.SCHROEDER@wsp.com Yes Schneider, Brett Thalle Construction bschneider@thalle.com Yes Co., Inc. Sharp, Brian THALLE bsharp@thalle.com Yes CONSTRUCTION CO INC Smith, Cody CLT Aviation cody.smith@cltairport.com Yes Starrett, Judith CLT Aviation jude.starrett@cltairport.com No Szlasa, Ross THALLE rszlasa@thalle.com Yes CONSTRUCTION CO INC Thames, Kelly HDR ENGINEERING kelly.thames@hdrinc.com Yes INC OF THE CAROLINA'S Torres, Michele CLT Aviation michele.torres@cltairport.co Yes m Turman, Jasmyne CLT Aviation Jasmyne.Turman@cltairport. No com Vaughan, Nicola CLT Aviation Nicola.Vaughan@cltairport.c Yes om Watson, Ashton CLT Aviation abwatson@cltairport.com Yes Wylie, William Talbert Bright and wwylie@tbeclt.com Yes Ellington Zoeckler, Brian CLT Aviation Brian.Zoeckler@cltairport.co Yes m Meeting Items 1.1 Topic: 01-Introductions Status: Open Discussion: Introductions & Oraanizational Chart - Started meeting by performing introductions for everyone in the room and on the WebEx call. - CLT Airport described and went through organizational chart for project. Action Item: # Subject Held By Date Due Status 1.2 Topic: 03-Meeting Agenda Status: Open Discussion: Housekeenina - Matt DuBose (WSP) mentioned Administrative NTP was issued on Nov. 22nd, 2020 and identified the anticipated construction NTP as March 1st, 2021. Leslie Jo Hurwitz will send out official construction Notice to Proceed to Thalle with March 1st date. - Matt DuBose (WSP) stated the contractor's insurance for the project is all in order and ready for construction. - Matt DuBose reminded Thalle of the DBE requirements (18%) for the contract. - Thalle mentioned the utilization of the company 'On -Spec' as one of their DBE subcontractors. - Thalle had their original third party Geotech firm for QC testing back out. - Thalle has all major scopes contracted. Thalle has chosen to sub out the Cast -in -Place (CIP) culvert. Thalle will send a preliminary list to the airport team. - Thalle has Authorized Signers in place and badging process has started. CLT mentioned it typically takes 3 to 4 weeks to retrieve a badge. - CLT Airport reiterated everyone working inside the AOA needs a badge. - CLT Airport reminded Thalle no firearms or weapons are allowed in the AOA. - Thalle posed the question - Are there any special security requirements for blasting operations? Per CLT Security, there are none unless inside fence where proper notice would be required. - CLT Security brought up to Thalle the need to notify them if any digging, drilling or boring is taking place under an AOA fence. - CLT Security told Thalle explosives are not allowed to be stored on site. Action Item: # Sub'ect Held By Date Due Status 1.3 Topic: 03-Meeting Agenda Status: Open Discussion: Proiect Review - Matt DuBose (WSP) gave a brief overview of the project scope & phasing plans including durations for the contract. - Discussed status of each permit in detail. - U.S. Army Corps of Engineers (USACE) permit is approved. Project has 19 Special Conditions (Use clean fill, proper Erosion & Sediment Control, etc.). USACE told Thalle they should have copies of the documents on site. USACE has required monitoring stations to be place pre- and post -construction due to detention basin design never been done at this size before. CLT Airport is aware of these monitoring requirements. - Notify USACE 60 days prior to Regional Detention Basin construction. - Sue Homewood discussed mitigation and Storm Water Management Plan needing to be approved. - It was discussed if an accident by the contractor takes place where an area is impacted or has caused a disturbance, work shall cease work and notify agencies of the impacts to the affected area. - NCDEQ permit is in place. - Regarding City of Charlotte - Land Development permit, Matt DuBose (WSP) stated tree protection fence was required to be added to the Detention construction entrances. - Regarding the Flood Management - CLOMR, Matt DuBose (WSP) stated they are seeking final approval from FEMA as WSP team is addressing their comments. It was mentioned the approval should be in 3 to 4 weeks. - Matt DuBose (WSP) spoke on actively seeking partial approval for tree removal only within the floodplain. WSP will reach out if partial approval is received. Would give more area for the contractor to work right away versus having to wait the 60 day period or full approval. - Matt DuBose provided an update that Dam Safety permit is under final review of plans. - Per Matt DuBose, Byrum Driveway permit is expected to be received in a couple weeks. - For contractor responsible permits, Thalle acknowledged needing a blasting permit as they have passed this requirement to their blasting subcontractor. Leslie Jo Hurwitz also mentioned to look into a Demolition Permit for Pipe & Boiler Building. - WSP stated design changes coming. Revisions will include minor Erosion & Sediment Control changes from second round of DEQ comments and tree protection fence addition. - Thalle posed question - Can we get IFC .dwg if they don't already? WSP to follow up. - Thalle posed question - Do the Schedule of Values in the pay application need to be modified to account for Quantity value changes? Per CLT, no need to address at this time. Quantities will get tracked as completed. - Thalle expects to have their revised, cost -loaded schedule by end of week, Friday. Thalle believes they have addressed all previous CLT comments as well as enhanced detail on critical activities of the project. - Thalle's Quality Control Program was submitted last night which includes the submittal register. WSP acknowledged receipt. Thalle noted the QC Plan omits third party Geotech firm due to back out of original company. Action Item: # Sub'ect Held By Date Due Status 1.4 Topic: 03-Meeting Agenda Status: Open Discussion: General - Logistics - No comments regarding Site Access / Parking / Staging Area. - CLT directed to put a lock on Piney Top gate off Byrum Drive. Notify CLT staff beforehand. - Even though Thalle has CLT locksmith number, they were reminded by CLT all requests should go through the airport construction staff first. - Thalle stated normal working hours as Monday through Friday, 10 hours a day, but critical activities will go to a 6-day work week. Some Saturday's will be used to make up weather impacts. Borrow Site #14 hauling operations will go to double shifts of day & night. - Ryan Fairchild noted he talked to Duke about potential hook ups for job site trailer and it came to be unfeasible. - Thalle stated they are looking to begin deliveries by the end of February. - Thalle posed question - Will there be any special inspections for delivered items? Per CLT, no. - Sierra Heaton provided a 7460 Update for the project and should obtain FAA approval by end of February. - Matt DuBose (WSP) stated Earthwork Management Plan Submittal will be returned either today or tomorrow. - Contractor should refer to the SPCD for site cleanliness. It was discussed the contractor should actively keep the roads clean for the multiple borrow pits. - Brian McMahan (TBE) noted inclement weather may be a reason to secure site and tie down items. Also mentioned this airport is very dust sensitive and the Earthwork Management Plan needs to have a dust control plan. - CLT Airport stated there shouldn't be any adjacent projects impacting this project. - Jeffrey Chandler (NCDEQ) noted the Distribution Center is still active. Cody Smith answered they will be submitting something soon to close the project out. - Matt DuBose (WSP) asked if there were any questions regarding existing utilities. No comments. - WSP acknowledged receipt of the SPCD and noted they were reviewing. Thalle was instructed to create an Emergency Contact List. - Logan Moran (CLT Security) discussed a 10' clear zone from the AOA fence for parking vehicles and equipment whether inside or outside. - Logan Moran (CLT Security) - If any damage to the AOA fence occurs, report instance to construction team as soon as possible. Action Item: # Sub'ect Held By Date Due Status 1.5 Topic: 03-Meeting Agenda Status: Open Discussion: General - Administrative - eBuilder will be used to run all paperwork. - Sierra Heaton reiterated where IFC drawings live and where individual sheets for current construction drawings are in eBuilder. - First weekly progress meeting schedule for 2/9/21 at 2:00 PM. No objection from Thalle. - CLT plans to have the monthly OAC meetings for the third Weds of each month at 2:00 PM. No objection from Thalle. - Nicola Vaughn stated eBuilder contractor process is up and running. Training course is available this week if any contractor personnel needs it. Thalle was going to send Nicola some names. - Anser question posed - When can expect to receive project control items? Thalle answered they would plan to have the documents sent by the following week. - Matt DuBose (WSP) noted the liquated damages associated with the project to Thalle in Section 80-08. - No comments regarding closeout. Nicola Vaughn stated she would send closeout information as the date gets closer. Action Item: # Subject Held By Date Due Status 1.6 Topic: Discussion/Brainstorm Status: Open Discussion: ODen Discussion - Thalle stated they would want to start clearing before CLOMR as it's a big part of the schedule and very important. Matt DuBose clarified clearing can start at all locations excluding the CLOMR limits. He reiterated they were seeking approval for the contractor to get inside the CLOMR affected limits earlier for clearing. Thalle was thankful for clarification and understands better. - Jeffery Chandler (NCDEQ) asked for clarifications for work proceeding in regards to the culvert, floodplain and CLOMR locations. Contractor plans to perform clearing only within the allowable areas (no grubbing) beyond just the E&S needs. Jeffrey Chandler (NCDEQ) asked a follow up question - So, you would cut at the stumps? Thalle answered yes, they would leave the stumps. - Jeffrey Chandler (NCDEQ) posed question - When is the anticipated clearing start date? Thalle stated the anticipated start would be March 1st. - Jeffrey Chandler (NCDEQ) asked to be notified before clearing begins. CLT airport acknowledged request. - Jeffrey Chandler (NCDEQ) posed question - Who would be the CLT contact? Ryan Fairchild stated he would be. - Jeffrey Chandler NCDEQ) posed question - Who will be responsible for performing daily DEQ E&S reporting? Thalle acknowledged they were the responsible party for all DEQ reports. Action Item: # Subject Held By Date Due Status