Loading...
HomeMy WebLinkAboutNC0001422_LVSuttonSARP_Rev0_AppendixG_20161201Appendix G Technical Specifications TECHNICAL SPECIFICATIONS L.V. SUTTON ENERGY COMPLEX SITE ANALYSIS AND REMOVAL PLAN December 2016 Revision 0 Prepared for Duke Energy Progress, LLC 526 South Church Street Charlotte, North Carolina 28202 Prepared by Geosyntec Consultants of NC, PC 1300 South Mint Street, Suite 300 Charlotte, North Carolina 28203 License No. C-3500 TECHNICAL SPECIFICATIONS SITE ANALYSIS AND REMOVAL PLAN L.V. SUTTON ENERGY COMPLEX WILMINGTON, NORTH CAROLINA Section 02 21 00 Surveying Section 31 00 00 Earthwork Section 31 02 19.13 Geotextiles Section 31 05 16 Granular Drainage Material Section 31 11 00 Clearing, Grubbing, and/or Stripping Section 31 23 33 Trenching and Backfilling Section 31 25 00 Sediment and Erosion Control Section 31 31 19 Vegetation Section 31 37 00 Riprap Section 32 92 19 Seeding Section 33 42 13 Pipe Culverts Section 33 49 00 Storm Water Structures and Swales Section 34 71 00 Road Construction Section 02 21 00: Surveying Sutton Removal Plan, Rev 0 GC5770\02 21 00 Surveying.docx 02 21 00-1 December 2015 SECTION 02 21 00 SURVEYING PART 1 GENERAL 1.01 SCOPE A. This section describes the requirements for surveying during construction, production of “as-built” documents, and computation of quantities for payment purposes. Survey work will be required to delineate areas for stripping; perform earthwork for general fill and CCR; and to perform other work, as needed, to complete various construction activities. 1.02 RELATED SECTIONS AND PLANS A. Section 31 11 00 - Clearing, Grubbing, and/or Stripping B. Section 31 00 00 - Earthwork C. Section 31 23 33 - Trenching and Backfilling D. Section 31 05 16 - Granular Drainage Material E. Section 31 31 19 - Vegetation F. Construction Quality Assurance (CQA) Plan. 1.03 REFERENCES A. National Geodetic Survey Standards. 1.04 SUBMITTALS A. Upon request, interim surveys performed shall be submitted to the OWNER with each payment request to substantiate the quantities claimed. B. CONTRACTOR will be required to submit survey notes during construction upon request by the ENGINEER. 1.05 PROJECT RECORD DOCUMENTS A. CONTRACTOR shall maintain on-site, a complete and accurate survey log documenting the survey work performed. B. CONTRACTOR shall maintain on-site, a plan clearly showing all site reference points, survey control points, and benchmarks. Section 02 21 00: Surveying Sutton Removal Plan, Rev 0 GC5770\02 21 00 Surveying.docx 02 21 00-2 December 2015 C. CONTRACTOR shall maintain on-site an accurate and current set of marked- up drawings indicating the as-built conditions. D. As-built surveys, stamped and signed, by a State of North Carolina Licensed/Registered Land Surveyor or Professional Engineer shall be submitted immediately following the completion of any applicable construction activity. Complete as-built surveys shall be submitted upon substantial completion of each phase of construction and are a prerequisite for contract closeout. E. Upon completion of each work item, the CONTRACTOR shall prepare and/or update the as-built drawings. PART 2 PRODUCTS 2.01 MATERIALS AND SURVEY EQUIPMENT A. Provide materials and survey equipment as required to properly perform the surveys, including, but not limited to, instruments, tapes, rods, measures, mounts, and tripods, stakes and hubs, nails, ribbons, other reference markers, and all else as required. B. The survey instruments used for this work shall be precise and accurate to meet the needs of the work described. All survey instruments should be capable of reading to a precision of 0.001 ft and with a setting accuracy of ± 0.8 seconds. PART 3 EXECUTION 3.01 GENERAL A. Maintain accurate and complete notes of surveys: 1. Handwritten survey notes and information shall be written with lead pencil(s) and entered in "write in rain" notebooks. A copy of the numbered, dated, and signed field book pages shall be provided to the ENGINEER upon request for use in checking the work. 2. Electronic field survey information shall be collected and backup equipment shall be available in the event of equipment malfunction. a. Electronic format for printed output of data collector field survey notes shall be compatible with the approved field book notation format. b. Electronic format for printed output of data collector field work shall be compatible with the CONTRACTOR's and ENGINEER's computer Section 02 21 00: Surveying Sutton Removal Plan, Rev 0 GC5770\02 21 00 Surveying.docx 02 21 00-3 December 2015 equipment and software for verifying and checking the work. A copy of the data disk shall be submitted to the ENGINEER upon request. B. During construction, survey notes shall be retained by the CONTRACTOR and shall be submitted to the ENGINEER for review upon request. Prior to the placement of successive soil layer, the CONTRACTOR shall submit a written statement certifying compliance of the preceding layer thickness and grades to the ENGINEER. Surveys will be required from the CONTRACTOR prior to approval by the ENGINEER for the placement of overlying materials. C. Conformance check surveys for elevation and for horizontal coordinates shall be to the nearest 0.01 ft and for angles shall be to the nearest 20 seconds. D. Measurement and payment surveys for elevation and for horizontal distances shall be to the nearest 0.1 ft ± 0.05 ft. E. Perform construction layout surveys in advance of scheduled construction activities. At completion of a survey, provide a copy of the field notes, drawings, or sketches to the ENGINEER for review. The CONTRACTOR shall allow the CQA Consultant and/or ENGINEER three business days for review. The CONTRACTOR is responsible for rework and/or construction delays caused by survey or staking errors. F. Set slope stakes in accordance with accepted surveying practices. G. Set grade stakes required for construction activities as the work progresses. Grade stakes shall be set regardless of whether GPS equipped grading equipment is used. The grade stakes are required to allow the OWNER, ENGINEER, and CQA personnel to readily field verify elevations and grades. Set fine grade stakes on all items for which the Construction Drawings specify a definite grade line. H. Upon completion of the work, the CONTRACTOR shall provide the ENGINEER with all original surveying field notes, layouts, computations, and electronic files in standard bound survey notebooks. Electronic file information shall be compatible with the ENGINEER's computer equipment and software as requested. I. Protect survey control points and replace disturbed survey control points at no additional cost to the Owner. 3.02 SPECIFIC FIELD REQUIREMENTS A. Establish temporary control points, as necessary, to support construction activities. B. Survey Documentation: Section 02 21 00: Surveying Sutton Removal Plan, Rev 0 GC5770\02 21 00 Surveying.docx 02 21 00-4 December 2015 1. Record the following information in survey notebooks for each control point established and for all other surveying: a. control point designation; b. northing and easting in State Plane North American Datum (NAD83); c. elevation in North American Vertical Datum (NAVD88); d. date of establishment; e. description and sketch of the control point location; and f. a minimum of three reference features that can be seen from the control point. 2. Document survey work in the field notebooks using the format and procedures described below: a. title and consecutive number on the front cover; b. consecutively numbered pages; c. table of contents, indicated by survey task, on the first numbered page; d. legend indicating symbols used in survey notes; e. names of survey team for each task; f. notes on weather and equipment; g. date and time on each page to indicate when work was recorded; h. notes in a uniform character such that they can be interpreted and used by anyone with survey knowledge; and i. description and/or sketches of the survey control used. C. Preliminary Surveys: 1. Earthwork Staking: Stakes for cut and fill limits shall establish the exterior limits of excavations and berms. The maximum staking interval shall be 50 feet. Stakes shall be prominently noted with description of point, vertical distance to design elevation, and offset distance as applicable. 2. Structures: Stake structure centerlines so that the orientation, position, limits, and foundation elevation(s) are positively identified. Mark stakes to reflect the design elevation and offset distance as applicable. 3. Ditches and Channels: Stake ditches and channels such that the layout remains undisturbed during construction. 4. Pipes and Culverts: Stake pipes and culverts on 50-ft maximum stationing. Place offset stakes beyond excavation limits and material stockpiles. Continuously check invert elevation during placement. D. Final Surveys: Section 02 21 00: Surveying Sutton Removal Plan, Rev 0 GC5770\02 21 00 Surveying.docx 02 21 00-5 December 2015 1. Final topography shall be staked at nominal 50-foot intervals. Additionally, the following points shall be staked and noted as applicable. a. Grade breaks. b. Mid-point of slopes less than 50 ft. c. Points of horizontal curvature and tangency. d. Points of stationing equation. 2. Pipes and culverts: Survey alignment and elevations of the top of all pipes at each change in direction, change in grade, all fittings (i.e., couplers, reducers, blind flanges, repairs, elbows, etc.), and at every 50 feet between fittings or changes in grade and direction. Survey inlet and outlet inverts of all pipes, culverts, and structures. 3. Survey other features including: buried electrical, manholes, leachate piping, pipe penetrations, and edge of liner markers. 3.03 SURVEYS FOR MEASUREMENT AND PAYMENT A. Perform surveys to evaluate quantities of work performed and percent of completed work. B. Calculate and certify quantities and submit survey results, calculations, and certification to the OWNER and ENGINEER for review and evaluation. 3.04 SURVEYS FOR CONFORMANCE CHECKS AND AS-BUILT DOCUMENTS A. Survey the following surfaces to verify the lines and grades achieved during construction: 1. For berms, ditches, drainage swales, roads, and other earthwork: a. original grade surface; b. compacted surface of cut slopes; c. top of general fill; and d. finished grade surface. B. Perform earthwork conformance checks and as-built surveying immediately upon completion of a given installation to verify compliance with the Construction Drawings, facilitate progress, and avoid delaying commencement of the next installation. Provide the following minimum spacing and locations for survey points: 1. surfaces with gradients less than 10 percent, survey on a square grid spaced not wider than 50 ft; Section 02 21 00: Surveying Sutton Removal Plan, Rev 0 GC5770\02 21 00 Surveying.docx 02 21 00-6 December 2015 2. on slopes greater than 10 percent, a square grid spaced not wider than 50 ft shall be used, but in all cases, a line at the crest, midpoint, and toe of the slope shall be taken; 3. a line of survey points spaced not more than 50 ft apart shall be taken along any slope break (this will include the inside edge and outside edge of any bench on a slope); and 4. a line of survey points spaced not more than 50 ft apart and at each end shall be taken at the top of any pipes, culverts, discharge structures, or other appurtenances. 3.05 PROJECT AS-BUILT DOCUMENTS A. The CONTRACTOR shall provide partially-complete or finalized as-built survey information at any stage of the work to the Project Manager, ENGINEER, or OWNER within 24 hours of being requested. These interim submittals may be in the form of as-built drawings or in the form of tabulated coordinates of verified construction control points, as requested. This information may be used to verify proper layout and layer thicknesses as the work progresses, to calculate material quantities, and to perform other activities deemed necessary by the Project Manager to check the CONTRACTOR's work. B. Within 7 days of construction completion, the contractor shall submit finalized as-built survey documents. Finalized as-built survey documents shall meet the following requirements: 1. Four (4) copies of as-built drawings shall be provided on D-size (24” x 36”) sheets with a north arrow, and a standard scale noted (e.g., 1”=50’, 1”=100’, etc.), unless otherwise approved by the ENGINEER. In addition, two CDs containing AutoCAD compatible versions of the as-built drawings shall be provided. 2. Each page of the as-built drawings shall bear a title block that includes: (i) the name and address of the general contractor responsible for the work; (ii) the name, date, address, and original signature and seal of the registered land surveyor who prepared the as-built drawing; and (iii) the facility / project name and location. The signatures included in the title block shall certify that the as-built drawings do, in fact, reflect the true as- built conditions as located under the direct supervision of the registered surveyor and/or professional engineer. The OWNER or ENGINEER will review and approve a preliminary set of finalized as-built drawings. The registered land surveyor shall make all appropriate changes to the as-built drawings to incorporate any OWNER or ENGINEER comments and to comply with these requirements. Section 02 21 00: Surveying Sutton Removal Plan, Rev 0 GC5770\02 21 00 Surveying.docx 02 21 00-7 December 2015 3. As-built drawings shall be clearly legible (e.g., no overlapping text) and include a legend/key that identifies points, series of points, and symbols shown on the sheet. 4. Fonts on all as-built drawings shall be black (i.e., not screened or grayscale), clear, and a minimum of 1/8 inch in height. [END OF SECTION] Section 31 00 00: Earthwork Sutton Removal Plan, Rev 0 GC5770\31 00 00 Earthwork.docx 31 00 00-1 December 2015 SECTION 31 00 00 EARTHWORK PART 1 GENERAL 1.01 SCOPE A. This section includes the requirements for site preparation, excavation, surface water control, excavation dewatering, stockpiling, subgrade preparation, general fill, subbase preparation, and earthwork materials. 1.02 RELATED SECTIONS AND PLANS A. Section 02 21 00 - Surveying B. Section 31 11 00 - Clearing, Grubbing, and/or Stripping C. Section 31 23 33 - Trenching and Backfilling D. Section 31 25 00 - Sediment and Erosion Control E. Construction Quality Assurance (CQA) Plan 1.03 REFERENCES A. Latest version of American Society of Testing and Materials (ASTM) standards and other standards noted in this specification. 1.04 SUBMITTALS A. Within 15 calendar days from Notice to Proceed, submit to the ENGINEER for review an Earthwork Work Plan. The Earthwork Work Plan shall include, at a minimum: 1. list of equipment proposed for the construction activities including earthwork and other scope of work specified described in the contract documents; 2. construction methods for each construction activity; 3. dewatering methods and techniques; 4. coordination of survey requirements for the earthwork; 5. proposed locations of temporary soil stockpile areas; 6. coordination of earthwork activities with surface water management and erosion and sediment control measures; 7. schedule for earthwork activities; and 8. dust control measures. Section 31 00 00: Earthwork Sutton Removal Plan, Rev 0 GC5770\31 00 00 Earthwork.docx 31 00 00-2 December 2015 1.05 CONSTRUCTION QUALITY ASSURANCE A. The earthwork will be monitored and tested by the CQA Consultant as required in the CQA Plan. B. The CQA Consultant will perform soil conformance testing on general fill to establish compliance with this section. Provide equipment and labor to assist the CQA Consultant in obtaining conformance samples from excavations and stockpiles. C. The CQA Consultant will perform soil performance testing on the subgrade surface and general fill lifts to evaluate compliance with this section. The CQA Consultant will indicate any portion of the earthwork that does not meet the requirements of this section and will delineate the extent of the nonconforming area. D. The CONTRACTOR shall correct all deficiencies and non-conformances identified by the CQA Consultant at no additional cost to the OWNER. E. The CONTRACTOR shall be aware of the activities required of the CQA Consultant by the CQA Plan and shall account for these activities in the construction schedule. 1.06 EXISTING CONDITIONS A. Existing site surface and subsurface conditions, based on available site data, are indicated on the Construction Drawings. B. CONTRACTOR shall verify existing conditions as indicated in Section 02 21 00. PART 2 PRODUCTS 2.01 MATERIALS A. Obtain material for general fill from borrow sources designated or approved by the ENGINEER. B. General fill material shall be free of debris, foreign objects, large rock fragments, organics, and other deleterious materials. General fill material shall classify as SW, SP, SW-SM, SW-SC, SP-SM, SP-SC, SM, or SC according to the Unified Soil Classification System (per ASTM D 2487). General fill material having the indicated classification is expected to be available from designated or approved borrow sources. Soils having other classifications may be acceptable as general fill, if approved by the ENGINEER. Section 31 00 00: Earthwork Sutton Removal Plan, Rev 0 GC5770\31 00 00 Earthwork.docx 31 00 00-3 December 2015 2.02 EQUIPMENT A. Furnish compaction equipment to achieve the required minimum soil dry density within the range of acceptable moisture contents. B. Furnish hand compaction equipment, such as a walk-behind compactor, hand tampers, or vibratory plate compactor, for compaction in areas inaccessible to large compaction equipment. C. Furnish water trucks, pressure distributors, or other equipment designed to apply water uniformly and in controlled quantities to variable surface widths for required in-place moisture adjustment, to prevent drying of soil surfaces, and for dust control. D. Furnish equipment such as excavators, scrapers, compactors, loaders, dozers, earth hauling equipment and all other equipment, as required for earthwork construction. PART 3 EXECUTION 3.01 GENERAL A. All general fill material to be compacted shall be at a moisture content that will readily facilitate effective compaction. B. General fill material placed wet that exhibits pumping shall not be accepted regardless of the in-place density or percent compaction. Wet materials shall not be placed and compacted. Wet materials, if used, shall be allowed to dry in place, if feasible, or removed and replaced with suitable materials as directed by the ENGINEER. 3.02 SITE PREPARATION A. Install construction fence and barricades around open trenches and excavated areas. B. Install erosion and sediment controls in relevant areas of construction as indicated on the Construction Drawings and as required by Section 31 25 00. Maintain the erosion and sediment controls for the duration of the Contract and until the contained areas are vegetated in accordance with Section 31 31 19. Accumulated sediment behind silt fences and from drainage swales and structures shall be removed as required or as directed by the ENGINEER. C. Prior to any earthwork activity, perform clearing, grubbing, and/or stripping as indicated on the Construction Drawings and in accordance with Section 31 11 00. Section 31 00 00: Earthwork Sutton Removal Plan, Rev 0 GC5770\31 00 00 Earthwork.docx 31 00 00-4 December 2015 3.03 SURFACE WATER CONTROL A. Installation of surface water and erosion controls shall be in accordance with Section 31 25 00. B. Install surface water and erosion controls in and around work areas to control runoff and erosion and to prevent surface water run-on into excavations. Perimeter controls may include shallow ditches, berms, or localized regrading. 3.04 EXCAVATION A. Excavate designated areas to the subgrade elevations or excavation limits indicated on the Construction Drawings. Stockpile excavated material in areas designated by the Project Manager for use in subsequent construction. 3.05 EXCAVATION DEWATERING A. Anticipate seepage of groundwater into, and accumulation of surface water runoff in excavations. Manage groundwater and surface water in excavations in accordance with this section. B. Prevent surface water run-on from adjacent areas from entering the excavation. C. All fill operations, except hydraulic filling, shall be performed in the dry. CONTRACTOR shall expect that groundwater is at or near the existing ground surface and shall be prepared to lower the groundwater in local areas as required. CONTRACTOR shall expect that work areas may be inundated with water and be prepared to dewater as required to perform work. 3.06 STOCKPILING A. Separate stockpiles by material type. B. Stockpile excavated soils at the areas indicated on the Construction Drawings or as designated by the ENGINEER. C. Construct stockpiles no steeper than 3H:1V (horizontal:vertical), grade to drain, seal by tracking perpendicular to the slope contours with a dozer, and dress daily during periods when fill is taken from the stockpile. D. Silt fence or berms shall be constructed at the base of stockpiles that will not be immediately used. E. Restore all areas used for stockpiling when stockpiles are removed as directed by the OWNER. Section 31 00 00: Earthwork Sutton Removal Plan, Rev 0 GC5770\31 00 00 Earthwork.docx 31 00 00-5 December 2015 3.07 SUBGRADE PREPARATION A. Subgrade material shall consist of soil relatively free of debris, foreign objects, organics and other deleterious materials. B. Compact all subgrade to a minimum 95 percent of the standard Proctor (ASTM D 698) maximum dry density at a moisture content as required to attain the specified density or as approved by the ENGINEER. C. In the presence of the CQA Consultant, perform subgrade proof rolling by driving a loaded dump truck (minimum weight of 10 tons per axle and minimum loaded weight of 20 tons) or other pneumatic-tired vehicle, back and forth across the area to confirm the firmness of subgrade surface. Overlap the passes such that one set of tires on each pass runs between the two sets of tire tracks from the previous pass. Soils shall not exhibit pumping or develop ruts more than two inches in depth. Minor rutting, defined as less than two inches in depth, shall be regraded or covered with general fill to match finish grade. D. Subgrade for general fill shall be scarified to a depth of 2 inches using equipment identified in this section. E. Unsuitable soils shall be removed and replaced with general fill to a minimum depth of 2 feet below the proposed subgrade elevation. Suitable soil exhibiting pumping or developing ruts more than two inches in depth will be removed to a minimum depth of 1 foot or dried in place, if feasible. Compact the general fill materials to a minimum 95 percent of standard Proctor (ASTM D 698) maximum dry density at a moisture content as required to attain the specified density or as approved by the ENGINEER. F. In excavations or other areas where water accumulates, implement measures to remove the water in accordance with this section. Maintain the subgrade surface free of standing water and in firm condition to meet proof rolling requirements of this section. Maintain dewatered areas until overlying construction is complete. G. Manage surface water as described in Section 31 25 00. 3.08 GENERAL FILL A. Use fill that meets the requirements of this section. Place fill to the limits and grades shown on the Construction Drawings. B. Place general fill material on surfaces that are free of debris, vegetation, or other deleterious material. C. Place general fill material in loose lifts with a thickness of 12 inches ± 1 inch. In areas where compaction is to be performed using hand operated Section 31 00 00: Earthwork Sutton Removal Plan, Rev 0 GC5770\31 00 00 Earthwork.docx 31 00 00-6 December 2015 equipment, place the fill material in loose lifts with a loose thickness of 6 inches ± 1 inch. D. Prior to placing a succeeding lift of material over a previously compacted lift, thoroughly scarify the previous lift to a depth of 2 inches by discing, raking, or tracking with a dozer. Moisture condition the preceding lift if not within the acceptable moisture range. E. The trafficking of scarified surfaces by trucks or other equipment, except compaction equipment, is not permitted. F. Except as specified in this section, compact general fill in each lift to at least 95 percent of its standard Proctor maximum dry density (ASTM D 698). Compact general fill at moisture content as required to attain the specified density or as approved by the ENGINEER. G. Do not place fill during periods of precipitation. Placement may occur during periods of misting or drizzle, but only as authorized by the ENGINEER. H. Dust shall be controlled by the application of water to the general fill surfaces. 3.09 SURVEY CONTROL A. Survey limits and elevations of excavations, subgrade, and top of general fill in accordance with Section 02 21 00. 3.10 TOLERANCES A. Perform the earthwork construction related to the berms, and composite liner system to within ±0.1 ft. of the elevations and within 10 percent of the slopes indicated on the Construction Drawings. B. Positively draining slopes shall be maintained during all construction. [END OF SECTION] Section 31 02 19.13: Geotextiles Sutton Removal Plan, Rev 0 GC5770\31 02 19.13 Geotextiles.docx 31 02 19.13-1 December 2015 SECTION 31 02 19.13 GEOTEXTILES PART 1 GENERAL 1.01 SCOPE A. This section includes the requirements for geotextile products and installation. 1.02 RELATED SECTIONS AND PLANS A. Section 31 23 33 - Trenching and Backfilling B. Section 31 05 16 - Granular Drainage Material C. Construction Quality Assurance (CQA) Plan 1.03 REFERENCES A. Latest version of American Society of Testing and Materials (ASTM) standards and other standards noted in this specification. B. Federal Standard No. 751a - Stitches, Seams, and Stitching. 1.04 SUBMITTALS A. Submit the following to the ENGINEER for review not less than 21 calendar days prior to use: 1. geotextile Manufacturer and product name; 2. certification of minimum average roll values and the corresponding test procedures for all geotextile properties listed in Tables 31 02 19.13-1 and 31 02 19.13-2; and 3. projected geotextile delivery dates. B. Submit to the ENGINEER for review at least 14 calendar days prior to geotextile placement, manufacturing quality control certificates for each roll of geotextile as specified in this section. 1.05 CONSTRUCTION QUALITY ASSURANCE A. The installation of geotextiles will be monitored by the CQA Consultant as required in the CQA Plan. B. The CQA Consultant will perform material conformance testing of the geotextiles as required in the CQA Plan. C. The CONTRACTOR shall be aware of the activities required of the CQA Consultant by the CQA Plan and shall account for these activities in the construction schedule. Section 31 02 19.13: Geotextiles Sutton Removal Plan, Rev 0 GC5770\31 02 19.13 Geotextiles.docx 31 02 19.13-2 December 2015 D. The CONTRACTOR shall correct all deficiencies and nonconformances identified by the CQA Consultant at no additional cost to the OWNER. PART 2 PRODUCTS 2.01 GEOTEXTILE A. Furnish geotextile products with minimum average roll values (95 percent lower confidence limit) meeting or exceeding the required property values in Tables 31 02 19.13-1 (for geotextile filters) and 31 02 19.13-2 (for geotextile separators). B. Furnish geotextiles that are stock products. C. Furnish geotextiles that are manufactured from first quality polymers, with no more than 20 percent reclaimed polymer used in production. D. Furnish polymeric threads for stitching that are ultra-violet (UV) light stabilized to at least the same requirements as the geotextile to be sewn. Furnish polyester or polypropylene threads that have a minimum size of 2,000 denier. 2.02 MANUFACTURING QUALITY CONTROL A. Sample and test the geotextile to demonstrate that the material conforms to the requirements of this section. B. Perform manufacturing quality control tests to demonstrate that the geotextiles properties conform to the values specified in Tables 31 02 19.13-1 and 31 02 19.13-2. Perform as a minimum, the following manufacturing quality control tests at a minimum frequency of once per 50,000 square feet with minimum of 1 test per resin lot: Test Procedure Mass per unit area ASTM D 5261 Grab strength ASTM D 4632 Tear strength ASTM D 4533 Static puncture strength ASTM D 6241 C. Perform additional manufacturing quality control tests on the geotextile filter at a minimum frequency of once per 100,000 square feet with minimum of 1 test per resin lot, to demonstrate that the apparent opening size (ASTM D 4751) and permittivity (ASTM D 4491) of the geotextile conform to the values specified in Table 31 02 19.13-1. D. Submit quality control certificates signed by the geotextile manufacturer quality control manager. The certificates shall state that the geotextiles are Section 31 02 19.13: Geotextiles Sutton Removal Plan, Rev 0 GC5770\31 02 19.13 Geotextiles.docx 31 02 19.13-3 December 2015 continuously inspected and are needle-free. The quality control certificates shall also include: lot, batch, and roll number and identification; and results of manufacturing quality control tests including description of test methods used. E. Do not supply any geotextile roll that does not comply with the manufacturing quality control requirements. F. If a geotextile sample fails to meet the quality control requirements of this section, sample and test rolls manufactured at the same time or in the same lot as the failing roll. Continue to sample and test the rolls until the extent of the failing rolls are bracketed by passing rolls. Do not supply failing rolls. 2.03 PACKAGING AND LABELING A. Supply geotextiles in rolls wrapped in relatively impermeable and opaque protective wrapping. Wrapping which becomes torn or damaged shall be repaired with similar materials. B. Mark or tag geotextile rolls in accordance with ASTM D 4873 with the following information: 1. manufacturer's name; 2. product identification; 3. lot or batch number; 4. roll number; and 5. roll dimensions. C. Geotextile rolls not labeled in accordance with this section or on which labels are illegible upon delivery to the site shall be rejected and replaced at no expense to the OWNER. 2.04 TRANSPORTATION A. Deliver geotextiles to the site at least 14 calendar days prior to the planned deployment date to allow the CQA Consultant adequate time to perform conformance testing on the geotextile samples as described in the CQA Plan. 2.05 HANDLING AND STORAGE A. Protect geotextiles from sunlight, moisture, excessive heat or cold, puncture, mud, dirt, and dust or other damaging or deleterious conditions. Follow all geotextile manufacturer recommendations for handling and storage. Geotextile rolls shall be covered with additional tarp cover (in addition to the roll cover) to prevent damage to the rolls. B. Store geotextile rolls on palates or other elevated structures. Do not store geotextile rolls directly on the ground. Section 31 02 19.13: Geotextiles Sutton Removal Plan, Rev 0 GC5770\31 02 19.13 Geotextiles.docx 31 02 19.13-4 December 2015 C. Outdoor storage of geotextile rolls shall not exceed the manufacturer's recommendation or longer than 6 months, whichever is less. PART 3 EXECUTION 3.01 PLACEMENT A. Do not commence geotextile installation until the CQA Consultant completes conformance evaluation of the geotextiles and performance evaluation of previous work, including evaluation of CONTRACTOR's survey results for previous work. B. Handle geotextiles so as to ensure they are not damaged in any way. C. Take necessary precautions to prevent damage to underlying layers including rutting during placement of the geotextiles. D. After unwrapping the geotextiles from its opaque cover, do not leave them exposed for a period in excess of 30 calendar days. E. If white colored geotextiles are used, take precautions against "snow blindness" of personnel. F. Examine the geotextile surface after installation to ensure that no potentially harmful foreign objects are present. Remove any such objects and replace any damaged geotextiles. 3.02 SEAMS AND OVERLAPS A. Continuously overlap a minimum of 6 inches and sew filter geotextiles (i.e., spot sewing is not allowed) using a "single prayer" seam. Sew seams using Stitch Type 401 as per Federal Standard No. 751a. In lieu of sewing, geotextile filters may be overlapped a minimum of two feet. B. Do not install horizontal seams on slopes that are steeper than 10 horizontal to 1 vertical. Seams shall be along, not across, the slopes. C. Overlap separator geotextiles a minimum of 12 inches and ensure that the overlap is maintained. 3.03 REPAIR A. Repair any holes or tears in the geotextiles using a patch made from the same geotextile material. Extend geotextile patches a minimum of 1 foot beyond the damaged area. Sew geotextile patches into place no closer than 1 inch from any panel edge. Should any tear exceed 50 percent of the width of the roll, remove and replace that roll. Section 31 02 19.13: Geotextiles Sutton Removal Plan, Rev 0 GC5770\31 02 19.13 Geotextiles.docx 31 02 19.13-5 December 2015 B. Remove any soil or other material that may have penetrated the torn geotextiles. 3.04 PLACEMENT OF SOIL MATERIALS A. Place soil materials on top of geotextiles in such a manner as to ensure that: 1. the geotextiles and the underlying materials are not damaged; and 2. slippage does not occur between the geotextile and the underlying layers during placement. B. Spread soil on top of the geotextile to cause the soil to cascade over the geotextile rather than be shoved across the geotextile. C. Place aggregate over geotextile separators as indicated on the Construction Drawings prior to trafficking. D. Place soil over geotextile filters as indicated on the Construction Drawings prior to trafficking. Section 31 02 19.13: Geotextiles Sutton Removal Plan, Rev 0 GC5770\31 02 19.13 Geotextiles.docx 31 02 19.13-6 December 2015 TABLE 31 02 19.13-1 REQUIRED PROPERTY VALUES FOR GEOTEXTILE FILTER Properties (6) Qualifier Units (5) Specified Values(1) Test method Product Requirements Type -- -- Nonwoven needle-punched -- Polymer composition Minimum % 95 polypropylene or polyester by wt -- Mass per unit area Minimum oz/yd2 8 ASTM D 5261 Filter Requirements Apparent opening size Maximum mm O95 ≤ 0.21 ASTM D 4751 Permittivity Minimum sec-1 0.5 ASTM D 4491 Mechanical Requirements Grab strength Minimum lb 200 ASTM D 4632(2) Tear strength Minimum lb 75 ASTM D 4533(3) Static puncture strength Minimum psi 500 ASTM D 6241 Durability Requirements Ultraviolet Resistance Minimum % 70 ASTM D 4355 Notes: 1. All values represent minimum average roll values. 2. Minimum of values measured in machine and cross machine directions with 1 inch clamp on Constant Rate of Extension (CRE) machine. 3. Minimum value measured in machine and cross machine direction. 4. Not Used. 5. mm = millimeter % = percent oz/yd2 = ounce per square yard sec = second lb = pound psi = pound per square inch 6. See Paragraph 2.02 for required MQC test frequencies. Section 31 02 19.13: Geotextiles Sutton Removal Plan, Rev 0 GC5770\31 02 19.13 Geotextiles.docx 31 02 19.13-7 December 2015 TABLE 31 02 19.13-2 REQUIRED PROPERTY VALUES FOR GEOTEXTILE SEPARATOR Properties (6) Qualifier Units (5) Specified Values (1) Test method Product Requirements Type -- -- Nonwoven needle- punched -- Polymer composition Minimum % 95 polypropylen e or polyester -- Mass per unit area Minimum oz/yd2 8 ASTM D 5261 Mechanical Requirements Grab strength Minimum lb 200 ASTM D 4632(2) Tear strength Minimum lb 75 ASTM D 4533(3) Static puncture strength Minimum psi 500 ASTM D 6241 Durability Requirements Ultraviolet Resistance Minimum % 70 ASTM D 4355 Notes: 1. All values represent minimum average roll values. 2. Minimum of values measured in machine and cross machine directions with 1 inch clamp on Constant Rate of Extension (CRE) machine. 3. Minimum value measured in machine and cross machine direction. 4. Not Used 5. % = percent oz/yd2 = ounce per square yard lb = pound psi = pound per square inch 6. See Paragraph 2.02 for required MQC test frequencies. [END OF SECTION] Section 31 05 16: Granular Drainage Material Sutton Removal Plan, Rev 0 GC5770\31 05 16 Granular Drainage Material.docx 31 05 16-1 December 2015 SECTION 31 05 16 GRANULAR DRAINAGE MATERIAL PART 1 GENERAL 1.01 SECTION INCLUDES A. This section includes the requirements for granular drainage material. 1.02 RELATED SECTIONS AND PLANS A. Section 02 21 00 - Surveying B. Section 31 02 19.13 - Geotextiles C. Construction Quality Assurance (CQA) Plan 1.03 REFERENCES A. Latest version of American Society of Testing and Materials (ASTM) standards and other standards noted in this specification. 1.04 SUBMITTALS A. For each source of granular drainage material, submit the following to the ENGINEER for review not less than 21 calendar days prior to use: 1. source of the material; 2. test results conducted on each material such that the material is fully represented in accordance with ASTM C 136, ASTM D 2434, and ASTM D 3042; and 3. a 50-pound representative sample of the material. 1.05 CONSTRUCTION QUALITY ASSURANCE A. The installation of the granular drainage material will be monitored by the CQA Consultant as required in the CQA Plan. B. The CQA Consultant will perform material conformance testing and installation quality control testing on the granular drainage materials as required in the CQA Plan. C. The CONTRACTOR shall be aware of the activities required of the CQA Consultant by the CQA Plan and shall account for these activities in the construction schedule. D. The CONTRACTOR shall correct all deficiencies and nonconformances identified by the CQA Consultant at no additional cost to the OWNER. Section 31 05 16: Granular Drainage Material Sutton Removal Plan, Rev 0 GC5770\31 05 16 Granular Drainage Material.docx 31 05 16-2 December 2015 PART 2 PRODUCTS 2.01 MATERIALS A. Furnish granular drainage materials consisting of homogeneous crushed or natural stones that is free of materials that, due to their nature or size, are deleterious to the intended use as determined by the ENGINEER. B. Granular drainage material shall be rounded or subrounded (as defined by ASTM D 2488), shall have a gradation (per ASTM C 136) that meets the requirements for a No. 57 stone in ASTM D 448, and shall have a minimum hydraulic conductivity of 1 cm/sec based on laboratory permeability testing conducted in accordance with the ASTM D 2434. C. Furnish granular drainage material having less than 5 percent loss by weight when tested in accordance with ASTM D 3042. 2.02 EQUIPMENT A. Furnish, operate, and maintain equipment necessary to transport, place, and spread the granular drainage materials without damage to adjacent geosynthetics. PART 3 EXECUTION 3.01 MATERIAL PLACEMENT A. Do not commence placement of the granular drainage material until the CQA Consultant has completed conformance evaluation of the material and evaluation of previous work, including evaluation of the CONTRACTOR's survey results for previous work. B. Place the granular drainage material to the minimum thicknesses and limits indicated on the Construction Drawings. C. Surround granular drainage material with geosynthetic material as indicated on the Construction Drawings. Care shall be taken to avoid damage to geosynthetics during granular drainage material placement. 3.02 SURVEY CONTROL A. Survey the limits and elevations of the top of the granular drainage material in accordance with Section 02 21 00. 3.03 TOLERANCES A. Construct the granular drainage material to the minimum thicknesses indicated on the Construction Drawings. Section 31 05 16: Granular Drainage Material Sutton Removal Plan, Rev 0 GC5770\31 05 16 Granular Drainage Material.docx 31 05 16-3 December 2015 [END OF SECTION] Section 31 11 00: Clearing, Grubbing, and Stripping Sutton Removal Plan, Rev 0 GC5770\31 11 00 Clearing, Grubbing, and Stripping.docx 31 11 00-1 December 2016 SECTION 31 11 00 CLEARING, GRUBBING, AND/OR STRIPPING PART 1 GENERAL 1.01 SCOPE A. This section describes the requirements for clearing, grubbing, and/or stripping activities. Clearing, grubbing, and/or stripping activities will be required to perform the earthwork, and to perform other work, as needed, to complete various construction activities. 1.02 RELATED SECTIONS AND PLANS A. Section 02 21 00 - Surveying B. Section 31 00 00 - Earthwork C. Section 31 25 00 - Sediment and Erosion Control D. Section 31 31 19 - Vegetation E. Construction Quality Assurance (CQA) Plan 1.03 COMPLIANCE WITH REGULATIONS A. It is the sole responsibility of the CONTRACTOR to be completely familiar with and to follow all local, state, and federal regulations pertaining to the work required in this section. 1.04 CONSTRUCTION QUALITY ASSURANCE A. Clearing, grubbing, and/or stripping operations shall be monitored by the CQA Consultant as outlined in the CQA Plan. B. The CONTRACTOR shall be aware of the activities set forth in the CQA Plan and shall account for these activities in the construction schedule. C. The CONTRACTOR shall assist CQA personnel in every manner necessary for the proper performance of activities set forth in the CQA Plan. D. CQA testing or inspections in no manner relieves the CONTRACTOR of the responsibility to perform all work in conformance with the Construction Drawings and Specifications. E. If quality control or quality assurance tests indicate work does not meet specified requirements, the CONTRACTOR shall perform the work as directed by the CQA Consultant at no additional cost to the OWNER. Section 31 11 00: Clearing, Grubbing, and Stripping Sutton Removal Plan, Rev 0 GC5770\31 11 00 Clearing, Grubbing, and Stripping.docx 31 11 00-2 December 2016 1.05 EXISTING CONDITIONS A. The CONTRACTOR shall comply with applicable regulations in locating and providing clearance for all underground and above ground utilities, if applicable, prior to beginning construction activities. The CONTRACTOR shall immediately notify the OWNER and the ENGINEER if utility lines or structures not shown on the Construction Drawings are encountered. Repair of damage and all restitution for liabilities resulting from damage to existing facilities due to activities by the CONTRACTOR shall be at the CONTRACTOR’s expense. PART 2 PRODUCTS 2.01 MATERIALS A. Materials to be cleared, grubbed, and/or stripped include trees, shrubs, debris, muck, or other foreign matter, as needed, to develop the work area and enable construction activities. B. Vegetative stabilization and erosion control of stripped soil stockpiles shall be as specified in Section 31 25 00. PART 3 EXECUTION 3.01 FAMILIARIZATION A. Prior to implementing any of the work described in this section, the CONTRACTOR shall become thoroughly familiar with the site, the site conditions, and all portions of the work described in this section. B. CONTRACTOR shall note that the elevation of groundwater is at or near the existing ground surface for areas covered under this Contract. Some areas may also be inundated with water at the start of construction. CONTRACTOR is responsible for any dewatering required to execute the required work. C. Inspection: 1. Prior to implementing any of the work in this section, the CONTRACTOR shall carefully inspect and verify that related work required by other sections is complete to the point where the work described in this section may properly commence without adverse impact. 2. If the CONTRACTOR has any concerns regarding the related work required by other sections, he shall notify the ENGINEER in writing prior to the commencement of operations. Failure to notify the ENGINEER will be construed as CONTRACTOR acceptance of the related work of all other sections. Section 31 11 00: Clearing, Grubbing, and Stripping Sutton Removal Plan, Rev 0 GC5770\31 11 00 Clearing, Grubbing, and Stripping.docx 31 11 00-3 December 2016 3.02 SEDIMENT AND EROSION CONTROL A. Prior to implementing any work described in this section, the CONTRACTOR shall install all sediment and erosion controls in the relevant area(s) of construction. B. CONTRACTOR is solely responsible for selecting, implementing, and maintaining proper and fully adequate sediment and erosion controls at all times during construction. 3.03 CLEARING AND GRUBBING A. Clearing and/or grubbing shall be performed in areas identified in the contract documents or as directed by the ENGINEER. All sediment and erosion controls, as described in Section 31 25 00 of the Specifications or as indicated on the Construction Drawings, shall be in place before the start of clearing. B. If weather conditions are unsuitable for clearing and/or grubbing, as determined by the ENGINEER, the CONTRACTOR shall cease operations until permission to resume operations is obtained from the ENGINEER. C. Clearing shall consist of removing trees, undergrowth, and deadwood. Trees shall be cut level with the adjacent ground surface. Grubbing shall consist of removing stumps, roots, and surficial debris from the areas identified in this section or as directed by the ENGINEER. D. Clearing and/or grubbing activities shall be performed in a manner so as to minimize disturbance to the surrounding areas. E. All cleared and/or grubbed materials shall be reduced to mulch and stockpiled as directed by the OWNER. 3.04 STRIPPING A. Stripping shall be performed in areas identified in this section or as directed by the ENGINEER. All sediment and erosion controls shall be in place before the start of stripping. Stripping shall include all vegetation, organics, and other deleterious materials as required by the ENGINEER. Stripping depth shall be a minimum of 6 inches. However, overstripping shall be avoided. B. If soil or weather conditions are unsuitable for stripping, as determined by the ENGINEER, the CONTRACTOR shall cease stripping activities until permission to resume work is obtained from the ENGINEER. C. Equipment and methods of operation shall be selected by the CONTRACTOR to minimize disturbance to the surrounding areas. Section 31 11 00: Clearing, Grubbing, and Stripping Sutton Removal Plan, Rev 0 GC5770\31 11 00 Clearing, Grubbing, and Stripping.docx 31 11 00-4 December 2016 D. All stripped material shall be stockpiled in the areas designated by the OWNER. Stockpiled material shall be sloped and grassed as required in the Specifications or as directed by the ENGINEER. 3.05 SURVEYING AND CONSTRUCTION TOLERANCES A. The CONTRACTOR shall retain a Surveyor who shall be responsible for providing survey control for the work. The areas to be cleared, grubbed, and/or stripped shall be surveyed prior to performing the work for the purpose of measurement and payment. All surveying shall be performed in accordance with Section 02 21 00 of the Specifications. 3.06 PROTECTION OF WORK A. The CONTRACTOR shall protect all prior work, including all materials and related work of other sections. B. In the event of damage, the CONTRACTOR shall immediately make all necessary repairs and replacements necessary, as directed and approved by the ENGINEER, at no additional cost to the OWNER. [END OF SECTION] Section 31 23 33: Trenching and Backfilling Sutton Removal Plan, Rev 0 GC5770\31 23 33 Trenching and Backfilling.docx 31 22 33-1 December 2015 SECTION 31 23 33 TRENCHING AND BACKFILLING PART 1 GENERAL 1.01 SCOPE A. This section describes the requirements for trenching, backfilling, placing, and compacting materials, and for performing other work as directed by the ENGINEER. 1.02 RELATED SECTIONS AND PLANS A. Section 02 21 00 - Surveying B. Section 31 00 00 - Earthwork C. Construction Quality Assurance (CQA) Plan 1.03 REFERENCES A. Latest version of American Society of Testing and Materials (ASTM) standards and other standards noted in this specification. B. Latest version of Occupational Safety and Health Administration (OSHA) Construction Standards. 1.04 SUBMITTALS A. Submit a list of equipment for trenching and backfilling to the ENGINEER no less than 15 calendar days prior to construction/installation. B. If the embedment fill material is obtained from a source different than the source of general fill, submit the source of the embedment fill, a representative sample, and results of tests conducted on the embedment fill samples in accordance with ASTM D 422 and ASTM D 2487. 1.05 CONSTRUCTION QUALITY ASSURANCE A. The trenching and backfilling will be monitored by the CQA Consultant as required in the CQA Plan. B. The CONTRACTOR shall be aware of the activities required of the CQA Consultant in the CQA Plan and shall account for these activities in the construction schedule. C. The CONTRACTOR shall correct all deficiencies and non-conformances identified by the CQA Consultant at no additional cost to the OWNER. Section 31 23 33: Trenching and Backfilling Sutton Removal Plan, Rev 0 GC5770\31 23 33 Trenching and Backfilling.docx 31 22 33-2 December 2015 1.06 EXISTING CONDITIONS A. In advance of trenching in an area, verify the accuracy of existing conditions indicated on the Construction Drawings. Immediately notify the ENGINEER in writing of deviations from the existing conditions indicated on the Construction Drawings. B. The approximate locations of all known underground utilities, above ground utilities, and other structures, if any, are indicated on the Construction Drawings. PART 2 PRODUCTS 2.01 MATERIALS A. Embedment material and backfill material shall be obtained from the designated or other borrow area and shall meet the material requirements for general fill as specified in Section 31 00 00. 2.02 EQUIPMENT A. Provide, operate, and maintain all equipment necessary to perform the work described in this section. PART 3 EXECUTION 3.01 GENERAL A. In areas of trenching and backfilling, maintain and protect existing underground utilities, above ground utilities, and other structures, if any. B. Do not damage or disturb, if possible, the existing work/systems that must remain after trenching and backfilling is completed. If damaged or disturbed, these systems shall be restored to the condition existing prior to the trenching and backfilling operations. 3.02 TRENCHING A. Use sheeting and bracing where and whenever necessary to maintain the safety and stability of all slopes, trenches, and adjacent structures, if any. Satisfy all applicable local, state, and federal requirements for slope and trench sheeting and bracing, including requirements of the Occupational Safety and Health Administration (OSHA) construction standards. Provide required sheeting and bracing materials on site prior to start of trenching. Adjust spacing and arrangement of sheeting and bracing as required by conditions encountered. Remove sheeting and bracing as backfill Section 31 23 33: Trenching and Backfilling Sutton Removal Plan, Rev 0 GC5770\31 23 33 Trenching and Backfilling.docx 31 22 33-3 December 2015 progresses. Fill any voids left from sheeting or bracing withdrawal with general fill or other approved materials. B. Trench soils for pipes, culverts, storm water structures and/or to perform other work to depths and minimum dimensions indicated on the Construction Drawings. Fill material shall be placed and compacted with a hand tamper so as not to damage the geosynthetics, structures, or displace the pipes. C. Protect and maintain the trench bottom. Remove rock fragments or raveled materials that collect on the trench bottom. Backfill excess excavation with general fill or other approved materials. Excavate any soft subgrade soils encountered at the trench bottom and backfill and compact general fill to subgrade elevation. D. Dewater trenches and excavations as needed. Perform dewatering in accordance with Section 31 00 00. E. Stockpile excess material from trenching in accordance with Section 31 00 00. 3.03 BACKFILLING A. General: 1. do not backfill with saturated material; 2. do not backfill over wet or soft subgrade; 3. do not disturb or damage the installed pipes during backfilling; and 4. do not use heavy compaction equipment which exerts greater than 5 pounds per square inch ground pressure over pipes that are covered by less than 12 inches of backfill material. B. Placement of backfill material: 1. place the first lift of backfill material in a 12-inch loose lift. Place subsequent lifts of trench backfill material in 8-inch ±1-inch loose lifts; and 2. compact each lift to 95 percent of the maximum standard Proctor dry unit weight at a moisture content generally within ±3 percent of the optimum moisture content as determined by ASTM D 698, or as directed by the ENGINEER. C. Placement of embedment fill: 1. place embedment fill in 7-inch ±1-inch thick loose lifts to the elevation of the bottom of the pipe; 2. compact embedment fill with a minimum of 4 passes of a vibratory plate compactor prior to placing pipe; Section 31 23 33: Trenching and Backfilling Sutton Removal Plan, Rev 0 GC5770\31 23 33 Trenching and Backfilling.docx 31 22 33-4 December 2015 3. place pipe on top of the compacted embedment fill; 4. for pipes 12 inches in diameter or less, place additional pipe embedment fill on the sides and hand tamp the fill around the sides as needed to insure intimate contact between the pipe and the embedment fill below the spring line. Continue placing embedment fill until it is even with the top of the pipe. Compact the embedment fill with a minimum of 4 passes of a vibratory plate compactor. Do not compact on top of the pipe unless a minimum of 12 inches of trench backfill separates the compactor from the top of the pipe; and 5. for pipes greater than 12 inches in diameter, place embedment fill in 7- inch ±1-inch thick loose lifts to the limits shown on the Construction Drawings. Compact each lift with a minimum of 4 passes of a vibratory plate compactor. 3.04 SURVEY CONTROL A. Survey the limits and invert elevations of all pipes, culverts, and structures in accordance with Section 02 21 00. B. Survey the alignment and elevations of the top of all pipes at each change in grade and every 50 feet between changes in grades in accordance with Section 02 21 00. 3.05 TOLERANCES A. Install pipes to within ±0.1 ft of the elevations and within 10 percent of the slopes indicated on the Construction Drawings. B. Excavate anchor trenches within 0 to +0.2 feet of the depth indicated on the Construction Drawings. [END OF SECTION] Section 31 25 00: Sediment and Erosion Control Sutton Removal Plan, Rev 0 GC5770\31 25 00 Sediment and Erosion Control.docx 31 25 00-1 December 2015 SECTION 31 25 00 SEDIMENT AND EROSION CONTROL PART 1 GENERAL 1.01 SCOPE A. Due to the nature of the work, site soils, and location with respect to active disposal cells and operation, the CONTRACTOR shall implement strict erosion and sedimentation control measures throughout the duration of the work. A preventative approach to sedimentation control shall be implemented by the CONTRACTOR in that multiple measures shall be installed and maintained to prevent sedimentation and/or erosion of exposed soils. The CONTRACTOR shall furnish all labor, materials, tools, and incidentals required to install and maintain the temporary sediment and erosion control measures and structures including, but not limited to, silt fence, straw bales, check dams, temporary diversion berms, and sediment traps, throughout the duration of the construction work. Such controls shall be implemented and maintained throughout the construction until the stabilization of permanent erosion control devices. The CONTRACTOR shall also be responsible for removing the temporary sediment and erosion control measures and structures after the construction work is completed. B. The CONTRACTOR shall contain all storm water discharges within the property boundary. No discharge shall be allowed off of property. C. The CONTRACTOR shall protect all existing storm water structures and ponds. Sediment deposits shall be removed and damaged vegetation shall be repaired. The CONTRACTOR shall maintain all existing storm water features including, but not limited to berms, swales, and culverts. Any disturbed storm water features shall be repaired by the CONTRACTOR. D. Regardless of any minimum requirements set forth in this section, it is the CONTRACTOR’S sole responsibility to select, implement, and maintain proper and fully adequate erosion and sediment controls at all times (24 hours a day on all days) throughout the duration of the project. Repair of any damage and all restitution for liabilities resulting from inadequate erosion and sediment control shall be at the CONTRACTOR’S expense. 1.02 RELATED SECTIONS AND PLANS A. Section 02 21 00 - Surveying B. Section 31 11 00 - Clearing, Grubbing and/or Stripping Section 31 25 00: Sediment and Erosion Control Sutton Removal Plan, Rev 0 GC5770\31 25 00 Sediment and Erosion Control.docx 31 25 00-2 December 2015 C. Section 31 00 00 - Earthwork D. Construction Quality Assurance (CQA) Plan 1.03 REFERENCES A. NCDENR Stormwater BMP Manual, May 2012. 1.04 COMPLIANCE WITH REGULATIONS A. It is the sole responsibility of the CONTRACTOR to be completely familiar and comply with all local, state, and federal regulations pertaining to the work required in this section. 1.05 CONSTRUCTION QUALITY ASSURANCE A. Sediment and erosion control activities shall be monitored as outlined in the CQA Plan. B. The CONTRACTOR shall be aware of the activities set forth in the CQA Plan and shall account for these activities in the construction schedule. C. The CONTRACTOR shall assist the CQA Consultant in every manner necessary for the proper performance of activities set forth in the CQA Plan. D. CQA testing or inspections does not relieve the CONTRACTOR of the responsibility to construct all work in conformance with the Construction Drawings and Specifications. E. If quality control or quality assurance tests indicate work does not meet specified requirements, the CONTRACTOR shall remove, replace, and retest the work at no additional cost to the OWNER. 1.06 SUBMITTALS A. The CONTRACTOR shall submit samples and manufacturer's product data sheets and recommended methods of installation for the proposed silt fence to the ENGINEER at least 14 days prior to starting installation. The manufacturer's product data sheets shall provide documentation and certification that the silt fence products meet or exceed the requirements specified in Part 2.01 of this section. PART 2 PRODUCTS 2.01 SILT FENCE A. Furnish silt fence with either woven or nonwoven fabric. Silt fence shall: Section 31 25 00: Sediment and Erosion Control Sutton Removal Plan, Rev 0 GC5770\31 25 00 Sediment and Erosion Control.docx 31 25 00-3 December 2015 1. be woven fabric consisting of slit films of polypropylene treated with ultraviolet light stabilizers or nonwoven fabric consisting of long chain polymeric filaments or polyester yarns; 2. be inert to hydrocarbons and chemicals commonly found in soils; 3. be resistant to mildew, rot, insects, and rodent attack; 4. have fence post of minimum 2” x 2” lumber and with minimum length of 36 inches spaced a maximum distance of 6 ft along fabric; and 5. have minimum fabric width of 36 inches. 2.02 STRAW BALES A. Furnish rectangular shaped bales of hay weighing at least 40 pounds per bale. Straw bales shall be free of primary noxious weed seeds and shall be staked in place. 2.03 VEGETATION A. Vegetation shall be as specified in Section 31 31 19 of these Specifications. PART 3 EXECUTION 3.01 INSTALLATION A. Silt fence shall be installed in accordance with the manufacturer’s recommendations as needed or as directed by the ENGINEER, prior to any construction activities. Minimum fabric burial depth shall be 6 inches or as recommended by the manufacturer, whichever is greater. B. Temporary diversions shall be provided as needed to prevent run-on of storm water from outside the limits of work from entering the work area. Temporary diversions shall not result in erosion or sedimentation, or cause flooding outside the limits of work. Temporary diversions intended for use longer than 30 days shall be established with vegetation in accordance with Section 31 31 19 of these Specifications. C. The exterior slopes of road shoulders (if applicable) shall be grassed immediately after final grading and shaping. D. The CONTRACTOR shall use straw bales to contain sediment and water from dewatering operations and promote infiltration. Accumulated sediment shall be removed and stockpiled for reuse in an area designated by the ENGINEER. Section 31 25 00: Sediment and Erosion Control Sutton Removal Plan, Rev 0 GC5770\31 25 00 Sediment and Erosion Control.docx 31 25 00-4 December 2015 3.02 PROTECTION OF WORK A. The CONTRACTOR shall protect all prior work, including materials and related work of other sections. B. In the event of damage, the CONTRACTOR shall immediately make all repairs and replacements necessary, as directed and approved by the ENGINEER, at no additional cost to the OWNER. [END OF SECTION] Section 31 31 19: Vegetation Sutton Removal Plan, Rev 0 GC5770\31 31 19 Vegetation.docx 31 31 19-1 December 2015 SECTION 31 31 19 VEGETATION PART 1 GENERAL 1.01 SCOPE A. This section includes the requirements for sodding, seeding, liming, fertilizing, and maintaining vegetation until established and accepted. Areas to be vegetated include areas noted on the Construction Drawings and any other areas as directed by the ENGINEER. 1.02 RELATED SECTIONS AND PLANS A. Section 02 21 00 - Surveying B. Section 31 00 00 - Earthwork C. Construction Quality Assurance (CQA) Plan 1.03 SUBMITTALS A. Submit the following to the ENGINEER not less than 30 calendar days prior to use for review: 1. proposed type and source of sod and seed; and 2. Manufacturer's product data for commercial fertilizer and lime and the recommended methods of application. B. Submit a plan for handling and storage of materials to prevent damage by moisture, heat, or exposure. Include all recommendations of Manufacturers and Suppliers. PART 2 PRODUCTS 2.01 MATERIALS A. Sod shall be live, thriving, and meet the requirements of North Carolina Department of Agriculture and Consumer Services. B. Seeds shall be live seed and meet the requirements of North Carolina Department of Agriculture and Consumer Services. C. The seeds should have been harvested from the previous year’s crop. D. All seed bags shall have a label attached stating the date of harvest, LOT number, percent purity, percent germination, noxious weed certification, and date of test. Section 31 31 19: Vegetation Sutton Removal Plan, Rev 0 GC5770\31 31 19 Vegetation.docx 31 31 19-2 December 2015 E. Use fertilizer that is dry or liquid commercial grade fertilizer uniform in composition that meets the requirements of all State and Federal regulations and standards of the Association of Agricultural Chemists. Deliver fertilizer to the site in original, properly labeled, unopened, clean, containers each showing the Manufacturer's guaranteed analysis conforming to applicable fertilizer regulations and standards. Use fertilizer that is 16-4-8 or as modified by the ENGINEER based on testing of the topsoil by the CONTRACTOR. Apply fertilizer to all sodded areas. F. Use lime that is agricultural ground limestone with a minimum total neutralizing power of 90 percent. The lime shall have a gradation of at least 40 percent passing the U.S. Standard Number 100 sieve, and at least 95 percent passing the U.S. Standard Number 8 sieve. PART 3 EXECUTION 3.01 PLANTING AND APPLICATION OF FERTILIZER A. Do not commence vegetation until the ENGINEER reviews the results of soil analyses. 3.02 NOTIFY THE ENGINEER 24 HOURS PRIOR TO LAYING SOD, SEEDING, OR FERTILIZING. A. The seed and fertilizer shall be placed by hydro seeding, or other method approved by the ENGINEER. B. The underlying soil layer should be graded to the lines and limits as indicated on the Construction Drawings. The soil layer surface shall be scarified and damp immediately prior to the seed or sod placement. C. Repair all gullies, washes, or disturbed areas that develop subsequent to final dressing of the prepared surface. D. Seeded areas shall be watered after germination as necessary until the vegetation is well established. E. Apply fertilizer and lime to all vegetated areas unless otherwise indicated by the ENGINEER. F. Apply fertilizer and lime at the specified rates. If not applied hydraulically, thoroughly rake the fertilizer and lime into the prepared surface to a minimum depth of 2 inches. G. Application rates: 1. Application rates for seeding shall be according to Manufacture/Supplier recommendations or as directed by the ENGINEER. Section 31 31 19: Vegetation Sutton Removal Plan, Rev 0 GC5770\31 31 19 Vegetation.docx 31 31 19-3 December 2015 2. Application rates for fertilizer and lime in this section may be adjusted after the results of the site soil test results performed by the CONTRACTOR are available. 3. Base contract price on application rates for fertilizer and lime specified in this section. Contract price will be adjusted for any variations either due to decreasing or increasing the application rates. H. For areas to be covered with seed or sod: 1. Apply fertilizer at a uniform rate of 1,200 pounds per acre or as otherwise directed by the ENGINEER. 2. Apply agricultural lime at a rate of two tons per acre or as otherwise directed by the ENGINEER. 3.03 MAINTENANCE A. Maintain seeded and sodded areas immediately after placement until vegetation is well established and exhibits a vigorous growing condition. B. The CONTRACTOR shall supply and apply supplemental irrigation for the maintenance period following the placement of the seed or sod. All seeded and sodded areas should receive a minimum of 1½ inches of water per week either by precipitation or supplemental irrigation. C. Maintain the seeded and sodded areas in satisfactory condition. Maintenance of the seeded and sodded areas includes repairing eroded areas, revegetating, watering, and mowing (if applicable). A satisfactory condition of a seeded or sodded area is defined as a 10,000 square feet section of turf that has no bare spots larger than three square feet. D. The inspection will be performed by the ENGINEER, who will determine whether repair of sodded areas or revegetation is required. 3.04 ACCEPTANCE A. The vegetated areas shall be accepted at the end of the warranty period if a satisfactory condition as defined in this section exists. 3.05 WARRANTY PERIOD A. Vegetated areas shall be subject to a warranty period of not less than 60 days from the issuance of the ENGINEER’s final completion notice to the CONTRACTOR for the Contract over 100 percent of the areas seeded and sodded. B. At the end of the warranty period, the ENGINEER will perform an inspection upon written request by the CONTRACTOR. Vegetated areas not demonstrating satisfactory condition of vegetation as outlined above, shall be Section 31 31 19: Vegetation Sutton Removal Plan, Rev 0 GC5770\31 31 19 Vegetation.docx 31 31 19-4 December 2015 repaired, resodded, and maintained to meet all requirements as specified herein at the CONTRACTOR's expense. All unaccepted areas requiring repair, replacement of sod and/or reseeding shall be subject to a 60 day warranty period commencing at the completion of the reworking. C. After all necessary corrective work has been completed, the ENGINEER will certify in writing the final acceptance of the vegetated areas. [END OF SECTION] Section 31 37 00: Riprap Sutton Removal Plan, Rev 0 GC5770\31 37 00 Riprap.docx 31 37 00-1 December 2015 SECTION 31 37 00 RIPRAP PART 1 GENERAL 1.01 SCOPE A. This section includes the requirements of riprap products and placement that will need to be installed at the location of the storm water drainage structures. 1.02 RELATED SECTIONS AND PLANS A. Section 33 49 00 - Storm Water Drainage Structures B. Section 31 02 19.13 - Geotextiles C. Construction Quality Assurance (CQA) Plan 1.03 SUBMITTALS A. Submit the following to the ENGINEER for review no less than 30 calendar days prior to riprap use. 1. source of the riprap; and 2. certification from the supplier that the riprap meets the material requirements of this Section. 1.04 CONSTRUCTION QUALITY ASSURANCE A. The placement of riprap will be monitored by the CQA Consultant as required by the CQA Plan. B. The CQA Consultant will perform material conformance testing as required by the CQA Plan. C. The CONTRACTOR shall be aware of the activities required of the CQA Consultant by the CQA Plan and account for these activities in the construction schedule. D. The CONTRACTOR shall correct all deficiencies and non-conformances identified by the CQA Consultant at no additional cost to the Owner. PART 2 PRODUCTS 2.01 MATERIALS A. Riprap shall consist of hard, durable, angular field or quarry stone. B. Riprap shall conform to NCDOT Class 1 riprap Specifications. Section 31 37 00: Riprap Sutton Removal Plan, Rev 0 GC5770\31 37 00 Riprap.docx 31 37 00-2 December 2015 PART 3 EXECUTION 3.01 PLACEMENT A. Place riprap to the thickness, elevations, and locations indicated on the Construction Drawings. B. Place riprap upon geotextile separator meeting requirements of Section 31 02 19.13 and over prepared layers as indicated on the Construction Drawings. C. Carefully place riprap to avoid segregation or disturbance or damage of the underlying material. Place the material in a manner to produce a well graded mass of riprap with the minimum practicable percentage of voids. Distribute the larger pieces throughout the entire mass such that the finished riprap is free from objectionable pockets of small or large pieces. D. Do not place riprap by dumping into chutes or by similar methods likely to cause segregation of various sizes. E. Do not place riprap in a manner that causes damage to an underlying geotextile separator or geocomposite. Repair damaged geotextile as directed by the ENGINEER and in accordance with Section 31 02 19.13. 3.02 SURVEY CONTROL A. Survey the location of riprap placement in accordance with Section 02 21 00. 3.03 TOLERANCES A. Place the riprap to the minimum thicknesses as indicated on the Construction Drawings. [END OF SECTION] Section 32 92 19: Seeding Sutton Removal Plan, Rev 0 GC5770\32 92 19 Seeding.doc 32 92 19-1 December 2015 SECTION 32 92 19 SEEDING PART 1 GENERAL 1.01 SUMMARY A. The CONTRACTOR shall furnish all labor, materials, and equipment required to complete seeding and establish vegetation in disturbed areas at the Site in accordance with this Section. B. The seeding activities relating to erosion and sediment control vegetation shall include, but not be limited to, the following: 1. determining herbicides, fertilizer, ratios, times of application, and schedules; 2. seeding of sediment and erosion control vegetation; 3. applying fertilizer and soil amendments; 4. installing, maintaining, replacing, and removing mulch; 5. soil tests to determine the required soil additives for all stabilized areas; and 6. mowing and other vegetation maintenance practices. 1.02 RELATED SECTIONS AND PLANS A. Section 01 00 00 – General Requirements B. Section 31 25 00 – Erosion and Sediment Control C. Section 31 11 00 – Clearing, Grubbing, and Stripping 1.03 REFERENCES A. Latest version of North Carolina Department of Environment and Natural Resources Manual (NCDENR), Practice Standards and Specifications, Chapter 6.11 Permanent Seeding B. Latest version of North Caroline Department of Transportation Standard Specifications for Roads and Structures (NCDOT), Section 1060. Section 32 92 19: Seeding Sutton Removal Plan, Rev 0 GC5770\32 92 19 Seeding.doc 32 92 19-2 December 2015 1.04 SUBMITTALS A. At least 30 calendar days prior to implementing permanent vegetative stabilization activities, the CONTRACTOR shall provide the Construction Manager with the following: 1. soil test results per NCDENR Chapter 6.11; 2. the seed mixture, quantity, and application rate proposed for use; 3. the mulch type and application rate proposed for use; 4. the fertilizer type and application rate proposed for use; and 5. the seed bed preparation process proposed for use. 1.05 PERFORMANCE REQUIREMENTS A. Project work shall conform to erosion and sediment control measures requirements of the NCDENR. B. Before proceeding with seeding activities, the CONTRACTOR shall carefully check and verify dimensions and quantities and shall immediately inform the Construction Manager of any discrepancies between the Drawings and actual conditions. No work shall be performed in an area where a discrepancy has been identified until approval has been provided by the Construction Manager. C. The CONTRACTOR shall be required to obtain all required permits, including the Land Disturbance Permit, upon contract award. 1.06 SAFETY A. The CONTRACTOR shall be familiar with, and shall at all times conform to, the regulations promulgated by the Occupational Safety and Health Administration (“OSHA”) and set forth in “General Industry Occupational Safety and Health Standards”, 29 C.F.R. Part 1910, and “Safety and Health Regulations for Construction,” 29 C.F.R. Part 1926, and other applicable state and local standards and regulations. B. The CONTRACTOR shall comply with all provisions of the OWNER’s safety policies. C. The CONTRACTOR shall perform work in a safe manner in accordance with the accepted CONTRACTOR’s Health and Safety Plan (“CHASP”). Section 32 92 19: Seeding Sutton Removal Plan, Rev 0 GC5770\32 92 19 Seeding.doc 32 92 19-3 December 2015 PART 2 PRODUCTS 2.01 MATERIALS A. Materials shall be checked and approved by the Construction Manager or his designee before delivery to the Site and/or installation. Such approval shall not relieve the CONTRACTOR of his obligations under the Construction Documents. B. Seeding materials under this Section 32 92 19 shall include but not be limited to the following items: 1. Fertilizer. Fertilizer shall be commercially-prepared and granular. Fertilizer shall be uniform in composition, dry, and free-flowing. a. Fertilizer shall conform to all applicable state and federal regulations. b. Fertilizer for permanent seeding shall be of the specified organic composition as determined by NCDOT 1060. 2. Limestone. Limestone shall be ground dolomitic limestone with 98-100 percent passing a 20 mesh sieve and 50 percent passing a 100 mesh sieve. 3. Seed. Grass seed shall meet the requirements specified in the NCDENR Manual. The CONTRACTOR shall use the seed mix requirements for General Slope (3:1 or less) for the appropriate region, as outlined by the NCDENR Manual. 4. Mulch. Oat or wheat straw shall be used. Straw shall be dry and free from weeds, weed seeds, and foreign matter detrimental to plant life. Mulch shall conform to NCDOT 1060-5. PART 3 EXECUTION 3.01 GENERAL REQUIREMENTS A. Preparation: 1. General. Rake the soil surface to remove all root clumps, stones, and debris 1 inch or greater in size. True up all depressions and edges. Soil in the area to be seeded shall be prepared in accordance NCDOT 1060. 2. Grading. Establish a smooth grade ready to receive seed. The finished grade must conform to the grades and elevations as shown on the Drawings. Section 32 92 19: Seeding Sutton Removal Plan, Rev 0 GC5770\32 92 19 Seeding.doc 32 92 19-4 December 2015 3. Topsoil. Topsoil shall be in place for areas to be permanently seeded. B. Application: 1. General. Seeding shall conform to NCDOT 1060 and the Erosion and Sediment Control Plan. Initial seeding shall consist of uniformly applying seed, mulch, and water on prepared areas. Over-seeding shall consist of applying seed, mulch, and water to areas previously seeded. 2. Lime: Apply lime uniformly at the rate of 2 tons per acre or as recommended in the soil test report using approved application methods listed in NCDOT 1060-3. After application, the soil shall be loosened to a depth of 3 inches by disking, harrowing, or other approved method. Washed and disturbed areas shall be final dressed prior to applying fertilizer. Lime application is not required for areas to be temporarily seeded for periods of less than 4 months. 3. Fertilizer. Incorporate fertilizer into the top 3 inches of soil by discing or power rake. a. For areas to be permanently seeded, apply fertilizer uniformly at the rate of 30 pounds per 1,000 square feet. b. For areas to be temporarily seeded, apply fertilizer uniformly at the rate of 15 pounds per 1,000 square feet. 4. Seeding Time. Seed shall be sown during favorable weather conditions. Seed shall not be sown when the ground is frozen or when air temperatures are below freezing. Do not sow under windy conditions. 5. Seeding. Sow seed uniformly, dividing the selected rate in half and sowing in cross directions using a mechanical spreader. Do not allow seed to drift into adjacent planting beds. 6. Rolling. After machine sowing, lightly cover seed by harrowing or raking. Compact lawn area seedbeds by rolling with a 200 pound hand roller. 7. Mulching. Mulching shall comply with the pertinent provisions NCDOT 1060-5 a. Apply mulch within 48 hours of sowing seed. Apply mulch of loose straw uniformly at the rate of 2 tons per acre. Between October 16 and January 31, the application rate shall be increased to 3 tons per acre. Mulch shall be anchored to the seeded surface by discing, netting, or by other methods approved by the OWNER or Construction Manager. b. Areas to be temporarily seeded need be mulched only during the fall Section 32 92 19: Seeding Sutton Removal Plan, Rev 0 GC5770\32 92 19 Seeding.doc 32 92 19-5 December 2015 or during the summer when weather conditions are excessively hot or dry. 8. Watering. Immediately after completion of mulching, apply water thoroughly to mulch and seedbed with a fine mist spray. Water heavily once per week during dry weather until a thick cover of grass is established. 9. Hydroseeding. Hydroseeding may be used as an alternative application method upon approval of the OWNER. The use of alternative soil amendments and mulch will be considered provided the application rates comply with the rates specified in this Section. C. The CONTRACTOR shall provide silt fences as needed to prevent runoff from seeded areas until vegetation has become established. D. Upon completion of work, the CONTRACTOR shall remove from the Site cord, wrappings, stakes, and extraneous materials. The CONTRACTOR shall remove tools, equipment, and other materials, except those necessary for maintenance. Litter developing by reason of the CONTRACTOR's maintenance activities shall be removed as it accumulates. E. The CONTRACTOR shall maintain areas until seed has germinated and produced a thick stand of grass but for not less than one (1) year following issuance of the notice of termination by NCDENR of the erosion and sediment control plan for the Site. F. During the maintenance period, the CONTRACTOR shall perform all mowing, watering, repair of erosion areas, replacement of cover soil and topsoil, cleaning of drainage ditches and drainage system components clogged by eroded topsoil and cover soil, and reseeding until a thick stand of grass has been produced as accepted by the Construction Manager and OWNER. Maintenance shall also include visual inspection of the cover system components for damage (e.g., penetrations of the soil cover or exposure of the geosynthetic layer). Observed damage shall be temporarily covered with a tarp or other impervious cover and notated within maintenance records maintained by the CONTRACTOR. The CONTRACTOR shall report the damage to the Construction Manager within one business day of being observed to initiate protocols to evaluate and repair the damage, and submit notification to NCDENR. G. Mow areas intended for “groomed appearance” on a schedule during the growing season and as required throughout the year to provide the desired appearance for the particular species used for erosion control. 1. The range of turf species suggested for lawns in the three growing regions of North Carolina vary as to optimum maintained height. The selected species should be maintained at a height recommended by the seed Section 32 92 19: Seeding Sutton Removal Plan, Rev 0 GC5770\32 92 19 Seeding.doc 32 92 19-6 December 2015 producer. Do not cut too short and do not allow the turf to attain a height that will cause the crop to decline or die. Consult individual seed producers and/or packaging for recommended mowing heights. 2. Mow with a mulching mower to limit the amount of clippings removed, or mow and blow in such a manner that clippings are not evident and not to adversely affect the growing capacity and/or health of the existing vegetation turf. It is important clippings are allowed to remain spread throughout the lawn area, to the extent possible, so that they might aid in building a more productive soil profile and root zone. 3. Mowing other stabilized areas to promote continued growth. Stabilized areas that are not to achieve a “groomed” appearance are to be mowed to recommended mowing heights for the particular species and as frequently as recommended by the individual seed producer to foster erosion control and ease of maintenance. In areas where it is desirable for woody native volunteer vegetation to become established, the CONTRACTOR will pay attention to mowing stakes or another indicator to protect desired woody natives from the mowing operation 4. The CONTRACTOR shall cut the grass at least once, but not more than twice per season, after a thick stand of grass is produced. The CONTRACTOR shall coordinate grass cutting with the Construction Manager or OWNER so that inspections can be conducted immediately following cutting. H. A satisfactory stand of vegetative cover shall be defined as a cover of living plants, after true leaves are formed, of the required seed species designated for use in which gaps larger than 25 square inches do not occur. I. The CONTRACTOR shall make site observations monthly to check for the presence of invasive species that could lead to unprotected soil and sediment damage and, if found, treat them immediately with the appropriate cultural practices and/or by the use of seasonally-appropriate and site appropriate herbicides. J. The CONTRACTOR shall commence post-construction maintenance within two weeks of notification that maintenance is required. Maintenance will be conducted to the satisfaction of the Construction Manager or OWNER. 3.02 ADJUSTMENT OF PRACTICES A. If the planned measures do not result in effective control of erosion and sediment runoff meeting the requirements of the General Permit for Discharges of Stormwater from Construction Activities, the CONTRACTOR shall immediately adjust his activities and/or institute additional measures so as to eliminate erosion and sediment runoff at no additional cost to the OWNER. Section 32 92 19: Seeding Sutton Removal Plan, Rev 0 GC5770\32 92 19 Seeding.doc 32 92 19-7 December 2015 B. If the CONTRACTOR fails or refuses to comply promptly, the Construction Manager may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No time lost due to stop orders shall be made the subject of a claim for extension of time or for excess costs or damages by the CONTRACTOR. [END OF SECTION] Section 33 42 13: Pipe Culverts Sutton Removal Plan, Rev 0 GC5770\33 42 13 Pipe Culverts.doc 33 42 13-1 December 2015 SECTION 33 42 13 PIPE CULVERTS PART 1 GENERAL 1.01 SUMMARY A. This Section includes all materials, equipment, and labor necessary for the installation of culverts and related appurtenances. 1.02 RELATED SECTIONS AND PLANS A. Section 00 21 00 – Surveying B. Section 31 25 00 – Sediment and Erosion Control C. Section 31 23 33 – Trenching and Backfilling D. Section 31 37 13 – Rip Rap 1.03 REFERENCES A. Latest version of American Association of State Highway Transportation Officials (AASHTO) Standards: 1. AASHTO M252 Standard Specification for Corrugated Polyethylene Drainage Pipe 2. AASHTO M294 Standard Specification for Corrugated Polyethylene Pipe, 300- to 1500-mm Diameter B. Latest version of ASTM International (ASTM) Standard: 1. ASTM D2321 Standard Practice for Underground Installation of Thermoplastic Pipe for Sewers and Other Gravity Flow Applications. 2. ASTM D3350 Standard Specification for Polyethylene Plastics Pipe and Fittings Materials. 3. ASTM D3212 Standard Specification for Joints for Drain and Sewer Plastic Pipes Using Flexible Elastomeric Seals. 4. ASTM F405 Standard Specification for Corrugated Polyethylene (PE) Pipe and Fittings. 5. ASTM F477 Standard Specification for Elastomeric Seals (Gaskets) for Joining Plastic Pipe. Section 33 42 13: Pipe Culverts Sutton Removal Plan, Rev 0 GC5770\33 42 13 Pipe Culverts.doc 33 42 13-2 December 2015 6. ASTM F667 Standard Specification for 3 through 24 in. Corrugated Polyethylene Pipe and Fittings. 7. ASTM F2306 Standard Specification for 12 to 60 in [300 to 1500 mm] Annular Corrugated Profile Wall Polyethylene (PE) Pipe and Fittings for Gravity Flow Storm Sewer and Subsurface Drainage Applications. 1.04 SUBMITTALS A. Submit the following to the ENGINEER for review at least 30 calendar days prior to use: 1. culverts Manufacturer's product data and recommended methods of storage, handling, and proposed installation; 2. shop drawings for culverts showing the layout and details of joints, special connections, and fittings; and 3. Manufacturer's written certification that culverts and joint material meet the material requirements of this Section. B. Provide list of equipment, description of installation methods, and other required information for installation of culverts. 1.05 CONSTRUCTION QUALITY ASSURANCE A. The installation of storm water drainage structure and swale will be monitored by the CQA Consultant as required by the CQA Plan. B. The CQA Consultant will perform material conformance testing and installation quality control testing during construction of drainage structure and swale as required by the CQA Plan. C. The CONTRACTOR shall be aware of the activities required of the CQA Consultant by the CQA Plan and account for these activities in the construction schedule. D. The CONTRACTOR shall correct all deficiencies and non-conformances identified by the CQA Consultant at no additional cost to the Owner. PART 2 PRODUCTS 2.01 CULVERTS AND FITTINGS A. Furnish ADS N-12 (water-tight) high density polyethylene (“HDPE”) corrugated plastic pipe (CPP) and fittings or ENGINEER approved equivalent. Section 33 42 13: Pipe Culverts Sutton Removal Plan, Rev 0 GC5770\33 42 13 Pipe Culverts.doc 33 42 13-3 December 2015 2.02 CULVERT OUTLET AND INLET PROTECTION A. Furnish riprap meeting the requirements of Section 31 37 00. 2.03 EQUIPMENT A. Furnish all equipment necessary to perform the Work specified in this Section. PART 3 EXECUTION 3.01 INSTALLATION A. Install culverts as shown on the Construction Drawings. B. Examine culverts and joint materials before installation for damage. Reject damage materials. Install culverts in accordance with Manufacturer’s installation recommendations and as approved by the ENGINEER. C. Prior to culvert installation, complete trenching and place pipe embedment fill in accordance with Section 31 23 33 unless otherwise shown on the Construction Drawings. D. Install CPP culverts to the lines and grades shown on the Construction Drawings. E. Install joints for CPP culverts in accordance with the Manufacturer's recommendations. F. After installation of the culverts, perform trench backfilling as specified in Section 31 23 33. G. Culvert inlet and outlet protection shall be placed as shown on the Construction Drawings. 3.02 SURVEY CONTROL A. Survey the final locations and invert elevations of the culverts in accordance with Section 02 21 00. 3.03 TOLERANCE A. Install culverts, and inlet structures within ±0.1 feet of the invert elevations indicated on the Drawings and to provide positive drainage at all times. [END OF SECTION] Section 33 49 00: Storm Water Structures and Swales Sutton Removal Plan, Rev 0 GC5770\33 49 00 Storm Water Structures Swales.docx 33 49 00-1 December 2016 SECTION 33 49 00 STORM WATER STRUCTURES AND SWALES PART 1 GENERAL 1.01 SCOPE A. This section includes the requirements for products and installation of storm water drainage structures and swales. 1.02 RELATED SECTIONS AND PLANS A. Section 31 00 00 - Earthwork B. Section 31 23 33 - Trenching and Backfilling C. Section 31 05 16 - Granular Drainage Materials D. Section 31 37 00 - Riprap E. Construction Quality Assurance (CQA) Plan 1.03 REFERENCES A. AASHTO M294 - Standard Specification for Corrugated Polyethylene Pipe, 300- to 900-mm (12- to 36-in.) Diameter. B. Guidelines for Drainage Studies and Hydraulic Design, North Carolina Division of Highways, March 1999 C. ASTM D 2412 - Test Method for Determination of External Loading Characteristics of Plastic Pipe by Parallel-Plate Loading. 1.04 SUBMITTALS A. Submit shop drawings for pre-cast concrete storm water drainage structures to the ENGINEER for approval a minimum of 30 days prior to use. B. The CONTRACTOR shall submit to the ENGINEER the Manufacturer’s certification of compliance with these Specifications for all materials delivered to the site and shall comply with the pipe Manufacturer’s recommendations for handling, storing, and installing pipes and fittings. C. Submit shop drawings for concrete headwall and thrust block to the ENGINEER for approval a minimum of 30 days prior to construction. 1.05 CONSTRUCTION QUALITY ASSURANCE A. The installation of storm water drainage structure and swale will be monitored by the CQA Consultant as required by the CQA Plan. Section 33 49 00: Storm Water Structures and Swales Sutton Removal Plan, Rev 0 GC5770\33 49 00 Storm Water Structures Swales.docx 33 49 00-2 December 2016 B. The CQA Consultant will perform material conformance testing and installation quality control testing during construction of drainage structure and swale as required by the CQA Plan. C. The CONTRACTOR shall be aware of the activities required of the CQA Consultant by the CQA Plan and account for these activities in the construction schedule. D. The CONTRACTOR shall correct all deficiencies and non-conformances identified by the CQA Consultant at no additional cost to the Owner. PART 2 PRODUCTS 2.01 MATERIALS A. The concrete junction box shall conform to Guidelines for Drainage Studies and Hydraulic Design (March 1999). B. Furnish corrugated HDPE pipe with diameter as indicated on the Construction Drawings and meeting the following requirements: 1. Pipe shall comply with AASHTO M294 Type “C” and shall be constructed of new polyethylene compounds which meet the minimum cell classification of 323410C or 333410B as defined and described in ASTM D 3550. Compounds that have a higher cell classification in one or more properties are acceptable provided the product requirements are met. 2. The minimum parallel plate stiffness values when tested in accordance with ASTM 2412 shall be 30-psi (0.21-Mpa). 3. The pipe shall be homogeneous throughout and free of foreign inclusions and visible defects. C. Furnish HDPE pipe fittings, as needed, based on the CONTRACTOR’s shop drawings that meet the following requirements: 1. Fittings shall not reduce or impair the overall integrity or function of the pipeline. 2. Only fittings supplied or recommended by the manufacturer shall be used. 3. Fittings for corrugated HDPE pipe shall comply with material requirements for the corrugated HDPE pipe. 4. Fittings shall be free of foreign inclusions and visible defects. D. The concrete headwall shall conform to Index No. 250 of the Guidelines for Drainage Studies and Hydraulic Design (March 1999). Section 33 49 00: Storm Water Structures and Swales Sutton Removal Plan, Rev 0 GC5770\33 49 00 Storm Water Structures Swales.docx 33 49 00-3 December 2016 PART 3 PART 3 EXECUTION 3.01 PREPARATION A. All excavation, shoring, and storm water control required for the construction of drainage structures shall be performed in accordance with Section 31 00 00. B. Excavation shall be to the required depth. Over-excavated areas shall be backfilled with general fill material, properly compacted as specified in Sections 31 00 00 and Section 31 23 33. 3.02 INSTALLATION A. Drainage Structures 1. Set drainage structures at the proper elevation with proper bearing on a suitable foundation. 2. Pipe openings shall be neatly cut two inches larger than the outside diameter of the pipe. Fill openings around pipe with non-shrink grout to provide a smooth watertight joint between structure and pipe. 3. Opening for the upstream pipe shall be covered with a piece of plywood for future use. 4. Cut pipe entering the structure to the correct length prior to installation. Removal of excess pipe in structure after installation will not be acceptable. 5. All backfilling required for the installation of drainage structures shall be performed in accordance with Section 31 23 33. 3.03 SURVEY CONTROL A. Survey the location and elevation of all storm water drainage structures and the lines, slopes, and grades in accordance with Section 02 21 00. 3.04 TOLERANCE A. Install drainage swales and structures to within ±0.1 ft of elevations indicated on the Construction Drawings or as directed by the ENGINEER. [END OF SECTION] Section 34 71 00: Road Construction Sutton Removal Plan, Rev 0 GC5770\34 71 00 Road Construction.docx 34 71 00-1 December 2015 SECTION 34 71 00 ROAD CONSTRUCTION PART 1 GENERAL 1.01 SCOPE A. This section describes the requirements for constructing the roads as indicated on the Construction Drawings. 1.02 RELATED SECTIONS AND PLANS A. Section 02 21 00 - Surveying B. Section 31 00 00 – Earthwork C. Section 31 31 19 - Vegetation D. Construction Quality Assurance (CQA) Plan 1.03 REFERENCES A. Latest version of American Society of Testing and Materials (ASTM) standards and other standards noted in this specification. 1.04 SUBMITTALS A. At least 14 days prior to the start of road construction, the CONTRACTOR shall provide for ENGINEER’s review the equipment and construction method for placing and compacting the road materials. B. For each source of the base material, submit the following to the ENGINEER for review at least 21 calendar days prior to road construction: 1. source of the material; 2. test results conducted on three samples of the material which demonstrates the material meets the requirements of the NCDOT Specifications; and 3. a 50-pound representative sample of the proposed material. 1.05 CONSTRUCTION QUALITY ASSURANCE A. The construction of the roads will be monitored by the ENGINEER as required by the CQA Plan. B. The CQA Consultant will perform material conformance testing and installation quality control testing during road construction as required by the CQA Plan. Section 34 71 00: Road Construction Sutton Removal Plan, Rev 0 GC5770\34 71 00 Road Construction.docx 34 71 00-2 December 2015 C. The CONTRACTOR shall be aware of the activities required by the CQA Consultant in the CQA Plan and account for these activities in the construction schedule. D. The CONTRACTOR shall correct all deficiencies and non-conformances identified by the CQA Consultant at no additional cost to the OWNER. PART 2 PRODUCTS 2.01 MATERIALS A. Furnish base material for the road and other roads meeting the requirements of Subgrades, Bases, and Shoulders, Division 5, Section 520 of the NCDOT Specifications. CONTRACTOR shall submit reports of testing and supplier certifications showing that base material meets this section at least 21 days before material is delivered to the site. B. Furnish embankment material and prepared subbase materials for the roads meeting the requirements of general fill material in Section 31 00 00 from designated borrow area or other areas as directed by the ENGINEER. 2.02 EQUIPMENT A. Furnish, operate, and maintain equipment necessary to construct roads in accordance with the requirements of this section. B. Use Caterpillar CS 563 or equivalent self-propelled vibratory compactor, as approved by the ENGINEER, for compacting the subgrade, embankment, and base materials. PART 3 EXECUTION 3.01 ROADS A. The roads shall be constructed to the thickness, grades, lines, and limits indicated on the Construction Drawings. B. The base materials shall be placed in two equal lifts and compacted to the grades, lines, and limits indicated on the Construction Drawings and compacted in accordance with this Section. 3.02 COMPACTION REQUIREMENTS AND TEST FREQUENCIES A. Embankment materials for roads shall be compacted to 95 percent of maximum dry density determined by ASTM D 698. Construction quality control tests will be performed by the CQA Consultant at a minimum Section 34 71 00: Road Construction Sutton Removal Plan, Rev 0 GC5770\34 71 00 Road Construction.docx 34 71 00-3 December 2015 frequency of one test for every 200 linear feet per lift or as directed by the ENGINEER. B. Prepared subbase for roads shall be compacted to 98 percent of maximum dry density determined by ASTM D 698. Construction quality control tests will be performed by the CQA Consultant at a minimum frequency of one test for every 200 linear feet per lift or as directed by the ENGINEER. C. Base course materials for roads shall be compacted to 95 percent of maximum dry density determined by ASTM D 698 or as directed by the ENGINEER. Construction quality control tests will be performed by the CQA Consultant at a minimum frequency of one test for every 200 linear feet per lift or as directed by the ENGINEER. 3.03 SURVEY CONTROL A. Survey the grades, lines, and limits of the roads construction in accordance with Section 02 21 00 to verify compliance with the Construction Drawings. 3.04 TOLERANCES A. Place and compact embankment materials and base materials to ± 0.1 ft of the elevations indicated on the Construction Drawings. B. Construct the roads to within ±0.1 ft of the final grades and slopes indicated on the Construction Drawings. [END OF SECTION]