HomeMy WebLinkAboutIH8119_20240418_Trust budget approvalFrom:Brian Loffman
To:Moore, Thomas
Subject:RE: [External] LECT: Charlotte Site - 2024 Budget Amendment 2024-01
Date:Thursday, April 18, 2024 9:54:56 AM
CAUTION: External email. Do not click links or open attachments unless verified. Report suspicious emails with the
Report Message button located on your Outlook menu bar on the Home tab.
Thomas,
Thank you for the quick review and approval.
Brian K. Loffman
Senior Program Manager | LE PETOMANE, INC
Direct 702.960.4301 | Cell 702.372.3153
510 S. Fourth Street, Henderson, NV 89015
brian.loffman@lepetomaneinc.com
From: Moore, Thomas <thomas.moore@deq.nc.gov>
Sent: Thursday, April 18, 2024 4:28 AM
To: Brian Loffman <brian.loffman@lepetomaneinc.com>
Subject: RE: [External] LECT: Charlotte Site - 2024 Budget Amendment 2024-01
Brian, the 2024 Budget Amendment 2024-01 is approved. I hope you have a great rest of the
week. Thomas
Thomas Moore
Hydrogeologist
NC Department of Environmental Quality, Winston-Salem Regional Office
Division of Waste Management, Superfund Section-IHSB Western Region
450 West Hanes Mill Road, Suite 300
Winston-Salem, NC 27105-7407
Work/mobile (919) 508-7121
Email: Thomas.moore@DEQ.NC.GOV
From: Brian Loffman <brian.loffman@lepetomaneinc.com>
Sent: Wednesday, April 17, 2024 2:11 PM
To: Moore, Thomas <thomas.moore@deq.nc.gov>
Cc: Andrew Steinberg <andrew.steinberg@lepetomaneinc.com>; Mark Hatch
<mark.hatch@lepetomaneinc.com>
Subject: [External] LECT: Charlotte Site - 2024 Budget Amendment 2024-01
CAUTION: External email. Do not click links or open attachments unless verified. Report suspicious emails with the
Report Message button located on your Outlook menu bar on the Home tab.
Good afternoon, Thomas
The Lyondell Environmental Custodial Trust (Trust) is pleased to submit the attached Charlotte
Site Environmental Budget Amendment 2024-01 (Amendment) for the North Carolina
Department of Environmental Quality (NCDEQ) review and approval.
As you are aware, the Trust submitted the 2024 budget on November 2, 2023 and was
subsequently approved by the NCDEQ on January 9, 2024. At the time of budget preparation
in late 2023, and through conversations with Arcadis, it was thought that substantial
completion of the remediation system would be completed and billed by December 31, 2023.
Thus, the 2024 budget did not include a carry over to fund remedial action implementation.
As noted in the 2024 budget transmittal, see below:
Consistent with prior years, the Budget includes the “Environmental Activities as
Directed by the Trust” contingency line item to fund currently undefined scopes of work
to be utilized as required to advance the project. Although it is anticipated that the
remedy construction/system start-up will occur in 2023, this line item would also fund
any minor increase in remedy related subcontractor or material costs that may occur
for remaining 2023 implementation efforts or the unlikely event final completion
extends into early 2024. To accommodate this potential, this budget line item has been
increased in 2024 to $150,000 from the $50,000 established in 2023.
Absent the continued permitting and contractor delays in Q4 2023 as documented in the
monthly project summaries provided by Arcadis, substantial completion of the system
installation would have been finished last year. As you are aware, system installation will be
completed this year and is on track for start-up/shakedown before the end of this month. As a
result of the greater effort required in 2024, and beyond the $150,000 in the Trust held
contingency line item, this Amendment is to fund the Remedial Action Implementation line
item with $250,000 to allow Arcadis to complete the system construction and start-up. Please
note this Amendment does not constitute a request for additional funding, rather this
Amendment is to include $250,000 of previously approved and unutilized portion of the 2023
Remedial Action Implementation line item which amounted to $458,900 due to the Q4 2023
delays. Please note that through this adjustment, the actual implementation cost of the
remedy will not exceed the remedy implementation budget established in 2022.
Please indicate, via reply email, if NCDEQ approves the attached 2024 Amendment. Should
you have questions or comments regarding the budget or site status/forward path, I would be
more than happy to discuss them with you.
Thank you,
Brian K. Loffman
Senior Program Manager | LE PETOMANE, INC
Direct 702.960.4301 | Cell 702.372.3153
510 S. Fourth Street, Henderson, NV 89015
brian.loffman@lepetomaneinc.com
Email correspondence to and from this address may be subject to the North Carolina Public Records Law and may be disclosed to thirdparties by an authorized state official.
TRUSTEE SITE COUNTY : STATE
CHARLOTTE SITE ENVIRONMENTAL BUDGET AMENDMENT
24-01
Trust Environmental Services
ꞏTrust services relating to environmental remediation and restoration
ꞏEnvironmental Activities as Directed By the Trust
Trust Legal Services
ꞏEnvironmental legal services rendered for the site
Environmental Site Consultant
ꞏSite maintenance, inspections and security
ꞏRemedial Action Implementation 250,000$
ꞏRemedial Action Completion Report, Groundwater Monitoring and Reporting
ꞏO&M Biosparge & SVE Systems
Lead Government Agency
Environmental Budget Site Totals 250,000$
To be paid from the Charlotte Site Environmental Account
Le Petomane XXIII Inc., Not
Individually, But Solely as Trustee CHARLOTTE MECKLENBURG:NC (336) 776-9678
AMENDMENT 24-01
2024 LYONDELL ENVIRONMENTAL CUSTODIAL TRUST BUDGET
LEAD GOVERNMENT AGENCY STATUS / VERSION
4/17/2024
Approved 1/9/24
AMENDED
TOTAL BUDGET
25,000$ 25,000$
150,000$ 150,000$
25,000$ 25,000$
15,000$ 15,000$
170,000$
155,000$
565,000$ 815,000$
-$ 250,000$
170,000$
155,000$
25,000$ 25,000$