Loading...
HomeMy WebLinkAbout22040_Metromont Vapor Intrusion Mitigation Plan Rev1_20231019Via Email October 19, 2023 NCDEQ – Division of Waste Management Brownfields Redevelopment Section 1646 Mail Service Center Raleigh, North Carolina 27699-1646 Attn: Mr. Bill Schmithorst Re: Vapor Intrusion Mitigation Plan – Revision 1 Sugar Creek Multifamily Apartments Metromont Concrete Facility Charlotte, North Carolina Brownfields Project No. 22040-18-060 H&H Project No. S2K-001 Dear Bill: On behalf of S2K Charlotte QOZB LLC (S2K Charlotte), please find the enclosed Vapor Intrusion Mitigation Plan (VIMP) – Revision 1 prepared for the above-referenced Site. The VIMP has been revised based on comments provided via email by DEQ Brownfields on October 6, 2023. Should you have questions or need additional information, please do not hesitate to contact us at (704) 586- 0007. Sincerely, Hart & Hickman, PC Matt Vawter, PE Haley Martin, PG Project Engineer Senior Project Geologist Enclosure: cc: Mr. Dan Wendover, CapRock (via email) Mr. Trinh DeSa, PE, Hart & Hickman, PC (via email) #C-1269 Engineering #C-245 Geology Vapor Intrusion Mitigation Plan Sugar Creek Multifamily Apartments - Revision 1 Metromont Concrete Facility Greensboro Street & Sugar Creek Road Charlotte, North Carolina Brownfields Project No. 22040-18-060 H&H Job No. S2K-001 August 29, 2023 Revised October 19, 2023 i https://harthick.sharepoint.com/sites/masterfiles-1/shared documents/aaa-master projects/s2k charlotte/metromont concrete facility/vimp/rev. 1/to deq/22040 - vapor intrusion mitigation plan_metromont concrete facility_rev. 1.doc Vapor Intrusion Mitigation Plan – Revision 1 Sugar Creek Multifamily Apartments Metromont Concrete Facility Charlotte, North Carolina Brownfields Project No. 22040-18-060 H&H Job No. S2K-001 Table of Contents 1.0 Introduction ................................................................................................................ 1  1.1 Background............................................................................................................2  1.2 Summary of Previous Environmental Assessment Activities ...............................2  1.3 Brownfields Assessment Activities .......................................................................6  1.4 Vapor Intrusion Risk Evaluation ...........................................................................8  2.0 Design Basis .............................................................................................................. 11  2.1 Base Course Layer and Vapor Barrier .................................................................13  2.2 Horizontal Collection Piping and Vertical Riser Piping .....................................15  2.3 Monitoring Points ................................................................................................16  2.4 General Installation Criteria ................................................................................17  3.0 Quality Assurance / Quality Control ...................................................................... 19  4.0 VIMS Effectiveness Testing .................................................................................... 20  4.1 Influence Testing .................................................................................................20  4.2 Pre-Occupancy Sub-Slab Soil Gas Sampling ......................................................20  4.3 Indoor Air Sampling (If Warranted) ....................................................................22  4.4 VIMS Effectiveness Results ................................................................................24  5.0 VIMS Effectiveness Monitoring ............................................................................. 26  6.0 Future Tenants & Building Uses ............................................................................ 27  7.0 Reporting .................................................................................................................. 28  ii https://harthick.sharepoint.com/sites/masterfiles-1/shared documents/aaa-master projects/s2k charlotte/metromont concrete facility/vimp/rev. 1/to deq/22040 - vapor intrusion mitigation plan_metromont concrete facility_rev. 1.doc Figures Figure 1 Site Location Map Figure 2 Site Map Figure 3 Sample Location Map Figure 4 Compound Concentration Map Appendices Appendix A Vapor Intrusion Mitigation Design Drawings Appendix B Previous Assessment Data Summary and Excerpts Appendix C Product Specification Sheets & Installation Instruction 1 https://harthick.sharepoint.com/sites/masterfiles-1/shared documents/aaa-master projects/s2k charlotte/metromont concrete facility/vimp/rev. 1/to deq/22040 - vapor intrusion mitigation plan_metromont concrete facility_rev. 1.doc Vapor Intrusion Mitigation Plan – Revision 1 Sugar Creek Multifamily Apartments Metromont Concrete Facility Charlotte, North Carolina Brownfields Project No. 22040-18-060 H&H Job No. S2K-001 1.0 Introduction On behalf of S2K Charlotte QOZB LLC (S2K Charlotte), Hart & Hickman, PC (H&H) has prepared this Vapor Intrusion Mitigation Plan (VIMP) for installation of a vapor intrusion mitigation system (VIMS) during construction of a proposed apartment building at the Metromont Concrete Facility Brownfields property (Brownfields Project No. 22040-18-060). Comments from the North Carolina Department of Environmental Quality (DEQ) to the VIMP – Revision 0 dated August 29,2023 were received on October 6, 2023, and responses and revisions to the comments are included herein. The Brownfields property is located at 3927, 4101, and 4109 Greensboro Street and 200 E. Sugar Creek Road in Charlotte, Mecklenburg County, North Carolina (Site). The Site consists of three contiguous parcels (Mecklenburg County Parcel identification Nos. {PINs} 09108106, 0910899, and 19108126) that collectively total approximately 18.3 acres of land located in a rapidly densifying area of the NoDa neighborhood in close proximity to the LYNX Blue Line light rail corridor and uptown Charlotte. A Site location map is provided as Figure 1, and the Site and surrounding area are shown in Figure 2. To address potential environmental concerns associated with historical on-Site and nearby off- Site operations, the Site was entered into the Brownfields Redevelopment Section and received a Letter of Eligibility dated July 6, 2018. Following completion of assessments and risk evaluations, a Notice of Brownfields Property was recorded on the property deed on December 2, 2019. Redevelopment of the Brownfields property will be completed in phases. This VIMP has been prepared for a high-density multifamily apartment building proposed for construction on the 2 https://harthick.sharepoint.com/sites/masterfiles-1/shared documents/aaa-master projects/s2k charlotte/metromont concrete facility/vimp/rev. 1/to deq/22040 - vapor intrusion mitigation plan_metromont concrete facility_rev. 1.doc westernmost Site parcel (PIN 09108106) known as Sugar Creek Multifamily Apartments. The ground level components of the proposed seven-story residential apartment building will include living spaces, amenity areas, a leasing office, a courtyard, and a parking garage. Details of the proposed building are shown in VIMS design sheets provided in Appendix A, and an overlay of the proposed apartment building is shown in Figure 3. Redevelopment plans for the central and eastern portions of the Site have not been finalized. A VIMP for future buildings proposed for construction in other portions of the Brownfields property will be submitted to DEQ for review and approval under separate cover. 1.1 Background The Site was predominantly undeveloped wooded land until the 1950s when the Site was developed with concrete manufacturing buildings. The Site was utilized as a concrete manufacturing facility by multiple tenants from the early to mid-1950s until approximately 1997. The Site was occupied by Exposaic Industries, Inc. (Exposaic) until 1995 and Metromont Corporation (Metromont) for structural pre-cast concrete manufacturing operations from 1995 until February 2019. In 2019, the southwestern portion of the Site was temporarily utilized by a contractor for the City of Charlotte, Johnson Brothers, Inc., as a temporary staging location for equipment, materials, rails, poles, and pre-cast concrete used for installation of the light rail. In 2022, the concrete manufacturing buildings were razed and limited grading and excavations for the installation of a stormwater collection and retention system were completed. The stormwater infrastructure activities were completed in accordance with the DEQ-approved Environmental Management Plan dated July 25, 2022. The Site is currently vacant undeveloped land with foundations and remnants of select former concrete manufacturing structures. 1.2 Summary of Previous Environmental Assessment Activities H&H reviewed several reports to obtain additional information and document previous environmental assessments completed at the Site. A brief summary of the sampling activities 3 https://harthick.sharepoint.com/sites/masterfiles-1/shared documents/aaa-master projects/s2k charlotte/metromont concrete facility/vimp/rev. 1/to deq/22040 - vapor intrusion mitigation plan_metromont concrete facility_rev. 1.doc and results pertinent to potential vapor intrusion for the proposed apartment building is provided below. Pertinent historical analytical documentation is provided in Appendix B. 1995 UST Closure Activities A UST Closure Report prepared by Trigon Engineering Consultants, Inc. (Trigon) on September 15, 1995 indicates that Exposaic operations at the Site included use of the following USTs: o Tank No. 1 – 8,000-gallon diesel UST installed in April 1960 o Tank No. 2 – 8,000-gallon gasoline UST installed in April 1975 o Tank No.3 – 8,000-gallon fuel oil UST installed in April 1962 o Tank No. 4 – 6,000-gallon fuel oil UST installed in April 1954 Information provided in the UST Closure Report indicates that Trigon removed Tank No. 1, Tank No. 2, and Tank No. 3 in August 1995. Tank No. 4 was closed in-place by filling the UST with concrete due to inaccessibility for heavy machinery needed to remove the tank. The approximate locations of the former USTs are shown in Figure 3. During removal of the tanks, Trigon observed evidence of a release to soil beneath Tank No. 1 and beneath the dispenser adjacent to Tank No. 2. No apparent petroleum contamination was observed in the Tank No. 3 UST basin. Approximately 25 cubic yards of potentially impacted soil was excavated from the Tank No. 1 diesel UST basin and approximately 5 cubic yards of potentially impacted soil was excavated from the Tank No. 2 gasoline UST dispenser system area. Laboratory analytical results of UST closure soil samples indicated that total petroleum hydrocarbons as diesel range organics (TPH-DRO) were detected above the laboratory reporting limits in soil samples collected beneath the Tank No. 3 fuel oil UST (274 milligrams per kilogram [mg/kg]) and beneath the Tank No. 2 gasoline UST dispenser system (761 mg/kg). TPH concentrations were not detected above the laboratory reporting limits for closure soil samples collected for the Tank No. 1 and Tank No. 2 UST basins. Phase III Groundwater Assessment 4 https://harthick.sharepoint.com/sites/masterfiles-1/shared documents/aaa-master projects/s2k charlotte/metromont concrete facility/vimp/rev. 1/to deq/22040 - vapor intrusion mitigation plan_metromont concrete facility_rev. 1.doc H&H reviewed a Phase III Groundwater Assessment report prepared by J.L. Rodgers and Callcott Engineers, Inc. (R&C) dated May 1996. Information provided in the report indicates that in July 1996, groundwater samples were collected from five groundwater monitoring wells and submitted for laboratory analysis of volatile organic compounds (VOCs) and Acid/Base Neutral Extractables. Laboratory analytical results indicated that naphthalene (22 micrograms per liter [µg/L]), 1,2,4- trimethylbenzene (11 µg/L), and 2-methylnaphthalene (25 µg/L) were detected at concentrations above the laboratory reporting limits in a groundwater sample (MW-1) collected in the vicinity of the abandoned fuel oil UST (Tank No. 4). The naphthalene concentration exceeded the DEQ 2L Groundwater Quality Standard (2L Standard) of 6 µg/L. No other compounds were detected at concentrations exceeding the 2L Standards in the July 1996 groundwater samples collected at the Site. Based on results of the UST closure activities completed at the Site by Trigon and the subsequent assessment activities completed at the Site by R&C, the DEQ UST Section Guidelines indicated that a Phase I Limited Site Assessment (LSA) should be performed to further evaluate risks associated with the release incident (Incident No. 15459). 2018 Phase I and II ESA In 2018, ECS Southeast, LLP (ECS) completed a Phase I and Phase II Environmental Site Assessment (ESA) activities at the Site to further evaluate the potential for impacts from on-Site and nearby off-Site operations. As part of Phase II ESA activities, ECS collected four (4) soil samples (SB-1, SB-3, SB-5, and SB-6) and the three (3) groundwater samples (GW-1, GW-4, and GW-6) for laboratory analysis. Soil laboratory analytical results did not identify TPH at concentrations exceeding the DEQ UST Section Action Levels in the Phase II ESA soil samples collected at the Site. Groundwater sample laboratory analytical results indicate that several compounds were detected at concentrations above the laboratory reporting limits in the groundwater sample collected in the northwestern and downgradient portion of the Site (GW-1). Several chlorinated compounds 5 https://harthick.sharepoint.com/sites/masterfiles-1/shared documents/aaa-master projects/s2k charlotte/metromont concrete facility/vimp/rev. 1/to deq/22040 - vapor intrusion mitigation plan_metromont concrete facility_rev. 1.doc including trichloroethene (TCE), cis-1,2-dichloroethene, and vinyl chloride were detected at concentrations exceeding the DEQ groundwater screening criteria in the groundwater sample collected from GW-1. No compounds were detected at concentrations above the DEQ groundwater screening criteria in GW-4 and GW-6, located in the eastern and southern portions of the Site, respectively. Phase I LSA In January and February 2019, H&H completed Phase I LSA soil and groundwater sampling activities at the Site to further the potential for impact in the areas of the three former USTs and the abandoned UST. Soil and groundwater samples were collected from each LSA soil boring/temporary monitoring well and submitted for laboratory analyses in accordance with the DEQ UST Section Guidelines based on the use of each former tank. Sampling activities and results are provided in a Phase I Limited Site Assessment Report prepared by H&H and dated March 18, 2019. A brief summary of the Phase I LSA sampling results is provided below. Soil samples were collected from depths corresponding to the base of the excavated and abandoned USTs as observed and reported by Trigon during tank closure activities completed in 1995. Soil sample analytical results indicate that no compounds were detected at concentrations exceeding the DEQ UST Section Maximum Soil Contaminant Concentrations (MSCCs) in the LSA soil samples. Laboratory analytical results indicate that low levels of several petroleum-related compounds were detected at concentrations above the laboratory method detection limits, but below the DEQ UST Section Groundwater Quality Standards (GWQSs) in the area of each former UST. In addition, low levels of the tentatively identified compounds (TICs) elcosene (25 micrograms per liter [µg/L]) and vanillin (14 µg/L) were detected at concentrations above the laboratory method detection limits in the TW-1 groundwater sample collected downgradient of the former diesel UST (Tank No.1). No GWQS has been established for elcosene and vanillin. A low level (2.6 µg/L) of the chlorinated solvent tetrachloroethylene (PCE) was detected at a concentration above the GWQS of 0.7 µg/L in groundwater sample TW-2 collected downgradient of the former gasoline tank (Tank No. 2). No other target compounds were 6 https://harthick.sharepoint.com/sites/masterfiles-1/shared documents/aaa-master projects/s2k charlotte/metromont concrete facility/vimp/rev. 1/to deq/22040 - vapor intrusion mitigation plan_metromont concrete facility_rev. 1.doc detected above applicable groundwater standards. No compound concentrations exceeded DEQ- defined Gross Contamination Levels (GCLs). Based on results of the Phase I LSA and following recordation of a groundwater use restriction on the property deed, the DEQ UST Section issued a No Further Action letter for the release incident dated July 10, 2019. 1.3 Brownfields Assessment Activities To address environmental concerns associated with historical on-Site operations, the Site was entered into the DEQ Brownfields Redevelopment Section and received an eligibility in a letter dated July 6, 2018. A kick-off/data gap meeting with DEQ Brownfields personnel was held on September 20, 2018, to discuss historical uses of the Site, available environmental information, proposed redevelopment plans, data gaps, and the proposed schedule for completing the Brownfields Agreement. Based on review of available information from previous assessments and the residential nature of the proposed redevelopment of the Site, DEQ Brownfields personnel requested additional data gap assessment. To address DEQ Brownfields requests for Site assessment activities, H&H submitted a Brownfields Assessment Work Plan (Work Plan) which received DEQ approval in an email dated January 22, 2019. Brownfields assessment activities were completed at the Site in January and February 2019, and the results of the assessment are documented in the Brownfields Assessment Report prepared by H&H and dated March 12, 2019. A brief summary of the Brownfields assessment activities and results is provided below. Brownfields assessment activities included the collection of soil, groundwater, and soil gas samples for laboratory analysis to further evaluate subsurface conditions for potential impacts and to evaluate risks associated with residential redevelopment of the Site. The 2019 Brownfields assessment sample locations are shown in Figure 3 and Figure 4 and a summary of the sampling activities and results is provided below. 7 https://harthick.sharepoint.com/sites/masterfiles-1/shared documents/aaa-master projects/s2k charlotte/metromont concrete facility/vimp/rev. 1/to deq/22040 - vapor intrusion mitigation plan_metromont concrete facility_rev. 1.doc Soil Assessment Activities H&H collected four (4) soil samples near former USTs and historical acid wash operations (TW- 1 through TW-4). H&H also collected two (2) shallow background soil samples to establish Site-specific background concentrations for naturally occurring metals. Laboratory analytical results did not identify organic compounds at concentrations above the DEQ Residential Preliminary Soil Remediation Goals (PSRGs) in the soil samples collected during 2019 Brownfields assessment activities. Several metals were detected at concentrations above laboratory reporting limits but below the DEQ PSRGs and consistent with Site-specific ranges for naturally occurring metals. In summary, results of soil assessment activities completed at the Site indicate that there is no evidence of a significant release in the area of the former USTs or in the area of former acid wash operations, and Site soils do not appear to pose a potential vapor intrusion risk to the proposed apartment building. Groundwater Assessment Activities Nine (9) temporary groundwater monitoring wells (TW-1 through TW-9) were installed at the Site in the areas of the former USTs and historical acid wash operations, along upgradient Site boundaries, and near former temporary well GW-1 located in the northwestern and downgradient portion of the Site to confirm the presence of chlorinated solvent impacts reported by others. As depicted in Figure 3, temporary monitoring wells TW-3 and TW-8 were located nearest to the proposed apartment building. With the exception of low-level aliphatic hydrocarbon fractions in the TW-3 groundwater sample, results of groundwater sampling did not identify organic compounds at concentrations above the DEQ Residential Vapor Intrusion Groundwater Screening Levels (GWSLs) in the TW-3 and TW-8 samples. Several metals were detected at concentration above the laboratory method detection limits, but below the 2L Groundwater Standards. Mercury was not detected at concentrations above the laboratory detection limits in the groundwater samples collected during 2019 Brownfields assessment activities. 8 https://harthick.sharepoint.com/sites/masterfiles-1/shared documents/aaa-master projects/s2k charlotte/metromont concrete facility/vimp/rev. 1/to deq/22040 - vapor intrusion mitigation plan_metromont concrete facility_rev. 1.doc Groundwater sample analytical results for remaining temporary monitoring wells identified low level chlorinated solvent impacts in the northwestern portion of the Site (TW-7) where redevelopment is not planned at this time. The chlorinated compounds TCE (2.8 µg/L) and vinyl chloride (0.95 J µg/L) were detected at concentrations above their respective DEQ Residential Vapor Intrusion GWSLs. In addition, a low level of PCE was detected in a groundwater sample (TW-2) collected in the east-central portion of the Site at a concentration below the DEQ Residential Vapor Intrusion GWSL. No other organic compounds were detected at concentrations exceeding the regulatory screening criteria in the groundwater samples. Exterior Soil Gas Sampling To address the potential for structural vapor intrusion into proposed Site buildings, H&H completed exterior soil gas assessment activities within the footprint of proposed buildings in the southwestern portion of the Site. Note that the proposed redevelopment plan has changed since completion of the 2019 Brownfields assessment activities. Four exterior soil gas points (SG-1 through SG-4) were installed in the southwestern portion of the Site to identify potential constituents that may pose a potential vapor intrusion risk (Figure 3). Results of four soil gas samples identified benzene in two (2) soil gas samples (SG-1 and SG-2) at concentrations above the DEQ Residential Vapor Intrusion Soil Gas Screening Level (SGSL). No other VOCs were detected at levels above the DEQ Vapor Intrusion SGSLs, including TCE and related chlorinated compounds. 1.4 Vapor Intrusion Risk Evaluation The DEQ Vapor Intrusion Screening Levels are conservative and based upon a Target Cancer Risk (TCR) of 1 x 10-6 for potential carcinogenic effects and a Target Hazard Quotient (THQ) of 0.2 for potential non-carcinogenic effects. Vapor intrusion mitigation or additional assessment is not typically warranted if the calculated cumulative lifetime incremental carcinogenic risk (LICR) is 1 x 10-4 or less and the acceptable level for non-carcinogenic risk is a calculated cumulative hazard index (HI) of 1.0 or less. 9 https://harthick.sharepoint.com/sites/masterfiles-1/shared documents/aaa-master projects/s2k charlotte/metromont concrete facility/vimp/rev. 1/to deq/22040 - vapor intrusion mitigation plan_metromont concrete facility_rev. 1.doc H&H utilized the DEQ Risk Calculator (January 2023) for residential land use scenarios to further evaluate potential cumulative risks for structural vapor intrusion based on results of soil gas samples collected at the Site. Risk calculator results for soil gas samples indicate that under a hypothetical worst-case scenario for the soil gas to indoor air vapor intrusion pathway the cumulative LICR is 2.5 x 10-6 and the cumulative HI is 0.20, which are below the unacceptable risk thresholds. Copies of the completed DEQ Risk Calculators are provided in Appendix B. Based on review of the laboratory analytical data and risk evaluation results, potential structural vapor intrusion for the proposed apartment building can be managed through installation of passive vapor intrusion mitigation system during construction of the proposed residential building. Additionally, installation of the VIMS is anticipated to satisfy the Land Use Restriction (LUR) 15.g., which generally states that no enclosed building may be constructed on the Brownfields property until DEQ determines that the building is or would be protective of the building’s users, public health, and the environment from risk of vapor intrusion. S2K Charlotte plans to install a passive VIMS during construction of the proposed residential building. The VIMS described herein has been designed with the capability to be converted to an active sub-slab depressurization system with electrically driven fans, if warranted based on results of post-installation VIMS efficacy sampling. 10 https://harthick.sharepoint.com/sites/masterfiles-1/shared documents/aaa-master projects/s2k charlotte/metromont concrete facility/vimp/rev. 1/to deq/22040 - vapor intrusion mitigation plan_metromont concrete facility_rev. 1.doc Engineer’s Certification According to the DWM Vapor Intrusion Guidance: “Risk-based screening is used to identify sites or buildings likely to pose a health concern, to identify buildings that may warrant immediate action, to help focus site-specific investigation activities or to provide support for building mitigation and other risk management options including remediation.” In addition, this VIMP was prepared to satisfy the standard vapor intrusion mitigation provisions included in the Notice of Brownfields Property recorded for the Site. Per the North Carolina Brownfields Property Reuse Act 130A-310.32, a prospective developer, with the assistance of H&H for this project, is to provide NCDEQ with “information necessary to demonstrate that as a result of the implementation of the brownfields agreement, the brownfields property will be suitable for the uses specified in the agreement while fully protecting public health and the environment instead of being remediated to unrestricted use standards.” It is in the context of these risk-based concepts that the H&H professional engineer makes the following statement: The vapor intrusion mitigation system detailed herein is designed to mitigate and minimize potential intrusion of subsurface vapors into the subject buildings from known Brownfields property contaminants in a manner that is in accordance with the most recent and applicable guidelines including, but not limited to, DWM Vapor Intrusion Guidance, Interstate Technology & Regulatory Council (ITRC) guidance, and American National Standards Institute (ANSI)/American Association of Radon Scientists and Technologists (AARST) standards. The sealing professional engineer below is satisfied that the design is fully protective of public health from known Brownfields property contaminants. [SEAL] Matt Vawter NC PE #054251 Hart & Hickman, PC (#C-1269) 11 https://harthick.sharepoint.com/sites/masterfiles-1/shared documents/aaa-master projects/s2k charlotte/metromont concrete facility/vimp/rev. 1/to deq/22040 - vapor intrusion mitigation plan_metromont concrete facility_rev. 1.doc 2.0 Design Basis The VIMS design drawings for the proposed multifamily apartment development are included in Appendix A. The following VIMS design sheets and will be used to guide construction of the VIMS:  Sheet VM-1 and VM-2 shows the VIMS layout on the ground floor levels (Level 1 and Level 2);  Sheet VM-3 shows the VIMS layout on the roof; and  Sheets VM-A, VM-B, VM-C, and VM-D include section details and specifications. Results of assessment activities completed at the Site did not identify potential structural vapor intrusion risks at unacceptable levels. To further reduce the potential for structural vapor intrusion at unacceptable levels, the VIMS will operate as passive sub-slab venting systems that include a network of horizontal sub-slab and vertical above-slab riser piping that will discharge vapors collected below the slab above the building roofline. The proposed seven-story high-density apartment building will consist of a total enclosed occupiable ground floor space of approximately 49,000 square feet (sq ft) which will be split into two levels (Level 1 and Level 2). The ground floor spaces are proposed to include living spaces, amenity areas, a leasing office, a courtyard, and a parking garage. The upper levels of the building surrounding the courtyard and parking deck are proposed to consist of residential units with a terrace on the seventh level. The current development plans do not contain proposed commercial spaces or pour-back spaces in the building. The residential building is proposed to be constructed with column-supported post-tensioned (PT) slab-on-grade as depicted on the VIMS design drawings, with select portions of the building containing thickened slabs below load-bearing walls. Note that it is not recommended that additional monitoring points be added, or other holes be drilled through the slab after tightening of the PT slab tendons. 12 https://harthick.sharepoint.com/sites/masterfiles-1/shared documents/aaa-master projects/s2k charlotte/metromont concrete facility/vimp/rev. 1/to deq/22040 - vapor intrusion mitigation plan_metromont concrete facility_rev. 1.doc On Level 1, the VIMS has been divided into three separately treated VIMS areas to the west, east, and south of a mechanically-vented and partially open-air parking garage. The far western and northwestern space of Level 1 (Area 1A) will contain mechanical and utility rooms, a trash room, and a dog washroom. The remainder of the western portion of Level 1 (Area 1B) is separated from Area 1A by a structural footer and will consist of residential living space that encompasses an open-air courtyard. The eastern portion of Level 1 (Area 1C) will contain a leasing office/amenity/lobby area and bike storage room. Area 1D consists only of Stair B, which is located in the southwest corner of the parking deck and is connected to the VIMS in Level 2. The mechanically vented and partially open-air parking garage contains a single utility room. Although this room does not contain living space above it, is not expected to be regularly occupied, and is separated from Area 1C by a slab step, out of an abundance of caution, the utility room will be constructed with a vapor barrier. The southern half of Level 2 (Area 2) is slab-on-grade and will contain a VIMS. Area 2 consists of residential living spaces, a fitness center, entertainment rooms, and amenity areas. Living space is located on the floors above Level 1 and Level 2. The remaining areas of Level 2 above Level 1 are proposed to contain living and amenity space. There are vertical retaining walls proposed between the ground floor sections of Level 1 and Level 2. Occupiable ground-level components of the proposed apartment building are further summarized in the table below. Residential Building Ground Floor Use VIMS Area Level Description Ground Floor Approx. Area (sq ft) Area 1A Level 1 Utility and Non-Living Space 3,360 Area 1B Level 1 Living Space 18,100 Area 1C Level 1 Amenity Areas and Leasing 1,820 Area 1D Level 1 Stair B 240 Area 2 Level 2 Living Space and Amenities 19,500 13 https://harthick.sharepoint.com/sites/masterfiles-1/shared documents/aaa-master projects/s2k charlotte/metromont concrete facility/vimp/rev. 1/to deq/22040 - vapor intrusion mitigation plan_metromont concrete facility_rev. 1.doc The courtyard and parking garage extend through all seven stories of the building and are enclosed by living spaces on Level 2 through Level 7. The parking deck is open to outside air on Level 1 and Level 7 and is mechanically vented on each level through vent shafts located on the far northwest and southeast corners of the parking deck. Additionally, the building will contain a flat roof with some mechanical equipment. The building also contains a total of four elevators that terminate on the top floor. Three elevators begin on Level 1, and one begins on Level 2. No elevators open directly to the parking garage. Additionally, there are three staircases in the building that start on Level 1 and terminate on the top floor. Stair C is part of Area 1A and opens to the building exterior and to the living spaces of Area 1B. Stair A is part of Area 1C and does not open to the parking garage until Level 2. Stair B (Area 1D) is located on Level 1 and opens to parking on each floor and living space beginning on Level 2. 2.1 Base Course Layer and Vapor Barrier The VIMS includes placement of a minimum 4-inch base course stone (gravel) layer consisting of high permeability stone below the concrete slab of the building (washed #57 stone, or similar high permeability stone approved by the VIMS design engineer certifying the VIMP [design engineer]). A vapor barrier (a.k.a., vapor liner) will be installed above the base course stone layer and directly beneath the slab. The vapor barrier will also be installed underneath and along vertical walls within elevator pits and on vertical sub-grade retaining walls backfilled with soil that are located adjacent to enclosed or occupiable interior spaces. The specified vapor barrier and waterproofing materials in these areas will be evaluated for compatibility. A horizontal collection pipe network will be installed within the base course stone layer below the ground floor slabs prior to placement of the vapor barrier. The horizontal vapor collection piping is discussed further in Section 2.2 below. The piping layouts are shown on the VIMS design drawings (Appendix A). The vapor liner will consist of a VOC-rated vapor barrier such as Vaporblock® Plus 20 (VBP20) manufactured by Viaflex, Inc. (Viaflex) or Drago® Wrap Vapor Intrusion Barrier (Drago Wrap) 14 https://harthick.sharepoint.com/sites/masterfiles-1/shared documents/aaa-master projects/s2k charlotte/metromont concrete facility/vimp/rev. 1/to deq/22040 - vapor intrusion mitigation plan_metromont concrete facility_rev. 1.doc manufactured by Stego® Industries (Stego). Vapor barriers will be installed per manufacturer installation instructions. Technical specifications for the vapor liner products listed above are included in Appendix C. Note that an equivalent VOC-rated vapor barrier, if approved by the design engineer, may be used by the installation contractor. If an alternate equivalent vapor barrier is selected for use, DEQ will be notified in writing, and specification and installation instruction sheets will be provided. The vapor barriers will be installed over the base course stone layer or applicable vertical sub- grade walls and footers to cover the areas shown on the design sheets. Each vapor barrier manufacturer recommends specific sealing agents (mastics, tapes, etc.) for their vapor barrier product. In accordance with manufacturer installation instructions, alternative vapor barrier products that are not approved by the manufacturers for sealing should not be used, unless approved by the design engineer and specific manufacturer. The exterior edges of the vapor barrier will be attached and sealed to building footings and subsurface concrete features utilizing the tape specified in the manufacturer instructions. Seams within the building envelope will have a minimum of 6 inches or 12 inches of overlap (depending on the vapor barrier manufacturing specifications) and will be sealed with the tape specified in the manufacturer instructions. If the vapor liner is damaged, torn, or punctured during installation, a patch will be installed by overlaying a piece of vapor liner that is cut to the approximate shape of the damaged area, and sized such that a minimum of 6-inches of patch surrounds the damaged area. The seams of the patch will then be sealed using the manufacturer recommended tape. In areas where utility penetrations (i.e., piping, ducts, etc.) are present and the use of the tape recommended by the manufacturer is not practical or deemed as “ineffective” by the design engineer certifying the VIMP, an alternative sealant product specified by the vapor barrier manufacturer can be used, such as Viaflex Pour-N-Seal™ or other low to no VOC containing manufacturer-approved mastics. Following successful installation of the vapor barrier, the finished concrete slab will be placed directly on top of the sealed vapor barrier to further seal the seams and penetrations. 15 https://harthick.sharepoint.com/sites/masterfiles-1/shared documents/aaa-master projects/s2k charlotte/metromont concrete facility/vimp/rev. 1/to deq/22040 - vapor intrusion mitigation plan_metromont concrete facility_rev. 1.doc 2.2 Horizontal Collection Piping and Vertical Riser Piping Passive sub-slab venting will be accomplished using horizontal slotted or perforated collection piping, which will collect vapor from beneath the ground floor slabs and discharge the vapors above the building roofline through solid vertical exhaust piping. Sub-slab piping will consist of 3-inch diameter Schedule 40 (SCH 40) PVC piping and above-slab piping will consist of either 3-inch or 4-inch diameter SCH 40 PVC piping and fittings unless otherwise specified in the design drawings (Appendix A). Solid sections of VIMS piping shall maintain a minimum of 1% slope toward slotted sections to drain potential condensation water. Product specifications for the sub-slab collection piping are provided in Appendix C. As an alternative to 3-inch diameter SCH 40 PVC horizontal piping, soil gas collector mat manufactured by Radon Professional Discount Supply (Radon PDS) may be used for sub-slab vapor collection piping. The Radon PDS soil gas collector mat is a polystyrene, plastic, rectangular conduit with a geotextile fabric covering. The mat is 1 inch thick and 12 inches wide and is specifically designed for collecting soil gas from below a building. If used, the soil gas collector mat will be connected to the proposed 3-inch diameter vertical risers and footing crossings using Radon PDS-manufactured riser connection fittings. In lieu of the soil gas collector mat extending unprotected through concrete, solid PVC pipe will be used as a soil gas collector mat conduit in locations of footings and thickened slab crossings. Product specifications for the soil gas collector mat are provided in Appendix C. The vertical riser pipes will terminate above the roofline. While a passive system can effectively operate without rooftop ventilators, to further enhance the passive VIMS, Empire Model SV04SS (stainless steel) wind-driven syphon ventilators (or design engineer-approved alternative) will be installed on the discharge end of the 3-inch or 4-inch SCH 40 PVC vertical riser piping above the building roofline to further promote air exhaust from the risers. The ventilators will generally be located on areas of the roof that receive effects from wind under normal weather conditions. However, as the ventilators are intended to enhance the passive VIMS and are not required for function of the system, some ventilators may be positioned in areas that receive intermittent effects from wind based on the building layout and other building 16 https://harthick.sharepoint.com/sites/masterfiles-1/shared documents/aaa-master projects/s2k charlotte/metromont concrete facility/vimp/rev. 1/to deq/22040 - vapor intrusion mitigation plan_metromont concrete facility_rev. 1.doc components. The requirements for the discharge location based on distances to building materials, operable openings, air intakes, etc. will be followed as indicated in the design drawings and applicable building code. To aid in identification of the vapor intrusion mitigation piping, the piping will be labeled by the Site contractors with stickers adhered to a smooth surface or permanent labels which read, “Vapor Mitigation – Contact Maintenance”, or similar language, on accessible piping at intervals of no greater than 10 linear feet. Similar labels will also be affixed near the exhaust discharge on the roof. VIMS labeling will be inspected by H&H prior to covering risers or building occupancy. Exhaust discharge locations must be a minimum of 2 ft above the roofline and a minimum 10 ft from an operable opening (e.g., door or window) or air intake into the building. Note that the exhaust locations on the roof depicted in the VIMS design may be repositioned within the requirements specified above and pending approval by the design engineer certifying the VIMP. Product specifications for the proposed turbine ventilators are provided in Appendix C. Electrical junction boxes (120VAC, min 15-amp required) will be installed on the roof in close proximity to riser exhaust discharges should connection to an electrical (active) fan be warranted in the future. 2.3 Monitoring Points Monitoring points constructed with 2-inch diameter SCH 40 PVC will be installed as part of the VIMS to conduct effectiveness testing (see Section 4.0), including vacuum influence measurements, and for the collection of sub-slab soil gas samples for laboratory analysis. Three temporary monitoring points (TMP1-1 through TMP1-3) will be installed on Level 1 of the building and one temporary monitoring point (TMP2-1) will be installed on Level 2. The temporary monitoring points will be abandoned following successful influence testing and/or sampling as discussed in Section 4.1. The temporary points will be abandoned by removing the pipe to the extent possible, filling in the hole with an air-tight sealant (such as Viaflex Pour N Seal), then patching the concrete to match the surrounding area. The monitoring point locations are shown on the VIMS design drawings (Appendix A). 17 https://harthick.sharepoint.com/sites/masterfiles-1/shared documents/aaa-master projects/s2k charlotte/metromont concrete facility/vimp/rev. 1/to deq/22040 - vapor intrusion mitigation plan_metromont concrete facility_rev. 1.doc In general, monitoring points are placed at remotely distant locations from vertical riser piping locations and in representative areas of the ground floor enclosed areas. To limit disturbance to occupants during future monitoring events, the majority of the monitoring point access ports will be located in stairwells, mechanical rooms, amenity spaces, or exterior-mounted locations. Each monitoring point access port will be protected by a floor clean-out cover, wall access panel, or a locking exterior waterproof wall enclosure. Several monitoring points will be connected to extended sub-slab horizontal pipes which place the intakes of the monitoring points below occupied spaces. The extended monitoring points are expected to have no more than approximately 6 ft of extension pipe. Product specifications for the proposed floor cleanout covers are provided in Appendix C. In the event that a monitoring point cannot be installed due to building component conflict or is damaged/destroyed during construction, a replacement monitoring point can be constructed, pending approval by the design engineer certifying the VIMP. The replacement point(s) shall consist of one of the specified designs in the design drawings. DEQ will be notified in advance if monitoring points are relocated significantly in relation to approved locations specified in the VIMP (i.e., if moved to a location in a different mitigation area, section of slab, or tenant area). The specific types and locations of monitoring points installed will be documented in as-built drawings provided in a VIMS installation completion report. 2.4 General Installation Criteria The installed VIMS components (e.g., vapor barrier, piping, monitoring points, etc.) shall be protected by the installation contractor and sub-contractors throughout the project. Protective measures (e.g., flagging, protective boards, etc.) shall be used as needed to prevent damage to the VIMS components. For example, the monitoring points and riser duct piping should be capped with a removable slip-cap or cover immediately following installation to prevent water and/or debris from entering the VIMS, and vapor barrier shall be protected from punctures and tears during work completed following placement and sealing of the liners. For each phase of construction (above and below slab), construction contractors and sub- contractors shall use “low or no VOC” products and materials, when possible. This applies to all 18 https://harthick.sharepoint.com/sites/masterfiles-1/shared documents/aaa-master projects/s2k charlotte/metromont concrete facility/vimp/rev. 1/to deq/22040 - vapor intrusion mitigation plan_metromont concrete facility_rev. 1.doc building products and materials and not only those directly related to the VIMS. Furthermore, the construction contractors shall not use products containing the compounds PCE or TCE. Prior to submittal of a VIMS installation completion report, the construction contractor and sub- contractors shall be directed to provide safety data sheets (SDSs) for all products and materials used during construction. SDSs provided by the contractor and subcontractors will be included in the VIMS installation completion report. Utility Trench Dam Evaluation Results of previous Site assessment activities did not identify the presence of chlorinated solvents (such as TCE) in proximity to the proposed building at concentrations above laboratory detection limits. In addition, Site-wide worst-case soil gas to indoor air vapor intrusion risk calculations are within acceptable levels for cumulative carcinogenic and noncarcinogenic risks. Also note that the generic sub-slab soil gas to indoor air attenuation factor that is the basis for DEQ risk calculation is conservative and is intended to estimate a potential upper-bound indoor air concentration accounting for temporal variability. In addition, the sub-slab soil gas to indoor air attenuation factors do not account for a VIMS with a vapor barrier and sub-slab depressurization that will greatly reduce the potential for unacceptable vapor intrusion risks. As noted above, chlorinated solvents such as TCE were not detected at concentrations above laboratory detection limits in soil, soil gas, and groundwater samples collected near the proposed building footprint. The groundwater samples that did contain TCE are located approximately 300 feet downgradient of the closet edge of the proposed building footprint and adjacent to Sugar Creek (Figure 4). Currently, there are no utilities for the proposed building that transect the area of known TCE impacts in groundwater. Therefore, utility trench dams that are sometimes installed to minimize lateral migration of vapors from an area of elevated concentrations to areas beneath a building footprint are not warranted or practical based on the known contaminant levels, locations of proposed utilities, and footprint of the proposed apartment building. 19 https://harthick.sharepoint.com/sites/masterfiles-1/shared documents/aaa-master projects/s2k charlotte/metromont concrete facility/vimp/rev. 1/to deq/22040 - vapor intrusion mitigation plan_metromont concrete facility_rev. 1.doc 3.0 Quality Assurance / Quality Control For quality assurance and quality control (QA/QC) purposes, inspections will be conducted during each phase of VIMS installation. The components that require inspection are outlined below: (1) Inspection of vapor barrier along the sub-grade elevator pits and applicable vertical retaining walls prior to backfilling; (2) Inspection of the base course stone layer, sub-slab piping layout, and monitoring points prior to installing the vapor barrier; (3) Inspection of the vapor barrier below slab areas prior to pouring concrete; (4) Inspection of above-grade vertical riser piping; and (5) Inspection of riser pipe connections, pipe exhaust, and ventilators. Additional inspections will be conducted if the system(s) are activated to verify electric fans (if installed) are functioning. Each inspection will be performed by, or under the direction of, the design engineer certifying the VIMP. Inspections will be combined, when possible, depending on construction sequencing and schedule. The inspections will include field logs and photographs for each section of slab. To minimize potential preferential pathways through the slab, contractors will not use hollow piping to support utilities in preparation for concrete pours. Contractors will be instructed to remove hollow piping observed during the field inspections. The contractor shall notify the engineer certifying the VIMP, or its designee, with a minimum two-business day notice prior to a planned inspection, and H&H will provide a subsequent two- business day notice to DEQ for the pending inspection. 20 https://harthick.sharepoint.com/sites/masterfiles-1/shared documents/aaa-master projects/s2k charlotte/metromont concrete facility/vimp/rev. 1/to deq/22040 - vapor intrusion mitigation plan_metromont concrete facility_rev. 1.doc 4.0 VIMS Effectiveness Testing 4.1 Influence Testing Post-installation (pre-occupancy) influence testing will be conducted on each VIMS treatment area to evaluate vacuum communication across the slab and confirm sufficient depressurization can be obtained should electric fans be needed in the future. Influence testing will be conducted for each treatment area following installation of the horizontal collection piping, placement of the vapor barrier, and completion of concrete slab pours. A two-business day notice will be provided to DEQ prior to each influence test. For system influence testing, one or more vapor extraction fans will be attached directly to vertical riser piping for the section of the slab being evaluated. Pressure differential will be measured at extraction fan locations and sub-slab vacuum levels will be measured at each monitoring point location. While even low level sub-slab vacuum measurements can indicate influence below the slab, a pressure differential below the slab of at least 4 pascals (approximately 0.016 inches of water column [in-WC]) at remote distances from riser location in each VIMS treatment area will be considered sufficient evidence of adequate sub-slab VIMS influence per evaluation by the design engineer certifying the VIMP. Vacuum influence testing results will be included in the VIMS installation completion report. If the influence testing results indicate that modifications to the VIMS are needed to achieve sufficient sub-slab depressurization, H&H will notify DEQ of the modifications prior to submittal of a VIMS installation completion report. 4.2 Pre-Occupancy Sub-Slab Soil Gas Sampling Following VIMS installation and prior to occupancy of the building, seven (7) sub-slab soil gas samples will be collected from select monitoring points on Level 1 and four (4) sub-slab soil gas samples will be collected from the slab-on-grade area of Level 2 to evaluate sub-slab conditions for compounds that may pose a potential structural vapor intrusion risk at unacceptable levels. The sub-slab soil gas samples will be collected from locations generally representative of the 21 https://harthick.sharepoint.com/sites/masterfiles-1/shared documents/aaa-master projects/s2k charlotte/metromont concrete facility/vimp/rev. 1/to deq/22040 - vapor intrusion mitigation plan_metromont concrete facility_rev. 1.doc slab conditions. Sub-slab soil gas sample analytical results will be used to evaluate efficacy of the VIMS and potential risks to future occupants of the building. The proposed sub-slab soil gas samples for the Site building will be collected from:  Area 1A: MP1-3  Area 1B: MP1-5, MP1-7, MP1-6, MP1-9  Area 1C: MP1-11, MP1-14  Area 2: MP2-2, MP2-4, MP2-5, MP2-7 For laboratory QA/QC purposes, one duplicate sub-slab soil gas sample will be collected during each sampling event using a laboratory-supplied “T” fitting which allows for the collection of two sub-slab soil gas samples from one sample location simultaneously. Prior to sample collection, leak tests will be performed at each sub-slab soil gas sample location. A shroud will be constructed around the monitoring point and sub-slab soil gas sampling train and sample canister. Air within the shroud will be flooded with helium gas, and helium concentrations will be measured and maintained using a calibrated helium gas detector. With helium concentrations within the shroud maintained, sub-slab soil gas will be purged from the sampling point with an air pump and collected into a Tedlar bag. The calibrated helium gas detector will be used to measure helium concentrations within the Tedlar bag sample to confirm concentrations are less than 10% of the concentration maintained within the shroud. A minimum of three sample train volumes will be purged from each point prior to and during the leak testing activities. The sub-slab soil gas samples will be collected over an approximate 10-minute period using laboratory supplied batch certified Summa canisters and laboratory supplied flow regulators calibrated with an approximate flow rate of 100 milliliters per minute. The vacuum in the Summa canisters will be measured at the start and end of the sampling event and will be recorded by sampling personnel. The vacuum in each canister at the conclusion of the sampling event shall remain above 0 inches of mercury (inHg), with a target vacuum of approximately 5 inHg. H&H understands that analytical results for a sample will not be accepted by DEQ if internal vacuum in a canister reaches 0 inHg. 22 https://harthick.sharepoint.com/sites/masterfiles-1/shared documents/aaa-master projects/s2k charlotte/metromont concrete facility/vimp/rev. 1/to deq/22040 - vapor intrusion mitigation plan_metromont concrete facility_rev. 1.doc The samples will be submitted to a qualified laboratory under standard chain of custody protocols for analysis of full-list VOCs by EPA Method TO-15. The analytical laboratory will be instructed to report sample canister vacuum measurements as received at the laboratory and laboratory estimated compound concentrations above the laboratory method detection limit, but below the laboratory reporting limits (i.e., J-flag concentrations). In addition, H&H will request that the laboratory report compound concentrations to the lower of the laboratory method detection limits or to the extent possible, the DEQ Residential Vapor Intrusion SGSLs. Upon receipt of the sub-slab soil gas sample analytical results, H&H will use the most current version of the DEQ Risk Calculator to evaluate cumulative risks of potential vapor intrusion for a residential use scenario. If calculated cumulative risks are greater than 1x10-4 for potential carcinogenic risks and/or above a hazard index of 1.0 for potential non-carcinogenic risks, indoor air sampling will be completed. The DEQ DWM VI Guidance indicates that if sub-slab soil gas concentrations do not exceed acceptable risk levels, typically no further investigation is necessary. However, as a very conservative approach, if the chlorinated solvent TCE is detected at a concentration above the laboratory reporting limits in a sub-slab soil gas sample, or if PCE is detected in the sub-slab soil gas samples above its Residential Vapor Intrusion SGSL, indoor air sampling will also be conducted as described below. 4.3 Indoor Air Sampling (If Warranted) Pre-occupancy indoor air sampling co-located with the sub-slab soil gas samples listed above is not anticipated for pre-occupancy sampling due to chlorinated solvents (including TCE) not being detected above laboratory detection limits in soil gas samples collected at the Site, Site- wide worst-case soil gas vapor intrusion risk calculations being well under the acceptable limits, and no detection of chlorinated solvents in groundwater or soil sample collected in close proximity of the proposed building footprint. If indoor air sampling is warranted based on results of VIMS efficacy sub-slab soil gas sampling, indoor air sampling will be completed as described in this section. 23 https://harthick.sharepoint.com/sites/masterfiles-1/shared documents/aaa-master projects/s2k charlotte/metromont concrete facility/vimp/rev. 1/to deq/22040 - vapor intrusion mitigation plan_metromont concrete facility_rev. 1.doc The building is intended to be occupied shortly following installation and operation of the HVAC systems. Therefore, the indoor air sampling events (if warranted) will be conducted following complete installation of the VIMS and after the building and/or sample area has been fully enclosed. When possible, the indoor air sampling will be completed a minimum of two weeks with operational ventilators but may be conducted prior to operation of the HVAC system(s). The DEQ DWM VI Guidance, indicates “higher indoor air concentrations might be expected when a building is sealed up and the HVAC is not running”, and “worse case conditions may also be considered when the building is closed up and the HVAC system is running.” HVAC equipment is typically not operational until approximately a few weeks prior to closing due to the timing of the Mecklenburg County approval for installation of natural gas and electrical meters. Conducting indoor air sampling with the building enclosed, but prior to HVAC operation, may allow for a more conservative indoor air sampling approach and will allow for time to conduct the pre-occupancy sampling and reporting for DEQ review. In addition, HVAC equipment is not operational until finishing activities including installation of flooring, cabinets, sealants, paints, industrial cleaning, etc. are being conducted. Potential off gassing of VOCs from building finishing materials and products can impact the indoor air concentrations and make it more difficult to evaluate the potential for a completed vapor intrusion pathway. To minimize the potential for false positive resultant from off gassing building construction materials, sampling ahead of operational HVACs and finishing activities is proposed if indoor air sampling is warranted. If indoor air sampling is warranted, the locations, number of indoor air samples, and timing for the indoor air samples will be based on sub-slab soil gas sampling analytical data and discussions between the design engineer and DEQ. The indoor air samples will be collected using individually certified 6-liter stainless steel Summa canisters connected to in-line flow controllers equipped with a vacuum gauge. The flow controllers will be set by the laboratory to allow for sample collection over an approximately 24- hour period in accordance with the DEQ DWM VI Guidance. The sample will be set so the intake point is positioned approximately 5 ft above grade (typical breathing zone height). In addition, during each indoor air sampling event, one duplicate sample will be collected for laboratory QA/QC and one background ambient air sample will be collected from a location 24 https://harthick.sharepoint.com/sites/masterfiles-1/shared documents/aaa-master projects/s2k charlotte/metromont concrete facility/vimp/rev. 1/to deq/22040 - vapor intrusion mitigation plan_metromont concrete facility_rev. 1.doc upwind of the building, as determined by conditions on the day of the sampling event. Prior to and after the indoor and background air samples are collected, vacuum in the canisters will be measured using a laboratory-supplied vacuum gauge and recorded by sampling personnel. A vacuum above 0 inHg and ideally around 5 inHg will be maintained within the canisters at the conclusion of the sampling event. The starting and ending vacuum in each canister will be recorded on the sample chain of custody. Periodic checks will be conducted by sampling personnel to monitor the pressure within the Summa canisters during sampling to ensure adequate sample volume is collected. The sample canisters will then be labeled and shipped under standard chain of custody protocols to a qualified laboratory for analysis of select VOCs by EPA Method TO-15. The select compound list will be based upon the compounds detected in sub-slab soil gas samples and previously identified Site contaminants of concern (COCs). The analytical laboratory will be instructed to report canister vacuum measurements at receipt and J-flag compound concentrations. The laboratory will be requested to report compound concentrations to the lower of the laboratory detection limits or to the extent possible, the DEQ Residential Vapor Intrusion Indoor Air Screening Levels (IASLs). In addition, an Indoor Air Building Survey form (Appendix C of the DWM VI Guidance) will be completed for each sampling event by sampling personnel. New construction materials such as treated lumber, paint, caulk, carpet, adhesives, sealants etc., which could be sources of VOCs in indoor air, may cause interference with Site-specific compounds of concern during indoor air sampling. As previously noted, the construction contractors and sub-contractors will be requested to provide SDSs for materials used during construction which will be submitted to DEQ, if needed to further evaluate sub-slab soil gas and indoor air sample data. 4.4 VIMS Effectiveness Results Following receipt of analytical results, the laboratory analytical report will be reviewed and DEQ will be notified in the event that TCE concentrations in sub-slab soil gas indicate potential vapor intrusion pathways may exist. If subsequent indoor air sampling is warranted, in accordance 25 https://harthick.sharepoint.com/sites/masterfiles-1/shared documents/aaa-master projects/s2k charlotte/metromont concrete facility/vimp/rev. 1/to deq/22040 - vapor intrusion mitigation plan_metromont concrete facility_rev. 1.doc with the DEQ DWM TCE Indoor Air Inhalation Immediate Action Levels and Response guidance (dated July 2019), DEQ will be notified within 24 hours if TCE is detected at a concentration exceeding 2.1 µg/m3 in indoor air based on the residential use of the building. Note that no residents will be living in the building during post-construction indoor air sampling. DEQ will also be notified prior to report submittal if sub-slab soil gas and indoor air sample results indicate a completed vapor intrusion pathway. The results and analysis of the sub-slab soil gas sampling (and indoor air sampling, if warranted) will be submitted to DEQ with the VIMS installation completion report. After receipt of the sub-slab soil gas and/or indoor air sample analytical results, H&H will use the most recent version of the DEQ Risk Calculator to evaluate cumulative vapor intrusion risks under a residential use scenario. H&H will consider the VIMS effective if the calculated cumulative risks for the sub-slab soil gas and/or indoor air samples are within acceptable levels in accordance with DEQ Risk Calculator results. The DEQ acceptable risk levels include:  cumulative carcinogenic risks less than 1x10-4; and  non-carcinogenic risk levels below a HI of 1.0. In the event that calculated cumulative risks are greater than the acceptable risks listed above, then an evaluation of potential interference of compounds from building material off gassing will be conducted, and the data will be presented to DEQ. If it is determined that the sub-slab soil gas concentrations are from Site contaminants and could lead to unacceptable vapor intrusion risks to the occupants of the building, confirmation sub-slab soil gas and/or indoor air samples may be collected from the area(s) of concern. Further, in this case, an evaluation to potentially convert the system to an active VIMS or other enhancements to the system will be conducted. If warranted, modifications to the VIMS will be presented to DEQ for review and approval prior to implementation. 26 https://harthick.sharepoint.com/sites/masterfiles-1/shared documents/aaa-master projects/s2k charlotte/metromont concrete facility/vimp/rev. 1/to deq/22040 - vapor intrusion mitigation plan_metromont concrete facility_rev. 1.doc 5.0 VIMS Effectiveness Monitoring The VIMS is proposed as a passive system which will include vapor extraction through sub-slab collection piping and solid exhaust risers that discharge sub-slab vapors above the roofline. The passive system will be enhanced with wind-turbine ventilators to promote air exhaust from the sub-slab. As such, differential pressure monitoring is not anticipated. If the VIMS is converted to an active system based on pre-occupancy or post-occupancy sub-slab soil gas assessment results, proposed modifications to the VIMP including modifying the VIMS design, testing and analytical sampling requirements, and details for long-term differential pressure monitoring across the slab will be submitted to the DEQ Brownfields Redevelopment Section in the VIMS installation completion report and supporting as-built drawings. The specific electric fans to be used will be selected by the VIMS design engineer based on the results of the influence testing discussed in Section 4.0. Post-occupancy sub-slab soil gas is proposed to be performed on a semi-annual basis for a minimum of two years (four total events) following initial occupancy of the Site building. The frequency, amount, and locations of the sub-slab (and indoor air samples, if applicable) for the post-occupancy sampling events may be reduced or modified depending on the pre-occupancy sampling results, pending DEQ review and approval. A recommendation regarding the post- occupancy sampling will be provided in the VIMS installation completion report based on the pre-occupancy sampling results and risk calculations. The post-occupancy sampling will be conducted using the procedures described in this VIMP. Further, after each post-occupancy semi-annual sampling event, if the sampling results indicate consistent or decreasing concentrations within acceptable risk levels, a request to modify or terminate sampling may be submitted for DEQ approval. No changes to the sampling frequency or termination of sampling will be implemented until written approval is obtained from DEQ. 27 https://harthick.sharepoint.com/sites/masterfiles-1/shared documents/aaa-master projects/s2k charlotte/metromont concrete facility/vimp/rev. 1/to deq/22040 - vapor intrusion mitigation plan_metromont concrete facility_rev. 1.doc 6.0 Future Tenants & Building Uses The future use of the proposed Site building includes multifamily residential apartments. After occupancy of the Site building, VIMS maintenance and upkeep will be the responsibility of the building owner or property management group. If vapor mitigation components are damaged or need to be altered for building renovations, the building owners or management will contact a North Carolina licensed Professional Engineer (NC PE) to oversee or inspect the modifications or repair activities, and a report will be prepared and submitted to DEQ detailing the repairs or alterations. To aid in identification of the vapor mitigation piping, the construction contractor will label the pipe with “Vapor Mitigation – Contact Maintenance”, or similar language, on accessible piping at intervals of no greater than 10 linear feet. The labels shall include a printed label or painted label with stencils adhered directly to the pipe. Similar labels will also be affixed near the exhaust discharge on the roof. As part of the standard annual Land Use Restriction Update submittal required as part of the Brownfields Agreement for the Site, the building owner or property management group should complete a visual inspection of the exposed parts of the system including, but not limited to, the vertical risers and ventilators on the roof and the monitoring points. Annual inspections are recommended to be documented and kept on record to be provided to DEQ upon request. 28 https://harthick.sharepoint.com/sites/masterfiles-1/shared documents/aaa-master projects/s2k charlotte/metromont concrete facility/vimp/rev. 1/to deq/22040 - vapor intrusion mitigation plan_metromont concrete facility_rev. 1.doc 7.0 Reporting A VIMS Installation Completion Report (sealed by a NC PE) documenting installation, vacuum pilot testing, and efficacy sampling activities associated with the VIMS will be submitted to DEQ with a request for written compliance approval following confirmation that the mitigation systems are installed and effectively mitigating potential vapor intrusion risks to building occupants. The report will include a summary of VIMS installation activities such as representative photographs and as-built drawings, QA/QC measures, SDSs of materials used in construction, VIMS effectiveness testing results, and inspection documents. The report will also include a statement by the design engineer as to whether the VIMS was installed in accordance with the DEQ approved VIMP and is protective of public health as evidenced by the VIMS inspections performed by the engineer or its designee, results of the influence testing, results of the analytical testing, and QA/QC measures as described in this VIMP. Deviations from the approved design will be provided in the report. The Notice of Brownfields Property agreement for the Site includes standard land use restrictions that indicate the building(s) shall not be occupied until DEQ provides written compliance approval for the installation and performance of the VIMS as documented in the installation report. However, as it has done in the past, DEQ may provide conditional approval with submittal of a data summary package in lieu of the full VIMS Installation Completion Report if warranted based on timing of the proposed building occupancy date and report review times. No occupancy of the building will occur without prior written approval of DEQ. After each semi-annual post-occupancy sub-slab soil gas sampling event, a report will be submitted to DEQ to document the sampling activities and results with recommendations for future post-occupancy sampling. The first post-occupancy semi-annual monitoring event is anticipated to be conducted approximately six (6) months after the initial occupancy of the building, or as otherwise approved by DEQ based on the results and timing of the occupancy of the Site buildings. USGS The National Map: National Boundaries Dataset, 3DEP ElevationProgram, Geographic Names Information System, National HydrographyDataset, National Land Cover Database, National Structures Dataset, andNational Transportation Dataset; USGS Global Ecosystems; U.S. CensusBureau TIGER/Line data; USFS Road Data; Natural Earth Data; U.S.Department of State Humanitarian Information Unit; and NOAA NationalCenters for Environmental Information, U.S. Coastal Relief Model. Datarefreshed June, 2022. SITE LOCATION MAP METROMONT CONCRETE FACILITY 4101 GREENSBORO STREETCHARLOTTE, NORTH CAROLINA DATE: 5-31-23 JOB NO: S2K-001 REVISION NO: 0 FIGURE. 1 2923 South Tryon Street - Suite 100Charlotte, North Carolina 28203704-586-0007 (p) 704-586-0373 (f)License # C-1269 / # C-245 Geology TITLE PROJECT 0 2,000 4,000 SCALE IN FEET Path: S:\AAA-Master Projects\S2K Charlotte\Metromont Concrete Facility\EMP\Figures\Figure-1.mxdN U.S.G.S. QUADRANGLE MAP CHARLOTTE EAST, NORTH CAROLINA 2022DERITA, NORTH CAROLINA 2022 QUADRANGLE7.5 MINUTE SERIES (TOPOGRAPHIC) SITE REVISION NO. 0 JOB NO. S2K-001 DATE: 5-31-23 FIGURE NO. 2 METROMONT CONCRETE FACILITY4101 GREENSBORO STREET CHARLOTTE, NORTH CAROLINA SITE MAP 2923 South Tryon Street-Suite 100Charlotte, North Carolina 28203704-586-0007(p) 704-586-0373(f)License # C-1269 / #C-245 Geology GREENSBORO STREE T EAST SUGAR CREEK ROAD PRE-S T R E S S CONCR E T E F O R M STAGIN G A R E A PRE-S T R E S S CONCR E T E F O R M STAGIN G A R E A SAND B L A S TI N G BUILDI N G N. TR Y O N ST R E ET LEGEND BROWNFIELDS PROPERTY BOUNDARY PARCEL LINE LITTLE SUGAR CREEK ABANDONED UST FORMER UST TRYON MALL CLEANER(451 E. SUGAR CREEK ROAD) BINGO TIRE & AUTO(4026 N. TRYON STREET) PALACE AUTO SALES(4104 N. TRYON STREET)ZOEWEE'S(4111 N. TRYON STREET) SUGAR CREEK TIRE & AUTO(126 E. SUGAR CREEK ROAD) EL NOA NOA(215 E. SUGAR CREEK ROAD) DINO'S(350 E. SUGAR CREEK ROAD) ESTRAMONTE CHIROPRACTIC (402 E. SUGAR CREEK ROAD) CONCRETE SUPPLY COMPANY(3940 GREENSBORO STREET) CONSOLIDATED PRESS(3900 GREENSBORO STREET) CONCRETE SUPPLY COMPANY (3823 RALEIGH STREET) FORMER TARMAC FACILITY(3934 RALEIGH STREET) FORMER ACID WASHOPERATIONS NOTES: 1. PARCEL DATA AND AERIAL IMAGERY OBTAINED FROM MECKLENBURG COUNTY GIS (2023). 2. UST = UNDERGROUND STORAGE TANK FORMER GASOLINEUST (TANK NO.2) FORMER HEATING OILUST (TANK NO.3) FORMER DIESEL UST (TANK NO.1) ABANDONED HEATING OIL UST (TANK NO.4) RALEIGH STRE E T CARS TO GO (3922 N. TRYON STREET) POPEYE'S (4050 N. TRYON STREET) LITTLE S U G A R C R E E K S:\AAA-Master Projects\S2K Charlotte\Metromont Concrete Facility\EMP\Redevelopment EMP\Figures\S2K.001_20230531.dwg, FIG 2 - SITE MAP, 6/1/2023 8:56:01 AM, shaynes SB-3 SB-6 MW-1 SB-5/GW-4 MW-3 MW-5 MW-4 GW-6 MW-2 N. TR Y O N ST R E ET TW-8 TW-9 SG-1 SG-2 SG-3 SG-4 BGS-1 TW-3 TW-7 TW-6 TW-5 BGS-2 TW-4 TW-1 TW-2 GREENSBORO STRE E T EAST SUGAR CREEK ROAD RALEIGH STRE E T TW-3 SB-1/GW-1 REVISION NO. 0 JOB NO. S2K-001 DATE: 5-31-23 FIGURE NO. 3 METROMONT CONCRETE FACILITY4101 GREENSBORO STREET CHARLOTTE, NORTH CAROLINA SAMPLE LOCATION MAP 2923 South Tryon Street-Suite 100Charlotte, North Carolina 28203704-586-0007(p) 704-586-0373(f)License # C-1269 / #C-245 Geology NOTES: 1. PROPOSED SITE PLAN BASED ON CONSTRUCTIONDOCUMENTS PREPARED BY COLEJENEST & STONEDATED 6/24/2022. 2. LOCATIONS FOR MONITORING WELLS MW-1 THROUGH MW-5 ARE APPROXIMATE BASED ON REVIEW OF THEPHASE III GROUNDWATER ASSESSMENT REPORT PREPARED BY ROGER AND COLLCOTT IN MAY 1996. 3. SOIL BORING (SB-3 THROUGH SB-6) AND TEMPORARYMONITORING WELL (GW-1, GW-4, AND GW-6)LOCATIONS ARE APPROXIMATE BASED ON REVIEW OFTHE PHASE II ESA REPORT PREPARED BY ECS IN MAY2018. 4. BROWNFIELDS SOIL AND GROUNDWATER BORINGSTW-1 THROUGH TW-9 WERE ADVANCED AND SAMPLED1/28/2019 THROUGH 1/30/2019 AND 2/4/2019. SG-1 THROUGH SG-4 WERE SAMPLED 1/31/2019 AND 2/4/2019. 5. UST = UNDERGROUND STORAGE TANK LEGEND BROWNFIELDS PROPERTY BOUNDARY PARCEL LINE LITTLE SUGAR CREEK ABANDONED UST FORMER UST HISTORICAL MONITORING WELL TEMPORARY MONITORING WELL CO-LOCATED SOIL BORING / TEMPORARYMONITORING WELL SOIL BORING LOCATION SOIL GAS SAMPLE SAMPLE LOCATION PROPOSED DIRECTION OF FLOW INTO THESEDIMENT POND PROPOSED GROUND FLOOR BUILDINGFOOTPRINT FORMER ACID WASHOPERATIONS FORMER GASOLINEUST (TANK NO.2) FORMER HEATING OIL UST (TANK NO.3) FORMER DIESELUST (TANK NO.1) ABANDONED HEATING OIL UST (TANK NO.4) EXISTINGSEDIMENT BASIN LITTLE S U G A R C R E E K PARKINGDECK POOLCOURTYARD S:\AAA-Master Projects\S2K Charlotte\Metromont Concrete Facility\EMP\Redevelopment EMP\Figures\S2K.001_20230531.dwg, FIG 3 - SAMPLES, 6/1/2023 9:00:41 AM, shaynes N. TR Y O N ST R E ET GREENSBORO STRE E T EAST SUGAR CREEK ROAD RALEIGH STRE E T REVISION NO. 0 JOB NO. S2K-001 DATE: 5-31-23 FIGURE NO. 4 METROMONT CONCRETE FACILITY4101 GREENSBORO STREET CHARLOTTE, NORTH CAROLINA COMPOUND CONCENTRATION MAP 2923 South Tryon Street-Suite 100Charlotte, North Carolina 28203704-586-0007(p) 704-586-0373(f)License # C-1269 / #C-245 Geology NOTES: 1. BOLD VALUES INDICATE CONCENTRATION EXCEEDSTHE 2L GROUNDWATER STANDARD. 2.UNDERLINED VALUES INDICATE CONCENTRATIONEXCEEDS THE DEQ DWM VAPOR INTRUSIONRESIDENTIAL GWSL. 3. SHADED VALUES INDICATE CONCENTRATION EXCEEDSTHE DEQ DWM VAPOR INTRUSION NON-RESIDENTIAL GWSL. 4.ITALICIZED VALUES INDICATE CONCENTRATIONEXCEEDS THE DEQ DWM VAPOR INTRUSIONRESIDENTIAL SGSL. 5. J = COMPOUND WAS DETECTED ABOVE THELABORATORY METHOD DETECTION LIMIT BUT BELOWTHE LABORATORY REPORTING LIMIT, RESULTING IN ALABORATORY ESTIMATED CONCENTRATION. 6. cis-1,2-DCE = cis-1,2-DICHLOROETHYLENEPCE = TETRACHLOROETHYLENETCE = TRICHLOROETHYLENEGWSL = GROUNDWATER SCREENING LEVELSSGSL = SOIL GAS SCREENING LEVELSUST = UNDERGROUND STORAGE TANK LEGEND BROWNFIELDS PROPERTY BOUNDARY PARCEL LINE LITTLE SUGAR CREEK ABANDONED UST FORMER UST TEMPORARY MONITORING WELL CO-LOCATED SOIL BORING / TEMPORARYMONITORING WELL SOIL GAS SAMPLE SAMPLE LOCATION PROPOSED DIRECTION OF FLOW INTO THESEDIMENT POND PROPOSED GROUND FLOOR BUILDINGFOOTPRINT FORMER ACID WASHOPERATIONS FORMER GASOLINEUST (TANK NO.2) FORMER DIESELUST (TANK NO.1) ABANDONED HEATING OIL UST (TANK NO.4) TW-1 TOTAL C9-C18 ALIPHATICS 27 µg/L TW-7 cis-1,2-DCE 160 μg/L TCE 2.8 μg/L VC 0.95 J μg/L TW-3 TOTAL C9-C18 ALIPHATICS 12 J μg/L TW-2 PCE 2.6 μg/L TOTAL C9-C18 ALIPHATICS 12 J μg/L TW-4 TOTAL C9-C18 ALIPHATICS 11 J μg/L GW-1 cis-1,2-DCE 170 μg/L TCE 24 μg/L VC 3.3 µg/L SG-2 / DUP-SG BENZENE 22 / 23 μg/m3 SG-2 TW-3 SB-1/GW-1 TW-7 TW-4 TW-1 TW-2 TW-7 cis-1,2-DCE 160 μg/L TCE 2.8 μg/L VC 0.95 J μg/L CONSTITUENT CONCENTRATION SAMPLE ID FORMER HEATING OIL UST (TANK NO.3) EXISTINGSEDIMENT BASIN LITTLE S U G A R C R E E K PARKINGDECK POOLCOURTYARD SG-3 SG-3 BENZENE 15 μg/m3 S:\AAA-Master Projects\S2K Charlotte\Metromont Concrete Facility\EMP\Redevelopment EMP\Figures\S2K.001_20230531.dwg, FIG 4 - CONC MAP, 6/1/2023 9:06:29 AM, shaynes Appendix A Vapor Intrusion Mitigation Design Drawings Sheets VM-1, VM-2, VM-3, VM-A, VM-B, VM-C, and VM-D RAMP UPRAMP UP703' - 2" 704' - 4" 708' - 0" 701' - 2"5.00%5.00%5.00% INTERIOR COURTYARD 118 COURTYARD 102 POOL EQUIP. 136 CHEM. 135 MAINTENANCE 133 CORR. 134 TRASH COMPACTOR ROOM 139 DOG WASH 100 COURTYARD CORR. 101 CORRIDOR 117 STAIR C 130 PARKING 138 MAIL 141 LOAD. LOBBY 142 STAIR A 143 PASSAGE 144 LONG TERM BICYCLE STORAGE 140 703' - 4" 703' - 4" STAIR B 1448.33%UNIT S5 108 REF A2.54 UNIT S5 106 REF A2.54 UNIT S5 104 REF A2.54 705' - 6" 705' - 6" UNIT S5 120 REF A2.54 UNIT S5 121 REF A2.54 UNIT S1 105 REF A2.50a UNIT S1 105 REF A2.50a UNIT S1 107 REF A2.50a UNIT S1 107 REF A2.50a UNIT S1 109 REF A2.50a UNIT S1 109 REF A2.50a UNIT A1 111 REF A2.60a UNIT A1 113 REF A2.60a UNIT A5 129 REF A2.64 UNIT A5 129 REF A2.64 UNIT S1 128 REF A2.50a UNIT S1 126 REF A2.50a UNIT A1 ALT 127 REF A2.60a UNIT A1 ALT 127 REF A2.60a UNIT A5 125 REF A2.64 UNIT A5 125 REF A2.64 UNIT A6 122 REF A2.65 UNIT A5 110 REF A2.64 UNIT S1 115 REF A2.50a UNIT S1 115 REF A2.50a UNIT A1 ALT 116 REF A2.60a UNIT A2 TYPE A 103 REF A2.81 700' - 4" ELEC / SWITCH GEAR 137 1ST FLR TRASH DROP 138 704' - 8" 704' - 8"MDF 776 4.84%703' - 0"8.33%703' - 0" 701' - 2" GENERTATOR 150 RAMP UP1 1 37 37 49 49 H H JJ JJ EE A A 2 2 3 4 4 5 5 7 76 10 11 11 12 14 19 25 27 2321 2616 16 29171518202428 22 30 353332 32 31 34 38 40 42 43 45 46 48 48 50 50 52 39 41 44 47 47 53 53 51 51 C C D D E F F G N R U X X CC HH LL LL NN NN DD FF GG BB AA Z Y W V T S P M K L J PP PP QQ QQ RR RR SS SS MM MM KK 8 8 B 9 Q EXPOSAIC AVENUEGIFFORD HILL DRIVESUGAREE STREET 5.00% 708' - 0" 703' - 4 1/4" 705' - 0" 704' - 9" LOADING/ENTRY 147 701' - 2" 8.33%5.28%ELEV 4 ELEV 1 ELEV 2 E-2 E-3 E-5 E-4 E-6 E-9 E-8GARAGE VENT GARAGE VENT MP1-1 MP1-9 MP1-5 MP1-6 MP1-7 MP1-8 TMP1-1 MP1-10 TMP1-2 MP1-12 MP1-13 MP1-11 MP1-14 MP1-15 ELEC. E-7 LEASING COWORK WORK ROOM OFFICE PACKAGE ROOM OFFICE MP1-3 MP1-4 E-1 MP1-2 PATIOPATIO PATIO PATIOPATIO PATIO TMP1-3 VAPOR INTRUSION MITIGATION PLAN PREPARED BY: 2923 South Tryon Street-Suite 100 Charlotte, North Carolina 28203 704-586-0007(p) 704-586-0373(f) License # C-1269 / #C-245 Geology VAPOR INTRUSION MITIGATION SYSTEM PLAN VIEW LAYOUT LEVEL 1 VM-1 PROFESSIONAL APPROVAL LEGEND OPEN-AIR OR PARKING DECK SPACE EXTENT OF VAPOR BARRIER (LEVEL 1) LOCATION OF INTERIOR FOOTERS (NOT ALL FOOTERS SHOWN) 3" SLOTTED HORIZONTAL COLLECTION PIPING 3" DIA SUBGRADE SCH 40 SOLID PVC PIPE ABOVE GRADE SCH 40 SOLID PVC PIPE (CONTINUE PIPE SIZE FROM BELOW) 3" DIA SCH 40 SOLID PVC VERTICAL RISER WITH IDENTIFICATION NUMBER (4" DIA WHERE NOTED) SCH 40 SOLID PVC VERTICAL RISER TO NEXT LEVEL (CONTINUE PIPE SIZE FROM BELOW) 2" DIA SOLID PVC MONITORING POINT WITH IDENTIFICATION NUMBER PROPOSED 2" DIA SOLID PVC TEMPORARY MONITORING POINT WITH IDENTIFICATION NUMBER SLAB STEP E-1 NOTES: 1.REFER TO DETAILS ON VM-A THROUGH VM-C AND SPECIFICATIONS ON SHEET VM-D. 2.STANDARD SLIP JOINT OR SOLVENT WELDED SCH 40 PVC FITTINGS SHALL BE USED ON HORIZONTAL SUB-SLAB COLLECTION PIPE. ABOVE-SLAB PIPES SHALL BE AIR-TIGHT WITH PVC PRIMER AND GLUE (SEE SPECIFICATION #4). 3.ALL HORIZONTAL, NON-SLOTTED SUB-SLAB PIPES SHOULD BE SLOPED 1% (1/8" PER FOOT) TOWARDS SLOTTED PIPE. ALL ABOVE-SLAB HORIZONTAL PIPES SHALL BE SLOPPED 1% (1/8" PER FOOT) TOWARDS THE SLAB PENETRATION. 4.ALL ABOVE-SLAB PIPING SHALL UTILIZE LONG-RADIUS ELBOWS UNLESS APPROVED OTHERWISE BY THE DESIGN ENGINEER. 5.THE END OF EACH HORIZONTAL COLLECTION PIPE AND EACH MONITORING POINT SHALL BE OPEN-ENDED OR CONTAIN A TERMINATION SCREEN PER SPECIFICATIONS #3 & #7. 6.THE INTAKE OF THE MONITORING POINTS SHALL BE A MINIMUM 12-INCHES FROM EXTERIOR WALLS OR FOOTINGS, OR AS OTHERWISE APPROVED BY THE DESIGN ENGINEER. 7.VIMS EXHAUST ABOVE-SLAB SOLID PIPING MAY BE ADJUSTED ALONG CEILINGS AND WALLS TO REACH THE FINAL TERMINATION POINT DEPICTED IN THESE PLANS, PENDING DESIGN ENGINEER APPROVAL. ABOVE-SLAB PIPING SHALL MINIMIZE TOTAL DISTANCE AND THE NUMBER OF TURNS, AND SATISFY THE CRITERIA LISTED IN SPECIFICATION #4. H&H NO. S2K-001 ARCHITECT: BB+M 1900 WEST MOREHEAD STREET, SUITE 200 CHARLOTTE, NC SUGAR CREEK MF4101 GREENSBORO STREETCHARLOTTE, NORTH CAROLINABROWNFIELDS PROJECT NO. 22040-18-060DATE: 8-29-23 LEVEL 2 ABOVE LEVEL 2 ABOVE LEVEL 2 ABOVE TO LEVEL 2 PARKING ABOVE PARKING ABOVE LIVING SPACE ABOVE LEVEL 2 ABOVE LEVEL 2 EXTENTS LEVEL 2 EXTENTS LEVEL 2 EXTENTS LEVEL 2 EXTENTS MP1-1 TMP1-1 SLIGHT OFFSET AT LEVEL 1 CEILING SLIGHT OFFSET AT LEVEL 1 CEILING OR LEVEL 2 FLOOR DUE TO PLUMBING ON LEVEL 2 28/32 VM-C31 VM-C 28 VM-C 28 VM-C 28 VM-C 28 VM-C 28/32 VM-C 34A/D VM-C 34A/D VM-C 34 VM-C 34A/D VM-C 34 VM-C 34 VM-C 34A/D VM-C 34C/E VM-C 34 VM-C 34 VM-C 34 VM-C 34 VM-C 34 VM-C 16 VM-B 16 VM-B 19 VM-B 18 VM-B 20 VM-B 24 VM-B 20 VM-B 18 VM-B 23/24 VM-B 23/24 VM-B 9 VM-A 18 VM-B 18 VM-B 26 VM-B 27 VM-B 23 VM-B 26 VM-B 1 VM-A 12 VM-A 2 VM-A 2 VM-A23 VM-B 4 VM-A 5 VM-A 10 VM-A 8 VM-A 6 VM-A 13/14 VM-A 12 VM-A 13 VM-A 14 VM-A 12 VM-A 5 VM-A 12 VM-A 13 VM-A 24 VM-B 2 VM-A 28 VM-C 26 VM-B 23 VM-B TEMPORARY MONITORING POINT TEMPORARY MONITORING POINT 34C VM-C 26 VM-B 1 VM-A 10 VM-A 9 VM-A 4 VM-A 29/32 VM-C OFFSET AT LEVEL 1 CEILING OPEN-AIR PATIO 4" DIA PVC RISER PARKING ABOVE 08/29/23 \\harthick.sharepoint.com@SSL\DavWWWRoot\sites\MasterFiles-1\Shared Documents\AAA-Master Projects\S2K Charlotte\Metromont Concrete Facility\VIMP\CAD\Sugar Creek MF_VIMS_R0.dwg, VM-1, 8/29/2023 3:13:17 PM,mvawter E-13 GRE E N S B O R O S T R E E T EXPOSAIC AVENUEGIFFORD HILL DRIVESUGAREE STREET COURTYARD BELOW ELEC.M. STO 715' - 8"8.33%713' - 8"8.33% UNIT S1 ALT. 229 REF A2.50a M. STO ELEC UNIT S2 ALT. 2 248 REF A2.51a UPDOWNDOWNUNIT A4 258 REF A2.63 UNIT B3 ALT 260 REF A2.72a UNIT B1 261 REF A2.70a UNIT S1 ALT 2 230 REF A2.50a UNIT B2 233 REF A2.71a UNIT A2 237 REF A2.61 UNIT A2 239 REF A2.61 UNIT A2 205 REF A2.61 UNIT A2 205 REF A2.61 UNIT B2 207 REF A2.71a UNIT S1 209 REF A2.50a UNIT S1 209 REF A2.50a UNIT S1 211 REF A2.50a UNIT S1 211 REF A2.50a UNIT S1 213 REF A2.50a UNIT S1 213 REF A2.50a UNIT A1 215 REF A2.60a UNIT A1 215 REF A2.60a UNIT A1 217 REF A2.60a UNIT A1 217 REF A2.60a UNIT A1 ALT 243 REF A2.60a UNIT S6 245 REF A2.55 UNIT S6 246 REF A2.55 715' - 8" UNIT A2 TYPE A 235 REF A2.81 UNIT S2 ALT. 2 244 REF A2.51a UNIT S2 ALT. 2 247 REF A2.51a UNIT B5 204 REF A2.74a UNIT A6 206 REF A2.65 UNIT A6 208 REF A2.65 UNIT A1 ALT 238 REF A2.60a UNIT S1 236 REF A2.50a UNIT A5 234 REF A2.64 UNIT A6 227 REF A2.65 UNIT A6 225 REF A2.65 UNIT A6 210 REF A2.65 UNIT B5 212 REF A2.74a UNIT A1 ALT 218 REF A2.60a UNIT S1 219 REF A2.50a UNIT A5 220 REF A2.64UNIT A6 223 REF A2.65 UNIT S3 203 REF A2.52 UNIT B3 242 REF A2.72a RISER 255 LOBBY 254 712' - 0" 712' - 0" UNIT A1 ALT 243 REF A2.60a UNIT S2 ALT. 2 247 REF A2.51a 715' - 8" ALUM. SUN SHADE ABOVE BUILDING EXTENTS ABOVE FITNESS 775CORRIDOR 200 M 1 1 37 37 49 49 H H JJ JJ EE A A 2 2 3 4 4 5 5 7 76 10 11 11 12 14 19 25 27 2321 2616 16 29171518202428 22 30 35 35 3332 32 31 34 38 40 42 43 45 46 48 48 50 50 52 39 4136 44 47 5351 C C D D E F F G N R U X X CC HH LL LL NN NN DD FF GG BB AA Z Y W V T S P M K L J PP PP QQ QQ RR RR SS SS MM MM KK 8 8 B 9 Q UNIT A3 257 REF A2.62 UNIT A3 256 REF A2.62 OPEN TO BELOW 8.33%UNIT A6 331 REF A2.65 UNIT A1 217 REF A2.60a UNIT A1 217 REF A2.60a UNIT A1 217 REF A2.60a ELEV 3 ELEV 4 ELEV 1 ELEV 2 E-15 E-11 E-10 STAIR C STAIR A STAIR B GARAGE VENT GARAGE VENT E-1 E-2 E-3 E-5 E-4 E-6 E-7 E-8 MP2-1 TMP2-1 MP2-2 MP2-4 MP2-3 MP2-5 MP2-7 MP2-6 E-12 E-14 ART STUDIO VIEWING ROOM CLUB ROOM GAMING LOUNGE E-9 53 237 PATIOPATIO PATIO PATIO PATIO PATIO PATIO PATIO PATIOPATIOPATIO VAPOR INTRUSION MITIGATION PLAN PREPARED BY: 2923 South Tryon Street-Suite 100 Charlotte, North Carolina 28203 704-586-0007(p) 704-586-0373(f) License # C-1269 / #C-245 Geology VAPOR INTRUSION MITIGATION SYSTEM PLAN VIEW LAYOUT LEVEL 2 VM-2 PROFESSIONAL APPROVAL H&H NO. S2K-001 ARCHITECT: BB+M 1900 WEST MOREHEAD STREET, SUITE 200 CHARLOTTE, NC SUGAR CREEK MF4101 GREENSBORO STREETCHARLOTTE, NORTH CAROLINABROWNFIELDS PROJECT NO. 22040-18-060DATE: 8-29-23 LEGEND OPEN-AIR OR PARKING DECK SPACE EXTENT OF LEVEL 1 VIMS (SEE VM-1) EXTENT OF VAPOR BARRIER (LEVEL 2) LOCATION OF INTERIOR FOOTERS (NOT ALL FOOTERS SHOWN) 3" SLOTTED HORIZONTAL COLLECTION PIPING 3" SUBGRADE SCH 40 SOLID PVC PIPE ABOVE GRADE SCH 40 SOLID PVC PIPE (CONTINUE PIPE SIZE FROM BELOW) 3" DIA SCH 40 SOLID PVC VERTICAL RISER WITH IDENTIFICATION NUMBER (4" DIA WHERE NOTED) SCH 40 SOLID PVC VERTICAL RISER TO NEXT LEVEL (CONTINUE PIPE SIZE FROM BELOW) 2" DIA SOLID PVC MONITORING POINT WITH IDENTIFICATION NUMBER PROPOSED 2" DIA SOLID PVC TEMPORARY MONITORING POINT WITH IDENTIFICATION NUMBER SLAB STEP E-1 NOTES: 1.REFER TO DETAILS ON VM-A THROUGH VM-C AND SPECIFICATIONS ON SHEET VM-D. 2.STANDARD SLIP JOINT OR SOLVENT WELDED SCH 40 PVC FITTINGS SHALL BE USED ON HORIZONTAL SUB-SLAB COLLECTION PIPE. ABOVE-SLAB PIPES SHALL BE AIR-TIGHT WITH PVC PRIMER AND GLUE (SEE SPECIFICATION #4). 2.RISER PIPE SHALL CONTINUE THE SAME PIPE SIZE AS PREVIOUS LEVEL. 3.ALL HORIZONTAL, NON-SLOTTED SUB-SLAB PIPES SHOULD BE SLOPED 1% (1/8" PER FOOT) TOWARDS SLOTTED PIPE. ALL ABOVE-SLAB HORIZONTAL PIPES SHALL BE SLOPPED 1% (1/8" PER FOOT) TOWARDS THE SLAB PENETRATION. 4.ALL ABOVE-SLAB PIPING SHALL UTILIZE LONG-RADIUS ELBOWS UNLESS APPROVED OTHERWISE BY THE DESIGN ENGINEER. 5.THE END OF EACH HORIZONTAL COLLECTION PIPE AND EACH MONITORING POINT SHALL BE OPEN-ENDED OR CONTAIN A TERMINATION SCREEN PER SPECIFICATIONS #3 & #7. 6.THE INTAKE OF THE MONITORING POINTS SHALL BE A MINIMUM 5 FT FROM EXTERIOR WALLS OR FOOTINGS, OR AS OTHERWISE APPROVED BY THE DESIGN ENGINEER. 7.VIMS EXHAUST ABOVE-SLAB SOLID PIPING MAY BE ADJUSTED ALONG CEILINGS AND WALLS TO REACH THE FINAL TERMINATION POINT DEPICTED IN THESE PLANS, PENDING DESIGN ENGINEER APPROVAL. ABOVE-SLAB PIPING SHALL MINIMIZE TOTAL DISTANCE AND THE NUMBER OF TURNS, AND SATISFY THE CRITERIA LISTED IN SPECIFICATION #4. MP2-1 TMP2-1 28 VM-C 28 VM-C 30 VM-C 28 VM-C 29 VM-C 29 VM-C E-1 E-2 E-5 E-6 E-7 34A VM-C 34C/E VM-C 34C/E VM-C 34C VM-C 34C/E VM-C 34C/E VM-C 34 VM-C 16 VM-B 26 VM-B 27 VM-B 26 VM-B 20 VM-B 20 VM-B 20 VM-B FROM LEVEL 119 VM-B 18 VM-B 12 VM-A 14 VM-A 1 VM-A 1 VM-A 2 VM-A 18 VM-B 18 VM-B 18 VM-B 8 VM-A 6 VM-A 3 VM-A 8 VM-A 3 VM-A 9 VM-A 12 VM-A14 VM-A 2 VM-A TEMPORARY MONITORING POINT 27 VM-B 26 VM-B SLIGHT OFFSET AT LEVEL 2 CEILING (SEE DETAIL 32/VM-C) OPEN-AIR PATIO OPEN-AIR PATIO OPEN-AIR PATIO 4" DIA PVC 08/29/23 \\harthick.sharepoint.com@SSL\DavWWWRoot\sites\MasterFiles-1\Shared Documents\AAA-Master Projects\S2K Charlotte\Metromont Concrete Facility\VIMP\CAD\Sugar Creek MF_VIMS_R0.dwg, VM-2, 8/29/2023 3:13:41 PM,mvawter TRASH CHUTES ELEVATOR OVER RUN ELEVATOR OVER RUN ELEVATOR OVER RUN RAMP UPRAMP DNSLOPE MIN.1/4" = 1'-0"SLOPE MIN.1/4" = 1'-0"SLOPE MIN. 1/4" = 1'-0" SLOPE MIN. 1/4" = 1'-0"SLOPE MIN.1/4" = 1'-0"SLOPE MIN.1/4" = 1'-0"SLOPE MIN. 1/4" = 1'-0" SLOPE MIN. 1/4" = 1'-0" ROOF HATCH ACCESS COURTYARD BELOW NON-COMBUSTIBLE ROOF DECKING NON-COMBUSTIBLE ROOF DECKING CENTERLINE OF FIREWALL BELOW CENTERLINE OF FIREWALL BELOW RAISED SKY LOUNGE ROOF E-14 E-13 E-12 E-11 E-10 E-2 E-3 E-5 E-4 E-6 E-7 E-8 E-1 E-15 E-9 E-14 VAPOR INTRUSION MITIGATION PLAN PREPARED BY: 2923 South Tryon Street-Suite 100 Charlotte, North Carolina 28203 704-586-0007(p) 704-586-0373(f) License # C-1269 / #C-245 Geology VAPOR INTRUSION MITIGATION SYSTEM PLAN VIEW LAYOUT ROOF VM-3 PROFESSIONAL APPROVAL NOTES: 1. REFER TO DETAILS ON VM-A THROUGH VM-C AND SPECIFICATIONS ON SHEET VM-D. 2. RISER PIPE SHALL CONTINUE THE SAME PIPE SIZE AS PREVIOUS LEVEL. 3. ABOVE-SLAB PIPES SHALL BE PVC WITH AIR-TIGHT FITTINGS (SEE SPECIFICATION #4). 4. ALL ABOVE-SLAB HORIZONTAL PIPES SHALL BE SLOPPED 1% (1/8" PER FOOT) TOWARDS THE SLAB PENETRATION. 5. ALL ABOVE-SLAB PIPING SHALL UTILIZE LONG-RADIUS ELBOWS UNLESS APPROVED OTHERWISE BY THE DESIGN ENGINEER. 6. VIMS EXHAUST ABOVE-SLAB SOLID PIPING MAY BE ADJUSTED ALONG CEILINGS AND WALLS TO REACH THE FINAL TERMINATION POINT DEPICTED IN THESE PLANS, PENDING DESIGN ENGINEER APPROVAL. ABOVE-SLAB PIPING SHALL MINIMIZE TOTAL DISTANCE AND THE NUMBER OF TURNS, AND SATISFY THE CRITERIA LISTED IN SPECIFICATION #4. 7. EXHAUST LOCATIONS MUST BE, AT MINIMUM: 7.1. 20-FT ABOVE FINAL EXTERIOR GRADE 7.2. 10 FT FROM ANY OPERABLE OPENINGS OR PUBLIC ACCESS 7.3. 10 FT FROM ANY AIR INTAKES 8. ELECTRICAL OUTLETS (120 VAC, MIN 15 AMP) MUST BE INSTALLED NEAR EXHAUSTS FOR POTENTIAL FUTURE ELECTRIC FAN INSTALLATION. H&H NO. S2K-001 ARCHITECT: BB+M 1900 WEST MOREHEAD STREET, SUITE 200 CHARLOTTE, NC SUGAR CREEK MF4101 GREENSBORO STREETCHARLOTTE, NORTH CAROLINABROWNFIELDS PROJECT NO. 22040-18-060LEGEND OPEN AIR SPACE TO LOWER LEVEL SCH 40 SOLID PVC PIPE (CONTINUE PIPE SIZE FROM BELOW) 3" DIA VERTICAL RISER WITH EXHAUST IDENTIFICATION NUMBER (4" DIA WHERE NOTED)E-1 DATE: 8-29-23 OFFSET: MIN. 10-FT FROM OPENINGS OR INTAKES (4" DIA PVC) 33A VM-C 33 VM-C 33 VM-C 33 VM-C 33 VM-C 33 VM-C 33 VM-C 33 VM-C 33 VM-C 33 VM-C 33 VM-C 33 VM-C 33 VM-C 33 VM-C 33 VM-C 08/29/23 \\harthick.sharepoint.com@SSL\DavWWWRoot\sites\MasterFiles-1\Shared Documents\AAA-Master Projects\S2K Charlotte\Metromont Concrete Facility\VIMP\CAD\Sugar Creek MF_VIMS_R0.dwg, VM-3, 8/29/2023 3:14:49 PM,mvawter 3" SCH 40 SLIP JOINT SLOTTED PVC PIPE SET WITHIN MIN 4" BASE COURSE (SEE SPECIFICATION #3) VAPOR BARRIER (SEE SPECIFICATION #2) SUB-BASE CONCRETE FLOOR SLAB SLOTTED COLLECTION PIPE (TYP) NTS VAPOR BARRIER AND BASE COURSE (TYP)1 BASE COURSE - CLEAN #57 STONE, OR SIMILAR, MIN 4" THICK BENEATH VAPOR BARRIER (SEE SPECIFICATION #2) VAPOR BARRIER (SEE SPECIFICATION #2) CONCRETE FLOOR SLAB SUB-BASE NTSVM-A VIMS PIPING THROUGH THICKENED FOOTING NTS 6 VM-A VIMS AT THICKENED SLAB (TYP) NTS 5 VM-A 2 VM-A T.O.C.SLP. VIMS AT RAMP WITH SLOTTED PIPE NTS 4 VM-A SLP. VIMS AT RAMP (TYP) NTS 3 VM-A PVC TERMINATION SCREEN (SEE SPECIFICATION #3) BASE COURSE SUB-BASE SOLID 3" SCH 40 PVC VAPOR BARRIER SEALED TO PIPE PER MANUFACTURER INSTRUCTIONS PROVIDE PIPE SUPPORT TO PREVENT LOW POINT IN SOLID PIPE. MAINTAIN 1% SLOPE TOWARD SLOTTED SECTION OF PIPE VAPOR BARRIER SOLID TO SLOTTED 3" SCH 40 PVC PIPE TRANSITION (SLIP COUPLING OR THREADED JOINT) WALL (VARIES) PIPE SLEEVE (SEE SPECIFICATION #12) VAPOR BARRIER WALL (VARIES) ENCLOSED SPACE ENCLOSED SPACE CONTINUOUS VAPOR BARRIER INSTALLED DIRECTLY BELOW CONCRETE FOOTER PER MANUFACTURER INSTRUCTIONS BASE COURSE SUB-BASE VAPOR BARRIER SUB-BASE SLOTTED 3-INCH SCH 40 PIPE VAPOR BARRIER (SEE SPECIFICATION #2)CONCRETE FLOOR SLAB BASE COURSE (SEE SPECIFICATION #2) SUB-BASE VAPOR BARRIER (SEE SPECIFICATION #2)CONCRETE FLOOR SLAB BASE COURSE (SEE SPECIFICATION #2) VIMS PIPING THROUGH SLAB STEP NTS 10 VM-A VIMS PIPING AT DEPRESSIONS IN SLAB-ON-GRADE NTS 8 VM-A NOTE: 90-DEGREE ELBOWS CAN BE USED IF SLAB STEP HEIGHT/DISTANCE DOES NOT PROVIDE SUFFICIENT SPACE FOR 45-DEGREE ELBOWS VIMS AT STAIR THICKENED SLAB (IF PRESENT)11 NTSVM-A VIMS AT SLAB STEP (TYP) NTS 9 VM-A SUB-BASE CONCRETE FLOOR SLAB VAPOR BARRIER BASE COURSE SOLID TO SLOTTED 3" SCH 40 PVC PIPE TRANSITION (SLIP COUPLING OR THREADED JOINT) 3" SCH 40 PVC 45-DEGREE OR 90-DEGREE ELBOW VAPOR BARRIER SEALED TO PIPE PER MANUFACTURER INSTRUCTIONS SOLID 3" SCH 40 PVCPIPE SLEEVE (SEE SPECIFICATION #12) WALL (VARIES) SUBBASE BASE COURSE 3" SCH 40 PVC 45-DEGREE ELBOW 3" SCH 40 SLOTTED PVC PIPE STAIR STRINGER (ORIENTATION VARIES) SUBBASEBASE COURSE CONCRETE FLOOR SLAB VAPOR BARRIER SOLID TO SLOTTED 3" SCH 40 PVC PIPE TRANSITION (SLIP COUPLING OR THREADED JOINT) VAPOR BARRIER SEALED TO PIPE PER MANUFACTURER INSTRUCTIONS PVC TERMINATION SCREEN (SEE SPECIFICATION #3) SUB-BASE BASE COURSE VAPOR BARRIER WALL (VARIES) PIPE SLEEVE (SEE SPECIFICATION #12) VIMS AT DEPRESSIONS IN SLAB-ON-GRADE (TYP) NTS 7 VM-A VAPOR BARRIER WALL (VARIES) SUBBASEBASE COURSE WALL (VARIES) VAPOR BARRIER VIMS AT INTERIOR COLUMN NTS 12 VM-A VIMS AT COLUMNS AND SHEAR WALLS - EXPANSION DETAIL (TYP) NTS 15 VM-A COLUMN BLOCKOUT VIMS AT EXTERIOR COLUMN AT OPEN-AIR SPACE NTS 13 VM-A MOISTURE BARRIER, IF WARRANTED, BY OTHERS VIMS AT PERIMETER COLUMN NTS 14 VM-A SUB-BASE CONCRETE FLOOR SLAB BASE COURSE VAPOR BARRIER CONCRETE COLUMN CONCRETE FOOTING VAPOR BARRIER SEALED OUTSIDE OF CONCRETE COLUMN ON ALL FOUR SIDES PER MANUFACTURER INSTRUCTIONS SEE DETAIL 15/VM-A SUB-BASE CONCRETE FLOOR SLAB CONCRETE FOOTING VAPOR BARRIER SEALED OUTSIDE OF CONCRETE COLUMN ON ALL SIDES PER MANUFACTURER INSTRUCTIONS SEE DETAIL 15/VM-A OPEN-AIR SPACE ENCLOSED INTERIOR BASE COURSE OPTIONAL VAPOR BARRIER INSTALLATION METHOD (OPEN-AIR SIDE ONLY): TERMINATE VAPOR AT SOIL GRADE, WHERE APPLICABLE WALL (VARIES) CIP CONCRETE COLUMN GRAVEL BETWEEN OPEN-AIR SPACE AND OCCUPIED SPACE SHALL BE DISCONTINUOUS (SEE SPECIFICATION #9) SUB-BASE CONCRETE FLOOR SLAB BASE COURSE VAPOR BARRIER CONCRETE COLUMN TERMINATE VAPOR BARRIER AT SOIL GRADE, WHERE APPLICABLE SEE DETAIL 15/VM-A OPEN-AIR SPACE FACADE WALL (IF PRESENT) CONCRETE COLUMN CONCRETE FLOOR SLAB VAPOR BARRIER SEALED TO CONCRETE PER MANUFACTURERS INSTRUCTIONS (e.g., VIAFLEX BUTYL-SEAL OR STEGO DRAGO-TACK TAPE) COLUMN EXPANSION FORM (INSTALLED OVER VAPOR BARRIER) VAPOR BARRIER VAPOR BARRIER SEALED OUTSIDE OF CONCRETE COLUMN ON ALL SIDES PER MANUFACTURER INSTRUCTIONS ENCLOSED INTERIOR VAPOR INTRUSION MITIGATION PLAN PREPARED BY: 2923 South Tryon Street-Suite 100 Charlotte, North Carolina 28203 704-586-0007(p) 704-586-0373(f) License # C-1269 / #C-245 Geology VAPOR INTRUSION MITIGATION SYSTEM DETAILS #1 - 15 VM-A PROFESSIONAL APPROVAL H&H NO. S2K-001 ARCHITECT: BB+M 1900 WEST MOREHEAD STREET, SUITE 200 CHARLOTTE, NC NOTES: 1.REFER TO SPECIFICATIONS ON SHEET VM-D. DATE: 8-29-23SUGAR CREEK MF4101 GREENSBORO STREETCHARLOTTE, NORTH CAROLINABROWNFIELDS PROJECT NO. 22040-18-06008/29/23 \\harthick.sharepoint.com@SSL\DavWWWRoot\sites\MasterFiles-1\Shared Documents\AAA-Master Projects\S2K Charlotte\Metromont Concrete Facility\VIMP\CAD\Sugar Creek MF_VIMS_R0.dwg, VM-A, 8/29/2023 3:15:42 PM,mvawter 17 VM-B NTS VIMS AT ELEVATOR PIT / RETAINING WALLS - WATERPROOFING DETAIL SOIL SUB-BASE (OR MUD SLAB) VAPOR BARRIER DRAINAGE MAT (IF PRESENT) CONCRETE WATERPROOFING MEMBRANE (IF PRESENT - REFER TO ARCH. PLANS) (SEE SPECIFICATION #13) 16 NTSVM-B VIMS AT ELEVATOR PIT CONTINUOUS VAPOR BARRIER SEALED PER MANUFACTURER INSTRUCTIONS SUMP PIT SUB-BASE BASE COURSE SEE DETAIL 17/VM-B VAPOR BARRIER SEALED TO OUTSIDE OF CONCRETE AND WATERPROOFING MEMBRANE (IF PRESENT) PER MANUFACTURER INSTRUCTIONS (SEE DETAIL 17/VM-B) WATERPROOFING MEMBRANE, BY OTHERS (SEE SPECIFICATION #13) DRAIN WALL (VARIES) CONTINUOUS VAPOR BARRIER, MIN. OVERLAP LENGTH PER MANUFACTURER SPECIFICATIONS (SEE DETAIL 21/VM-B) VIMS AT RETAINING WALL AT ENCLOSED INTERIORS (TYP) NTS 18 VM-B OCCUPIED SPACE SUB-BASE BASE COURSE VAPOR BARRIER DRAIN, IF PRESENT VAPOR BARRIER SEALED TO OUTSIDE OF CONCRETE AND WATERPROOFING MEMBRANE, IF PRESENT, (DESIGNED BY OTHERS) PER MANUFACTURER INSTRUCTIONS (SEE DETAIL 17/VM-B) WALL (VARIES) CONTINUOUS VAPOR BARRIER, MIN. OVERLAP LENGTH PER MANUFACTURER SPECIFICATIONS (SEE DETAIL 21/VM-B) STAIR B VIMS AT STAIRWELL WITH PIPE CONNECTION (STAIR B) NTS 19 VM-B SUB-BASE BASE COURSE VAPOR BARRIER VAPOR BARRIER SEALED TO OUTSIDE OF CONCRETE AND WATERPROOFING MEMBRANE, IF PRESENT (DESIGNED BY OTHERS), PER MANUFACTURER INSTRUCTIONS (SEE DETAIL 17/VM-B) DRAIN WALL (VARIES) CONCRETE FLOOR SLAB SOLID TO SLOTTED 3" SCH 40 PVC PIPE TRANSITION (SLIP COUPLING OR THREADED JOINT) 3" SCH 40 PVC 90-DEGREE ELBOW 3" SCH 40 PVC 45-DEGREE ELBOW PIPE SLEEVE SLOPE WATERPROOFING AND INSULATION DESIGNED BY OTHERS, IF PRESENT CONCRETE FLOOR SLAB CONTINUOUS VAPOR BARRIER, MIN. OVERLAP LENGTH PER MANUFACTURER SPECIFICATIONS (SEE DETAIL 21/VM-B) CONTINUOUS VAPOR BARRIER, MIN. OVERLAP LENGTH PER MANUFACTURER SPECIFICATIONS (SEE DETAIL 21/VM-B) ENCLOSED INTERIOR ENCLOSED INTERIOR OPTION - CONTINUOUS VAPOR BARRIER UNDER STEM WALL OPTION - CONTINUOUS VAPOR BARRIER UNDER STEM WALL VAPOR BARRIER SEALED TO PIPE PER MANUFACTURER INSTRUCTIONS SEE DETAIL 15/VM-A SEE DETAIL 15/VM-A ENCLOSED INTERIOR SPACE VIMS AT STEM WALL ADJACENT TO OPEN AIR SPACE (TYP) NTS 20 VM-B OPEN AIR SPACE SUB-BASE BASE COURSE VAPOR BARRIER WALL (VARIES) SEE DETAIL 15/VM-A DRAIN, IF PRESENT WATERPROOFING, IF PRESENT MOISTURE BARRIER, IF WARRANTED, BY OTHERS CONCRETE FLOOR SLAB 26 VM-B TERMINATE VAPOR BARRIER AT SOIL GRADE, WHERE APPLICABLE VAPOR BARRIER AT SLAB EDGE ADJACENT TO OPEN-AIR SPACE24 NTS MOISTURE BARRIER, IF WARRANTED, BY OTHERS VM-B WALL (VARIES) BASE COURSESUB-BASE VAPOR BARRIER OPEN-AIR SPACE ENCLOSED INTERIOR GRAVEL BETWEEN OPEN-AIR SPACE AND OCCUPIED SPACE SHALL BE DISCONTINUOUS (SEE SPECIFICATION #9) REFER TO STRUCTURAL PLANS FOR FINAL LAYOUT AND FOOTER DIMENSIONS VAPOR BARRIER AT SLAB EDGE PATIO27 NTSVM-B WALL (VARIES) EXTERIOR FASCADE (VARIES) VAPOR BARRIER FINAL GRADE (VARIES) OPEN-AIR PATIO SPACE ENCLOSED INTERIOR OPTIONAL VAPOR BARRIER INSTALLATION METHOD, OR MOISTURE BARRIER (BY OTHERS), IF APPLICABLE TERMINATE VAPOR BARRIER AT SLAB, WHERE POSSIBLE BASE COURSE SUB-BASE VAPOR BARRIER AT SLAB EDGE NTS WALL (VARIES) BASE COURSE SUB-BASE VAPOR BARRIER FINAL GRADE IS BELOW INTERIOR SLAB-ON-GRADE TERMINATE VAPOR BARRIER ON EXTERIOR SEVERAL INCHES BELOW SOIL GRADE, WHERE POSSIBLE ENCLOSED INTERIOR FINAL GRADE IS ABOVE INTERIOR SLAB-ON-GRADE TERMINATE VAPOR BARRIER AT SOIL GRADE, WHERE APPLICABLE ENCLOSED INTERIOR REFER TO STRUCTURAL PLANS FOR FINAL LAYOUT AND FOOTER DIMENSIONS VAPOR BARRIER AT SLAB EDGE WITH BRICK/FACADE25 NTSVM-B WALL (VARIES) WALL (VARIES) VAPOR BARRIER FINAL GRADE ABOVE BRICK/FACADE ENCLOSED INTERIOR SUB-BASE REFER TO STRUCTURAL PLANS FOR FINAL LAYOUT AND FOOTER DIMENSIONS FINAL GRADE IS BELOW BRICK/FACADE ENCLOSED INTERIOR TERMINATE VAPOR BARRIER ON EXTERIOR SEVERAL INCHES BELOW SOIL GRADE, WHERE POSSIBLE OPTIONAL VAPOR BARRIER INSTALLATION METHOD TERMINATE VAPOR BARRIER AT SOIL GRADE, WHERE POSSIBLEBASE COURSE VIMS AT RETAINING WALL / ELEVATOR CREST - VAPOR BARRIER OVERLAP NTS 21 VM-B FINISHED INTERIOR SPACE UNFINISHED INTERIOR SPACE SLAB-ON-GRADE SUB-BASE WALL (VARIES) VAPOR BARRIER (AND WATERPROOFING, IF PRESENT) LEAVE ADDITIONAL ~2-FT OF UNDAMAGED VAPOR BARRIER FOR FUTURE CONTINIOUS VAPOR BARRIER OVERLAP TEMPORARILY TAPE TOP 2" OF VAPOR BARRIER TO WALL (IF POSSIBLE) SUB-BASE BASE COURSE WALL (VARIES) FLOOR (IF PRESENT) CONTINUOUS VAPOR BARRIER OVERLAP (MIN OVERLAP AS SPECIFIED BY MANUFACTURER INSTRUCTIONS) FLOOR (IF PRESENT) VIMS AT EXTERIOR TURNED-DOWN SLAB (IF NEEDED PER SPECIFICATION #9) NTSVM-B 23 VAPOR BARRIER (SEE SPECIFICATION #2) BASE COURSE BETWEEN OPEN-AIR SPACE AND ENCLOSED SPACE SHALL BE DISCONTINUOUS (SEE SPECIFICATION #9) NON-LOAD BEARING WALL (IF PRESENT) OPEN-AIR SPACEENCLOSED SPACE EXTEND TURNED DOWN SLAB MINIMUM 2" BELOW STONE LAYERS. SOIL SUB-BASE EXTEND VAPOR BARRIER ON OUTSIDE OF TURNED DOWN SLAB, WHERE POSSIBLE MOISTURE BARRIER, IF WARRANTED, BY OTHERS VIMS AT INTERIOR TURNED-DOWN SLAB (ONLY IF NEEDED; SEE VM-1 AND VM-2) NTSVM-B 22 VAPOR BARRIER (SEE SPECIFICATION #2) BASE COURSE DISCONTINUOUS AT INTERIOR NON-LOAD BEARING WALLS, ONLY AS SPECIFIED IN THE PLANS (VM-1 AND VM-2) NON-LOAD BEARING WALL (IF PRESENT) ENCLOSED SPACE EXTEND TURNED DOWN SLAB MINIMUM 2" BELOW STONE LAYERS. SOIL SUB-BASE CONTINUOUS VAPOR BARRIER ENCLOSED SPACE BASE COURSE (IF WARRANTED) CONTINUOUS VAPOR BARRIER INSTALLED DIRECTLY BELOW CONCRETE FOOTER PER MANUFACTURER INSTRUCTIONS VAPOR INTRUSION MITIGATION PLAN PREPARED BY: 2923 South Tryon Street-Suite 100 Charlotte, North Carolina 28203 704-586-0007(p) 704-586-0373(f) License # C-1269 / #C-245 Geology VAPOR INTRUSION MITIGATION SYSTEM DETAILS #16 - 27 VM-B PROFESSIONAL APPROVAL H&H NO. S2K-001 ARCHITECT: BB+M 1900 WEST MOREHEAD STREET, SUITE 200 CHARLOTTE, NC NOTES: 1.REFER TO SPECIFICATIONS ON SHEET VM-D. DATE: 8-29-23SUGAR CREEK MF4101 GREENSBORO STREETCHARLOTTE, NORTH CAROLINABROWNFIELDS PROJECT NO. 22040-18-06008/29/23 \\harthick.sharepoint.com@SSL\DavWWWRoot\sites\MasterFiles-1\Shared Documents\AAA-Master Projects\S2K Charlotte\Metromont Concrete Facility\VIMP\CAD\Sugar Creek MF_VIMS_R0.dwg, VM-B, 8/29/2023 3:16:22 PM,mvawter VIMS AT VERTICAL RISERS WITH 90 DEGREE ELBOW (TYP) NTS 29 VM-C VIMS AT VERTICAL RISERS WITH PVC TEE (TYP) NTS 28 VM-C VIMS AT SLAB STEP WITH RISER DUCT PIPING - OPTION (E-1) NTS 31A VM-C VIMS VERTICAL RISER AT INTERIOR COLUMN (E-3) NTS 30 VM-C BASE COURSE SUB-BASE SLOTTED 3" SCH 40 PVC VAPOR BARRIER SEALED TO PIPE PER MANUFACTURER INSTRUCTIONS VAPOR BARRIER 3" DIA SCH 40 RISER DUCT PIPE (SEE SPECIFICATION #4, #5 & #6) WALL OR COLUMN (VARIES) 3" SCH 40 PVC 90-DEGREE ELBOW 3" SCH 40 PVC COUPLING SUPPORT PIPE PER NC CODE AIR-TIGHT 3" DIA COUPLING BASE COURSE (SEE SPECIFICATION #2) SUB-BASE 3" SCH 40 PVC RISER DUCT PIPE (SEE SPECIFICATION #4, #5 & #6) WALL (VARIES) SLOTTED 3" SCH 40 PVC VAPOR BARRIER SEALED TO PIPE PER MANUFACTURER INSTRUCTIONS VAPOR BARRIER (SEE SPECIFICATION #2) 3" SCH 40 PVC TEE SUB-BASE CONCRETE FLOOR SLABVAPOR BARRIER BASE COURSE WALL (VARIES) SOLID TO SLOTTED 3" SCH 40 PVC PIPE TRANSITION (SLIP COUPLING OR THREADED JOINT) VAPOR BARRIER SEALED TO PIPE PER MANUFACTURER INSTRUCTIONS (TYP) 3" SCH 40 PVC 90-DEGREE ELBOW 3" SCH 40 PVC 90-DEGREE TEE PIPE SLEEVE (SEE SPECIFICATION #12) 4" SCH 40 PVC PIPE 3"x4" REDUCER FERNCO (OR SIMILAR) SUB-BASE BASE COURSE VAPOR BARRIER CONCRETE COLUMN SEE DETAIL 15/VM-A VAPOR BARRIER SEALED OUTSIDE OF CONCRETE COLUMN PER MANUFACTURER INSTRUCTIONS VAPOR BARRIER SEALED TO PIPE PER MANUFACTURER INSTRUCTIONS SLOTTED 3" SCH 40 PVC 3" SCH 40 PVC 90-DEGREE ELBOW 3" SCH 40 PVC COUPLING 3" SCH 40 PVC RISER DUCT PIPE (SEE SPECIFICATION #4, #5 & #6) STUD WALL (WHERE PRESENT) VIMS AT SLAB STEP WITH RISER DUCT PIPING (E-1) NTS 31 VM-C SUB-BASE CONCRETE FLOOR SLAB VAPOR BARRIER BASE COURSE WALL (VARIES) VAPOR BARRIER SEALED TO PIPE PER MANUFACTURER INSTRUCTIONS (TYP) 4" SCH 40 PVC LONG-RADIUS 90-DEGREE ELBOW 4" SCH 40 PVC 90-DEGREE TEE PIPE SLEEVE (SEE SPECIFICATION #12) 4" SCH 40 PVC RISER DUCT PIPE (SEE SPECIFICATION #4, #5 & #6) SUPPORT PIPE AS NEEDED TO NOT STRESS TRANSITION COUPLING SLOTTED 3" SCH 40 PVC 4" TO 3" SCH 40 PVC REDUCER (IF APPLICABLE) SLOTTED 3" SCH 40 PVC 4" TO 3" SCH 40 PVC REDUCER 4" SCH 40 SOLID PVC PIPE WITH MIN. TWO (2) 5/8" PERFORATION POSITIONED DOWNWARDS WITHIN BASE COURSE MIN 1% SLOPE TOWARD SLOTTED PVC SLOTTED 3" SCH 40 PVC SLOTTED 3" SCH 40 PVC SOLID TO SLOTTED 3" SCH 40 PVC PIPE TRANSITION (SLIP COUPLING OR THREADED JOINT) 34C VM-C EXTERIOR PERMANENT VACUUM MEASURING POINT (IF WARRANTED) NTS VIMS MONITORING POINT AT WALL CONNECTION (IF WARRANTED) NTS 34D VM-C WALL (VARIES)PROVIDE LOCKABLE WEATHERPROOF ENCLOSURE ON OUTSIDE OF BUILDING WALL (e.g., IP65 HINGED JUNCTION BOX OR SIMILAR). AFFIX LABEL AT BOX WITH "VAPOR MITIGATION SYSTEM". PLACE REMOVABLE PIPE PLUG AT END OF 2" PIPE. 2" SCH 40 PVC 90 DEGREE ELBOW 2" SOLID SCH 40 PVC PIPE INSTALLER SHALL SECURE PIPE TO PREVENT MOVEMENT OR DAMAGE TO PIPE DURING THE CONCRETE POUR EXTERIOR GRADE (VARIES)BASE COURSE PVC TERMINATION SCREEN (SEE SPECIFICATION #7) PIPE SLEEVE. SLEEVE SHALL NOT PENETRATE VAPOR BARRIER (SEE SPECIFICATION #12) VAPOR BARRIER VAPOR BARRIER SEALED TO PIPE PER MANUFACTURERS INSTRUCTIONS POSITION PIPE TO AVOID REINFORCING (REBAR). SEE STRUCTURAL DRAWINGS FOR REINFORCING DETAILS BASE COURSE VAPOR BARRIER SEALED TO PIPE PER MANUFACTURER INSTRUCTIONS WALL (VARIES) POSITION TOP OF 2" PIPE MINIMUM 10" FROM TOP OF ACCESS PANEL DOOR 2" SCH 40 PVC 90 DEGREE ELBOW VAPOR BARRIER 12" X 12" FIRE-RATED WALL ACCESS PANEL TO MATCH FIRE-REATING OF WALL 2" DRAIN EXPANSION TEST PLUG POSITION AT CENTER OF WALL OR ALLOW FOR AT LEAST 1/2" DISTANCE AROUND ALL SIDES OF PIPE 2" SOLID SCH 40 PVC PIPE PVC PRIMER AND GLUE ALL JOINTS ABOVE GRADE EXTERIOR PERMANENT VACUUM MONITORING POINT - GROUND DESIGN34E NTSVM-C EXTERNAL WALL (VARIES) VAPOR BARRIER SHALL SEALED TO PIPE PER MANUFACTURER INSTRUCTIONS 2" SCH 40 PVC 90 DEGREE ELBOW SECURE PIPE WITHIN ENCLOSURE TO PREVENT MOVEMENT PIPE SLEEVE (SEE SPECIFICATION #12) EXTERIOR GRADE (VARIES) PVC TERMINATION SCREEN (SEE SPECIFICATION #7) IRRIGATION STYLE BOX ENCLOSURE ON OUTSIDE OF BUILDING WALL (OR SIMILAR). AFFIX LABEL AT BOX WITH "VAPOR MITIGATION SYSTEM". PLACE REMOVABLE WATERTIGHT PIPE PLUG AT END OF 2" PIPE. OPEN BOTTOM TO ALLOW WATER DRAINAGE PVC TERMINATION SCREEN (SEE SPECIFICATION #7) SEE DETAILS 25/VM-B AND 26/VM-B FOR LOCATION OF VAPOR BARRIER TERMINATION SEE DETAILS 25/VM-B AND 26/VM-B FOR LOCATION OF VAPOR BARRIER TERMINATION SEAL PIPE AT CONCRETE JOINT WITH CAULK VIMS RISER WITH UPPER LEVEL OFFSET (IF NEEDED) NTS 32 VM-C MIN 1% SLOPE TOWARD EXTRACTION POINT CEILING TRUSSES NEXT LEVEL FLOOR PIPE SUPPORTS PER NC BUILDING CODE NEXT LEVEL WALL (VARIES) FROM LOWER LEVEL RISER (MATCHING PIPE SIZE) TO NEXT LEVEL AND/OR ROOF EXHAUST EXHAUST (MATCHING PIPE SIZE) SCH 40 90-DEGREE PVC LONG-RADIUS ELBOW SCH 40 90-DEGREE PVC LONG-RADIUS ELBOW VIMS TURBINE VENTILATOR33 NTS FLASHING ROOFTOP VM-C TURBINE VENTILATOR FAN (EMPIRE MODEL TV04SS OR ENGINEER APPROVED EQUIVALENT) OUTDOOR RATED ELECTRICAL JUNCTION BOX FOR POTENTIAL FUTURE VACUUM FAN (REFER TO SPECIFICATION #5) 4" HEAVY DUTY NO HUB COUPLING NO-HUB 4" X 3" REDUCER TURBINE VENTILATOR FAN (EMPIRE MODEL TV04SS OR ENGINEER APPROVED EQUIVALENT) OUTDOOR RATED ELECTRICAL JUNCTION BOX FOR POTENTIAL FUTURE VACUUM FAN (REFER TO SPECIFICATION #5) LOWER LEVEL WALL (VARIES) SCH 40 PVC RISER DUCT PIPE, LENGTHS VARY SCH 40 PVC RISER DUCT PIPE, LENGTHS VARY PREVIOUS LEVEL CEILING (IF PRESENT) 3" RISER DUCT PIPE THROUGH ROOF 4" RISER DUCT PIPE THROUGH ROOF FLASHING ROOFTOP WIND-DRIVEN VENTILATOR, WITH OFFSET33A NTSVM-C SOLID SCH 40 PVC PIPE (PIPE SIZE AS BELOW; SLOPED TO DRAIN TOWARD VENT); MINIMUM LENGTH AND HEIGHT NECESSARY TO ACHIEVE SPECIFICATION #5 4" HEAVY DUTY NO HUB COUPLING SOLID SCH 40 PVC PIPE THROUGH ROOF (PIPE SIZE AS BELOW) PARAPET WALL (IF PRESENT) ROOFTOP TURBINE VENTILATOR FAN (EMPIRE MODEL TV04SS OR ENGINEER APPROVED EQUIVALENT) RISER SUPPORT CONNECTED TO ROOFTOP (AS NEEDED) ROOF FLASHING SCH 40 90-DEGREE PVC LONG-RADIUS ELBOW VIMS AT UTILITY BANK (IF WARRANTED)35 NTSVM-C INSTALL VAPOR BARRIER AS CLOSELY AS POSSIBLE TO EACH PENETRATION PRIOR TO APPLICATION OF SEALANT SEALANT SET AROUND UTILITY BANKS WITHIN DAM (e.g. VIAFLEX POUR 'N SEAL OR DRAGO SEALANT) WITH 2" MIN OVERLAP WITH VAPOR BARRIER (SEE SPECIFICATION #10) SUB-BASE BASE COURSE VAPOR BARRIER CONCRETE SLAB FINISHED FLOOR ELEVATION 2" SCH 40 PVC SET WITHIN GRAVEL LAYER 2" DRAIN EXPANSION TEST PLUG (OATEY 2-IN GRIPPER, OR SIMILIAR) VIMS MONITORING POINT (TYP) NTSVM-C VAPOR BARRIER PENETRATION SEALED TO PIPE PER MANUFACTURER INSTRUCTIONS 2" SCH 40 PVC 90 DEGREE ELBOW BASE COURSE FLOOR CLEANOUT, ADJUSTABLE, 4" DIA ZURN INDUSTRIES MODEL #CO2450-PV4 (OR ENGINEER APPROVED EQUIVALENT) SEE DETAIL 32/VM-C FLUSH WITH FINISHED FLOOR 34A NTSVM-C VIMS MONITORING POINT WITH EXTENDED INTAKE PIPE 2" DRAIN EXPANSION TEST PLUG 34 BASE COURSE FLOOR CLEANOUT, ADJUSTABLE, 4" DIA ZURN INDUSTRIES MODEL #CO2450-PV4 (OR ENGINEER APPROVED EQUIVALENT) SEE DETAIL 32/VM-C FLUSH WITH FINISHED FLOOR PROVIDE PIPE SUPPORT TO PREVENT LOW POINT IN SOLID SECTION OF PIPE. MAINTAIN MINIMUM 1% SLOPE TOWARD SLOTTED SECTIONS OF PIPE. 34B VIMS MONITORING POINT THROUGH THICKENED SLAB WITH EXTENDED INTAKE PIPE NTSVM-C 2" SOLID SCH 40 PVC FLOOR CLEANOUT, ADJUSTABLE, 4" DIA ZURN INDUSTRIES MODEL #CO2450-PV4 (OR ENGINEER APPROVED EQUIVALENT) FLUSH WITH FINISHED FLOOR BASE COURSE 4" x 2" FLUSH REDUCER BUSHING PVC TERMINATION SCREEN (SEE SPECIFICATION #7) VAPOR BARRIER 2" SOLID SCH 40 PVC LENGTH VARIES - REFER TO SHEET VM-1/VM-2 2" SCH 40 PVC 90-DEGREE ELBOW VAPOR BARRIER PENETRATION SEALED TO PIPE PER MANUFACTURER INSTRUCTIONS WALL (VARIES) PVC TERMINATION SCREEN (SEE SPECIFICATION #7) PIPE SLEEVE (SEE SPECIFICATION #12) PVC TERMINATION SCREEN (SEE SPECIFICATION #7) 2" SCH 40 PVC 90-DEGREE ELBOWVAPOR BARRIER PENETRATION SEALED TO PIPE PER MANUFACTURER INSTRUCTIONS WALL (VARIES) VAPOR BARRIER EXTENDED TO EXTERIOR SIDE OF FOOTER SEVERAL INCHES BELOW FINISHED GRADE, WHERE POSSIBLE OPEN-AIR ENTRANCEENCLOSED INTERIOR 36 VM-C VIMS ELECTRIC FAN AND RISER ON ROOFTOP (IF NEEDED IN FUTURE) NTS ELECTRIC FAN (RADONAWAY RP265 OR ENGINEER-APPROVED EQUIVALENT) FAN LABEL (SEE SPECIFICATION #6) DEDICATED ELECTRIC OUTLET (120V AC) INAREA OF RISER LOCATION - SEE SPECIFICATION #5 CEILING TRUSSES WATERPROOF FLASHING SCH 40 VARMINT SCREEN / PIPE GUARD (RADONAWAY PART #76041-2, OR SIMILAR) ROOFTOP RUBBER NO-HUB REDUCER/COUPLING RUBBER NO-HUB COUPLING SOLID SCH 40 PVC SUPPORT PIPE PER NC BUILDING CODE 3" OR 4" SCH 40 PVC RISER (MATCHING LOWER LEVEL) VAPOR INTRUSION MITIGATION PLAN PREPARED BY: 2923 South Tryon Street-Suite 100 Charlotte, North Carolina 28203 704-586-0007(p) 704-586-0373(f) License # C-1269 / #C-245 Geology VAPOR INTRUSION MITIGATION SYSTEM DETAILS #28 - 36 VM-C PROFESSIONAL APPROVAL H&H NO. S2K-001 ARCHITECT: BB+M 1900 WEST MOREHEAD STREET, SUITE 200 CHARLOTTE, NC NOTES: 1.REFER TO SPECIFICATIONS ON SHEET VM-D. DATE: 8-29-23SUGAR CREEK MF4101 GREENSBORO STREETCHARLOTTE, NORTH CAROLINABROWNFIELDS PROJECT NO. 22040-18-06008/29/23 \\harthick.sharepoint.com@SSL\DavWWWRoot\sites\MasterFiles-1\Shared Documents\AAA-Master Projects\S2K Charlotte\Metromont Concrete Facility\VIMP\CAD\Sugar Creek MF_VIMS_R0.dwg, VM-C, 8/29/2023 3:25:22 PM,mvawter VAPOR INTRUSION MITIGATION PLAN PREPARED BY: 2923 South Tryon Street-Suite 100 Charlotte, North Carolina 28203 704-586-0007(p) 704-586-0373(f) License # C-1269 / #C-245 Geology VAPOR INTRUSION MITIGATION SYSTEM SPECIFICATIONS VM-D PROFESSIONAL APPROVAL H&H NO. S2K-001 VAPOR INTRUSION MITIGATION SYSTEM (VIMS) SPECIFICATIONS 1.THIS VAPOR MITIGATION PLAN IS INTENDED TO BE USED FOR DIRECTION OF VIMS COMPONENT INSTALLATION ONLY AND IS NOT INTENDED TO GUIDE CONSTRUCTION OF BUILDING STRUCTURAL COMPONENTS. CONSTRUCTION CONTRACTOR SHALL VERIFY CONSISTENCY OF VIMS DETAILS WITH APPLICABLE STRUCTURAL, ARCHITECTURAL, MECHANICAL, & PLUMBING PLANS AND RESOLVE ANY INCONSISTENCIES PRIOR TO VIMS INSTALLATION. 2.VIMS VAPOR BARRIER (LINER) SHALL BE VAPORBLOCK PLUS 20 (VBP20) 20-MIL VAPOR LINER MANUFACTURED BY VIAFLEX, INC. (VIAFLEX). AS AN ALTERNATIVE, DRAGO WRAP 20-MIL VAPOR INTRUSION BARRIER MANUFACTURED BY STEGO INDUSTRIES, LLC (STEGO) CAN BE USED, PENDING APPROVAL BY THE VIMS DESIGN ENGINEER (DESIGN ENGINEER). THE VAPOR LINER SHALL BE INSTALLED AS SPECIFIED HEREIN AND PER MANUFACTURER INSTALLATION INSTRUCTIONS TO CREATE A CONTINUOUS LINER BELOW MITIGATED AREAS, ALONG RETAINING WALLS, AND AT SLAB-ON-GRADE STEPS WITHIN THE EXTENT OF VAPOR LINER BOUNDARY. A MINIMUM 4-INCH THICK BASE COURSE CONSISTING OF CLEAN #57 STONE (WASHED WITH NO FINES) SHALL BE INSTALLED BENEATH THE VIMS VAPOR LINER. A SIMILAR HIGH PERMEABILITY STONE MAY BE USED, PENDING APPROVAL BY THE DESIGN ENGINEER AND STRUCTURAL OR GEOTECHNICAL ENGINEER. 2.1.THE VAPOR BARRIER SHALL BE PROPERLY SEALED IN ACCORDANCE WITH THE MANUFACTURER INSTALLATION INSTRUCTIONS AS SPECIFIED IN THESE DRAWINGS AT FOOTERS, SLAB STEPS, RETAINING WALLS, PENETRATIONS (SUCH AS PIPE PENETRATIONS), OR OTHER BUILDING COMPONENTS WITHIN THE VIMS EXTENTS. 2.2.VAPOR BARRIER SHALL BE INSTALLED UNDER SLABS, ON WALLS, AND ALONG OTHER STRUCTURAL COMPONENTS WHICH COME IN CONTACT WITH BOTH AN OCCUPIABLE ENCLOSED SPACE AND SOIL. NOT ALL AREAS FOR THE VAPOR BARRIER MAY BE DEPICTED ON THE DRAWINGS. THE GENERAL CONTRACTOR SHALL VERIFY ALL REQUIRED LOCATIONS FOR VAPOR BARRIER ALONG VERTICAL WALLS PRIOR TO CONSTRUCTION AND BACKFILLING ACTIVITIES. 2.3.ALL CONCRETE BOX-OUTS, INCLUDING BUT NOT LIMITED TO SHOWER/BATH TUB DRAINS, SHALL HAVE A CONTINUOUS VAPOR BARRIER INSTALLED BELOW. 2.4.VAPOR BARRIER SHALL EXTEND ALONG FOOTING EXTERIOR, IF POSSIBLE, AT LOCATIONS WHERE EXTERIOR GRADE IS HIGHER THAN INTERIOR GRADE. 2.5.IN AREAS WITH EXPANSION BOARDS (E.G. ALONG COLUMNS), THE VAPOR BARRIER MUST BE SEALED DIRECTLY TO THE CONCRETE WITH THE EXPANSION BOARD INSTALLED OVER THE VAPOR BARRIER. 2.6.THE INTERFACE OF THE STEEL COLUMNS (IF PRESENT) AND THE CONCRETE SLAB SHALL BE SEALED AT GRADE WITH A SELF-LEVELING POLYURETHANE SEALANT PER DIRECTION OF THE DESIGN ENGINEER OR DESIGN ENGINEER'S DESIGNEE. SIMILAR SEALANT PRODUCTS MAY BE APPROVED BY THE DESIGN ENGINEER. 3.SUB-SLAB SLOTTED VAPOR COLLECTION PIPE SHALL BE SOCKET-WELD 3-INCH (") SCH 40 PVC PIPE WITH 0.020" TO 0.060" SLOT WIDTH AND 1/8" SLOT SPACING. AN ALTERNATE SLOT PATTERN, OR SCH 40 PVC PERFORATED PIPE WITH 5/8" OR SMALLER DIAMETER PERFORATIONS, MAY BE USED PENDING APPROVAL BY THE DESIGN ENGINEER. 3.1.SLOTTED COLLECTION PIPING SHALL BE SET WITHIN THE MINIMUM 4” BASE COURSE LAYER, WITH APPROXIMATELY 1” OF BASE COURSE MATERIAL BELOW THE PIPING. 3.2.A PVC TERMINATION SCREEN (WALRICH CORPORATION #2202052, OR SIMILAR) SHOULD BE INSTALLED ON THE END OF PIPE. 4.3" OR 4" SCH 40 PVC RISER DUCT PIPING SHALL BE INSTALLED TO CONNECT EACH SLAB PENETRATION LOCATION TO A ROOFTOP EXHAUST DISCHARGE POINT WITH STATIONARY VENTILATOR (SEE SPECIFICATION #5). ABOVE-SLAB RISER DUCT PIPE THAT RUNS BETWEEN THE SLAB PENETRATION AND THE ROOFTOP EXHAUST DISCHARGE SHALL BE INSTALLED PER APPLICABLE BUILDING CODE AND AS SPECIFIED IN THE CONSTRUCTION DOCUMENTS AND DRAWINGS. 4.1.VERTICAL RISER PIPING SHALL BE AIRTIGHT, CONNECTED WITH PVC PRIMER AND GLUE. 4.2.VERTICAL RISER PIPING MUST BE INSTALLED PER 2018 NORTH CAROLINA STATE PLUMBING CODE. 4.3.VIMS BELOW AND ABOVE GRADE SOLID PIPING SHALL NOT BE TRAPPED AND SHALL BE SLOPED A MINIMUM OF 1/8 UNIT VERTICAL BY 12 UNITS HORIZONTAL (1% SLOPE) TO GRAVITY DRAIN. BENDS, TURNS, AND ELBOWS IN VERTICAL RISER PIPES SHALL BE MINIMIZED FROM THE SLAB TO THE EXHAUST DISCHARGE. 4.4.ABOVE-SLAB PIPING SHALL UTILIZE LONG-RADIUS ELBOWS UNLESS OTHERWISE APPROVED BY THE DESIGN ENGINEER. 4.5.RISER PIPE SHALL CONTINUE THE SAME PIPE DIAMETER ON EACH LEVEL, UNLESS SHOWN IN THE DETAILS AND/OR APPROVED BY THE DESIGN ENGINEER. 5.THE RISERS SHALL DISCHARGE IN A VERTICAL ORIENTATION AS SHOWN IN THE DESIGN DRAWINGS. EXHAUST DISCHARGE LOCATIONS SHALL BE A MINIMUM 2 FT ABOVE THE BUILDING ROOF LINE AND 10 FT FROM ANY OPERABLE OPENING OR AIR INTAKE INTO THE OCCUPIABLE SPACES OF THE BUILDING. NOTE THAT DISCHARGE LOCATIONS IN THE VAPOR MITIGATION PLAN MAY BE REPOSITIONED AS LONG AS THE NEW POSITION MEETS THE REQUIREMENTS PRESENTED IN THIS SPECIFICATION AND IN ACCORDANCE WITH BUILDING CODE, PENDING DESIGN ENGINEER APPROVAL. 5.1.EMPIRE MODEL TV04SS VENTILATOR (OR ALTERNATE APPROVED BY DESIGN ENGINEER) SHALL BE INSTALLED ON THE EXHAUST DISCHARGE END OF EACH RISER DUCT PIPE. THE RISER DUCT PIPE AND THE VENTILATOR SHALL BE SECURED TO THE PVC RISER IN A VERTICAL ORIENTATION. 5.2.A VARMINT SCREEN, OR DESIGN ENGINEER-APPROVED EQUIVALENT, SHALL BE INSTALLED ON THE EXHAUST DISCHARGE END OF RISER EXHAUST PIPES. 5.3.AN ELECTRICAL JUNCTION BOX (120VAC, MIN 15 AMP REQUIRED) SHALL BE INSTALLED NEAR THE EACH RISER PIPE DISCHARGE LOCATION FOR FUTURE INSTALLATION OF AN ELECTRIC FAN AND SEPARATE VACUUM ALARM, IF WARRANTED. ALL WIRING AND ELECTRICAL SHALL BE INSTALLED PER APPLICABLE BUILDING AND ELECTRICAL CODES. 5.4.REMOVABLE AIR-TIGHT FITTINGS ON RISERS SHALL BE INSTALLED IN A MANNER TO ALLOW ACCESS FOR FUTURE UPFIT OF AN ELECTRIC FAN, IF WARRANTED (SEE DETAIL 36/VM-C). 5.3.THE LOCATION OF DISCHARGE SHALL REMAIN ACCESSIBLE FOR FUTURE MAINTENANCE AND/OR UPFIT TO ELECTRIC FANS. 5.4.WHERE NECESSARY, THE EXHAUST PIPE SHALL BE PROTECTED FROM PHYSICAL DAMAGE BY INSTALLING BOLLARDS, GUARDRAILS, OR OTHER PROTECTIVE BARRIER AROUND THE PIPE 6.ABOVE-SLAB ACCESSIBLE RISER DUCT PIPING SHALL BE PERMANENTLY IDENTIFIED BY MEANS OF A TAG OR STENCIL AT A MINIMUM OF ONCE EVERY ACCESSIBLE 10-LINEAR FT WITH "VAPOR MITIGATION: CONTACT MAINTENANCE". LABELS SHALL ALSO BE FIXED NEAR THE EXHAUST DISCHARGE IN AN ACCESSIBLE LOCATION. 7.MONITORING POINTS SHALL CONSIST OF 2" DIAMETER SCH 40 PVC PIPE WITH A 90-DEGREE ELBOW TO FORM AN “L” SHAPE. A MINIMUM OF 6” SECTION OF PIPE AND MAXIMUM 6 FT SECTION OF PIPE, OR OTHERWISE APPROVED BY THE DESIGN ENGINEER, SHALL BE SET WITHIN THE BASE COURSE LAYER WITH AN OPEN ENDED PIPE OR PIPE PROTECTION SCREEN AT THE TERMINATION. THE PIPE TERMINATION SHALL BE ENCASED WITHIN THE BASE COURSE LAYER. 7.1.THE HORIZONTAL PIPING SHALL BE SLOPED A MINIMUM OF 1/8 UNIT VERTICAL BY 12 UNITS HORIZONTAL (1% SLOPE) TO GRAVITY DRAIN TOWARDS THE PIPE TERMINATION AND PREVENT MOISTURE FROM COLLECTING AT THE 90-DEGREE ELBOW. 7.2.THE MONITORING POINT INTAKE SHALL BE PLACED A MINIMUM OF 12-INCHES FROM EXTERIOR WALLS OR FOOTERS, OR AS OTHERWISE APPROVED BY THE DESIGN ENGINEER. 7.3.MONITORING POINTS LOCATED IN STAIRWELLS ARE INTENDED TO BE INSTALLED BELOW STAIRWELL LANDINGS AND MAY BE RE-POSITIONED TO PROVIDE SUITABLE ACCESS TO THE POINT PER APPROVAL OF THE DESIGN ENGINEER. 7.4.THE SUB-SLAB END OF THE PIPE SHALL CONTAIN A PVC TERMINATION SCREEN, HAVE A MINIMUM OF THREE 5/8" DIA HOLES DRILLED INTO A SOLID CAP, OR BE AN OPEN ENDED PIPE. 7.5.A 4-INCH DIAMETER ADJUSTABLE FLOOR CLEAN-OUT (ZURN INDUSTRIES MODEL #CO2450-PV4, OR EQUIVALENT) SHALL BE INSTALLED AND SET FLUSH WITH THE FINISHED CONCRETE SURFACE FOR FLOOR MOUNTED LOCATIONS. 7.7.MONITORING POINTS IN POUR-BACK AREAS MAY BE REPOSITIONED DURING UPFIT ACTIVITIES WITH PERMISSION OF THE DESIGN ENGINEER. 7.8.IF INSTALLED, TEMPORARY MONITORING POINTS MAY BE ABANDONED USING AIR-TIGHT SEALANT AND CONCRETE AFTER TESTING PER PERMISSION OF THE DESIGN ENGINEER. 8.CONSTRUCTION CONTRACTORS AND SUB-CONTRACTORS SHALL USE "LOW OR NO VOC" PRODUCTS AND MATERIALS, WHEN POSSIBLE, AND SHALL NOT USE PRODUCTS CONTAINING THE COMPOUNDS TETRACHLOROETHENE (PCE) OR TRICHLOROETHENE (TCE). THE CONSTRUCTION CONTRACTOR AND SUB-CONTRACTORS SHALL PROVIDE SAFETY DATA SHEETS (SDS) TO THE DESIGN ENGINEER FOR THE PRODUCTS AND MATERIALS USED FOR CONSTRUCTION OF THE VIMS. 9.IN INSTANCES WHERE A THICKENED FOOTING OR RETAINING WALL IS NOT SPECIFIED AT THE EXTENT OF VAPOR LINER, A THICKENED SLAB OR FOOTER SHALL BE INSTALLED BY THE CONTRACTOR THAT INCLUDES A SOIL SUBBASE TO CREATE A CUT-OFF FOOTER AT THE EXTENT OF VAPOR LINER. THE ADDITIONAL THICKENED SLAB OR FOOTER SHALL NOT ALLOW FOR CONTINUOUS GRAVEL BETWEEN THE VIMS EXTENTS AND EXTERIOR NON-MITIGATED AREAS. 10.CONSTRUCTION CONTRACTORS AND SUB-CONTRACTORS SHALL AVOID THE USE OF TEMPORARY FORM BOARDS THAT PENETRATE THE VAPOR LINER WHERE POSSIBLE. IF TEMPORARY FORM BOARDS ARE USED, THE SIZE AND NUMBER OF PENETRATIONS THROUGH THE VAPOR LINER SHALL BE LIMITED AND SMALL DIAMETER SOLID STAKES (I.E. METAL STAKES) SHALL BE USED. IN ALL CASES, AS FORM BOARDS ARE REMOVED, THE CONTRACTOR OR SUB-CONTRACTORS SHALL RESEAL ALL PENETRATIONS IN ACCORDANCE WITH VAPOR LINER MANUFACTURER INSTALLATION INSTRUCTIONS. 10.1.HOLLOW FORMS OR CONDUITS THAT CONNECT THE SUB-SLAB ANNULAR SPACE TO ENCLOSED ABOVE SLAB SPACES SHALL NOT BE PERMITTED. 10.2.AREAS OF UTILITY BANKS (e.g. LOCATION OF MULTIPLE ADJACENT UTILITIES THROUGH THE SLAB) SHALL BE SEALED TO CREATE AN AIR-TIGHT BARRIER AROUND THE UTILITY CONDUITS USING VIAFLEX POUR N'SEAL OR STEGO-INDUSTRIES DRAGO SEALANT PRIOR TO THE SLAB POUR. OTHER SEALANT METHODS IF USED SHALL BE APPROVED BY THE DESIGN ENGINEER PRIOR TO APPLICATION. SINGLE UTILITY PENETRATIONS SHALL BE SEALED PER THE VAPOR BARRIER MANUFACTURER INSTALLATION INSTRUCTIONS. 11.INSPECTIONS: INSPECTIONS OF EACH COMPONENT OF THE VIMS SHALL BE CONDUCTED BY THE DESIGN ENGINEER, OR DESIGN ENGINEER'S DESIGNEE, TO CONFIRM VIMS COMPONENTS ARE INSTALLED PER THE APPROVED DESIGN. THE REQUIRED INSPECTION COMPONENTS INCLUDE: (1) INSPECTION OF VAPOR BARRIER PRIOR TO BEING COVERED (INCLUDING ELEVATOR PITS AND RETAINING WALLS); (2) INSPECTION OF SUB-SLAB PIPING LAYOUT, (3) GRAVEL PLACEMENT, AND (4) MONITORING POINT PLACEMENT PRIOR TO INSTALLING VAPOR BARRIER; (5) INSPECTION OF VAPOR BARRIER PRIOR TO POURING CONCRETE; (6) INSPECTION OF ABOVE-GRADE PIPING LAYOUT; AND (7) INSPECTION OF EXHAUST DISCHARGE AND RISER DUCT PIPE CONNECTIONS. INSPECTIONS WILL BE COMBINED WHEN POSSIBLE DEPENDING ON THE CONSTRUCTION SEQUENCE/SCHEDULE. THE CONSTRUCTION CONTRACTOR(S) SHALL COORDINATE WITH THE DESIGN ENGINEER TO PERFORM THE REQUIRED INSPECTIONS. A MINIMUM TWO (2) BUSINESS DAY NOTICE SHALL BE GIVEN TO THE DESIGN ENGINEER PRIOR TO THE REQUIRED INSPECTION(S), WITH SUBSEQUENT NOTIFICATION PROVIDED TO NCDEQ BY THE DESIGN ENGINEER. THE CONTRACTORS SHALL NOT COVER COMPONENTS OF THE VIMS WITHOUT INSPECTION AND DESIGN ENGINEER'S, OR DESIGN ENGINEER'S DESIGNEE, APPROVAL. 12.PIPE SLEEVES, WHERE USED, SHALL BE PROPERLY SEALED TO PREVENT A PREFERENTIAL AIR PATHWAY FROM BELOW THE SLAB INTO THE BUILDING. REFER TO TO STRUCTURAL DRAWINGS FOR DETAILS ADDRESSING PIPE SLEEVES. 13.WATERPROOFING INCLUDING MEMBRANES AND DRAINAGE MATS SHALL BE INSTALLED IN ACCORDANCE WITH THE ARCHITECTURAL AND STRUCTURAL PLANS. IF WATERPROOFING IS PRESENT, THE VAPOR BARRIER SHALL BE INSTALLED BETWEEN WATERPROOFING AND ANY DRAINAGE FEATURES INCLUDING DRAINAGE MATS. THE INSTALLER SHALL CONFIRM THAT THE WATERPROOFING PRODUCTS AND SEALANTS USED DURING CONSTRUCTION ARE COMPATIBLE WITH THE SPECIFIED VAPOR BARRIER. DATE: 8-29-23 ARCHITECT: BB+M 1900 WEST MOREHEAD STREET, SUITE 200 CHARLOTTE, NC SUGAR CREEK MF4101 GREENSBORO STREETCHARLOTTE, NORTH CAROLINABROWNFIELDS PROJECT NO. 22040-18-06008/29/23 \\harthick.sharepoint.com@SSL\DavWWWRoot\sites\MasterFiles-1\Shared Documents\AAA-Master Projects\S2K Charlotte\Metromont Concrete Facility\VIMP\CAD\Sugar Creek MF_VIMS_R0.dwg, VM-D, 8/29/2023 3:17:35 PM,mvawter Appendix B Previous Assessment Data Summary and Excerpts Table 1 Summary of Soil Analytical Data Metromont Concrete Facility 4101 Greensboro Street Charlotte, North Carolina H&H Job No. S2K-001 Sample ID SB-1 SB-3 SB-5 SB-6 TW-1 TW-2 Depth (ft bgs)4-8 0-1 8-12 4-7 10 10 Date 4/27/2018 2/4/2019 1/28/2019 Range Mean TPH (8015) DRO 1 0.39 0.24 <0.3 NA NA ----100 ---- GRO <0.62 <0.22 <0.24 <0.3 NA NA ----50 ---- VOCs (8260) Acetone NA NA NA NA 0.15 <0.00084 14,000 210,000 ------ SVOCs (8270)NA NA NA NA ALL BRL NA -------- EPH/VPH (MADEP) C5-C8 Aliphatics (Low) NA NA NA NA <0.64 <0.38 44 310 ------ Total C9-C18 Aliphatics (Medium)NA NA NA NA 5.5 J 1.6 J 20 93 ------ C19-C36 Aliphatics (High)NA NA NA NA 50 NA 47,000 700,000 ------ Total C9-C22 Aromatics (Medium)NA NA NA NA 13 <0.13 62 370 ------ Metals (6020/7471/7199) Arsenic NA NA NA NA NA NA 0.68 3.0 --1.0 - 18 4.8 Barium NA NA NA NA NA NA 3,100 47,000 --50 - 1,000 356 Cadmium NA NA NA NA NA NA 1.4 20 --1.0 - 10 4.3 Chromium (total)NA NA NA NA NA NA NE NE --7.0 - 300 65 Hexavalent Chromium NA NA NA NA NA NA 0.31 6.5 --NS NS Trivalent Chromium NA NA NA NA NA NA 23,000 350,000 --NS NS Lead NA NA NA NA NA NA 400 800 --ND - 50 16 Mercury NA NA NA NA NA NA 4.7 70 --0.03 - 0.52 0.121 Selenium NA NA NA NA NA NA 78 1,200 --<0.1 - 0.8 0.42 Silver NA NA NA NA NA NA 78 1,200 --ND - 5.0 NS Notes: 1) North Carolina Department of Environmental Quality (DEQ) Preliminary Soil Remediation Goals (PSRGs) dated January 2023 2) DEQ Uunderground Storage Tank (UST) Section Action Levels dated July 2016 3) Range and mean values of background metals for North Carolina soils taken from Elements in North American Soils by Dragun and Chekiri, 2005. Background Cd and Ag concentrations were taken from Southeastern and Conterminous US soils. Soil concentrations are reported in milligrams per kilogram (mg/kg).Compound concentrations are reported to the laboratory method detection limits. Only those compounds detected in at least one sample are shown above.Laboratory analytical methods are shown in parentheses. VOCs = volatile organic compounds; SVOCs = semi-volatile organic compounds; ft bgs= feet below ground surface BRL = below laboratory reporting limit; NE = not established; NS= not specified; NA = not analyzed; -- = not applicable; ND = not detected J = Compound was detected above the laboratory method detection limit, but below the laboratory reporting limit resulting in a laboratory estimated concentration. Sample Location 4/26/2018 Northwestern (downgradient) Former UST No. 4 (heating oil tank) Former UST No. 2 (gasoline tank) Former UST No. 3 (heating oil tank) Former UST No. 1 (diesel tank) Former UST No. 2 (gasoline tank) Screening Criteria Residential PSRGs (1) Industrial/ Commercial PSRGs (1) Action Level (2) Regional Background Metals in Soil (3) https://harthick.sharepoint.com/sites/MasterFiles-1/Shared Documents/AAA-Master Projects/S2K Charlotte/Metromont Concrete Facility/EMP/Redevelopment EMP/Tables/Metromont Data Tables 5/31/2023 Table 1 (Page 1 of 2) Hart & Hickman, PC Table 1 Summary of Soil Analytical Data Metromont Concrete Facility 4101 Greensboro Street Charlotte, North Carolina H&H Job No. S2K-001 Sample ID TW-4 BGS-1 BGS-2 Depth (ft bgs)4-5 DUP-1 (4-5)10 5-6 2-4 0-2 Date 1/29/2019 1/29/2019 1/29/2019 Range Mean TPH (8015) DRO NA NA NA NA NA NA ----100 ---- GRO NA NA NA NA NA NA ----50 ---- VOCs (8260) Acetone 0.035 0.021 J <0.0013 0.062 NA NA 14,000 210,000 ------ SVOCs (8270)ALL BRL ALL BRL ALL BRL ALL BRL NA NA -------- EPH/VPH (MADEP) C5-C8 Aliphatics (Low)NA NA <0.51 <0.49 NA NA 44 310 ------ Total C9-C18 Aliphatics (Medium)NA NA 2.0 J <0.79 NA NA 20 93 ------ C19-C36 Aliphatics (High)NA NA <3.6 <3.5 NA NA 47,000 700,000 ------ Total C9-C22 Aromatics (Medium)NA NA <2.2 <2.1 NA NA 62 370 ------ Metals (6020/7471/7199) Arsenic 2.5 2.2 NA NA 2.5 2.1 0.68 3.0 --1.0 - 18 4.8 Barium 39 32 J NA NA 73 75 3,100 47,000 --50 - 1,000 356 Cadmium <0.026 <0.025 NA NA 0.053 J 0.060 J 1.4 20 --1.0 - 10 4.3 Chromium (total)130 110 NA NA 120 67 NE NE --7.0 - 300 65 Hexavalent Chromium 0.86 0.85 NA NA 1.37 0.19 J 0.31 6.5 --NS NS Trivalent Chromium 129.14 109.15 NA NA 118.63 66.81 23,000 350,000 --NS NS Lead 7.2 7.3 NA NA 15 7.6 400 800 --ND - 50 16 Mercury 0.026 J 0.023 J NA NA 0.016 J 0.012 J 4.7 70 --0.03 - 0.52 0.121 Selenium 0.87 J 0.84 J NA NA 0.79 J 0.69 J 78 1,200 --<0.1 - 0.8 0.42 Silver <0.026 <0.025 NA NA 0.031 J 0.023 J 78 1,200 --ND - 5.0 NS Notes: 1) North Carolina Department of Environmental Quality (DEQ) Preliminary Soil Remediation Goals (PSRGs) dated January 2023 2) DEQ Uunderground Storage Tank (UST) Section Action Levels dated July 2016 3) Range and mean values of background metals for North Carolina soils taken from Elements in North American Soils by Dragun and Chekiri, 2005. Background Cd and Ag concentrations were taken from Southeastern and Conterminous US soils. Soil concentrations are reported in milligrams per kilogram (mg/kg).Compound concentrations are reported to the laboratory method detection limits. Only those compounds detected in at least one sample are shown above.Laboratory analytical methods are shown in parentheses. VOCs = volatile organic compounds; SVOCs = semi-volatile organic compounds; ft bgs= feet below ground surfaceBRL = below laboratory reporting limit; NE = not established; NS= not specified; NA = not analyzed; -- = not applicable; ND = not detectedJ = Compound was detected above the laboratory method detection limit, but below the laboratory reporting limit resulting in a laboratory estimated concentration. Former UST No. 4 (heating oil tank) TW-3 / DUP-1 Background Screening Criteria Residential PSRGs (1) Industrial/ Commercial PSRGs (1) Regional Background Metals in Soil (3)Action Level (2)1/28/2019 Former Acid Wash Operations Former UST No. 3 (heating oil tank)Sample Location https://harthick.sharepoint.com/sites/MasterFiles-1/Shared Documents/AAA-Master Projects/S2K Charlotte/Metromont Concrete Facility/EMP/Redevelopment EMP/Tables/Metromont Data Tables 5/31/2023 Table 1 (Page 2 of 2) Hart & Hickman, PC Table 2 Summary of Groundwater Analytical Data Metromont Concrete Facility 4101 Greensboro Street Charlotte, North Carolina H&H Job No. S2K-001 Sample ID TW-1 GW-4 TW-2 TW-3 TW-4 Date 2/4/2019 4/27/2018 1/29/2019 1/30/2019 1/30/2019 Sample Location UST No. 1 UST No. 3 & Former Acid Wash Operations UST No. 4 VOCs (8260/6200/602) Acetone NA 66 <0.31 NA NA <0.31 <0.31 6,000 NE NE 1,1-Dichloroethene NA <0.083 <0.083 NA NA <0.083 <0.083 350 39 160 Chloroform NA <0.076 <0.076 NA NA 0.27 J 0.42 J 70 0.81 3.6 cis-1,2-Dichloroethene NA <0.056 <0.056 NA NA <0.056 <0.056 70 50 210 Methyl-tert Butyl Ether (MTBE)<0.042 <0.042 1.3 <0.042 <0.042 1.2 1.3 20 450 2,000 Tetrachloroethylene NA <0.098 2.6 NA NA <0.098 <0.098 0.7 12 48 Trichlorofluoromethane NA <0.062 <0.062 NA NA <0.062 <0.062 2,000 NE NE Toluene <0.044 <0.044 <0.044 3.0 <0.044 1.2 1.4 600 3,800 16,000 trans-1,2-Dichloroethene NA <0.094 <0.070 NA NA <0.094 <0.094 100 22 91 Trichloroethene NA <0.078 <0.078 NA NA <0.078 <0.078 3 1.0 4.4 Vinyl chloride NA <0.097 <0.097 NA NA <0.097 <0.097 0.03 0.15 2.5 SVOCs (8270/625) Elcosene (TIC)25 NA NE NE NE Vanillin (TIC)14 NA NE NE NE VPH/EPH (MADEP) C5-C8 Aliphatics (Low)<1.7 NA <1.7 5.3 J 8.1 J NA NA 400 14 57 Total C9-C18 Aliphatics (Medium)27 J NA 12 J 12 J 11 J NA NA 700 0.15 0.63 C19-C36 Aliphatics (High)96 J NA NA <85 <75 NA NA 10,000 NE NE Total C9-C22 Aromatics (Medium)<78 NA <0.40 <74 <65 NA NA 200 48 200 Metals (6020/7470) Arsenic NA NA NA 0.49 J NA 0.18 J 0.18 J 10 ---- Barium NA NA NA 160 NA 80 81 700 ---- Cadmium NA NA NA <0.078 NA <0.078 <0.078 2 ---- Chromium (total)NA NA NA 7.4 NA 1.1 J 0.92 J 10 ---- Lead NA NA <5.0 0.90 J NA 0.28 J 0.33 J 15 ---- Mercury NA NA NA <0.000036 NA <0.000036 <0.000036 1 0.18 0.75 Selenium NA NA NA <0.63 NA <0.63 <0.63 20 ---- Silver NA NA NA <0.063 NA <0.063 0.22 J 20 ---- Notes:1) North Carolina Department of Environmental Quality (DEQ) 15A North Carolina Administrative Code 02L.0202 Groundwater Quality Standard dated April 20222) DEQ Division of Waste Management (DWM) Vapor Intrusion Groundwater Screening Levels (GWSLs) dated January 2023Compound concentrations are reported in micrograms per liter (μg/L).Compound concentrations are reported to the laboratory method detection limits.Only those compounds detected in at least one sample are shown in the table above. Laboratory analytical methods are shown in parentheses. Bold values indicates concentration exceeds NCAC 2L Groundwater Standard.Underlined values indicates concentration exceeds DWM Residential GWSL.Grey shaded values indicates concentration exceeds the DWM Non-Residential GWSL.UST = underground storage tank; VOCs = volatile organic compounds; SVOCs = semi-volatile organic compoundsNE = not established; NS= not specified; NA = not analyzed; -- = not applicable; BRL = below laboratory reporting limitJ = Compound was detected above the laboratory method detection limit, but below the laboratory reporting limit resulting in a laboratory estimated concentration. Screening Criteria 2L Standard (1) Residential GWSLs (2) Non-Residential GWSLs (2) TW-5 / DUP-1 1/30/2019 Eastern (upgradient) ALL BRL ALL BRL ALL BRL ALL BRL UST No. 2 ALL BRL https://harthick.sharepoint.com/sites/MasterFiles-1/Shared Documents/AAA-Master Projects/S2K Charlotte/Metromont Concrete Facility/EMP/Redevelopment EMP/Tables/Metromont Data Tables 5/31/2023 Table 2 (Page 1 of 2) Hart & Hickman, PC Table 2 Summary of Groundwater Analytical Data Metromont Concrete Facility 4101 Greensboro Street Charlotte, North Carolina H&H Job No. S2K-001 Sample ID TW-6 GW-1 TW-7 GW-6 TW-8 TW-9 Date 1/30/2019 4/26/2018 1/29/2019 4/26/2018 1/30/2019 1/30/2019 Sample Location Southeastern (upgradient) Southwestern (upgradient) VOCs (8260/6200/602) Acetone <0.31 5.1 <0.31 75 <0.31 <0.31 6,000 NE NE 1,1-Dichloroethene <0.083 1.4 1.1 <0.083 <0.083 <0.083 350 39 160 Chloroform <0.076 <0.076 <0.076 <0.076 <0.076 <0.076 70 0.81 3.6 cis-1,2-Dichloroethene <0.056 170 160 <0.056 <0.056 <0.056 70 50 210 Methyl-tert Butyl Ether (MTBE)<0.042 <0.042 <0.042 <0.042 <0.042 <0.042 20 450 2,000 Tetrachloroethylene <0.098 <0.098 <0.098 <0.098 <0.098 <0.098 0.7 12 48 Trichlorofluoromethane <0.062 1.1 <0.062 <0.062 <0.062 <0.062 2,000 NE NE Toluene 1.5 <0.044 <0.044 <0.044 0.92 J 2.0 600 3,800 16,000 trans-1,2-Dichloroethene <0.094 <0.094 0.57 J <0.094 <0.094 <0.094 100 22 91 Trichloroethene <0.078 24 2.8 <0.078 <0.078 <0.078 3 1.0 4.4 Vinyl chloride <0.097 3.3 0.95 J <0.097 <0.097 <0.097 0.03 0.15 2.5 SVOCs (8270/625) Elcosene (TIC)NE NE NE Vanillin (TIC)NE NE NE VPH/EPH (MADEP) C5-C8 Aliphatics (Low)NA NA NA NA NA NA 400 14 57 Total C9-C18 Aliphatics (Medium)NA NA NA NA NA NA 700 0.15 0.63 C19-C36 Aliphatics (High)NA NA NA NA NA NA 10,000 NE NE Total C9-C22 Aromatics (Medium)NA NA NA NA NA NA 200 48 200 Metals (6020/7470) Arsenic NA NA NA NA NA NA 10 ---- Barium NA NA NA NA NA NA 700 ---- Cadmium NA NA NA NA NA NA 2 ---- Chromium (total)NA NA NA NA NA NA 10 ---- Lead NA NA NA NA NA NA 15 ---- Mercury NA NA NA NA NA NA 1 0.18 0.75 Selenium NA NA NA NA NA NA 20 ---- Silver NA NA NA NA NA NA 20 ---- Notes:1) North Carolina Department of Environmental Quality (DEQ) 15A North Carolina Administrative Code 02L.0202 Groundwater Quality Standard dated April 20222) DEQ Division of Waste Management (DWM) Vapor Intrusion Groundwater Screening Levels (GWSLs) dated January 2023Compound concentrations are reported in micrograms per liter (μg/L).Compound concentrations are reported to the laboratory method detection limits.Only those compounds detected in at least one sample are shown in the table above. Laboratory analytical methods are shown in parentheses. Bold values indicates concentration exceeds NCAC 2L Groundwater Standard.Underlined values indicates concentration exceeds DWM Residential GWSL.Grey shaded values indicates concentration exceeds the DWM Non-Residential GWSL.UST = underground storage tank; VOCs = volatile organic compounds; SVOCs = semi-volatile organic compoundsNE = not established; NS= not specified; NA = not analyzed; -- = not applicable; BRL = below laboratory reporting limitJ = Compound was detected above the laboratory method detection limit, but below the laboratory reporting limit resulting in a laboratory estimated concentration. ALL BRL ALL BRL Northwestern (downgradient)Southern (upgradient) ALL BRL ALL BRLALL BRL Screening Criteria 2L Standard (1) Residential GWSLs (2) Non-Residential GWSLs (2) ALL BRL https://harthick.sharepoint.com/sites/MasterFiles-1/Shared Documents/AAA-Master Projects/S2K Charlotte/Metromont Concrete Facility/EMP/Redevelopment EMP/Tables/Metromont Data Tables 5/31/2023 Table 2 (Page 2 of 2) Hart & Hickman, PC Table 3 Summary of Soil Gas Analytical Data Metromont Concrete Facility 4101 Greensboro Street Charlotte, North Carolina H&H Job No. S2K-001 Sample ID SG-1 SG-3 SG-4 Date 1/31/2019 1/31/2019 2/4/2019 Depth (ft bgs)7 7 7 VOCs (TO-15) Acetone 51 150 87 <66 78 NE NE Benzene 12 22 23 15 1.1 J 12 160 2-Butanone (MEK)12 J <2.3 <2.3 <9.2 41 J 35,000 440,000 Carbon Disulfide 320 400 410 150 <0.77 4,900 61,000 Carbon Tetrachloride 1.6 1.9 J 2.0 J <4.1 <0.74 16 200 Cyclohexane <0.49 940 970 <4.9 <0.88 42,000 530,000 Ethanol 6.9 J <17 <17 <67 36 NE NE Ethyl Acetate <0.54 <1.3 <1.3 <5.4 37 490 6,100 Ethylbenzene 9.5 14 15 16 <0.90 37 490 4-Ethyltoluene 8.6 11 12 <6.0 <1.1 NE NE Heptane 17 900 920 <4.8 4.0 2,800 35,000 Hexane 49 320 330 <12 <2.2 4,900 61,000 Isopropanol 7.2 J <1.5 <1.5 <6.0 15 J 1,400 18,000 Methylene Chloride 1.1 J <2.1 <2.1 <8.4 <1.5 3,400 53,000 4-Methyl-2-pentanone (MIBK)4.3 <0.99 <0.99 <3.9 <0.71 21,000 260,000 Tetrachloroethylene 1.2 J 2.2 J <1.9 <7.5 <1.4 280 3,500 Toluene 180 170 170 3,700 140 35,000 440,000 Trichlorofluoromethane (Freon 11)2.2 J <1.6 <1.6 <6.5 <1.2 NE NE 1,1,2-Trichloro-1,2,2-trifluoroethane (Freon 113)1.4 J <2.3 <2.3 <9.3 <1.7 35,000 440,000 1,2,4-Trimethylbenzene 11 15 17 8.1 J <1.1 420 5,300 1,3,5-Trimethylbenzene 2.4 3.8 <1.5 <6.2 <1.1 420 5,300 m&p-Xylene 39 58 61 51 1.9 J 700 8,800 o-Xylene 13 22 23 18 <0.97 700 8,800 Notes: 1) North Carolina Department of Environmental Quality (DEQ) Division of Waste Management (DWM) Sub-slab and Exterior Soil Gas Screening Levels (SGSLs) datd January 2023 Compound concentrations are reported in micrograms per cubic meter (μg/m3). Compound concentrations are reported to the laboratory method detection limits. Only those compounds detected in at least one sample are shown in the table above. Laboratory analytical methods are shown in parentheses. Bold values indicates concentration exceeds the DWM Residential SGSL. VOCs = volatile organic compounds; ft bgs= feet below ground surface; NE = not established J = Compound was detected above the laboratory method detection limit, but below the laboratory reporting limit resulting in a laboratory estimated concentration. SG-2 / DUP-SG 1/31/2019 7 Screening Criteria Residential SGSLs (1) Non-Residential SGSLs (1) https://harthick.sharepoint.com/sites/MasterFiles-1/Shared Documents/AAA-Master Projects/S2K Charlotte/Metromont Concrete Facility/EMP/Redevelopment EMP/Tables/Metromont Data Tables 5/31/2023 Table 3 (Page 1 of 1) Hart & Hickman, PC Version Date: Basis: Site Name: Site Address: DEQ Section: Site ID: Exposure Unit ID: Submittal Date: Reviewed By: Hypothetical Worst Case Scenario - Soil Gas North Carolina Department of Environmental Quality Risk Calculator Metromont Concrete Facility 4101 Greensboro Street, Charlotte, North Carolina Brownfields Redevelopment Section 22040-18-060 January 2023 November 2022 EPA RSL Table Prepared By:Hart & Hickman, PC 2923 S. Tryon Street, Suite 100, Charlotte, NC North Carolina DEQ Risk Calculator Complete Exposure Pathways Version Date: January 2023 Basis: November 2022 EPA RSL Table Site ID: 22040-18-060 Exposure Unit ID: Hypothetical Worst Case Scenario - Soil Gas Note: Risk output will only be calculated for complete exposure pathways. Receptor Pathway Check box if pathway complete Soil Groundwater Use Soil Groundwater Use Construction Worker Soil Soil Surface Water Groundwater to Indoor Air Soil Gas to Indoor Air Indoor Air Groundwater to Indoor Air Soil Gas to Indoor Air Indoor Air Source Soil Source Groundwater Source Soil Source Groundwater Resident Non-Residential Worker CONTAMINANT MIGRATION PATHWAYS Groundwater Surface Water Input Form 1A VAPOR INTRUSION PATHWAYS DIRECT CONTACT SOIL AND WATER PATHWAYS Resident Non-Residential Worker Recreator/Trespasser North Carolina DEQ Risk Calculator Exposure Point ConcentrationsVersion Date: January 2023Basis: November 2022 EPA RSL TableSite ID: 22040-18-060Exposure Unit ID: Hypothetical Worst Case Scenario - Soil Gas Description of Exposure Point Concentration Selection:Exposure Point Concentration (ug/m3)Notes:CAS NumberChemicalMinimum Concentration (Qualifier)Maximum Concentration (Qualifier)UnitsLocation of Maximum ConcentrationDetection FrequencyRange of Detection LimitsConcentration Used for ScreeningBackground ValueScreening Toxicity Value (Screening Level) (n/c)Potential ARAR/TBC ValuePotential ARAR/TBC SourceCOPC Flag (Y/N)Rationale for Selection or Deletion15067-64-1Acetoneug/m32371-43-2Benzeneug/m341075-15-0Carbon Disulfideug/m3256-23-5Carbon Tetrachlorideug/m3970110-82-7Cyclohexaneug/m337141-78-6Ethyl Acetateug/m316100-41-4Ethylbenzeneug/m3920142-82-5Heptane, N-ug/m3330110-54-3Hexane, N-ug/m31567-63-0Isopropanolug/m34178-93-3Methyl Ethyl Ketone (2-Butanone)ug/m34.3108-10-1Methyl Isobutyl Ketone (4-methyl-2-pentanone)ug/m31.175-09-2Methylene Chlorideug/m32.2127-18-4Tetrachloroethyleneug/m33700108-88-3Tolueneug/m31.476-13-1Trichloro-1,2,2-trifluoroethane, 1,1,2-ug/m32.275-69-4Trichlorofluoromethaneug/m31795-63-6Trimethylbenzene, 1,2,4-ug/m33.8108-67-8Trimethylbenzene, 1,3,5-ug/m361108-38-3Xylene, m-ug/m32395-47-6Xylene, o-ug/m3Input Form 2DSoil Gas Exposure Point Concentration TableNote: Chemicals highlighted in orange are non-volatile chemicals. Since these chemicals do not pose a vapor intrusion risk, no risk values are calculated for these chemicals.If the chemical list is changed from a prior calculator run, remember to select "See All Chemicals" on the data output sheet or newly added chemicals will not be included in risk calculationsNorth Carolina DEQ Risk Calculator Risk for Individual Pathways Output Form 1A Version Date: January 2023 Basis: November 2022 EPA RSL Table Site ID: 22040-18-060 Exposure Unit ID: Hypothetical Worst Case Scenario - Soil Gas Receptor Pathway Carcinogenic Risk Hazard Index Risk exceeded? Soil NC NC NC Groundwater Use*NC NC NC Soil NC NC NC Groundwater Use*NC NC NC Construction Worker Soil NC NC NC Soil NC NC NC Surface Water*NC NC NC Receptor Pathway Carcinogenic Risk Hazard Index Risk exceeded? Groundwater to Indoor Air NC NC NC Soil Gas to Indoor Air 2.5E-06 2.0E-01 NO Indoor Air NC NC NC Groundwater to Indoor Air NC NC NC Soil Gas to Indoor Air NC NC NC Indoor Air NC NC NC Pathway Source Source Soil NC Source Groundwater NC Source Soil NC Source Groundwater NC Groundwater Exceedence of 2L at Receptor? Exceedence of 2L at Receptor? 1. If lead concentrations were entered in the exposure point concentration tables, see the individual calculator sheets for lead concentrations in comparison to screening levels. Note that lead is not included in cumulative risk calculations. Notes: 3. NM = Not modeled, user did not check this pathway as complete. 4. NC = Pathway not calculated, required contaminant migration parameters were not entered. DIRECT CONTACT SOIL AND WATER CALCULATORS Resident Non-Residential Worker Recreator/Trespasser 2. * = If concentrations in groundwater exceed the NC 2L Standards or IMAC, or concentrations in surface water exceed the NC 2B Standards, appropriate remediation and/or institutional control measures will be necessary to be eligible for a risk-based closure. Surface Water Exceedence of 2B at Receptor? Exceedence of 2B at Receptor? VAPOR INTRUSION CALCULATORS Resident Non-Residential Worker CONTAMINANT MIGRATION CALCULATORS Target Receptor Concentrations Exceeded? North Carolina DEQ Risk Calculator DEQ Risk Calculator - Vapor Intrusion - Resident Soil Gas to Indoor Air Version Date: January 2023 Basis: November 2022 EPA RSL Table Site ID: 22040-18-060 Exposure Unit ID: Hypothetical Worst Case Scenario - Soil Gas CAS #Chemical Name: Soil Gas Concentration (ug/m3) Calculated Indoor Air Concentration (ug/m3) Target Indoor Air Conc. for Carcinogens @ TCR = 1E-06 Target Indoor Air Conc. for Non- Carcinogens @ THQ = 0.2 Calculated Carcinogenic Risk Calculated Non- Carcinogenic Hazard Quotient 67-64-1 Acetone 150 4.5 -- 71-43-2 Benzene 23 0.69 3.6E-01 6.3E+00 1.9E-06 2.2E-02 75-15-0 Carbon Disulfide 410 12.3 -1.5E+02 1.7E-02 56-23-5 Carbon Tetrachloride 2 0.06 4.7E-01 2.1E+01 1.3E-07 5.8E-04 110-82-7 Cyclohexane 970 29.1 -1.3E+03 4.7E-03 141-78-6 Ethyl Acetate 37 1.11 -1.5E+01 1.5E-02 100-41-4 Ethylbenzene 16 0.48 1.1E+00 2.1E+02 4.3E-07 4.6E-04 142-82-5 Heptane, N-920 27.6 -8.3E+01 6.6E-02 110-54-3 Hexane, N-330 9.9 -1.5E+02 1.4E-02 67-63-0 Isopropanol 15 0.45 -4.2E+01 2.2E-03 78-93-3 Methyl Ethyl Ketone (2-Butanone)41 1.23 -1.0E+03 2.4E-04 108-10-1 Methyl Isobutyl Ketone (4-methyl-2-pentanone) 4.3 0.129 -6.3E+02 4.1E-05 75-09-2 Methylene Chloride 1.1 0.033 1.0E+02 1.3E+02 3.3E-10 5.3E-05 127-18-4 Tetrachloroethylene 2.2 0.066 1.1E+01 8.3E+00 6.1E-09 1.6E-03 108-88-3 Toluene 3700 111 -1.0E+03 2.1E-02 76-13-1 Trichloro-1,2,2-trifluoroethane, 1,1,2-1.4 0.042 -1.0E+03 8.1E-06 75-69-4 Trichlorofluoromethane 2.2 0.066 -- 95-63-6 Trimethylbenzene, 1,2,4-17 0.51 -1.3E+01 8.2E-03 108-67-8 Trimethylbenzene, 1,3,5-3.8 0.114 -1.3E+01 1.8E-03 108-38-3 Xylene, m-61 1.83 -2.1E+01 1.8E-02 95-47-6 Xylene, o-23 0.69 -2.1E+01 6.6E-03 Cumulative: 2.5E-06 2.0E-01 All concentrations are in ug/m3 Output Form 3B Carcinogenic risk and hazard quotient cells highlighted in orange are associated with non-volatile chemicals. Since these chemicals do not pose a vapor intrusion risk, no risk values are calculated for these chemicals. North Carolina DEQ Risk Calculator Appendix C Product Specification Sheets & Installation Instructions VIMS Specification Sheet 1 (Option) VaporBlock 20 (VBP-20) Product Specification Sheets & Installation Instructions PRODUCT PART # VaporBlock® Plus™ 20 ................................................................ VBP20 UNDER-SLAB VAPOR / GAS BARRIER Under-Slab Vapor/Gas Retarder © 2018 RAVEN INDUSTRIES INC. All rights reserved. VAPORBLOCK® PLUS™VBP20 PRODUCT DESCRIPTION VaporBlock® Plus™ is a seven-layer co-extruded barrier made using high quality virgin-grade polyethylene and EVOH resins to provide unmatched impact strength as well as superior resistance to gas and moisture transmission. VaporBlock® Plus™ 20 is more than 100 times less permeable than typical high-performance polyethylene vapor retarders against Methane, Radon, and other harmful VOCs. Tested and verified for unsurpassed protection against BTEX, HS, TCE, PCE, methane, radon, other toxic chemicals and odors. VaporBlock® Plus™ 20 multi-layer gas barrier is manufactured with the latest EVOH barrier technology to mitigate hazardous vapor intrusion from damaging indoor air quality, and the safety and health of building occupants. VBP20 is one of the most effective underslab gas barriers in the building industry today far exceeding ASTM E-1745 (Plastic Water Vapor Retarders Used in Contact with Soil or Granular Fill Under Concrete Slabs) Class A, B and C requirements. Available in a 20 (Class A) mil thicknesses designed to meet the most stringent requirements. VaporBlock® Plus™ 20 is produced within the strict guidelines of our ISO 9001 Certified Management System. PRODUCT USE VaporBlock® Plus™ 20 resists gas and moisture migration into the building envelop when properly installed to provide protection from toxic/harmful chemicals. It can be installed as part of a passive or active control system extending across the entire building including floors, walls and crawl spaces. When installed as a passive system it is recommended to also include a ventilated system with sump(s) that could be converted to an active control system with properly designed ventilation fans. VaporBlock® Plus™ 20 works to protect your flooring and other moisture-sensitive furnishings in the building’s interior from moisture and water vapor migration, greatly reducing condensation, mold and degradation. SIZE & PACKAGING VaporBlock® Plus™ 20 is available in 10’ x 150’ rolls to maximize coverage. All rolls are folded on heavy-duty cores for ease in handling and installation. Other custom sizes with factory welded seams are available based on minimum volume requirements. Installation instructions and ASTM E-1745 classifications accompany each roll. APPLICATIONS Radon Barrier Methane Barrier VOC Barrier Brownfields Barrier Vapor Intrusion Barrier Under-Slab Vapor Retarder Foundation Wall Vapor Retarder VaporBlock® Plus™ is a seven-layer co-extruded barrier made using high quality virgin-grade polyethylene and EVOH resins to provide unmatched impact strength as well as superior resistance to gas and moisture transmission. VaporBlock® Plus™ Placement All instructions on architectural or structural drawings should be reviewed and followed. Detailed installation instructions accompany each roll of VaporBlock® Plus™ and can also be located at www.ravenefd.com. ASTM E-1643 also provides general installation information for vapor retarders. VAPORBLOCK® PLUS™ 20 PROPERTIES TEST METHOD IMPERIAL METRIC AppeArAnce White/Gold Thickness, nominAl 20 mil 0.51 mm WeighT 102 lbs/MSF 498 g/m² clAssificATion ASTM E 1745 CLASS A, B & C ³ Tensile sTrengTh ASTM E 154Section 9(D-882)58 lbf 102 N impAcT resisTAnce ASTM D 1709 2600 g permeAnce (neW mATeriAl) ASTM E 154Section 7ASTM E 96Procedure B 0.0098 Perms grains/(ft²·hr·in·Hg) 0.0064 Perms g/(24hr·m²·mm Hg) permeAnce (AfTer condiTioning) (sAme meAsuremenT As Above permeAnce) ASTM E 154Section 8, E96Section 11, E96Section 12, E96Section 13, E96 0.00790.00790.00970.0113 0.00520.00520.00640.0074 WvTr ASTM E 96Procedure B 0.0040 grains/hr-ft²0.0028 gm/hr-m² benzene permeAnce See Note ⁶1.13 x 10-¹⁰ m²/sec or 3.62 x 10-¹³ m/s Toluene permeAnce See Note ⁶1.57 x 10-¹⁰ m²/sec or 1.46 x 10-¹³ m/s eThylbenzene permeAnce See Note ⁶1.23 x 10-¹⁰ m²/sec or 3.34 x 10-¹⁴ m/s m & p-Xylenes permeAnce See Note ⁶1.17 x 10-¹⁰ m²/sec or 3.81 x 10-¹⁴ m/s o-Xylene permeAnce See Note ⁶1.10 x 10-¹⁰ m²/sec or 3.43 x 10-¹⁴ m/s hydrogen sulfide See Note 9 1.92E-⁰⁹ m/s TrichloroeThylene (Tce) See Note ⁶7.66 x 10-¹¹ m²/sec or 1.05 x 10-¹⁴ m/s perchloroeThylene (pce)See Note ⁶7.22 x 10-¹¹ m²/sec or 1.04 x 10-¹⁴ m/s rAdon diffusion coeffiecienT K124/02/95 < 1.1 x 10-13 m2/s meThAne permeAnce ASTM D 1434 3.68E-¹² m/sGas Transmission Rate (GTR):0.32 mL/m²•day•atm mAXimum sTATic use TemperATure 180° F 82° C minimum sTATic use TemperATure - 70° F - 57° C UNDER-SLAB VAPOR / GAS BARRIER VAPORBLOCK® PLUS™VBP20 © 2018 RAVEN INDUSTRIES INC. All rights reserved. Scan QR Code to download current technical data sheets via the Raven website. Note: To the best of our knowledge, unless otherwise stated, these are typical property values and are intended as guides only, not as specification limits. Chemical resistance, odor transmission, longevity as well as other performance criteria is not implied or given and actual testing must be performed for applicability in specific applications and/or conditions. RAVEN INDUSTRIES MAKES NO WARRANTIES AS TO THE FITNESS FOR A SPECIFIC USE OR MERCHANTABILITY OF PRODUCTS REFERRED TO, no guarantee of satisfactory results from reliance upon contained information or recommendations and disclaims all liability for resulting loss or damage. Limited Warranty available at www.RavenEFD.com 061318 EFD 1125 RAVEN ENGINEERED FILMSP.O. Box 5107 Sioux Falls, SD 57117-5107Ph: +1 (605) 335-0174 • TF: +1 (800) 635-3456 efdsales@ravenind.comwww.ravenefd.com ³ Tests are an average of machine and transverse directions.5 Raven Industries performs seam testing at 20” per minute.6 Aqueous Phase Film Permeance. Permeation of Volatile Organic Compounds through EVOH Thin Film Membranes and Coextruded LLDPE/EVOH/ LLDPE Geomembranes, McWatters and Rowe, Journal of Geotechnical and Geoenvironmental Engineering© ASCE/ September 2015. (Permeation is the Permeation Coefficient adjusted to actual film thickness - calculated at 1 kg/m³.) The study used to determine PCE and TCE is titled: Evaluation of diffusion of PCE & TCE through high performance geomembranes by Di Battista and Rowe, Queens University 8 Feb 2018.9 The study used to determine diffusion coefficients is titled: Hydrogen Sulfide (H₂S) Transport through Simulated Interim Covers with Conventional and Co-Extruded Ethylene-Vinyl Alcohol (EVOH) Geomembranes. INSTALLATION GUIDELINES - With VaporSeal™ Tape VaporSeal™ 4” Tape VaporSeal™ 4” Tape Optional Butyl Seal 2-Sided Tape Gas Barrier Applications Elements of a moisture/gas-resistant floor system. General illustration only.(Note: This example shows multiple options for waterstop placement. VaporSeal™ 4” Tape VaporSeal™ 4” Tape Optional Butyl Seal 2-Sided Tape Gas Barrier Applications Fig. 2: VaporBlock® Plus™ Overlap Joint Sealing Methods Fig. 1: VaporBlock® Plus™ Overlapping Roll-out Method Please Note: Read these instructions thoroughly before installation to ensure proper use of VaporBlock® Plus™. ASTM E 1465, ASTM E 2121 and, ASTM E 1643 also provide valuable information regarding the installation of vapor / gas barriers. When installing this product, contractors shall conform to all applicable local, state and federal regulations and laws pertaining to residential and commercial building construction. • When VaporBlock® Plus™ gas barrier is usedas part of an active control system for radon orother gas, a ventilation system will be required. • If designed as a passive system, it is recommended to install a ventilation system that could beconverted to an active system if needed. Materials List:VaporBlock® Plus™ Vapor / Gas BarrierVaporSeal™* 4” Seaming TapeVaporSeal™* 12” Seaming/Repair TapeButyl Seal 2-Sided TapeVaporBoot Plus Pipe Boots 12/Box (recommended)VaporBoot Tape (optional)POUR-N-SEAL™ (optional)1” Foam Weather Stripping (optional)Mako® Screed Supports (optional) VAPORBLOCK® PLUS™ PLACEMENT 1.1. Level and tamp or roll granular base as specified. A base for a gas-reduction system may require a 4” to 6” gas permeable layer of clean coarse aggregate as specified by your architectural or structural drawings after installation of the recommended gas collection system. In this situation, a cushion layer consisting of a non-woven geotextile fabric placed directly under VaporBlock® Plus™ will help protect the barrier from damage due to possible sharp coarse aggregate. 1.2. Unroll VaporBlock® Plus™ running the longest dimension parallel with the direction of the pour and pull open all folds to full width. (Fig. 1) 1.3. Lap VaporBlock® Plus™ over the footings and seal with Raven Butyl Seal tape at the footing-wall connection. Prime concrete surfaces, when necessary, and assure they are dry and clean prior to applying Raven Butyl Seal Tape. Apply even and firm pressure with a rubber roller. Overlap joints a minimum of 6” and seal overlap with 4” VaporSeal™ Tape. When used as a gas barrier, overlap joints a minimum of 12” and seal in-between overlap with an optional 2-sided Raven Butyl Seal Tape. Then seal with 4” VaporSeal™ Tape centered on the overlap seam. (Fig. 2) Page 1 of 4 T�������������������������������� by the Portland Cement Association.Reference: Kanare, Howard M., Concrete Floors and Moisture, EB119, Portland Cement Association, Skokie, Illinois, and National Ready Mixed Concrete Association, Silver Spring, Maryland, USA, 2008, 176 pages. 1.4. Seal around all plumbing, conduit, support columns or other penetrations that come through the VaporBlock® Plus™ membrane. 1.4a. Method 1: Pipes four inches or smaller can be sealed with Raven VaporBoot Plus preformed pipe boots. VaporBoot Plus preformed pipe boots are formed in steps for 1”, 2”, 3” and 4” PVC pipe or IPS size and are sold in units of 12 per box (Fig. 3 & 5). Pipe boots may also be fabricated from excess VaporBlock® Plus™ membrane (Fig. 4 & 6) and sealed with VaporBoot Tape or VaporSeal™ Tape (sold separately). 1.4b. Method 2: To fabricate pipe boots from VaporBlock® Plus™ excess material (see Fig. 4 & 6 for A-F): A) Cut a square large enough to overlap 12” in all directions. B) Mark where to cut opening on the center of the square and cut four to eight slices about 3/8” less than the diameter of the pipe. C) Force the square over the pipe leaving the tightly stretched cut area around the bottom of the pipe with approximately a 1/2” of the boot material running vertically up the pipe. (no more than a 1/2” of stretched boot material is recommended) D) Once boot is positioned, seal the perimeter to the membrane by applying 2-sided Raven Butyl Seal Tape in between the two layers. Secure boot down firmly over the membrane taking care not to have any large folds or creases. E) Use VaporBoot Tape or VaporSeal™ Tape to secure the boot to the pipe. VaporBoot Tape (option) – fold tape in half lengthwise, remove half of the release liner and wrap around the pipe allowing 1” extra for overlap sealing. Peel off the second half of the release liner and work the tape outward gradually forming a complete seal. VaporSeal™ Tape (option) - Tape completely around pipe overlapping the VaporBlock® Plus™ square to create a tight seal against the pipe. F) Complete the process by taping over the boot perimeter edge with VaporSeal™ Tape to create a monolithic membrane between the surface of the slab and gas/moisture sources below and at the slab perimeter. (Fig. 4 & 6) Preformed Pipe Boot Square Material Pipe Boot Fig. 3 SINGLE PENETRATION PIPE BOOT INSTALLATION Fig. 5 Fig. 6 1. Cut a square of VaporBlock® Plus™ barrier to extend at least 12” from the pipe in all directions. 2. Cut four to eight slices about 3/8” less than the diameter of the pipe. 5. Use Raven VaporBoot or VaporSeal™ Tape and overlap 1” at the seam. 4. Tape over the boot perimeter edge with VaporSeal™ Tape. 1. Cut out one of the preformed boot steps (1” to 4”). 2. Tape the underside boot perimeter with 2-sided Butyl Seal Tape. 3. Force the boot over pipe and press tape firmly in place. 4. Use VaporSeal™ Tape to secure boot to the pipe. 5. Tape around entire boot edge with VaporSeal™ Tape. VaporBoot Flexible Tapeor VaporSeal™ 4” TapeVaporSeal™ 4” Tape VaporBlock® Plus™Material VaporSeal™ 4” Tape Raven Butyl Seal2-Sided Tape Raven Butyl Seal2-Sided Tape VaporBoot PlusPreformed Boot 12”(minimum) 3. Force over pipe and tape the underside boot perimeter to existing barrier with 2-sided Butyl Seal Tape. Fig. 4 Page 2 of 4 ��������������������������������ortland Cement Association.Reference: Kanare, Howard M., Concrete Floors and Moisture, EB119, Portland Cement Association, Skokie, Illinois, and National Ready Mixed Concrete Association, Silver Spring, Maryland, USA, 2008, 176 pages.Method 1 Method 2 VaporSeal™4” Tape VaporBoot PlusPerformed Boot Raven Butyl Seal 2-sided Tape Raven Butyl Seal 2-sided Tape 1.5. Sealing side-by-side multiple penetrations (option 1); A) Cut a patch large enough to overlap 12” in all directions (Fig. 7) of penetrations. B) Mark where to cut openings and cut four to eight slices about 3/8” less than the diameter of the penetration for each. C) Force patch material over penetration to achieve a tight fit and form a lip. D) Once patch is positioned, seal the perimeter to the membrane by applying 2-sided Raven Butyl Seal Tape in-between the two layers. (Fig. 8) E) After applying Raven Butyl Seal Tape between the patch and membrane, tape around each of the penetrations and the patch with VaporSeal™ 4” tape. (Fig. 9) For additional protection apply POUR-N-SEAL™ or an acceptable polyurethane elastomeric sealant around the penetrations. (Fig. 10) Fig. 7 Fig. 8 Fig. 9 Fig. 10 MULTIPLE PENETRATION PIPE BOOT INSTALLATION Fig. 6 Cut a patch large enough to overlap 12” in all directions and slide over penetrations (Make openings as tight as possible.) Once the overlay patch is positioned, seal the perimeter to the membrane by applying 2-sided Raven Butyl Seal Tape in-between the two layers. After applying Raven Butyl Seal Tapebetween the patch and membrane, tape around the perimeter of the penetration and the patch with VaporSeal™ 4” Tape. For additional protection apply POUR-N-SEAL™ or an acceptable polyurethane elastomeric sealant around the penetrations. VaporSeal™ 4” Tape VaporSeal™ 4” Tape Page 3 of 4 Option 1 Raven Butyl Seal 2-sided Tape 1.6. POUR-N-SEAL™ method of sealing side-by-side multiple penetrations (option 2); A) Install the vapor barrier as closely as possible to pipe penetrations to minimize the amount of POUR-N-SEAL™ necessary to seal around all penetrations. B) Once barrier is in place, remove soil or other particles with a dry cloth or a fine broom to allow for improved adhesion to the POUR-N-SEAL™ liquid. C) Create a dam around the penetration area approximately 2” away from the pipe or other vertical penetrations by removing the release liner from the back of a 1” weather stripping foam and adhere to the vapor barrier. Form a complete circle to contain the POUR-N-SEAL™ materials (Fig. 11). D) Once mixed, pour contents around the pipe penetrations. If needed, a brush or a flat wooden stick can be used to direct the sealant completely around penetrations creating a complete seal (Fig. 12-13). E) DO NOT leave excess POUR-N-SEAL™ in plastic container for longer than the time it takes to pour sealant. Fig. 12 Fig. 13 Fig. 11 Option 2 VAPORBLOCK® PLUS™ REPAIR INSTRUCTIONS 1.7. Proper installation requires all holes and openings are repaired prior to placing concrete. When patching small holes, simply cut a 12” long piece of 12” wide VaporSeal™ tape. Remove release liner and center over the opening. Apply pressure to create a seal (Fig. 14-15). 1.8. When installing VaporBlock® Plus™ around pipe penetrations, vertical columns, electrical ducts and other obstructions, you will find it necessary to cut it to the nearest outside edge. This cut can be easily sealed with 12” wide VaporSeal™ tape, by simply centering it over the cut, 6” on either side. Once the tape is placed correctly, apply pressure to assure a complete seal (Fig. 16). Reminder Note: All holes or penetrations through the membrane will need to be patched with 12” VaporSeal™ Tape. Fig. 14 Page 4 of 5 Fig. 15 2.1. When installing reinforcing steel and utilities, in addition to the placement of concrete, take precaution to protect VaporBlock® Plus™. Carelessness during installation can damage the most puncture–resistant membrane. Sheets of plywood cushioned with geotextile fabric temporarily placed on VaporBlock® Plus™ provide for additional protection in high traffic areas including concrete buggies. 2.2. Use only brick-type or chair-type reinforcing bar supports to protect VaporBlock® Plus™ from puncture. 2.3. Avoid driving stakes through VaporBlock® Plus™. If this cannot be avoided, each individual hole must be repaired per section 1.7. 2.4. To avoid penetrating VaporBlock® Plus™ when installing screed supports, utilize non-penetrating support, such as the Mako® Screed Support System (Fig. 17). Avoid driving stakes through VaporBlock® Plus™. If this cannot be avoided, each individual hole must be repaired per figures 14-15. 2.5. If a cushion or blotter layer is required in the design between VaporBlock® Plus™ and the slab, additional care should be given if sharp crushed rock is used. Washed rock will provide less chance of damage during placement. Care must be taken to protect blotter layer from precipitation before concrete is placed. VaporBlock® Plus™ Gas & Moisture Barrier can be identified on site as gold/white in color printed in black ink with following logo and classification listing (Fig. 18) Page 5 of 5 VaporBlock® Plus™ Gas & Moisture Barrier Note: To the best of our knowledge, unless otherwise stated, these are typical property values and are intended as guides only, not as specification limits. Chemical resistance, odor transmission, longevity as well as other performance criteria is not implied or given and actual testing must be performed for applicability in specific applications and/or conditions. RAVEN INDUSTRIES MAKES NO WARRANTIES AS TO THE FITNESS FOR A SPECIFIC USE OR MERCHANTABILITY OF PRODUCTS REFERRED TO, no guarantee of satisfactory results from reliance upon contained information or recommendations and disclaims all liability for resulting loss or damage. Limited Warranty available at wwww.RavenEFD.com ENGINEERED FILMSP.O. Box 5107 Sioux Falls, SD 57117-5107Ph: +1 (605) 335-0174 • TF: +1 (800) 635-3456 efdsales@ravenind.comwww.ravenefd.com 020316 EFD 1127 VAPORBLOCK® PLUS™ PROTECTION Fig. 16 Fig. 18 Fig. 17 * Patent Pending © Raven 2016. All Rights Reserved. Drago Wrap Product Specification Sheets & Installation Instructions VIMS Specification Sheet 2 (Option) P1 OF 2 DRAGO® WRAPVAPOR INTRUSION BARRIER A STEGO TECHNOLOGY, LLC INNOVATION | VAPOR RETARDERS 07 26 00, 03 30 00 | VERSION: 2/22/2019 1. PRODUCT NAME DRAGO WRAP VAPOR INTRUSION BARRIER 2. MANUFACTURER c/o Stego® Industries, LLC* 216 Avenida Fabricante, Suite 101 San Clemente, CA 92672 Sales, Technical Assistance Ph: (877) 464-7834 Fx: (949) 257-4113 www.stegoindustries.com 3. PRODUCT DESCRIPTION TABLE 4.1: PHYSICAL PROPERTIES OF DRAGO WRAP VAPOR INTRUSION BARRIER PROPERTY TEST RESULTS Under Slab Vapor Retarders ASTM E1745 – Standard Specification for Water Vapor Retarders Used in Contact with Soil or Granular Fill under Concrete Slabs ASTM E1745 Compliant Water Vapor Permeance ASTM F1249 – Test Method for Water Vapor Transmission Rate Through Plastic Film and Sheeting Using a Modulated Infrared Sensor 0.0069 perms Push-Through Puncture ASTM D4833 – Test Method for Index Puncture Resistance of Geotextiles, Geomembranes, and Related Products 183.9 Newtons Tensile Strength ASTM D882 – Test Method for Tensile Properties of Thin Plastic Sheeting 53.5 lbf/in Permeance After Conditioning ASTM E154 Section 8, F1249 – Permeance after wetting, drying, and soaking 0.0073 perms(ASTM E1745 ASTM E154 Section 11, F1249 – Permeance after heat conditioning 0.0070 permsSections 7.1.2 - 7.1.5) ASTM E154 Section 12, F1249 – Permeance after low temperature conditioning 0.0062 perms ASTM E154 Section 13, F1249 – Permeance after soil organism exposure 0.0081 perms Hydrocarbon Attenuation Factors Contact Stego Industries’ Technical Department Chlorinated Solvent Attenuation Factors Contact Stego Industries’ Technical Department Methane Transmission Rate ASTM D1434 – Test Method for Determining Gas Permeability Characteristics of 7.0 GTR** Plastic Film and Sheeting (mL(STP)/m2*day) Radon Diffusion Coefficient K124/02/95 9.8 x 10-14 m2/second Thickness 20 mil Roll Dimensions 14' x 105' or 1,470 ft2 Roll Weight 150 lb Note: perm unit = grains/(ft2*hr*in-Hg) ** GTR = Gas Transmission Rate USES: Drago Wrap is specifically engineered to attenuate volatile organic compounds (VOCs) and serve as a below-slab moisture vapor barrier. COMPOSITION: Drago Wrap is a multi-layered plastic extrusion that combines uniquely designed materials with only high grade, prime, virgin resins. ENVIRONMENTAL FACTORS: Drago Wrap can be used in systems for the control of various VOCs including hydrocarbons, chlorinated solvents, radon, methane, soil poisons, and sulfates. 4. TECHNICAL DATA Continued... Note – legal notice on page 2. DRAGO® WRAPVAPOR INTRUSION BARRIER A STEGO TECHNOLOGY, LLC INNOVATION | VAPOR RETARDERS 07 26 00, 03 30 00 | VERSION: 2/22/2019 DATA SHEETS ARE SUBJECT TO CHANGE. FOR MOST CURRENT VERSION, VISIT WWW.STEGOINDUSTRIES.COM (877) 464-7834 | www.stegoindustries.com *Stego Industries, LLC (“Stego”) is the exclusive Representative for Drago Wrap and Pango Wrap. All designated trademarks are the intellectual property of Stego or the entity for which it is acting as a Representative. Installation, Warranty, State Approval Information and Disclosure of Representative Status: www.stegoindustries.com/legal. ©2019 Stego Industries, LLC. All rights reserved. 5. INSTALLATION UNDER SLAB: Unroll Drago Wrap over a tamped aggregate, sand, or earth base. Overlap all seams a minimum of 12 inches and tape using Drago® Tape. All penetrations must be sealed using a combination of Drago Wrap and Drago Accessories. Review Drago Wrap’s complete installation instructions prior to installation. 6. AVAILABILITY & COST Drago Wrap is available nationally through our network of building supply distributors. For current cost information, contact your local Drago distributor or Stego Industries’ Sales Representative. 7. WARRANTY Stego Industries, LLC believes to the best of its knowledge, that specifications and recommendations herein are accurate and reliable. However, since site conditions are not within its control, Stego Industries does not guarantee results from the use of the information provided and disclaims all liability from any loss or damage. Stego Technology, LLC does offer a limited warranty on Drago Wrap. Please see www.stegoindustries.com/legal. 8. MAINTENANCE Store Drago Wrap in a dry and temperate area. 9. TECHNICAL SERVICES Technical advice, custom CAD drawings, and additional information can be obtained by contacting Stego Industries or by visiting the website. Contact Number: (877) 464-7834 Website: www.stegoindustries.com 10. FILING SYSTEMS • www.stegoindustries.com P2 OF 2 INSTALLATIONINSTRUCTIONS DRAGO® WRAP VAPOR INTRUSION BARRIER Engineered protection to create a healthy built environment. 2.Unroll Drago Wrap over the area where the slab is to be placed. Drago Wrap should completely cover the concrete placement area. All joints/seams should be overlapped a minimum of 12 inches and taped using Drago® Tape. (Fig. 1). If additional protection is needed, install DragoTack™ Tape in between the overlapped seam in combination with Drago Tape on top of the seam. NOTE: The area of adhesion should be free from dust, dirt, moisture, and frost to allow maximum adhesion of the pressure-sensitive tape. Ensure that all seams are taped with applied pressure to allow for maximum and continuous adhesion of the pressure-sensitive Drago Tape. Adhesives should be installed above 40°F. In temperatures below 40°F, take extra care to remove moisture/frost from the area of adhesion. 3.ASTM E1643 requires sealing the perimeter of the slab. Extend vapor retarder over footings and seal to foundation wall or grade beam at an elevation consistent with the top of the slab or terminate at impediments such as waterstops or dowels. Consult the structural and environmental engineer of record before proceeding. IMPORTANT: Please read these installation instructions completely, prior to beginning any Drago Wrap installation. The following installation instructions are generally based on ASTM E1643 – Standard Practice for Selection, Design, Installation, and Inspection of Water Vapor Retarders Used in Contact with Earth or Granular Fill Under Concrete Slabs. There are specific instructions in this document that go beyond what is stated in ASTM E1643 to take into account vapor intrusion mitigation. If project specifications call for compliance with ASTM E1643, then be sure to review the specific installation sections outlined in the standard along with the techniques referenced in these instructions. DRAGO TAPE Minimum 12” overlap VAPOR INTRUSION BARRIER Fig.1: UNDER-SLAB INSTALLATION DRAGO® WRAP VAPOR INTRUSION BARRIERINSTALLATION INSTRUCTIONS UNDER-SLAB INSTRUCTIONS: FOOTING DRAGOTACK TAPE VAPOR INTRUSION BARRIER Fig.2a: SEAL TO PERIMETER WALL Fig. 2b: SEAL TO FOOTING FOOTING DRAGOTACK TAPE VAPOR INTRUSION BARRIER SEAL TO PERIMETER WALL OR FOOTING WITH DRAGOTACK TAPE: (Fig. 2a and 2b) a.Make sure area of adhesion is free of dust, dirt, debris, moisture, and frost to allow maximum adhesion. b.Remove release liner on one side and stick to desired surface.c.When ready to apply Drago Wrap, remove the exposed release liner and press firmly against DragoTack Tape to secure. d.If a mechanical seal is needed, fasten a termination bar over the top of the Drago Wrap inline with the DragoTack Tape. NOTE: If sealing to the footing, the footing should receive a hand float finish to allow for maximum adhesion. 1.Drago Wrap has been engineered to be installed over a tamped aggregate, sand, or earth base. It is not typically necessary to have a cushion layer or sand base, as Drago Wrap is tough enough to withstand rugged construction environments. NOTE: Drago Wrap must be installed with the gray facing the subgrade. P2 of 4 Continued ... Note - legal notice on last page. DETAIL PATCH FOR PIPE PENETRATION SEALING: (Fig. 4b)a.Install Drago Wrap around pipe penetrations by slitting/cutting material as needed. Try to minimize void space created. b.If Drago Wrap is close to pipe and void space is minimized, proceed to step d. c.If void space exists, then i.Cut a detail patch to a size and shape that creates a 6-inch overlap on all edges around the void space at the base of the pipe. ii.Cut an “X” slightly smaller than the size of the pipe diameter in the center of the detail patch and slide tightly over pipe. iii.Tape the edges of the detail patch using Drago Tape. d.Seal around the base of the pipe using Drago Tape and/or Drago Sealant and Drago Sealant Form. i.If Drago Sealant is used to seal around pipe, make sure Drago Wrap is flush with the base of the penetration prior to pouring Drago Sealant. 5.IMPORTANT: ALL PENETRATIONS MUST BE SEALED. All pipe, ducting, rebar, and block outs should be sealed using Drago Wrap, Drago Tape, and/or Drago® Sealant and Drago® Sealant Form. (Fig. 4a). Drago accessories should be sealed directly to the penetrations. DRAGO TAPE DAMAGED AREA DRAGO TAPE DRAGO TAPE SMALL HOLE VAPOR INTRUSION BARRIER VAPOR INTRUSION BARRIER VAPOR INTRUSION BARRIER VAPOR INTRUSION BARRIER Fig. 3: SEALING DAMAGED AREAS 4.In the event that Drago Wrap is damaged during or after installation, repairs must be made. Cut a piece of Drago Wrap to a size and shape that covers any damage by a minimum of 6 inches in all directions. Clean all adhesion areas of dust, dirt, moisture, and frost. Tape down all edges using Drago Tape. (Fig. 3) MINIMAL VOID SPACE CREATED DRAGO SEALANTDRAGO TAPE OR DRAGO SEALANT FORM VAPOR INTRUSION BARRIER VAPOR INTRUSION BARRIER VAPOR INTRUSION BARRIER Fig. 4a: PIPE PENETRATION SEALING DRAGO TAPE LARGE VOID SPACE CREATED DRAGO SEALANTDRAGO TAPE OR DRAGO SEALANT FORM VAPOR INTRUSION BARRIERVAPOR INTRUSION BARRIERVAPOR INTRUSION BARRIER VAPOR INTRUSION BARRIER Fig. 4b: DETAIL PATCH FOR PIPE PENETRATION SEALING Continued ... Note - legal notice on last page. P3 of 4 DRAGO® WRAP VAPOR INTRUSION BARRIERINSTALLATION INSTRUCTIONS STEGO INDUSTRIES, LLC • SAN CLEMENTE, CA • 949-257-4100 • 877-464-7834 • www.stegoindustries.com *Stego Industries, LLC (“Stego”) is the exclusive Representative for Drago Wrap and Pango Wrap. All designated trademarks are the intellectual property of Stego or the entity for which it is acting as a Representative. Installation, Warranty, State Approval Information and Disclosure of Representative Status: www.stegoindustries.com/legal. ©2019 Stego Industries, LLC. All rights reserved. 11/2019 NOTE: While Drago Wrap installation instructions are based on ASTM E1643 - Standard Practice for Selection, Design, Installation, and Inspection of Water Vapor Retarders Used in Contact with Earth or Granular Fill Under Concrete Slabs, these instructions are meant to be used as a guide, and do not take into account specific job site situations. Consult local building codes and regulations along with the building owner or owner’s representative before proceeding. If you have any questions regarding the above-mentioned installation instructions or products, please call us at 877-464-7834 for technical assistance. While Stego Industries’ employees and representatives may provide technical assistance regarding the utility of a specific installation practice or Stego product, they are not authorized to make final design decisions. MULTIPLE PIPE PENETRATION SEALING: (Fig. 5) NOTE: Multiple pipe penetrations in close proximity may be most efficiently sealed using Drago Wrap, Drago Sealant, and Drago Sealant Form for ease of installation. a. Cut a hole in Drago Wrap such that the membrane fits over and around the base of the pipes as closely as possible, ensuring that it is flush with the base of the penetrations. b. Install Drago Sealant Form continuously around the entire perimeter of the group of penetrations and at least 1 inch beyond the terminating edge of Drago Wrap. c. Pour Drago Sealant inside of Drago Sealant Form to create a seal around the penetrations. d. If the void space between Drago Wrap and the penetrations is not minimized and/or the base course allows for too much drainage of sealant, a second coat of Drago Sealant may need to be poured after the first application has cured. IMPORTANT: AN INSTALLATION COMPLETED PER THESE INSTRUCTIONS SHOULD CREATE A MONOLITHIC MEMBRANE BETWEEN ALL INTERIOR INTRUSION PATHWAYS AND VAPOR SOURCES BELOW THE SLAB AS WELL AS AT THE SLAB PERIMETER. THE UNDERLYING SUBBASE SHOULD NOT BE VISIBLE IN ANY AREA WHERE CONCRETE WILL BE PLACED. IF REQUIRED BY THE DESIGN ENGINEER, ADDITIONAL INSTALLATION VALIDATION CAN BE DONE THROUGH SMOKE TESTING. Stego Industries* recommends the use of BEAST vapor barrier-safe concrete accessories, to help eliminate the use of non-permanent penetrations in Drago Wrap installations. MINIMAL VOID SPACE CREATED DRAGO SEALANT DRAGO SEALANT FORM DRAGO SEALANT FORM DRAGO SEALANT FORM DRAGO SEALANT VAPOR INTRUSION BARRIER VAPOR INTRUSION BARRIER VAPOR INTRUSION BARRIER VAPOR INTRUSION BARRIER Fig. 5: MULTIPLE PIPE PENETRATION SEALING BEAST® CONCRETE ACCESSORIES - VAPOR BARRIER SAFE BEAST® SCREED BEAST® HOOK P3 of 4 BEAST® FORM STAKE Locate itand lock it down!Improve efficiency and maintain concrete floor levelness with the BEAST SCREED SYSTEM! The Stego barrier-safe forming system that prevents punctures in the vapor barrier. P1 OF 2 DRAGO® TAPE A STEGO TECHNOLOGY, LLC INNOVATION | VAPOR RETARDERS 07 26 00, 03 30 00 | VERSION: 11/27/2019 1. PRODUCT NAME DRAGO TAPE 2. MANUFACTURER c/o Stego® Industries, LLC* 216 Avenida Fabricante, Suite 101 San Clemente, CA 92672 Sales, Technical Assistance Ph: (877) 464-7834 Fx: (949) 257-4113 www.stegoindustries.com 3. PRODUCT DESCRIPTION USES: Drago Tape is a low-permeance tape designed for protective sealing, seaming, splicing, and patching applications where a highly conformable material is required. It has been engineered to bond specifically to Drago® Wrap Vapor Intrusion Barrier, making it ideal for sealing Drago Wrap seams and penetrations. COMPOSITION: Drago Tape is a multi-layered plastic extrusion that combines uniquely designed materials with only high grade, prime, virgin resins, and an acrylic, pressure-sensitive adhesive. SIZE: Drago Tape is 3.75" x 180'. Drago Tape ships 12 rolls in a case. 4. TECHNICAL DATA APPLICABLE STANDARDS: Pressure Sensitive Tape Council (PSTC) • PSTC 101 – International Standard for Peel Adhesion of Pressure Sensitive Tape • PSTC 107 – International Standard for Shear Adhesion of Pressure Sensitive Tape American Society for Testing & Materials (ASTM) • ASTM E1643 – Standard Practice for Selection, Design, Installation, and Inspection of Water Vapor Retarders Used In Contact with Earth or Granular Fill under Concrete Slabs. TABLE 4.1: PHYSICAL PROPERTIES OF DRAGO TAPE PROPERTY TEST RESULTS Total Thickness 8 mil Permeance ASTM F1249 0.031 perms Tensile Strength MD ASTM D882 20.5 lbf/in Elongation (at break) MD ASTM D882 702% 180° Peel Adhesion PSTC 101 20-min dwell to Drago Wrap 50.1 oz/in PSTC 101 24-hour dwell to Drago Wrap 92.9 oz/in Shear Adhesion PSTC 107 24-hour dwell (1" x 1", 1kg/wt) to Drago Wrap 188 minutes Note: perm unit = grains/(ft2*hr*in-Hg) Continued... Note – legal notice on page 2. DRAGO® TAPE A STEGO TECHNOLOGY, LLC INNOVATION | VAPOR RETARDERS 07 26 00, 03 30 00 | VERSION: 11/27/2019 DATA SHEETS ARE SUBJECT TO CHANGE. FOR MOST CURRENT VERSION, VISIT WWW.STEGOINDUSTRIES.COM (877) 464-7834 | www.stegoindustries.com *Stego Industries, LLC (“Stego”) is the exclusive Representative for Drago Wrap and Pango Wrap. All designated trademarks are the intellectual property of Stego or the entity for which it is acting as a Representative. Installation, Warranty, State Approval Information and Disclosure of Representative Status: www.stegoindustries.com/legal. ©2019 Stego Industries, LLC. All rights reserved. 5.INSTALLATION SEAMS: Overlap Drago Wrap a minimum 12 inches and seal with Drago Tape. Make sure the area of adhesion is free from dust, moisture and frost to allow maximum adhesion of the pressure-sensitive tape. PIPE PENETRATION SEALING: •Install Drago Wrap around pipe by slitting/cutting material. •If void space is minimal, seal around base of pipe with Drago Tape and/or Drago® Sealant and Drago® Sealant Form. DETAIL PATCH FOR PIPE PENETRATION SEALING: •Cut a piece of Drago Wrap that creates a 6 inch overlap around all edges of the void space. •Cut an “X” slightly smaller than the size of the pipe diameter in the center of the detail patch. •Slide detail patch over pipe, secure tightly. •Tape down all sides of detail patch with Drago Tape. •Seal around base of pipe with Drago Tape and/or Drago Sealant and Drago Sealant Form. Drago Tape should be installed above 40°F. In temperatures below 40°F, take extra care to remove moisture or frost from the area of adhesion. Ensure that the entirety of all seams are taped with applied pressure to allow for maximum and continuous adhesion of the pressure-sensitive Drago Tape. Review Drago Wrap’s complete installation instructions prior to installation. 6.AVAILABILITY & COST Drago Tape is available nationally through our network of building supply distributors. For current cost information, contact your local Drago distributor or Stego Industries’ Sales Representative. 7.WARRANTY Stego Industries, LLC believes to the best of its knowledge, that specifications and recommendations herein are accurate and reliable. However, since site conditions are not within its control, Stego Industries does not guarantee results from the use of the information provided and disclaims all liability from any loss or damage. Stego Technology, LLC does offer a limited warranty on Drago Wrap. Please see www.stegoindustries.com/legal. 8.MAINTENANCE Store Drago Tape in a dry and temperate area. 9.TECHNICAL SERVICES Technical advice, custom CAD drawings, and additional information can be obtained by contacting Stego Industries or by visiting the website. Contact Number: (877) 464-7834 Website:www.stegoindustries.com 10.FILING SYSTEMS •www.stegoindustries.com P2 OF 2 P1 OF 2 DRAGOTACK™ TAPE A STEGO TECHNOLOGY, LLC INNOVATION | VAPOR RETARDERS 07 26 00, 03 30 00 | VERSION: 2/22/2019 1.PRODUCT NAME DRAGOTACK TAPE 2.MANUFACTURER c/o Stego® Industries, LLC* 216 Avenida Fabricante, Suite 101 San Clemente, CA 92672 Sales, Technical Assistance Ph: (877) 464-7834 Fx: (949) 257-4113 www.stegoindustries.com 3.PRODUCT DESCRIPTION TABLE 4.1: PHYSICAL PROPERTIES OF DRAGOTACK TAPE PROPERTY TEST RESULTS Dimensions 2" x 50' Total Thickness 30 mil Color Grey Material Synthetic rubber blend Permeance ASTM F1249 0.03 perms (30 mil) Adhesion to Steel ASTM D1000 12.5 lbs/in width Chemical Resistance No significant change to(TCE, PCE, Toluene, Xylene) ASTM D471 / D543 mass or volume. Installation Temperature 40°F / 110° In Service Temperature Range -20°F / +140°F VOC Content No VOCs, 100% solids Note: perm unit = grains/(ft2*hr*in-Hg) USES: DragoTack Tape is a solvent-resistant, double-sided adhesive strip used to bond and seal Drago® Wrap Vapor Intrusion Barrier to concrete, masonry, wood, metal, and other surfaces. DragoTack Tape is a flexible and moldable material to allow for a variety of applications and installations. COMPOSITION: DragoTack Tape is made from a solvent-resistant blend of synthetic rubber and resins. SIZE: DragoTack Tape is 2" x 50'. DragoTack Tape ships 12 rolls in a case. 4.TECHNICAL DATA Continued... Note – legal notice on page 2. DRAGOTACK™ TAPE A STEGO TECHNOLOGY, LLC INNOVATION | VAPOR RETARDERS 07 26 00, 03 30 00 | VERSION: 2/22/2019 DATA SHEETS ARE SUBJECT TO CHANGE. FOR MOST CURRENT VERSION, VISIT WWW.STEGOINDUSTRIES.COM (877) 464-7834 | www.stegoindustries.com *Stego Industries, LLC (“Stego”) is the exclusive Representative for Drago Wrap and Pango Wrap. All designated trademarks are the intellectual property of Stego or the entity for which it is acting as a Representative. Installation, Warranty, State Approval Information and Disclosure of Representative Status: www.stegoindustries.com/legal. ©2019 Stego Industries, LLC. All rights reserved. 5.INSTALLATION TO WALLS AND FOOTINGS: Make sure the area of adhesion is free of dust, dirt, debris, moisture, and frost to allow maximum adhesion. Remove release liner on one side and stick to desired surface. When ready to apply Drago Wrap, remove the exposed release liner and press Drago Wrap firmly against DragoTack Tape to secure. Cut DragoTack Tape using a utility knife or scissors. Cut DragoTack Tape before removing the release liner for easier cutting. Install DragoTack Tape between 40°F and 110°F. Review Drago Wrap’s complete installation instructions prior to installation. 6.AVAILABILITY & COST DragoTack Tape is available nationally through our network of building supply distributors. For current cost information, contact your local Drago distributor or Stego Industries’ Sales Representative. 7.WARRANTY Stego Industries, LLC believes to the best of its knowledge, that specifications and recommendations herein are accurate and reliable. However, since site conditions are not within its control, Stego Industries does not guarantee results from the use of the information provided and disclaims all liability from any loss or damage. Stego Technology, LLC does offer a limited warranty on Drago Wrap. Please see www.stegoindustries.com/legal. 8.MAINTENANCE Store DragoTack Tape in a dry and temperate area. 9.TECHNICAL SERVICES Technical advice, custom CAD drawings, and additional information can be obtained by contacting Stego Industries or by visiting the website. Contact Number: (877) 464-7834 Website:www.stegoindustries.com 10.FILING SYSTEMS •www.stegoindustries.com P2 OF 2 P1 OF 2 DRAGO® SEALANT FORM A STEGO TECHNOLOGY, LLC INNOVATION | VAPOR RETARDERS 07 26 00, 03 30 00 | VERSION: 2/22/2019 1. PRODUCT NAME DRAGO SEALANT FORM 2. MANUFACTURER c/o Stego® Industries, LLC* 216 Avenida Fabricante, Suite 101 San Clemente, CA 92672 Sales, Technical Assistance Ph: (877) 464-7834 Fx: (949) 257-4113 www.stegoindustries.com 3. PRODUCT DESCRIPTION USES: Drago Sealant Form is used in conjunction with Drago® Sealant to help create an efficient and effective seal around pipe penetrations in Drago® Wrap Vapor Intrusion Barrier. COMPOSITION: Drago Sealant Form is a low-density, cross-linked, closed-cell polyethylene foam with an acrylic, pressure-sensitive adhesive. SIZE: Drago Sealant Form is ½" x ½" x 24". Drago Sealant Form comes in 200 pieces per case (10 boxes of 20 pieces). 4. TECHNICAL DATA TABLE 4.1: PHYSICAL PROPERTIES OF DRAGO SEALANT FORM PROPERTY RESULTS Dimensions ½” x ½” x 24” Color White Weight 0.11 oz (3.1 grams) Continued... Note – legal notice on page 2. 5. INSTALLATION PENETRATIONS: Make sure the area of adhesion is free of dust, debris, moisture, and frost to allow maximum adhesion. When ready to apply to Drago Wrap, remove the release liner and press Drago Sealant Form firmly against Drago Wrap to secure. Install Drago Sealant Form continuously around the entire perimeter of the penetration(s) and at least 1 inch beyond the terminating edge of Drago Wrap. Install Drago Sealant Form between 40°F and 110°F. Pour Drago Sealant inside of Drago Sealant Form to create a seal around the penetration(s). Review Drago Wrap’s complete installation instructions prior to installation. 6. AVAILABILITY & COST Drago Sealant Form is available nationally through our network of building supply distributors. For current cost information, contact your local Drago distributor or Stego Industries’ Sales Representative. DRAGO® SEALANT FORM A STEGO TECHNOLOGY, LLC INNOVATION | VAPOR RETARDERS 07 26 00, 03 30 00 | VERSION: 2/22/2019 DATA SHEETS ARE SUBJECT TO CHANGE. FOR MOST CURRENT VERSION, VISIT WWW.STEGOINDUSTRIES.COM (877) 464-7834 | www.stegoindustries.com *Stego Industries, LLC (“Stego”) is the exclusive Representative for Drago Wrap and Pango Wrap. All designated trademarks are the intellectual property of Stego or the entity for which it is acting as a Representative. Installation, Warranty, State Approval Information and Disclosure of Representative Status: www.stegoindustries.com/legal. ©2019 Stego Industries, LLC. All rights reserved. 7.WARRANTY Stego Industries, LLC believes to the best of its knowledge, that specifications and recommendations herein are accurate and reliable. However, since site conditions are not within its control, Stego Industries does not guarantee results from the use of the information provided and disclaims all liability from any loss or damage. Stego Technology, LLC does offer a limited warranty on Drago Wrap. Please see www.stegoindustries.com/legal. 8.MAINTENANCE Store Drago Sealant Form in a dry and temperate area. 9.TECHNICAL SERVICES Technical advice, custom CAD drawings, and additional information can be obtained by contacting Stego Industries or by visiting the website. Contact Number: (877) 464-7834 Website:www.stegoindustries.com 10.FILING SYSTEMS •www.stegoindustries.com P2 OF 2 Big Foot Slotted PVC Pipe Product Specification Sheet VIMS Specification Sheet 3 (Option) FERGUSON 3” SCH40 SLOTTED .060” wide x .375” spacing x 3 rows @ 120 East Hwy 30 Paxton, Nebraska 69155 308-239-4281 Customer Signature Approval__________________ 3” SCH40 120° Centers Specifications 3” SCH40 OD – 3.50” Wall – 0.216” ID – 3.068” Weight – 1.458 lbs per foot Slot Spacing Slot Width .375”.060” VIMS Specification Sheet 4 (Option) PDS Soil Gas Collector Mat Product Specification Sheets & Installation Instructions 1RADONPDS.COM | 719-444-0646 | ORDERS@RADONPDS.COM SOIL GAS COLLECTOR MAT SUBMITTAL PACKAGE & INSTALL GUIDE PHOTOS, VIDEOS, & MORE @WWW.RADONMAT.COM THE WORLD’S CHOICE FOR SOIL GASES FOR THREE DECADES!2 SOIL GAS COLLECTOR MAT FOR RADON READY NEW CONSTRUCTION According to the US EPA’s model standards for radon control systems in new building construction, a means for collecting soil gas should be installed beneath the slab. More and more mitigators and buildiers are using PDS’ soil gas collector mat (SGC Mat) because its installation does not entail any special coordination with plumbers or other site contractors. Low profile mat saves time as it removes the need for trenching. Just lay radon mat down around the inside perime-ter of the foundation, secure it with spikes or land-scaping staples, and pour the concrete. SGC mat is superior to other mat systems because of its thickness and it has a geotextile fabric cloth surrounding the entire mat material. This feature eliminates the need to lay a plastic barrier or sheet on top of the mat to protect the matrix. Using plastic sheeting can cause concrete cracking due to differential dewatering. The full fabric design greatly enhances both the installation as well as the quali-ty of the concrete slab. When SGC mat is installed below the slab, you’re providing an airspace that in-tercepts radon--and other soil gases and vapors--be-fore it seeps into the building through the slab. SGC mat also works well as a soil gas collector beneath crawlspace barrier due to its low-profile. WHY AND HOW IT WORKSThe matting is a one inch high by twelve inch wide matrix enveloped in a geotextile filter fabric. 90% of the geomatrix is airspace, which means soil gas has room to move to the collection point. This creates incredible pressure field extension for post construc-tion system activation. The mat can support con-crete without compressing, yet is extremely light-weight and easy to handle. This system allows for radon to flow through the filter fabric and into the airspace. The airspace does not clog because the filter fabric retains the under-lying gravel and soil. The natural airflow through the mat then channels the radon to the T riser to pipe connection. From there, hazardous gas can be vent-ed safely through the roof of the building. Another key element of a soil gas collection system is attaching the 4” riser* ( 3” and 6” options avail-able) to the mat, such that airflow is not restricted at this critical juncture. The soil gas T riser is unique as it has three ports, two redundant mat entries and one PVC connection to outside air. This unique fitting connects all three sides without special con-nections or fittings. Use SGC Seam Tape to ensure air tight splices and corners. 3RADONPDS.COM | 719-444-0646 | ORDERS@RADONPDS.COM TABLE OF CONTENTS Installation Instructions Making Corners and Splices Connecting the Mat to the T-Riser Trench and Footer Crossings Pouring Concrete Radon Risk About Us Product Materials and Safety Information Product Data Sheet Product Materials - Technical Specifications & Performance Misc Drawings and Specifications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4 6 7 8 11 12 13 14 16 18 22+ THE WORLD’S CHOICE FOR SOIL GASES FOR THREE DECADES!4 INSTALLATION INSTRUCTIONS* Begin work on the sub grade (soil, sand, or gravel) after the final preparation and before the concrete is poured. Start with T-Riser(s) and work out to en-sure smooth mat placement. Position the T-Riser(s) in appropriate location(s) and secure with nails or staples. Slide mat into flat openings on either end of T-ris-er with a portion of the fabric around the outside. Tape the fabric to the outside of the T-Riser with duct tape and staple mat to the ground with land-scape staples to ensure soil contact remains during pour stage. Mat is typically laid out in a rectangular loop in the largest area with branches or legs into smaller areas (FREE takesoffs at www.radonmat.com). There is no need to trench the mat. Roll out the SGC mat and smooth it onto the ground. To avoid wrinkles and buckling, work away from the risers, stapling to the ground as you go. The mat should be stapled every three to four feet, in addition to corners, tee junctions & ends. Corners are constructed by peeling back the filter fabric, cutting two ends of the matrix at 45 degree angles, and butting (or overlapping: no more than 1/2”) the matrix together. Pull the filter fabric back and tape into place. Staple across the joint of the matrix and each leg of the corner. Use a minimum of four staples at each corner-- two across the joint and one on each leg. The tees for branches and legs are constructed by slitting the fabric of the main loop at the location desired. Cut the fabric of the branch at the edges and expose two inces of the matrix. Cut off the exposed matrix and but the matrix of the branch (or overlap 1/2”)to the matrix of the main loop. Pull the filter fabric of the branch back over the main loop and tape into place. Staple across joint of the matrix with two staples and one each on the branch and main loop. Use a minimum of four staples at each tee, two across the joint and one on each loop and branch. STEP ONE STEP TWO STEP THREE STEP FOUR STEP FIVE 5RADONPDS.COM | 719-444-0646 | ORDERS@RADONPDS.COM INSTALLATION INSTRUCTIONS All openings in the fabric at joints, T’s, and ends of branches should be taped to keep out concrete. Stub up a few feet of 4” schedule 40 PVC** from all T risers before pour. Seal with caulk and screws. This ensures no concrete aggregate enters the ris-er during slab pour. Be sure to label “CAUTION RADON REDUCTION SYSTEM” on all pipe. **(6” PVC may be substituted--for large multifamily proj-ects. Simply cut T riser 4” insert away to reveal 6” Legacy T Riser). PVC sizes vary by code and design. 3”, 4”, & 6” schedule 40 PVC are acceptable. When the building is ready for the vent pipe to be installed above the slab, fit to pre-stubbed PVC with PVC straight connect. Always label “CAUTION RADON REDUCTION SYSTEM” every 10 feet to avoid confusion on site and for the building occupants. STEP SIX STEP SEVEN STEP EIGHT NOTE: The openings in the riser are laid out at 180 degrees to accomodate straight runs of mat. However, if the riser is to be placed in a corner, which is not uncommon, the front of the T can be cut and the SGC mat inserted into the new opening. The side of the T that is unused should be sealed with tape. This creates a 90 degree T which will allow corner placement for the riser. Mat should al-ways enter the T riser from at least two directions and exhaust to pipe vertically. CONTINUED *These are the manufacturer’s instructions to ensure a proper functioning system. Certain code variants across the US have more lax or more con- servative requirements. PDS’ soil gas collector can be installed to meet any code requirement (as of publication of this document). Please reach out to PDS or a certified radon mitigator for consulting on specific code variants. INSTALL VIDEO THE WORLD’S CHOICE FOR SOIL GASES FOR THREE DECADES!6 MAKING CORNERS AND SPLICES The geotextile mat should be routed around the inside perimeter of the foundation. This will require occasional corner junctions. Furthermore, splices will have to be made to join two lengths of mat to-gether. Corners and splices are very easy to make, and do not require any special fittings. Cut back the filter fabric to reveal the core material. In the case of a splice, merely overlap the core by at least one corrugation, replace the cloth, and tape it using PDS SGC seam tape. Use two landscape staples to hold the splice in place. In the case of a corner, peel back geotextile fabric and slice the core of the two adjoining legs at 45 degree angles which mirror each other; overlap the edges by one corrugation; return grey geotextile fabric, tape, and staple the corner together. 7RADONPDS.COM | 719-444-0646 | ORDERS@RADONPDS.COM CONNECTING THE MAT TO THE T RISER A convenient T-riser with dual entry allows for ei-ther end of the loop of mat to be secured to the riser. Slide the mat into each end of the riser and tape the edge to prevent wet concrete from enter-ing. Cap the riser to ensure no concrete enters. T Riser caps can be purchased in lieu of duct tape. A prestub of PVC pipe can also serve the same pur-pose. See steps 8-9 above. ***Due to high product demand, several T riser de-signs have been tested and approved for sale. Your riser may look different than the one pictured here, however its function is the same. Ensure you stub up the PVC pipe and seal all openings with tape so that concrete does not enter during the pour. Secure mat to the ground with staples so riser doesnot float. THE WORLD’S CHOICE FOR SOIL GASES FOR THREE DECADES!8 INSTALL INFORM FORMFORMGRAVEL OR SOIL UNDER MAT FOOTER FORM GRAVEL OR SOIL UNDER MAT SOIL GAS MAT SOIL GAS MAT8” STRONG SLEEVE SOIL GAS MAT SOIL GAS MAT 8” STRONG SLEEVE TOP VIEW GOING OVER FOOTER / WALL / TRENCH SIDE VIEW GOING THRU FOOTER/ INTERMEDIATE WALL FORM*See misc drawings at end of guide for more information. STRONG SLEEVE SKU: 05-139-S TRENCH & FOOTER CROSSING OPTIONS 9RADONPDS.COM | 719-444-0646 | ORDERS@RADONPDS.COM SOIL GAS MAT SOIL GAS MAT PVC PIPE GRAVEL OR SOIL UNDER MAT FOOTER / INTERMEDIATE WALL / TRENCH GRAVEL OR SOIL UNDER MAT TOP VIEW GOING OVER FOOTER / WALL / TRENCH SOIL GAS MAT SOIL GAS MAT4” sch. 40 PVC PIPE *IDEAL FOR LONG SPANS SIDE VIEW GOING THRU FOOTER/ INTERMEDIATE WALL TRENCH & FOOTER CROSSING OPTIONS FLAT END COMBO OUTLET SGC TO PVC TRANSITION TRENCHTRENCH*Three feet or more SKU: 05-141-2F TRENCH THE WORLD’S CHOICE FOR SOIL GASES FOR THREE DECADES!10 STEEL SLEEVE SKU: 05-141-W & 05-141-36 *Rebar is a low-cost option that may be used in place of steel sleeve. Place two to three pieces of rebar underneath gas mat trench spans. Rebar must extend past trench at least one foot. Secure with SGC Seam Tape. Priority is to keep mat level and in tact during and after pour. IDEAL FOR SHORT TRENCHES TRENCHTRENCHGRAVEL OR SOIL UNDER MAT FOOTER / INTERMEDIATE WALL / TRENCH GRAVEL OR SOIL UNDER MAT SOIL GAS MAT SOIL GAS MAT STEELSLEEVE*(Avail. in 24” or 36”) SOIL GAS MAT SOIL GAS MAT STEEL SLEEVE*1” THICK TOP VIEW GOING OVER FOOTER / WALL / TRENCH SIDE VIEW GOING THRU FOOTER/ INTERMEDIATE WALL 24” (36”) X 1” X 12” TRENCH & FOOTER CROSSING OPTIONS 11RADONPDS.COM | 719-444-0646 | ORDERS@RADONPDS.COM The filter fabric that comes sewn around the soil gas collector prevents the wet concrete from entering the mat and reducing its air collection capacity. The only precaution that needs to be taken is that the fabric is taped closed at seams of splices and corner to sufficiently keep the uncured concrete from entering. The mat also needs to be secured to the soil with landscape staples to prevent the concrete from lifting off the soil while it is being applied. Re-enforcing bars and wire can be laid on top of the mat. Note: the mat is strong enough to withstand concrete workers and their wheel barrows. POURING CONCRETE THE WORLD’S CHOICE FOR SOIL GASES FOR THREE DECADES!12 RADON RISK! RADON-INDUCED LUNG CANCER CLAIMS THE LIVES OF OVER 22,000 AMERICANS EACH YEAR FACT: Radon is found at dangerous levels in all 50 US states. The EPA action level is 4.0 pci/L or higher FACT: All US Homes have high radon potential, even those without basements FACT: Radon is the leading cause of lung cancer among “never smokers” FACT: Radon is a nobel gas and a natural part of the Uranium 238 breakdown chain FACT: Breathing 6.2 pci/L is the equivalent radiation dosage of a THREE chest x-rays each week for your lungs FACT: Radon is colorless, odorless, and invisible to the naked eye FACT: Radon testing is cheap and you can do it yourself! GET THE FACTS @ WWW.RADONREALITY.COM 13RADONPDS.COM | 719-444-0646 | ORDERS@RADONPDS.COM ABOUT US PROFESSIONAL DISCOUNT RADON SUPPLY Family-owned and operated since 1996. Situated on Colorado’s front range, PDS focuses on generating radon awareness through one-on-one technical support and trouble-shooting. Our products have been successfully installed in all 50 states and several foreign countries. Distribution opportunities available.Please call for availability in your market PDS Family: Owners / Operators 5720 Observation CourtColorado Springs, CO 80916 (719) 444-0646 brent@radonpds.com www.radonpds.com THE WORLD’S CHOICE FOR SOIL GASES FOR THREE DECADES!14 PRODUCT MATERIALS & SAFETY INFORMATION RECOMMENDED MAXIMUM OCCUPATIONAL EXPOSURE LIMITS COMPONENT EXPOSURE LIMITS OSHA - PEL.HAZARD DATACAS NO. Polystyrene 9003-55-6 None Established No hazardous Ingredients PROPERTIES DATA FIRE HANDLING MEASURES Extinguishing Media Fire Fighting Procedure Water Spray (except when fire is of electrical origin), Foam, Dry Powder, CO2 Self-contained breathingapparatus & suitableprotective equipment PROPERTIES DATA PHYSICAL DATA Form Color Odor Boiling Point Melting Point (°F) Flash Point (°F) Flamable Limits (°F) VAC Volatility Specific Gravity Solubility in Water Molded Sheet Black None Not Applicable 270 Not Applicable Not Applicable 0% <0.75% Moisture 1.02–1.08 Not Soluable PROPERTIES DATA ECOLOGICAL INFORMATION & DISPOSAL Ecological information Toxicological Disposal Not associated with anyknown ecological problems No negative effects onhumans Polystyrene recycles well.Can be disposed of assolid waste or burnedin a suitable installationsubject to local regulations.Effluents disposal shouldalso be in accordancewith local legislation. SOIL GAS COLLECTOR MATSafety data for our non-woven, spun-bonded, polypropylene, gray geotextile fabric is shown below. 15RADONPDS.COM | 719-444-0646 | ORDERS@RADONPDS.COM PERFECT FOR RADON CONTROL SYSTEMS IN NEW HOME CONSTRUCTION PROPERTIES DATA PHYSICAL DATA Stablitity Incompatibility (Materials to avoid) Hazardous Decomposition Conditions to avoid Stable Can react with strong oxidixers Carbon dioxide, carbon monoxide, various hydrocarbons None The economical alternative to aggregate systems—quick and easy installation DESCRIPTION INFORMATION SPECIAL HANDLING INFORMATION Handling & Storage Precaution Eye Protection, Recommended Skin Other Clothing & Equipment Work Practices, Hygiene Handling & Storage, Other Protective Measures, Maintenance Protect against flame & intense heat. Avoid breathing hot vapors. Use OSHA approved safety glasses when handling. Wash with soap & water. Get medical attention if irritation developsor persists. Gloves recommended due to sharp edges. Use standard work practices for hygienic safety. Store in well-ventillated area. Avoid extreme heat & sources of ignition oropen flame. Not Applicable To the best of our knowledge, the information presented herein is accurate. However, it is not a warranty or a guarantee and is provided for reference only. THE WORLD’S CHOICE FOR SOIL GASES FOR THREE DECADES!16 PRODUCT DATA SHEET MATERIAL PHYSICAL PROPERTIES PROPERTY TEST METHOD CUSPATED PLASTIC Specific Gravity (g/cc) Melt Flow @ 200°C/5000g (g/10 min) Tensile Strength @ Yield (psi) Tensile Modulus (psi) Elongation @ Break (%) Flexural Modulus (psi) Impact Strength, Notched Izod @ 73°F (ft-lb/in) Heat Deflection Temperature @ 264 psi (°F) Vicat Softening Point (°F) ASTM D-792 ASTM D-1238 ASTM D-638 ASTM D-638 ASTM D-638 ASTM D-790 ASTM D-256 ASTM D-648 ASTM D-1525 VALUE 1.04 2.5 2,900 275,000 70 300,000 2.1 183 210 PROPERTY TEST METHOD COVER FABRIC Grab Tensile (lbs) Elongation (%) Trapezoid Tear (lbs) Puncture (lbs) Mullen Burst (psi) AOS (U.S. sieve number) Permittivity (sec-1) Permeability (cm/sec) Water Flow (gal/min/sf) UV Stability (%) ASTM D4632 ASTM D4632 ASTM D4533 ASTM D4833 ASTM D3786 ASTM D4571 ASTM D4491 ASTM D4491 ASTM D4491 ASTM D4355 VALUE 130 > 50 60 41 140 70 0.8 0.04 60 70 SOIL GAS COLLECTOR MAT Safety data for our non-woven, spun-bonded, polypropylene, gray geotextile fabric is shown below. SKU: 05-140-3 (replaces SKU 05-140-1) 17RADONPDS.COM | 719-444-0646 | ORDERS@RADONPDS.COM PERFECT FOR RADON CONTROL SYSTEMS IN NEW HOME CONSTRUCTIONThe economical alternative to aggregate systems—quick and easy installation To the best of our knowledge, the information presented herein is accurate. However, it is not a warranty or a guarantee and is provided for reference only. MATERIAL PHYSICAL PROPERTIES PROPERTY TEST METHOD BINDING METHOD External Binder Type Stitching Type Thread Tensile Strength (lbs) Thread Gage Chemically Impervious Standard Standard Standard ASTM D4632 Standard Standard VALUE Sewn Lock Stitch HB92 Nylon 11 2 IOx4 denier MI Natural CONTINUED THE WORLD’S CHOICE FOR SOIL GASES FOR THREE DECADES!18 PRODUCT MATERIALS & SAFETY INFORMATION SOIL GAS COLLECTOR MAT RECOMMENDED MAXIMUM OCCUPATIONAL EXPOSURE LIMITS Safety data for our non-woven, spun-bonded, polypropylene, gray geotextile fabric is shown below. COMPONENT EXPOSURE LIMITS OSHA - PEL.HAZARD DATACAS NO. Polystyrene 9003-07-0 None Established No hazardous Ingredients PROPERTIES DATA FIRE HANDLING MEASURES Extinguishing Media Fire Fighting Procedure Water Spray (except when fire is of electrical origin), Foam, Dry Powder, CO2 Self-contained breathingapparatus & suitableprotective equipment PROPERTIES DATA PHYSICAL DATA Form Color Odor Boiling Point Melting Point (°F) Flash Point (°F) Flamable Limits (°F) Auto ignition temperature Vapor Pressure (Pascal) Density (g/cm3) @20 ºC Solubility in Water Thermal decomposition (ºF) Molded Sheet Black None Not Applicable 270 Not Applicable Not Applicable Not Applicable Not Volatile 0.91 Not Soluable Above 570 PROPERTIES DATA ECOLOGICAL INFORMATION & DISPOSAL Ecological information Toxicological Disposal Not associated with anyknown ecological problems No negative effects onhumans Polystyrene recycles well.Can be disposed of assolid waste or burnedin a suitable installationsubject to local regulations.Effluents disposal shouldalso be in accordancewith local legislation. 19RADONPDS.COM | 719-444-0646 | ORDERS@RADONPDS.COM PERFECT FOR RADON CONTROL SYSTEMS IN NEW HOME CONSTRUCTIONThe economical alternative to aggregate systems—quick and easy installation To the best of our knowledge, the information presented herein is accurate. However, it is not a warranty or a guarantee and is provided for reference only. PROPERTIES DATA STABILITY & REACTIVITY Stablitity Incompatibility (Materials to avoid) Hazardous Decomposition Conditions to avoid Stable Can react with strong oxidixers, base, or acid Carbon dioxide, carbon monoxide, low molecular weight oxygenated organic None DESCRIPTION INFORMATION SPECIAL HANDLING INFORMATION Handling & Storage Precaution Eye Protection, Recommended Skin Other Clothing & Equipment Work Practices, Hygiene Handling & Storage, Other Protective Measures, Maintenance Avoid breathing hot vapors, oiled mists, and airborne fibers. Use OSHA approved safety glasses when handling rolls Wash with soap & water. Get medical attention if irritation developsor persists. Not applicable Use standard work practices for hygienic safety. Store rolls In accordance with good material handling practice. Not Applicable THE WORLD’S CHOICE FOR SOIL GASES FOR THREE DECADES!20 PRODUCT MATERIALS, TECHNICAL SPECIFICATIONS & PERFORMANCE SOIL GAS COLLECTOR MATOur non-woven, spun-bonded, polypropylene, gray geotextile fabric with the minimumvalues shown below. PROPERTY TEST METHOD Grab Tensile Strength (lbs) Elongation (%) Trapezoid Tear (lbs) Puncture (lbs) Mullen Burst (psi) AOS (U.S. sieve no.) Permittivity (sec-1) Permeability (cm/sec) Vertical Water Flow Rate (gal/min/sf) UV Stability (%) ASTM D4632 ASTM D4632 ASTM D4533 ASTM D4833 ASTM D3786 ASTM D4571 ASTM D4491 ASTM D4491 ASTM D4491 ASTM D4355 VALUE 130 >50 60 41 140 70 0.8 0.04 60 70 21RADONPDS.COM | 719-444-0646 | ORDERS@RADONPDS.COM PRODUCT MATERIALS, TECHNICAL SPECIFICATIONS & PERFORMANCE PROPERTY TEST METHOD Specific Gravity Melt Flow (g/10min) Tensile @ Yield (psi) Tensile Modulus (psi) Elognation @Break (%) Flexural Modulus (psi) Notched Izod @ 73ºF (ft-lb/in) HDT @ 264 psi (ºF) Vicat Softening Point (ºF) ASTM D-792 ASTM D-1238 ASTM D-638 ASTM D-638 ASTM D-638 ASTM D-790 ASTM D-256 ASTM D-648 ASTM D-1525 VALUE 1.04 2.5 2,900 275,000 70 300,000 2.1 183 210 THE WORLD’S CHOICE FOR SOIL GASES FOR THREE DECADES!22 Product DetailsVer. 3/1/2023 1. Product NameModel SSK-08 2. ManufacturerStrong Sleeves™ LLC10 Town Plaza, #444Durango, CO 81301www.strongsleeves.com 3. Product DescriptionUses: Strong Sleeves™ are installed when forming concrete structural supports, creating a continuous path-way for effective soil gas collection systems. In accordance with the Drawings, the pre-manufactured Strong Sleeve devices allow radon mitigation mats to easily be continued through concrete grade beams and con-crete stem walls without transitioning to round pipe.Advantages: Strong Sleeves are designed and engineered for safer construction of new residential, commer-cial, and school buildings by eliminating extensive trenching and specialized gravel fill materials. 4. Installation a. Install at elevations and locations shown on the Drawings or as otherwise directed by the Archi tect. Coordinate all locations with the Structural Engineer to confirm that the block-out locations through the grade beams and stem walls have sufficient structural strength and adequate reinforce ment. b. Attach the Sleeve to the interior walls of the concrete forms using the (4) pre-drilled holes in each Sleeve unit. Adjust steel reinforcement as directed by the Structural Engineer for wall or grade beam penetrations. c. After pouring concrete and removing concrete forms, remove the foam insert within each Sleeve. Use mechanical means only, DO NOT USE SOLVENTS TO DISSOLVE THE FOAM. Using solvents (such as gasoline) to remove the foam blocking may damage radon mitigation equipment and may lead to the risk of fire. 5. Availability and CostStrong Sleeves™ are available through our network of specialty radon supply distributors. For current cost information and availability contact Radon PDSwww.radonpds.com. 23RADONPDS.COM | 719-444-0646 | ORDERS@RADONPDS.COM Product DetailsVer. 3/1/2023 6. Hazards and Exposure ControlsThis product is exempt from hazard classification according to OSHA Hazard Communication Standard, 29 CFR 1910.1200.This product is considered to be an article which does not release or otherwise result in exposure to a haz-ardous chemical under normal use conditions. No engineering controls or personal protective equipment (PPE) are necessary. 7. Materials DataEach Sleeve shall be constructed of a minimum of 22 gage galvanized sheet steel according to the sizes shown on the Drawings. 8. WarrantyStrong Sleeves LLC shall guarantee the Sleeve components against all manufacturer originated defects in materials or workmanship for a period of twelve (12) months from the date the components are delivered for installation. The manufacturer shall upon its determination repair, correct or replace any manufacturer originated defects advised in writing to the manufacturer within the referenced warranty period. The cost of the replacement or repair of the Strong Sleeves shall be limited to the cost of the Strong Sleeve products supplied. The use of Sleeves shall be limited to the application for which they were specifically designed. 9. Technical ServicesTechnical advice, custom CAD drawings, custom Sleeve sizing, and additional information can be obtained by contacting Strong Sleeves or by visiting the website. PROPERTY COMPONENT Appearance:Metallic Physical State:Solid Solubility in Water:Insoluable Melting Point:2,372~2,800 °F Specific Gravity (water = 1):7.5~8.5 Odor:Odorless Product DetailsVer. 3/1/2023 PROJECTTITLEDRAWNCHECKEDAPPROVEDSCALEWEIGHTSHEETDWG NOREVCODESIZE1/12/28/2023Dylan McClain001BRENT ULBERTABRENT ULBERTPDS RADON SUPPLYDETAIL, PRODUCT 05-140-3SOIL GAS MAT SUB-SLABCONCRETE SLABFIELDTOPPREPARED SUB-SLABOR SOILFIGURE 1FIGURE 212in1inSGC MAT 05-140-312inSOIL GAS COLLECTION MATPRODUCT 05-140-34in 2inFOAMFOAMFIELDEDGE/PERIMETERVOIDFIGURE 1FIGURE 22in13in13inVOIDSOIL GAS RETARDER BARRIER, SEEARCHITECTURAL SPECIFICATIONS FORMATERIAL PROPERTIES ANDINSTALLATION.PREPARED SUB SLAB MATERIAL,SEE GEOTECH AND STRUCTURAL FOR DETAILSSTRONG SLEEVES LLCSOIL GAS MAT SUB-SLABPREPARATION DETAILSTRONG SLEEVES LOGOAND BUSINESS INFOPREPARED SUB SLAB MATERIAL,SEE GEOTECH AND STRUCTURAL FOR DETAILSSOIL GAS RETARDER BARRIER, SEEARCHITECTURAL SPECIFICATIONS FORMATERIAL PROPERTIES ANDINSTALLATION.CONCRETE SLAB, SEE STRUCTURALFOR THICKNESS AND REINFORCEMENTDETAILSCONCRETE SLAB, SEE STRUCTURALFOR THICKNESS AND REINFORCEMENTDETAILSSOIL GAS MAT SUB-SLAB PREPARATION DETAIL.DWG 2/28/2023 GRADE BEAM / STEM WALLWIDTH VARIES, SEESTRUCTURAL FOR DETAILS. PDS RADON SUPPLY T RISER DETAILT RISER DETAIL.DWG3/27/202312.625 IN 11.625 IN 4 IN Ø4 IN 5.813 IN 1.375 IN VIMS Specification Sheet 5 Ventilator Specification Sheets TURBINE VENTILATORS CONSTRUCTION SPECIFICATIONS “A” THROAT SIZE GUAGE NO. OF BRACES BRACE MATERIALCROWN GALV.BLADE GALV.THROAT GALV. 4 24 28 26 3 ALUMINUM 6 24 28 26 3 ALUMINUM 8 24 28 26 3 ALUMINUM 10 24 28 26 3 ALUMINUM 12 24 28 24 3 ALUMINUM 14 22 26 24 3 ALUMINUM 16 22 26 24 3 STEEL 18 22 26 24 4 STEEL 20 20 26 24 4 STEEL 24 20 26 22 4 STEEL DIMENSIONAL AND PERFORMACE DATA “A” THROAT SIZE “B” HEIGHT “C” OVERALL WIDTH EXHAUSTED CAPACITY* APPROX. SHIPPING WEIGHT 4 12 10 1/4 125 5 6 14 1/2 12 3/4 147 7 8 15 14 1/4 255 8 10 16 1/4 16 1/4 425 11 12 17 19 631 13 14 19 3/4 22 3/4 700 21 16 21 3/4 25 1/2 950 31 18 24 29 1200 38 20 25 1/4 31 5/8 1700 46 24 28 1/4 35 3/4 2350 58 *4 MPHWIND CFM Monitoring Point Specification Sheets VIMS Specification Sheet 5 Application • Easy access to walls and ceilings • Economical and attractive Product Features • High impact styrene plastic with U.V. stabilizers • Hinged with a removable feature PA-3000 Access Door Specifications: Door / Door Frame: 1/8" high impact styrene plastic with U.V. stabilizers Flush to frame — rounded safety corners, one piece outside flange with 3/4" deep mounting frame Standard Latch: Snap latches allow door to fit tightly within frame Door Hinge: Concealed Finish: White, with textured exposed surfaces PA-3000 View of door backP A - 3 0 0 0 P R O D U C T IN F O R M A T I O N PA3000 STANDARD SIZES Nominal Door Size W&H Weight per Door inches mm lbs. kg. 4 X 6 102 X 152 .5 .25___________________________________ 6 X 9 152 X 229 .5 .25___________________________________ 8 X 8 203 X 203 .5 .25___________________________________ 12 X 12 305 X 305 .5 .25___________________________________ 14 X 14 356 X 356 .75 .33___________________________________ 14 X 29 356 X 737 4 1.87___________________________________ 18 X 18 457 X 457 2.25 1___________________________________ 22 X 22 559 X 559 4 1.87___________________________________ 24 x 24 610 x 610 4.75 2.15___________________________________ Wall or ceiling opening is W + 3/8” ( 9 mm) For detailed specifications see submittal sheet FLUSH NONRATED Plastic Access Door PA-3000 *22 x 22 and 24 x 24 sizes are designed for wall installation only. * * U.S.A.: info@acudor.com / 800.722.0501 CANADA: info@acudor.ca / 844.228.3671 INTERNATIONAL: info@acudorintl.com / 905.428.2240 MEXICO: infomx@acudor.com / +521 (844) 101-0081 INDIA / MIDDLE EAST / NORTH AFRICA: ap-imea@acudor.com / +971-4-399-6966 SITE: www.acudor.com This document contains proprietary information which is the property of Acudor Products. It shall not be modified, copied, furnished, nor distributed (in whole or in part) without proper authorization. Copyright © 2020 Acudor Products. Family Owned & Operated Since 1990 WBCA 2019 1330 Progress Drive • Front Royal, VA 22630 • Phone: 1-800-255-5515 • www.wbdoors.com "CLEAROPENINGHEIGHT CLEAR OPENINGWIDTH C C "DOORCLEARANCE LATCH BOLT COVEREXTENDS 1/2" BEYONDOUTSIDE EDGE OF FRAME SPRINGMOUNTBRACKET INTERIORRELEASEMECHANISM WALL &CEILING SPECIFICATIONS: Door: 20 ga. steel Trim: 16 ga. steel Finish: Primed white baked enamel, paintable surface Latches: Knurled knob lock w/1 Flush key Hinge: Flush continuous piano type hinge., Concealed pin. Allows opening to 180° Insulation: 2” thick mineral wool in between two pieces of 20 ga. steel Ceiling Installation: To comply with current fire regulations, largest size acceptable is 24” x 36” OPTIONS (at additional cost) Finishes: q Stainless Steel Type 304 No. 4 Satin Finish Brushed q Stainless Steel Type 316 No. 4 Satin Finish Brushed Options: (additional cost) q Mortise Best Lock or locks by others q Hot Smoke Seal gasket all 4 sides** q Special sizes available q _____________________________________________ 4 ModelNo. DoorSizeW x H WallOpening SlamCatch ShipWt. Lbs. FR 800 8 x 8 8 1/4 x 8 1/4 1 8 FR 800 10 x 10 10 1/4 x 10 1/4 1 10 FR 800 12 x 12 12 1/4 x 12 1/4 1 12 FR 800 12 x 18 12 1/4 x 18 1/4 1 15 FR 800 12 x 24 12 1/4 x 24 1/4 1 19 FR 800 14 x 14 14 1/4 x 14 1/4 1 14 FR 800 16 x 16 16 1/4 x 16 1/4 1 17 FR 800 18 x 18 18 1/4 x 18 1/4 1 21 FR 800 18 x 24 18 1/4 x 24 1/4 1 26 FR 800 20 x 30 20 1/4 x 30 1/4 1 24 FR 800 22 x 22 22 1/4 x 22 1/4 1 28 FR 800 22 x 24 22 1/4 x 24 1/4 1 29 FR 800 22 x 30 22 1/4 x 30 1/4 2 39 FR 800 22 x 36 22 1/4 x 36 1/4 2 47 FR 800 24 x 24 24 1/4 x 24 1/4 1 32 FR 800 24 x 30 24 1/4 x 30 1/4 2 43 FR 800 24 x 36 24 1/4 x 36 1/4 2 48 FR 800 24 x 48*24 1/4 x 48 1/4 2 62 FR 800 30 x 30*30 1/4 x 30 1/4 2 48 FR 800 32 x 32*30 1/4 x 32 1/4 2 55 FR 800 36 x 36*36 1/4 x 36 1/4 2 58 FR 800 36 x 48*36 1/4 x 48 1/4 2 62 FR 800 48 x 48*48 1/4 x 48 1/4 2 68 UL Listed “B” label for 1-1/2 hours (vertical). Warnock-Hersey listed for 3 hours (horizontal). ** Hot Smoke SealTM fire tested: Listed to meet the requirements of standards UL10B, UL10C, UBC 7-2, Part 1 and BS476: 1987 for application to fire rated door assemblies. Tested for smoke controlled assemblies: Listed to meet the requirements of standards UL1784, NFPA 105, UBC 7-2, Part 2, and BS476:Part 31, Section 31.1:1983. It also is a chemically inert, highly stable, expandable graphite strip, tested and proven in positive pressure conditions to withstand both hot smoke and hot gasses, resulting in the longer integrity of a door assembly. More economical to use than specially modified doors in “tested assembly only” classifications. Chemically inert, and therefore will not degrade from carbon dioxide and ozone like the many intumescents being offered by other manufacturers. Hot Smoke Seal™ is not affected by moisture and will not break down like fiber or cellulose based products and does not require periodic after market field inspections. Insulation: is a rigid mineral wool (stone wool) insulation board for high temperature industrial applications subject to light mechanical loads.] - 2” thickness. Fire-rated access door for ceiling installation for 3 hr max size 24 x 36. CEILING OPENING – DOOR SIZE + 3/8” 5/8” FIRE CODEGYPSUM BOARD INTERIOR LATCH RELEASE AUTOMATIC SPRING CLOSER ON ALL DOORS KNURLED KNOB/FLUSH KEYOR KEY OPERATED 1.4” INSULATION2” AROUND ROUGH OPENING WOODJOIST CONCEALED ROD HINGE #12 SELF TAPPING 2”SCREWS C-SHAPEDSTEEL JOIST FLOOR 1.4” This fire-rated door can be used wherever it is necessary to provide service access to shafts and any other location which must have a fire rating. Approved ceiling use. NOTE: For fire-rated ceiling access doors, on size 16” x 16” and larger, extra spring supplied with door must be attached from back of door pan to framing or floor above. In horizontal (ceiling) applications door has self-assisted closing. Knurled Knob Lock w/1 Flush Key Optional HOT Smoked Seal* gasket WB FR 800 Series Fire-Rated Access Door 24 SECTION DETAIL Project: __________________________________________________________________________________Date: ___________________ Contractor: _________________________________________Architect: _____________________________________________________ Sizes: ______________________________________________Quantity: ______________________App Initials: ___________________ RELATED PRODUCTS WB FRU 810 Ultra Series Fire-Rated SUBMITTAL SHEET FRONT ELEVATION Self latching Slam Catch * Wall installation only WAL-RICH CORPORATION • NEW PRODUCT BULLETIN CALL (800) 221-1157 · www.wal-rich.com · FAX (516) 277-2177 STAINLESS STEEL TERMINATION SCREENS Ideal for use on high efficiency heating equipment Also as condensate trap screen & vent stack guard. Patent# D715,409 2202050 2” Stainless Steel Termination Screen22020523” Stainless Steel Termination Screen 2202054 4” Stainless Steel Termination Screen 2202056 6” Stainless Steel Termination Screen 2202060 1” Stainless Steel Termination Screen Part# Description made in usa ♦♦♦♦♦Prevent pests, debris, & leaves from entering vent piping ♦♦♦♦♦Push into hub for easy flush installation. No gluing! ♦♦♦♦♦Patented condensate channel prevents buildup & freezing ♦♦♦♦♦Professional grade finish