HomeMy WebLinkAbout19072_Radio Center_SIR_20221101
DWM Brownfields Inspection Report
Submitted By: jkslaughter_ncdenr
Submitted Time: 11/02/2022 2:00 PM
I. Inspection Information
Date & Time: 11/01/2022 10:41 AM Inspection Type: Drive-By
Brownfields Staff:
Kevin Slaughter
Other Personnel:
Billy Threatt – Construction Superintendent
Location:
Lat: 35.19568206, Long: -80.87137571
Brownfields Inspection Report: Radio Center Property, 19072-15-060
11/01/2022 10:41 AM
Page 2 of 6
II. Project Information
Number: 19072-15-060 Name: Radio Center Property
Address: 3229, 3235 South
Boulevard
City: Charlotte
County: Mecklenburg
III. Environmental
Current Use of Property: Commercial/Retail
Structures on Property: New Structures Violation: No
Vapor Mitigation Systems: Not Observed Vapor Mitigation Violation: No
Use of Surface Water or Groundwater: Not Observed Water Use Violation: No
Exposed Soils: Observed Exposed Soils Violation: No
Summary: Installation has not started yet; however, according to the Site
Superintendent. The VIMS installation is expected to start in 2-3 weeks, and ECS will be
overseeing its installation.
Summary: N/A
Summary: A Lidl supermarket is currently under construction on the southwestern
portion of the property (Photos 1-5).
Summary: Observed exposed soil on the property, as well as utility trench work being
performed on the northern side of the building (Photos 1 - 5).
Brownfields Inspection Report: Radio Center Property, 19072-15-060
11/01/2022 10:41 AM
Page 3 of 6
Use of Basements: Not Observed Basement Violation: No
Storage of Chemicals: Not Observed Chemical Violation: No
Groundwater Monitoring Wells: Not Observed Monitoring Well Violation: No
Current Exposure to Public/Public Risk:
Summary: N/A
Summary: N/A
Condition:
Summary: N/A
The perimeter of the property is fenced, and no public risk was observed at the time of
the Site Inspection.
Brownfields Inspection Report: Radio Center Property, 19072-15-060
11/01/2022 10:41 AM
Page 4 of 6
IV. Inspector Comments
V. PHOTOGRAPHS
Photo 1: View of future Lidl grocery store facing south.
The Site Inspection was performed as construction work was observed taking place on
the property, and it was unknown if the VIMS installation had begun, or possibly even
been completed as the sidewalls and roof were installed on the future grocery store.
During the Site Inspection, met with the site superintendent, Mr. Billy Threatt. Mr.
Threatt indicated that the VIMS installation should start within the next 2-3 weeks as
discussed previously, and a hard copy of the EMP was present on-site.
Brownfields Inspection Report: Radio Center Property, 19072-15-060
11/01/2022 10:41 AM
Page 5 of 6
Photo 2: Photo inside building along northern wall. Utility conduit entering northern side of
building (Photos 4 and 5) visible on left side of photo.
Photo 3: Additional photo taken near the entrance of the building during construction.
Brownfields Inspection Report: Radio Center Property, 19072-15-060
11/01/2022 10:41 AM
Page 6 of 6
Photo 4: Utility line trenching on northern side of building.
Photo 5: View of utility conduit piping crossing under northern building footer.