Loading...
HomeMy WebLinkAbout24025_Crayton Printing_SIR_2022.05.18 DWM Brownfields Inspection Report Submitted By: jkslaughter_ncdenr Submitted Time: 05/20/2022 11:20 AM I. Inspection Information Date & Time: 05/18/2022 8:51 AM Inspection Type: Meeting Brownfields Staff: Kevin Slaughter Other Personnel: Juliana Lima - H&H Location: Lat: 35.20722505038602, Long: -80.86574474602725, Brownfields Inspection Report: Crayton Printing (RN), 24025-20-060 05/18/2022 8:51 AM Page 2 of 7 II. Project Information Number: 24025-20-060 Name: Crayton Printing (RN) Address: 2301, 2321, 2327 Distribution St.; 2300, 2302, 2304, 2306 Dunavant St. City: Charlotte County: Mecklenburg III. Environmental Current Use of Property: Residential Structures on Property: New Structures Violation: No Vapor Mitigation Systems: Observed Vapor Mitigation Violation: No Use of Surface Water or Groundwater: Not Observed Water Use Violation: No Exposed Soils: Observed Exposed Soils Violation: No Summary: During Site Inspection, inspected section of VIMS barrier not completed in time for complete inspection), in addition to section of slab which had been inspected previously prior to pouring the concrete slab (Photos x – x) Summary: Summary: Construction of multi-story residential apartments, and parking deck taking place at the property (Photos 1-7) Summary: Exposed soils are present but are consistent with EMP and site development activities. Brownfields Inspection Report: Crayton Printing (RN), 24025-20-060 05/18/2022 8:51 AM Page 3 of 7 Use of Basements: Not Observed Basement Violation: No Storage of Chemicals: Not Observed Chemical Violation: No Groundwater Monitoring Wells: Not Observed Monitoring Well Violation: No Current Exposure to Public/Public Risk: Summary: N/A Summary: N/A Condition: Summary: N/A No risk to the public observed at the time of the Site Inspection. Brownfields Inspection Report: Crayton Printing (RN), 24025-20-060 05/18/2022 8:51 AM Page 4 of 7 IV. Inspector Comments V. PHOTOGRAPHS Photo 1: Section of VIMS barrier scheduled for inspection by H&H. Work was still taking place on the barrier installation, and it will require a reinspection. The Site Inspection was performed to coincide with a planned H&H barrier inspection at the property. Upon arrival, it was determined that the barrier installation had not been completed in time and will require a H&H VIMS barrier reinspection (Photos 1 and 2). While on-site, I was able to inspect a section of VIMS barrier that had previously been inspected by H&H and was awaiting a concrete pour (Photos 3 and 4). In addition, photos were taken of area I had previously attended a H&H barrier inspection on 4/22/2022 which also required a reinspection. The concrete floor slab has since been poured in this area (Photos 5 through 7). Brownfields Inspection Report: Crayton Printing (RN), 24025-20-060 05/18/2022 8:51 AM Page 5 of 7 Photo 2: Vapor Block “Pour-N-Seal” used to seal around utility conduits. Photo 3: Portion of barrier that had been completed and inspected by H&H prior to the barrier inspection that was attended today. Brownfields Inspection Report: Crayton Printing (RN), 24025-20-060 05/18/2022 8:51 AM Page 6 of 7 Photo 4: Close-up of barrier sealing around concrete column, and pieces of concrete being used as rebar "chairs". Orange PVC VIMS riser visible in upper left of photo. Photo 5: Three-inch dia. PVC riser (painted orange) stubbed up in finished floor slab. Brownfields Inspection Report: Crayton Printing (RN), 24025-20-060 05/18/2022 8:51 AM Page 7 of 7 Photo 6: Another photo of a stubbed-up VIMS riser pipe. Photo 7: Two-inch dia. PVC monitoring point within floor slab (also painted orange).