HomeMy WebLinkAbout03001_Terrell Machine_SIR_2022.02.23
DWM Brownfields Inspection Report
Submitted By: jkslaughter_ncdenr
Submitted Time: 03/01/2022 9:40 AM
I. Inspection Information
Date & Time: 02/23/2022 1:23 PM Inspection Type: Meeting
Brownfields Staff:
Kevin Slaughter
Other Personnel:
Al Quarles – ATC, and Alex Moose - Hendrix
Construction
Location:
Lat: 35.1991906, Long: -80.8693168,
Brownfields Inspection Report: Terrell Machine, 03001-99-060
02/23/2022 1:23 PM
Page 2 of 7
II. Project Information
Number: 03001-99-060 Name: Terrell Machine
Address: 3030 South Blvd
City: Charlotte
County: Mecklenburg
III. Environmental
Current Use of Property: Residential
Structures on Property: Existing Structures Violation: No
Vapor Mitigation Systems: Observed Vapor Mitigation Violation: No
Use of Surface Water or Groundwater: Not Observed Water Use Violation: No
Exposed Soils: Observed Exposed Soils Violation: No
Summary: Observed smoke test and coupon thickness measurements on Building 7
during Site Inspection prior to concrete slab pour scheduled for next week.
Summary: N/A
Summary: Existing and new construction townhomes.
Summary: Exposed soil around building footprint consistent with EMP and construction
taking place.
Brownfields Inspection Report: Terrell Machine, 03001-99-060
02/23/2022 1:23 PM
Page 3 of 7
Use of Basements: Not Observed Basement Violation: No
Storage of Chemicals: Not Observed Chemical Violation: No
Groundwater Monitoring Wells: Not Observed Monitoring Well Violation: No
Current Exposure to Public/Public Risk:
Summary: N/A
Summary: N/A
Condition:
Summary: N/A
No exposure to the public observed at the time of the Site Inspection. Construction area
enclosed by temporary construction fencing with barrier screen attached (Photo 1).
Brownfields Inspection Report: Terrell Machine, 03001-99-060
02/23/2022 1:23 PM
Page 4 of 7
IV. Inspector Comments
V. PHOTOGRAPHS
Photo 1: Clearing pooled water off barrier prior to testing.
Site inspection performed to inspect smoke test to be performed on Building 7 VIMS
barrier. Low points in barrier holding water which had to be removed prior to smoke test
(Photo 1). Smoke and pressurized air were then blown below barrier to check for leaks.
No smoke was observed during the test except for where smoke exited the future VIMS
riser when uncapped (Photos 2 and 3). Barrier repaired following coupon testing (Photos
4 and 5), and Geo-Seal Bond layer installed prior to Cetco personnel completing Building
7 slab prior to concrete pour (Photos 6 and 7).
Brownfields Inspection Report: Terrell Machine, 03001-99-060
02/23/2022 1:23 PM
Page 5 of 7
Photo 2: Smoke test performed with fog machine and leaf blower.
Photo 3: Fog visible exiting VIMS riser. Barrier inflated in photo.
Brownfields Inspection Report: Terrell Machine, 03001-99-060
02/23/2022 1:23 PM
Page 6 of 7
Photo 4: Coupon test area repair in progress.
Photo 5: Photo taken during coupon thickness measurement.
Brownfields Inspection Report: Terrell Machine, 03001-99-060
02/23/2022 1:23 PM
Page 7 of 7
Photo 6: Following smoke test, coupon sample repair geotextile Geo-Seal Bond layer installed.
Photo 7: Completion of Geo-Seal Bond layer installation.