I. Inspection Information
Date & Time: 06/24/2021 7:20 AM Inspection Type: Meeting
Brownfields Staff:
Kevin Slaughter
Other Personnel:
Andrew Besu, Matt Vawder H&H. David
Nichols, & Hugo Avila Liles Construction
Location:
Lat: 35.24144, Long: -80.81507,
Brownfields Inspection Report: North Davidson II, 24003-20-060
06/24/2021 7:20 AM
Page 2 of 7
II. Project Information
Number: 24003-20-060 Name: North Davidson II
Address: 2315 N. Davidson
St.; 421 E. 26th St.
City: Charlotte
County: Mecklenburg
III. Environmental
Current Use of Property: Commercial/Retail
Structures on Property: Existing Structures Violation: No
Vapor Mitigation Systems: Observed Vapor Mitigation Violation: No
Use of Surface Water or Groundwater: Not Observed Water Use Violation: No
Exposed Soils: Observed Exposed Soils Violation: No
Summary: VIMS risers and Stego Wrap visible where utility cut-outs were made. On the
east side of the warehouse, a VIMS suction line is visible below where kitchen will be
constructed.
Summary: N/A
Summary: This inspection covers the structure located at 421 E. 26th Street.
The property consists of a metal truss constructed warehouse with ribbed metal
sheathing. The building is undergoing renovation and will be utilized as a restaurant.
Summary: N/A
Brownfields Inspection Report: North Davidson II, 24003-20-060
06/24/2021 7:20 AM
Page 3 of 7
Use of Basements: Not Observed Basement Violation: No
Storage of Chemicals: Not Observed Chemical Violation: No
Groundwater Monitoring Wells: Not Observed Monitoring Well Violation: No
Current Exposure to Public/Public Risk:
Summary: N/A
Summary: N/A
Condition:
Summary: N/A
Site perimeter fenced with chain-link temporary construction fencing. No risk of public
exposure at the time of the Site Inspection.
Brownfields Inspection Report: North Davidson II, 24003-20-060
06/24/2021 7:20 AM
Page 4 of 7
IV. Inspector Comments
V. PHOTOGRAPHS
Photo 1: Building exterior facing north.
Site Inspection made to check progress of VIMS Installation.
Requested hardcopy of EMP be posted in construction trailer as a hardcopy was not
available when the Site Inspection was performed. One sub-slab monitoring point near
center of building was not installed and will have to be installed following the saw cutting
of a 2'x2' square in the concrete slab.
This is one of the better appearing roll-out type barrier installations this inspector has
visited. This is a result of an overhead roof preventing the barrier from being rained on,
and with much of concrete slab being present, enabling site workers to step over, or go
around areas where Stegowrap was installed.
Brownfields Inspection Report: North Davidson II, 24003-20-060
06/24/2021 7:20 AM
Page 5 of 7
Photo 2: H&H personnel inspecting barrier installation.
Photo 3: Stego barrier installed with double sided tape around perimeter. Edges of concrete
were ground smooth following saw cutting.
Brownfields Inspection Report: North Davidson II, 24003-20-060
06/24/2021 7:20 AM
Page 6 of 7
Photo 4: Future VIMS riser piping and floor drain.
Photo 5: View from northern end of former warehouse looking south.
Brownfields Inspection Report: North Davidson II, 24003-20-060
06/24/2021 7:20 AM
Page 7 of 7
Photo 6: View looking north at soil pile and future kitchen area.
Photo 7: Gravel and slotted piping installed within future kitchen area.