HomeMy WebLinkAbout22030 Durafiber Eastern Fence EMP 20211027
Environmental Management Plan
Eastern Fence Expansion Project
Durafiber Brownfields Site
Salisbury, North Carolina
Brownfields Project No. 24030-18-080
H&H Job No. OAN-001
October 26, 2021
#C-1269 Engineering
#C-245 Geology
Environmental Management Plan
Eastern Fence Expansion
Durafiber Brownfields Site
Salisbury, North Carolina
Brownfields Project No. 24030-18-080
H&H Job No. OAN-001
Table of Contents
Completed EMP Template Form
List of Figures
Figure 1 NCBP Diagram for Temporary Containment of Impacted or Potentially
Impacted Soil
Figure 2 Site Map
Figure 3 P Building Area Detail
Figure 4 P Building Soil Disturbance Area Detail
List of Appendices
Appendix A Construction Drawings
Appendix B Draft Brownfields Plat and Contaminant Tables
Appendix C Soil Vapor Sample Location Map and Data Summary
Appendix D Liquid Stabilizer SDS
1
EMP Version 2, January 2021
NORTH CAROLINA BROWNFIELDS PROGRAM
ENVIRONMENTAL MANAGEMENT PLAN
This form is to be used to prepare an Environmental Management Plan (EMP) for projects in
the North Carolina Brownfields Program at the direction of a Brownfields project manager.
The EMP is a typical requirement of a Brownfields Agreement (BFA). Its purpose is to clarify
actions to be taken during the demolition and construction at Brownfields properties in an
effort to avoid delays in the event of the discovery of new contamination sources or other
environmental conditions. The EMP provides a means to document redevelopment plans and
environmental data for each applicable environmental medium to inform regulatory-compliant
decision-making at the site. As much detail as possible should be included in the EMP,
including contingency planning for unknowns. Consult your project manager if you have
questions.
Prospective Developers and/or their consultants must complete and submit this form and all
pertinent attachments, see checklist below, to their Brownfields project manager prior to any
earthmoving or other development-related activities that have the potential to disturb soil at
the Brownfields Property, including demolition. For the resultant EMP to be valid for use, it
must be completed, reviewed by the program, signed by all parties working on the project,
and approved by the Brownfields project manager. Failure to comply with the requirements of
the EMP could jeopardize project eligibility, or in the event of a completed agreement, be
cause for a reopener.
The EMP is valid only for the scope of work described herein and must be updated to be
applicable for new phases of redevelopment or after significant changes in applicable
regulatory guidance.
Voluntary Metrics Tab
The NC Brownfields Program updates estimated capital investment (from the Brownfields
Property Application) and estimated jobs created (from the Brownfields Agreement) whenever
possible. As a voluntary measure, you may opt to complete the below information for capital
investment and jobs created as estimated by your final redevelopment plans for the Brownfields
Property:
1. Estimated capital investment in redevelopment project: Click or tap here to enter text.
2. Estimated jobs created:
a. Construction Jobs:
b. Full Time Post-Redevelopment Jobs: Click or tap here to enter text.
2
EMP Version 2, January 2021
Table of Contents
NORTH CAROLINA BROWNFIELDS PROGRAM ENVIRONMENTAL MANAGEMENT PLAN ........................... 1
GENERAL INFORMATION ........................................................................................................................ 4
COMMUNICATIONS ................................................................................................................................ 4
NOTIFICATIONS TO THE BROWNFIELDS PROGRAM ............................................................................... 5
REDEVELOPMENT PLANS ........................................................................................................................ 6
CONTAMINATED MEDIA ......................................................................................................................... 8
PART 1. Soil ......................................................................................................................................... 8
PART 2. GROUNDWATER .................................................................................................................. 17
PART 3. SURFACE WATER .................................................................................................................. 19
PART 4. SEDIMENT ............................................................................................................................ 19
PART 5. SOIL VAPOR ......................................................................................................................... 19
PART 6. SUB-SLAB SOIL VAPOR ........................................................................................................ 20
PART 7. INDOOR AIR ......................................................................................................................... 21
VAPOR INTRUSION MITIGATION SYSTEM ............................................................................................. 22
CONTINGENCY PLAN – encountering unknown tanks, drums, or other waste materials ..................... 22
POST-REDEVELOPMENT REPORTING..................................................................................................... 24
APPROVAL SIGNATURES ....................................................................................................................... 26
3
EMP Version 2, January 2021
So that the EMP provides value in protecting brownfields eligibility and public health, the
preparer shall ensure that the following steps have been completed prior to submitting the
EMP for review. Any EMP prepared without completing these steps is premature.
܈܈ Site sampling and assessment that meets Brownfields’ objectives is complete and has
been reviewed and approved by the Brownfields Project Manager.
܈ Brownfields objectives at the date of the signing of this EMP are to begin construction
activities in accordance with EMP requirements. Specific redevelopment plans, even if
conceptual, have been developed for the project, submitted and reviewed by the
Brownfields Project Manager.
Please submit, along with the completed EMP form, the following attachments, as relevant
and applicable to the proposed redevelopment:
܈ A set of redevelopment plans, including architectural/engineering plans, if available; if
not conceptual plans may suffice if updated when detailed plans are drafted.
܆ A figure overlaying redevelopment plans on a map of the extent of contamination for
each media.
܆ Site grading plans that include a cut and fill analysis.
܆ A figure showing the proposed location and depth of impacted soil that would remain
on site after construction grading.
܆ Any necessary permits for redevelopment (i.e. demolition, etc.).
܈ A detailed construction schedule that includes timing and phases of construction.
܈ Tabulated data summaries for each impacted media (i.e. soil, groundwater, soil gas,
etc.) applicable to the proposed redevelopment.
܈ Figures with the sampling locations and contamination extents for each impacted media
applicable to the proposed redevelopment.
܆ A full final grade sampling and analysis plan, if the redevelopment plan is final.
܆ If known, information about each proposed potential borrow soil source, such as aerial
photos, historic site maps, historic Sanborn maps, a site history, necessary for
brownfields approval.
܆ Information and, analytical data if required, for quarries, or other borrow sources,
4
EMP Version 2, January 2021
detailing the type of material proposed for importation to the Brownfields Property.
܆܆ A work plan for the sampling and analysis of soil to be brought onto the Brownfields
Property. Refer to Issue Resolution 15 in Brownfields Program Guidelines.
܆ A map of the Brownfields Property showing the location of soils proposed for export
and sampling data from those areas.
܆ If a Vapor Mitigation System is required by the Brownfields Program, the Vapor
Intrusion Mitigation System (VIMS) plan will be signed and sealed by a NC Professional
Engineer. The VIMS Plan may also be submitted under separate cover.
GENERAL INFORMATION
Date: 10/26/2021 Revision Date (if applicable): Click or tap to enter a date.
Brownfields Assigned Project Name: Durafiber
Brownfields Project Number: 24030-18-080
Brownfields Property Address: 7401 Statesville Blvd, Salisbury, Rowan County
Brownfields Property Area (acres): The Brownfields property consists of approximately 500 acres.
The area which is the subject of this EMP is located near the P Building (formerly known as the
Training Building) in the southeastern portion of the former Durafiber plant. A Site map showing the
location of the P Building is provided as Figure 2.
Is Brownfields Property Subject to RCRA Permit?.......................܆ Yes ܈ No
If yes enter Permit No.: Site is subject to RCRA Administrative Order but not a RCRA Permit.
Is Brownfields Property Subject to a Solid Waste Permit….……..܆ Yes ܈ No
If yes, enter Permit No.: Click or tap here to enter text.
COMMUNICATIONS
A copy of this EMP shall be distributed to all the parties below as well as any contractors or site workers
that may be exposed to site vapors, soil, groundwater, and/or surface water. Additionally, a copy of the
EMP shall be maintained at the Brownfields Property during redevelopment activities. NOTE, THE EMP
DOES NOT TAKE THE PLACE OF A SITE-SPECIFIC HEALTH AND SAFETY PLAN.
Prospective Developer: Salisbury Investments I, LLC
Contact Person: Mr. Houston Roberts
Phone Numbers: Office: 704-364-9100 Mobile: 704-361-0129
Email: Houston@forsiteinc.com
5
EMP Version 2, January 2021
Prospective Developer
Contact Person: Houston Roberts
Phone Numbers: Office: Click or tap here to enter text. Mobile: 704-361-0129
Email: houston@forsiteinc.com
Contractor for Construction: OA Newton
Contact Person: Dean Hetrick
Phone Numbers: Office: Click or tap here to enter text. Mobile: 302-337-3720
Email: dean.hetrick@oanewton.com
Environmental Consultant: Hart & Hickman, PC
Contact Person: Mr. Steve Hart
Phone Numbers: Office: 704-887-4610 Mobile: 704-576-0145
Email: shart@harthickman.com
Brownfields Program Project Manager: Mr. Bill Schmithorst
Phone Numbers: Office: 919-707-8159 Mobile: 919-441-3606
Email: william.schmithorst@ncdenr.gov
Other DEQ Program Contacts (if applicable, i.e., UST Section, Inactive Hazardous Site Branch,
Hazardous Waste, Solid Waste):
Rob McDaniel
DEQ Hazardous Waste Section
Robert.mcdaniel@ncdenr.gov
919-707-8215
NOTIFICATIONS TO THE BROWNFIELDS PROGRAM
Written advance Notification Times to Brownfields Project Manager: Check each box to accept
minimum advance notice periods (in calendar days) for each type of onsite task:
On-site assessment or remedial activities:……………………………………….…… 10 days Prior ܆܆
Construction or grading start:……………………………………….………………………. 10 days Prior ܈
Discovery of stained soil, odors, USTs, buried drums or waste, landfill, or other signs of previously
unknown contamination: ……………………………….……………………………………. Within 48 hours ܈
Implementation of emergency actions (e.g. dewatering, flood or soil erosion control measures in
area of contamination, ventilation of work zones):…………….……….……… Within 48 hours ܈
Installation of mitigation systems:………………………….………………….……….. 10 days Prior ܆
Other notifications as required by local, state or federal agencies to implement redevelopment
activities: (as applicable): ……………………….…………………………………………..… Within 30 days ܆
6
EMP Version 2, January 2021
REDEVELOPMENT PLANS
1) Type of Redevelopment (check all that apply):
܆Residential ܆Recreational ܆Institutional ܆Commercial ܆Office ܆Retail ܈Industrial
܆Other specify:
2) Check the following activities that will be conducted prior to commencing earth-moving activities
at the site:
܆ Review of historic maps (Sanborn Maps, facility maps)
܈ Conducting geophysical surveys to evaluate the location of suspect UST, fuel lines, utility
lines, etc.
܈ Interviews with employees/former employees/facility managers/neighbors
3) Summary of Redevelopment Plans (MANDATORY: attach detailed plans or conceptual plans, if
detailed plans are not available. EMP review without such information would be premature):
Provide brief summary of redevelopment plans, including demolition, removal of building
slabs/pavement, grading plans and planned construction of new structures:
The redevelopment activities covered under this EMP include shallow soil excavations within and
north of the P Building (formerly known as the Training Building) for the installation of concrete
foundations for additional equipment to be used by the current tenant Eastern Fence. Eastern
Fence manufactures PVC fencing at the P Building using PVC powder and injection molding
equipment. The construction activities include installation of concrete foundations for the
following:
x Two silos north of the P Building. These silos will contain a mixture of PVC powder and
calcium carbonate.
x Three silos northeast of the P Building. The westernmost of these silos will contain
calcium carbonate, and the other two will contain PVC powder.
x Liquid stabilizer tank containment north of the P Building. A Safety Data Sheet for the
liquid stabilizer is provided in Appendix D. The liquid stabilizer tank will be in secondary
containment. The containment will have a central drain that will remain closed until
accumulated rainwater is inspected and verified to be non-impacted before draining.
x Mixer/cooler within the P Building. This is a high intensity mixer and a vertical drum
cooler with a water jacket.
x Approximate 100 ft long trench to a new power pole will also be performed to install a
new underground power line to the P Building.
The approximate locations and sizes and depths of the excavations are indicated in Figures 3 and
4, respectively. Construction drawings are provided in Appendix A. Excavation depths are not
expected to exceed 2.5 ft. In addition, two blower pads will be installed northeast and east of
7
EMP Version 2, January 2021
the P Building; however, they will be installed on existing ground surface and will involve minimal
soil disturbance. The locations of the blower pads are indicated in Figure 4.
4) Do plans include demolition of structure(s)?:
܆܆Yes ܈No܆Unknown
܆If yes, please check here to confirm that demolition will be conducted in accordance with
applicable legal requirements, including without limitation those related to lead and asbestos
abatement that are administered by the Health Hazards Control Unit within the Division of Public
Health of the North Carolina Department of Health and Human Services. If available, please
provide a copy of your demolition permit.
5) Are sediment and erosion control measures required by federal, state, or local regulations?
܆Yes ܈No ܆Unknown
܆ If yes, please check here to confirm that demolition will be conducted in accordance with
applicable legal requirements. If soil disturbance is necessary to install sediment and erosion
control measures, they may not begin until this EMP is approved.
6) Which category of risk-based screening level is used or is anticipated to be specified in the
Brownfields Agreement? Note: If children frequent the property, residential screening levels shall
be cited in the Brownfields Agreement for comparison purposes.
܆Residential ܈Non-Residential or Industrial/Commercial
7) Schedule for Redevelopment (attach construction schedule):
a) Construction start date: 11/1/2021
b) Anticipated duration (specify activities during each phase):
It is anticipated that the activities will be conducted over a one to two months period.
c) Additional phases planned? ܆ Yes ܈ No
If yes, specify the start date and/or activities if known:
Start Date: Click or tap to enter a date.
Planned Activity:
There are no plans for additional phases of redevelopment.
Start Date: Click or tap to enter a date.
Planned Activity:
Click or tap here to enter text.
Start Date: Click or tap to enter a date.
Planned Activity:
Click or tap here to enter text.
d) Provide the planned date of occupancy for new buildings: Not Applicable
8
EMP Version 2, January 2021
CONTAMINATED MEDIA
Please fill out the sections below, using detailed site plans, if available, or estimate using known areas
of contaminated soil and a conceptual redevelopment plan. Provide a figure overlaying new
construction onto figure showing contaminated soil and groundwater locations.
1) Contaminated Media on the Brownfields Property
Part 1. Soil:……………………………………….……………. ܈܈ Yes ܆ No ܆ Suspected ܆ Unknown
Part 2. Groundwater:.……………………….……..……. ܈ Yes ܆ No ܆ Suspected ܆ Unknown
Part 3. Surface Water:.……………...……..…………… ܈ Yes ܆ No ܆ Suspected ܆ Unknown
Part 4. Sediment:.……………...……..…………………… ܈ Yes ܆ No ܆ Suspected ܆ Unknown
Part 5. Soil Vapor:…..…………...……..…………………. ܆ Yes ܆ No ܆ Suspected ܈ Unknown
Part 6. Sub-Slab Soil Vapor:……...……..…………….. ܆ Yes ܈ No ܆ Suspected ܆ Unknown
Part 7. Indoor Air:...……..…………………………………. ܆ Yes ܈ No ܆ Suspected ܆ Unknown
2) For the Area of Proposed Redevelopment on the Brownfields Property, attach tabulated data
summaries for each impacted media and figure(s) with sample locations.
PART 1. Soil
1) Known or suspected contaminants in soil (list general groups of contaminants):
There are no known or suspected soil impacts in the area of the proposed soil excavations. The P
Building was previously used for training, and manufacturing operations were not conducted in
the building. The locations of soil samples at the site above DEQ screening levels and a summary
of soil analytical data are provided in the draft Brownfields plat and Contaminant Tables
provided in Appendix B. As indicated in the figure, there are no soil samples with compound
concentrations above health-based screening levels in the area of the proposed excavations.
The primary areas where contamination has been detected at the Site are the former DowTherm
heater areas located east of the main manufacturing building and two disposal areas located in
the eastern portion of the site (see Figure 2). These areas are not located in the vicinity of the P
Building.
2) Depth of known or suspected contaminants (feet):
There are no known soil impacts in the area of the proposed excavations.
3) Area of soil disturbed by redevelopment (square feet):
~2,100 sq ft
4) Depths of soil to be excavated (feet):
9
EMP Version 2, January 2021
Up to approximately 2.5 ft deep.
5) Estimated volume of soil (cubic yards) to be excavated (attach grading plan):
~200
6) Estimated volume of excavated soil (cubic yards) anticipated to be impacted by contaminants:
None
7) Estimated volume of contaminated soil expected to be disposed of offsite, if applicable:
None
Part 1.A. MANAGING ONSITE SOIL
If soil is anticipated to be excavated from the Brownfield Property, relocated on the Brownfields
Property, or otherwise disturbed during site grading or other redevelopment activities, please
provide a grading plan that clearly illustrates areas of cut and fill (approximate areas & volumes are
acceptable, if only preliminary data available).
1) HAZARDOUS WASTE DETERMINATION:
a) Does the soil contain a LISTED WASTE as defined in the North Carolina Hazardous
Waste Section under 40 CFR Part 261.31-261.35?....................................... ܆܆Yes ܈No
܆ If yes, explain why below, including the level of knowledge regarding processes
generating the waste (include pertinent analytical results as needed).
Click or tap here to enter text.
܆ If yes, do the soils exceed the “Contained-Out” levels in Attachment 1 of the
North Carolina Contained-In Policy?................................................. ܆ Yes ܆ No
b) NOTE: IF SOIL MEETS THE DEFINITION OF A LISTED HAZARDOUS WASTE AND EXCEEDS
THE CONTAINED-OUT LEVELS IN ATTACHMENT 1 TO THE NORTH CAROLINA
CONTAINED-IN POLICY THE SOIL MAY NOT BE RE-USED ON SITE AND MUST BE
DISPOSED OF IN ACCORDANCE WITH DEQ HAZARDOUS WASTE SECTION RULES AND
REGULATIONS.
c) Does the soil contain a CHARACTERISTIC WASTE?.................................... ܆ Yes ܈ No
܆ If yes, mark reason(s) why below (and include pertinent analytical results).
܆ Ignitability Click or tap here to enter text.
܆ Corrosivity Click or tap here to enter text.
܆ Reactivity Click or tap here to enter text.
܆ Toxicity Click or tap here to enter text.
܆ TCLP results Click or tap here to enter text.
10
EMP Version 2, January 2021
܆܆ Rule of 20 results (20 times total analytical results for an individual
hazardous constituent on TCLP list cannot, by test method, exceed regulatory
TCLP standard)
Click or tap here to enter text.
܈ If no, explain rationale:
No soil impacts are expected in the area of the excavations. If potentially
impacted soil is identified during excavation based upon field screening, the soil
will be sampled and managed as described below under Part 1.A. Section 4
below.
d) NOTE: IF SOIL MEETS THE DEFINITION OF A CHARACTERISTIC HAZARDOUS WASTE, THE
SOIL MAY NOT BE RE-USED ON SITE AND MUST BE DISPOSED OF IN ACCORDANCE
WITH DEQ HAZARDOUS WASTE SECTION RULES AND REGULATIONS.
2) Screening criteria by which soil disposition decisions will be made (e.g., left in place, capped in
place with low permeability barrier, removed to onsite location and capped, removed offsite):
܆ Preliminary Health-Based Residential SRGs
܈ Preliminary Health-Based Industrial/Commercial SRGs
܈ Division of Waste Management Risk Calculator (For Brownfields Properties Only)
܆ Site-specific risk-based cleanup level. Please provide details of methods used for
determination/explanation.
Click or tap here to enter text.
Additional comments:
Click or tap here to enter text.
3) If known impacted soil is proposed to be reused within the Brownfields Property Boundary,
please check the measures that will be utilized to ensure safe placement and documentation of
same. Please attach a proposed location diagram/site map.
܆ Provide documentation of analytical report(s) to Brownfields Project Manager
܆ Provide documentation of final location, thickness and depth of relocated soil on site map
to Brownfields Project Manager once known
܆ Geotextile to mark depth of fill material.
Provide description of material:
Click or tap here to enter text.
܆ Manage soil under impervious cap ܈ or clean fill ܈
܆ Describe cap or fill:
11
EMP Version 2, January 2021
܆܆ Confer with NC BF Project Manager if Brownfield Plat must be revised (or re-recorded if
actions are Post-Recordation).
܆ GPS the location and provide site map with final location.
܆ Other. Please provide a description of the measure:
4) Please describe the following action(s) to be taken during and following excavation and
management of site soils:
Management of fugitive dust from site
܈ Yes, describe the method will include:
Contaminated soil is not expected to be encountered or disturbed as part of the
excavations. However, the construction contractor will take into account conditions such as
wind speed, wind direction, and moisture content of soil during soil disturbance and
stockpiling activities to minimize dust generation. Particular attention will be paid by
contractors to implement dust control measures as needed based on Site and atmospheric
conditions (i.e., by controlled water application, hydro-seeding, and/or mulch, stone, or
plastic cover).
܆ No, explain rationale:
Click or tap here to enter text.
Field Screening of site soil
܈ Yes, describe the field screening method, frequency of field screening, person conducting
field screening:
During soil disturbance at the Site, the contractor will observe soils for evidence of
potential significantly impacted soil. Evidence of potential impacted soil includes a distinct
unnatural color, strong odor, or filled or previously disposed materials of concerns (i.e.,
chemicals, tanks, drums, etc.). Should the above be noted during Site work, the contractor
will contact the project environmental consultant to observe the suspect condition. If the
project environmental engineer confirms that the material may be impacted, then the
procedures below will be implemented. In addition, the environmental consultant will
contact the DEQ Brownfields project manager within 48-hours to advise that person of the
condition.
܆ No, explain rationale:
Click or tap here to enter text.
Soil Sample Collection
܆ Yes, describe the sampling method (e.g., in-situ grab, composite, stockpile, etc.):
Click or tap here to enter text.
܈ No, explain rationale:
Click or tap here to enter text.
12
EMP Version 2, January 2021
Collection of additional soil samples is not anticipated based on results of previous Site
assessment activities and previous use of the P Building for training. If previously
unknown significant soil impact is encountered during soil disturbance, excavation will
proceed only as far as needed to allow construction to continue and/or only as far as
needed to allow alternate corrective measures described below.
Suspect impacted soil excavated during will be stockpiled and covered in a secure area to
allow construction to progress. Suspect impacted soil will be underlain by and covered
with minimum 10-mil plastic sheeting. At least one representative soil sample (no less
than 3 aliquot soil samples) at a sample ratio of 1 soil sample per every approximately
200 cubic yards of soil will be collected for the analyses selected below (i.e., total VOCs,
SVOCs, and RCRA metals plus hexavalent chromium). If the soil sample laboratory
analytical results indicate that the soil could potentially exceed toxicity characteristic
hazardous waste criteria, then the soil will also be analyzed by TCLP for those
compounds that could exceed the toxicity characteristic hazardous waste criteria.
Impacted soil will be managed in the manner described below based upon the laboratory
analyses:
i. If no organic compounds are detected in a sample (other than which are
attributable to sampling or laboratory artifacts) and metals are below the Protection of
Groundwater or Residential PSRG (whichever is lower for the detected compounds) and
are consistent with Site-specific background levels with acceptable cumulative risk
calculator results, then the soil will be deemed suitable for use as on-Site fill or as off-Site
fill. The proposed location(s) for off-Site placement of soil (other than a permitted
facility) along with the receiving facility’s written approval for acceptance of the soil will
be provided to DEQ for approval prior to taking the soil off-Site.
ii. If detectable levels of compounds are found which do not exceed the DEQ IHSB
Industrial PSRGs (other than which are attributable to sampling or laboratory artifacts or
which are consistent with Site-specific background levels for metals), the TCLP
concentrations are below hazardous waste criteria, and cumulative risk calculator results
are acceptable, then the soil may be used on-Site as fill without conditions.
iii. If detectable levels of compounds are found which exceed the DEQ IHSB
Industrial PSRGs (other than which are attributable to sampling or laboratory artifacts or
which are consistent with background levels for metals) and the TCLP concentrations are
below hazardous waste criteria, then the soil, with DEQ written approval, may be used
on-Site as fill below an impervious surface, or at least 2 ft of documented compacted
clean soil. If the impacted soil with concentrations above Industrial PSRGs is moved to
an on-Site location, its location and depth will be documented using GPS, and its location
will be provided to DEQ
iv. Impacted soil may be transported to a Brownfields approved permitted facility
such as a landfill provided that the soil is accepted at the disposal facility. If soil is
transported to a permitted facility, the permitted facility’s written approval or
acceptance to dispose of soil from the Site will be provided to the DEQ Brownfields
project manager.
v. In the unlikely event that the sample data indicates concentrations above TCLP
hazardous waste criteria, then the soil must be transported off-Site to a permitted
disposal facility that can accept or treat hazardous waste.
13
EMP Version 2, January 2021
*Please note that should export soil be transported off-Site to a permitted facility or to a
another DEQ Brownfields pre-approved receiving facility, soil will be direct loaded onto
trucks for transport off-Site.
If soil samples are collected for analysis, please check the applicable chemical analytes:
܈ Volatile organic compounds (VOCs) by EPA Method 8260
܈ Semi-volatile organic compounds (SVOCs) by EPA Method 8270
܈ Metals RCRA List (8) (arsenic, barium, cadmium, chromium, mercury, lead, selenium
and silver): Specify Analytical Method Number(s):
EPA Methods 6020/7471
܆ Pesticides: Specify Analytical Method Number(s):
Click or tap here to enter text.
܆ PCBs: Specify Analytical Method Number(s):
Click or tap here to enter text.
܈ Other Constituents & Respective Analytical Method(s) (i.e. Hexavalent Chromium,
Herbicides, etc.): Specify Analytical Method Number(s):
Hexavalent Chromium by EPA Method 7199
܈ Check to confirm that stockpiling of known or suspected impacted soils will be conducted
in accordance with Figure 1 of this EMP. Stockpile methodology should provide erosion
control, prohibiting contact between surface water/precipitation and contaminated soil,
and preventing contaminated runoff. Explain any variances or provide additional details as
needed:
܆ Final grade sampling of exposed native soil (i.e., soil that will not be under buildings or
permanent hardscape). Select chemical analyses for final grade samples with check boxes
below (Check all that apply):
܆ Volatile organic compounds (VOCs) by EPA Method 8260
܆ Semi-volatile organic compounds (SVOCs) by EPA Method 8270
܆ Metals RCRA List (8) (arsenic, barium, cadmium, chromium, mercury, lead,
selenium and silver): Specify Analytical Method Number(s):
Click or tap here to enter text.
܆ Pesticides: Specify Analytical Method Number(s):
Click or tap here to enter text.
܆ PCBs: Specify Analytical Method Number(s):
Click or tap here to enter text.
Click or tap here to enter text.
14
EMP Version 2, January 2021
܆܆ Other Constituents & Respective Analytical Method(s) (i.e. Hexavalent
Chromium, Herbicides, etc.):
Click or tap here to enter text.
Please provide a scope of work for final grade sampling, including a diagram of soil
sampling locations, number of samples to be collected, and brief sampling methodology.
Samples should be collected from 0-2 ft below ground surface, with the exception of VOCs
which should be taken from 1-2 ft below ground surface. Alternatively, indicate if a work
plan for final grade sampling may be submitted under separate cover.
܈ If final grade sampling was NOT selected, please explain rationale:
No final grade soil sampling is proposed because there are no known soil impacts in the
area of the excavations and there will be minimal disturbance of soil outside the
excavation areas. If significantly impacted soil is identified during the excavations and the
impacted soil removed from the excavations is found to contain compounds above
Industrial PSRGs, then the need for final grade soil sampling will be discussed with the
Brownfields Project Manager.
Part 1.B. IMPORTED FILL SOIL
NO SOIL MAY BE BROUGHT ONTO THE BROWNFIELDS PROPERTY WITHOUT PRIOR APPROVAL
FROM THE BROWNFIELDS PROGRAM. According to the Brownfields IR 15, “Documenting
imported soil (by sampling, analysis, and reporting in accordance with review and written
approval in advance by the Brownfields Program), will safeguard the liability protections provided
by the brownfields agreement and is in the best interest of the prospective developer/property
owner.”
Requirements for importing fill:
1) Will fill soil be imported to the site?................................................܆Yes ܈No ܆Unknown
2) If yes, what is the estimated volume of fill soil to be imported?
Click or tap here to enter text.
3) If yes, what is the anticipated depth that fill soil will be placed at the property? (If a range
of depths, please list the range.)
4) Provide the source of fill, including: location, site history, nearby environmental concerns,
etc. Attach aerial photos, maps, historic Sanborn maps and a borrow source site history:
15
EMP Version 2, January 2021
5) PRIOR TO ITS PLACEMENT AT THE BROWNFIELDS PROPERTY, provide a plan to analyze fill
soil to demonstrate that it meets acceptable standards applicable to the site and can be
approved for use at the Brownfields property.
In the unlikely event that import fill soil is needed, it will be taken from a location on-Site south
of the parking lot where no prior industrial activities have occurred. If off-Site fill soil is needed
for some reason, then the location where the fill soil will be obtained while be submitted to the
DEQ Project Manager for prior approval. If the import fill soil is not from a DEQ Brownfields pre-
approved soil import facility (i.e., pre-characterized quarry), then a plan for characterization of
the soil will also be submitted for DEQ approval.
6) Please check the applicable chemical analytes for fill soil samples. (Check all that apply):
܈܈ Volatile organic compounds (VOCs) by EPA Method 8260
܈ Semi-volatile organic compounds (SVOCs) by EPA Method 8270
܈ Metals RCRA List (8) (arsenic, barium, cadmium, chromium, mercury, lead,
selenium and silver): Specify Analytical Method Number(s):
EPA Methods 6020/7471
܆ Pesticides: Specify Analytical Method Number(s):
Click or tap here to enter text.
܆ PCBs: Specify Analytical Method Number(s):
Click or tap here to enter text.
܈ Other Constituents & Respective Analytical Method(s) (i.e. Hexavalent
Chromium, Herbicides, etc.):
Hexavalent Chromium by EPA Method 7199
7) The scope of work for import fill sampling may be provided below or in a Work Plan
submitted separately for DEQ review and approval. Attach specific location maps for in-situ
borrow sites. If using a quarry, provide information on the type of material to be brought
onto the Brownfields Property.
See above.
Part 1.C. EXPORTED SOIL
NO SOIL MAY LEAVE THE BROWNFIELDS PROPERTY WITHOUT APPROVAL FROM THE
BROWNFIELDS PROGRAM. FAILURE TO OBTAIN APPROVAL MAY VIOLATE A BROWNFIELDS
AGREEMENT CAUSING A REOPENER OR JEOPARDIZING ELIGIBILITY IN THE PROGRAM,
ENDANGERING LIABILITY PROTECTIONS AND MAKING SAID ACTION POSSIBLY SUBJECT TO
ENFORCEMENT. JUSTIFICATIONS PROVIDED BELOW MUST BE APPROVED BY THE PROGRAM IN
WRITING PRIOR TO COMPLETING TRANSPORT ACTIVITIES. Please refer to Brownfields IR 15 for
16
EMP Version 2, January 2021
additional details.
1) If export from a Brownfields Property is anticipated, please provide details regarding the
proposed export actions. Volume of exported soil, depths, location from which soil will
be excavated on site, related sampling results, etc. Provide a site map with locations of
export and sampling results included.
No off-Site export of soil is anticipated based upon the large size of the Site where soil can be
placed (unless impacted soil is identified in the excavations and is disposed off-Site in accordance
with Part 1.A. Section 4.)
2) To what type of facility will the export Brownfields soil be sent?
܈܈ Subtitle D/Municipal Solid Waste Landfill (analytical program to be determined by
landfill)
܆ Permitted but Unlined Landfill (i.e. LCID, C&D, etc.) Analytical program to be
determined by the accepting Landfill;
܆ Landfarm or other treatment facility
܆ Use as fill at another suitable Brownfields Property – determination that a
site is suitable will require, at a minimum, that similar concentrations of the same or
similar contaminants already exist at both sites, use of impacted soil will not increase
the potential for risk to human health and the environment at the receiving Brownfields
property, and that a record of the acceptance of such soil from the property owner of
the receiving site is provided to Brownfields. Please provide additional details below.
܆ Use as Beneficial Fill off-site at a non-Brownfields Property - Please provide
documentation of approval from the property owner for receipt of fill material. This will
also require approval by the DEQ Solid Waste Section. Additional information is
provided in IR 15. Please provide additional details below.
3) Additional Details: (if transfer of soil to another property is requested above, please provide
details related to the proposed plans).
Part 1.D. MANAGEMENT OF UTILITY TRENCHES
܆ Install liner between native impacted soils and base of utility trench before filling with clean fill
(Preferred)
܈ Last out, first in principle for impacted soils (if soil can safely be reused onsite and is not a
hazardous waste), i.e., impacted soils are placed back at approximately the depths they
were removed from such that impacted soil is not placed at a greater depth than the original
depth from which it was excavated.
܆ Evaluate whether necessary to install barriers in conduits to prevent soil vapor transport,
and/or degradation of conduit materials due to direct impact with contaminants?
܆ If yes, provide specifications on barrier materials or provide the results of this evaluation in the
17
EMP Version 2, January 2021
Vapor Mitigation Plan. Note that if vapor mitigation is planned for site buildings, utility
corridors will need to be evaluated as part of mitigation designs:
Click or tap here to enter text.
܈܈ If no, include rationale here:
Results of previous sub-slab soil vapor assessment activities completed below the P Building (as
well as elsewhere at the Site) did not indicate the presence of compounds above DEQ Non-
Residential Soil Gas Screening Levels (SGSLs). Therefore, no soil vapor impacts are expected in
utility trenches or other excavations.
܆ Unknown, details to be provided in the Vapor Mitigation Plan for site buildings
Other comments regarding managing impacted soil in utility trenches:
The contractor and workers will observe soil for potential impacts during utility installation activities.
Evidence of potential significant impacted soil includes a distinct unnatural color, strong odor, or filled
or previously disposed materials of concerns (i.e., chemicals, tanks, drums, etc.). Should the above be
noted during utility work, the contractor will contact the project environmental consultant to observe
the suspect condition. If the project environmental consultant confirms that the material may be
impacted, then the procedures outlined in Part 1.A. Section 4 above will be implemented. In addition,
the environmental consultant will contact the DEQ Brownfields project manager within 48-hours to
advise that person of the condition.
Should impacted soil be discovered during utility trenching activities, appropriate safety screening will
be performed by the contractor to protect workers during utility installation activities. If safety
screening results indicate further action is warranted, the environmental consultant will be contacted
and the work zone will be evacuated until appropriate engineering controls (such as use of industrial
fans) are implemented. The environmental consultant will notify the DEQ project manager within 48
hours if engineering controls are warranted.
PART 2. GROUNDWATER
1) What is the depth to groundwater at the Brownfields Property?
The depth to groundwater in the area of the P Building is approximately 30 ft below ground
surface.
2) Is groundwater known to be contaminated by ܈onsite ܆offsite ܆both or ܆unknown
sources? Describe source(s):
The primary sources of groundwater impacts are the former DowTherm heaters located east of
the main Site building, the Glycol Recovery Unit Bottom (GRUB) landfill in the eastern portion of
the site, the Chromium Reduction Unit basins in the area of the current wastewater treatment
plant, and the wastewater polishing ponds. These areas are identified in Figure 2.
3) What is the direction of groundwater flow at the Brownfields Property?
18
EMP Version 2, January 2021
Groundwater flow is to the east toward Second Creek (see Figure 2).
4) Will groundwater likely be encountered during planned redevelopment activities?
܆܆Yes ܈No
If yes, describe these activities:
.
Regardless of the answer; in the event that contaminated groundwater is encountered
during redevelopment activities (even if no is checked above), list activities for contingent
management of groundwater (e.g., dewatering of groundwater from excavations or
foundations, containerizing, offsite disposal, discharge to sanitary sewer, NPDES permit, or
sampling procedures).
Appropriate worker safety measures will be undertaken in the highly unlikely event that
groundwater gathers in an open excavation within an area determined to be impacted during
construction activities. The accumulated water will be allowed to evaporate/infiltrate to the
extent time for dissipation does not disrupt the construction schedule. Should the time needed
for natural dissipation of accumulated water be deemed inadequate, an environmental
professional will be contacted and the water will be tested and disposed off-Site or discharged
to the on-site wastewater treatment plant.
5) Are monitoring wells currently present on the Brownfields Property?.................܈Yes ܆No
If yes, are any monitoring wells routinely monitored through DEQ or other
agencies?..................................................................................................................܈Yes ܆No
6) Please check methods to be utilized in the management of known and previously
unidentified wells.
܆ Abandonment of site monitoring wells in accordance with all applicable regulations. It
is the Brownfields Program’s intent to allow proper abandonment of well(s) as
specified in the Brownfields Agreement, except if required for active monitoring
through another section of DEQ or the EPA.
܆ Location of existing monitoring wells marked
܈ Existing monitoring wells protected from disturbance
܆ Newly identified monitoring wells will be marked and protected from further
disturbance until notification to DEQ Brownfields can be made and approval for
abandonment is given.
7) Please provide additional details as needed:
Please note, disturbance of existing site monitoring wells without approval by DEQ is not
permissible. If monitoring wells are damaged and/or destroyed, DEQ may require that the PD
be responsible for replacement of the well.
No monitoring wells are located in the area of the proposed excavations. The closest monitoring well
is located approximately 180 ft northwest of the closest excavation area (well DT-3SS; see plat in
Appendix B).
19
EMP Version 2, January 2021
PART 3. SURFACE WATER
1) Is surface water present at the property? ܈܈ Yes ܆ No ܆ Unknown
2) Attach a map showing the location of surface water at the Brownfields Property.
3) Is surface water at the property known to be contaminated? ܈ Yes ܆ No
4) Will workers or the public be in contact with surface water during planned redevelopment
activities? ܆ Yes ܈ No
5) In the event that contaminated surface water is encountered during redevelopment
activities, or clean surface water enters open excavations, list activities for management of
such events (e.g., flooding, contaminated surface water run-off, stormwater impacts):
If surface water run-off gathers in an open excavation within an area determined to contain
impacted soil, appropriate worker safety measures will be undertaken. The accumulated water
will be allowed to evaporate/infiltrate to the extent time for dissipation does not disrupt the
construction schedule. Should the time needed for natural dissipation of accumulated water be
deemed inadequate, the water will be tested and disposed off-Site or discharged to the on-Site
wastewater treatment plant. If surface water collects in an excavation with non-impacted soil,
the water will be discharged to the surface and allowed to evaporate or discharged to the on-Site
wastewater treatment plant.
PART 4. SEDIMENT
1) Are sediment sources present on the property? ܈ Yes ܆ No
2) If yes, is sediment at the property known to be contaminated: ܈ Yes ܆ No ܆ Unknown
3) Will workers or the public be in contact with sediment during planned redevelopment
activities? ܆ Yes ܈ No
4) Attach a map showing location of known contaminated sediment at the property.
5) In the event that contaminated sediment is encountered during redevelopment activities, list
activities for management of such events (stream bed disturbance):
Contaminated sediment is known to present in the wastewater polishing ponds. The closest pond
is located greater than 900 ft from the P Building.
PART 5. SOIL VAPOR
1) Do concentrations of volatile organic compounds at the Brownfields property exceed the
following vapor intrusion screening levels (current version) in the following media:
IHSB Residential Screening Levels:
20
EMP Version 2, January 2021
Soil Vapor:………..܆܆ Yes ܆ No ܈ Unknown
Groundwater:.….܆ Yes ܆ No܈ Unknown
IHSB Industrial/Commercial Screening Levels:
Soil Vapor:………..܆ Yes ܆ No܈ Unknown
Groundwater:…..܈ Yes ܆ No܆ Unknown
2) Attach a map showing the locations of soil vapor contaminants that exceed site
screening levels.
3) If applicable, at what depth(s) is soil vapor known to be contaminated?
4) Will workers encounter contaminated soil vapor during planned redevelopment activities?
܆ Yes ܈ No܆ Unknown
In the event that contaminated soil vapor is encountered during redevelopment activities
(trenches, manways, basements or other subsurface work,) list activities for management of
such contact:
If potential soil or vapor impacts are identified during excavation, appropriate vapor monitoring
will be performed by the contractor. If vapor monitoring results indicate potential vapor phase
contamination at levels of concern for worker protection, an environmental professional will be
contacted and the work zone will be evacuated until appropriate engineering controls (such as
use of industrial fans) are implemented.
PART 6. SUB-SLAB SOIL VAPOR
1) Do concentrations of volatile organic compounds at the Brownfields property exceed the
following vapor intrusion screening levels (current version) in sub-slab soil vapor:
IHSB Residential Screening Levels:
Soil Vapor:………..܆ Yes ܆ No ܈ Unknown
Groundwater:.….܆ Yes ܆ No܈ Unknown
IHSB Industrial/Commercial Screening Levels:
Soil Vapor:………..܆ Yes ܈ No܆ Unknown
Groundwater:…..܈ Yes ܆ No܆ Unknown
2) If data indicate that sub-slab soil vapor concentrations exceed screening levels, attach a map
showing the location of these exceedances.
3) At what depth(s) is sub-slab soil vapor known to be contaminated? ܈0-6 inches ܆Other, please
describe:
H&H collected sub-slab soil gas samples for laboratory analysis in June 2020 from below the P
Building as well as other Site buildings. The sample locations and a summary of the sub-slab soil
vapor analytical data is provided in Appendix C. As shown in Appendix C, no VOCs were detected
at concentrations above the DEQ Non-Residential SGSLs below the P Building or other Site
See below regarding sub-slab soil vapor.
21
EMP Version 2, January 2021
buildings where samples were collected.
.
4) Will workers encounter contaminated sub-slab soil vapor during planned redevelopment
activities? ܆܆ Yes ܈ No ܆ Unknown
܆ If no, include rationale here:
Based upon previous sub-slab soil vapor analytical data at the P Building, it is unlikely that
contaminated soil vapor will be encountered during the shallow soil excavations.
5) In the event that contaminated soil vapor is encountered during redevelopment activities, list
activities for management of such contact
As noted above, if potential soil or vapor impacts are identified during excavation, appropriate
vapor monitoring will be performed by the contractor. If vapor monitoring results indicate
potential vapor phase contamination at levels of concern for worker protection, an
environmental professional will be contacted and the work zone will be evacuated until
appropriate engineering controls (such as use of industrial fans) are implemented.
PART 7. INDOOR AIR
1) Are indoor air data available for the Brownfields Property? ܆ Yes ܈ No ܆ Unknown
2) Attach a map showing the location(s) where indoor air contaminants exceed site screening levels.
3) If the structures where indoor air has been documented to exceed risk-based screening levels will
not be demolished as part of redevelopment activities, will workers encounter contaminated
indoor air during planned redevelopment activities? ܆ Yes ܈ No ܆ Unknown
܈ If no, include rationale here:
Previous sampling of sub-slab soil vapor at the P Building did not indicate concentrations above
SGSLs. Therefore, it is unlikely that there are contaminants in indoor above risk-based screening
levels from soil or groundwater impacts at the Site.
4) In the event that contaminated indoor air is encountered during redevelopment activities, list
activities for management of such contact:
In the unlikely event there is evidence of potential indoor air issues (i.e., unusual odors) during the
interior soil excavation, appropriate indoor air monitoring will be performed by the contractor. If
indoor air monitoring results indicate potential indoor air contamination of concern for worker
protection, an environmental professional will be contacted and the work area will be evacuated until
appropriate engineering controls (such as use of industrial fans) are implemented and follow up
sampling is performed to confirm a safe working environment.
22
EMP Version 2, January 2021
VAPOR INTRUSION MITIGATION SYSTEM
Is a vapor intrusion mitigation system (VIMS) proposed for this Brownfields Property?
܆܆ Yes ܈ No ܆ Unknown
܈ If no or unknown, include rationale here as well as plans for pre-occupancy sampling, as
necessary:
Sub-slab sampling did not indicate that vapor mitigation is warranted at the Brownfields site for
existing buildings. No vapor mitigation is required for existing buildings per the draft Brownfields
agreement.
If yes, ܆ VIMS Plan Attached or ܆ VIMS Plan to be submitted separately
If submitted separately provide date:
VIMS Plan shall be signed and sealed by a NC Professional Engineer
If no, please provide a brief rationale as to why no vapor mitigation plan is warranted:
See above.
Note that approval of this EMP does not imply approval with any vapor intrusion mitigation land
use restrictions or requirements of the recorded or draft Brownfields Agreement and that
separate approval of mitigation measures will be required.
CONTINGENCY PLAN – encountering unknown tanks, drums, or other waste materials
In this section please provide actions that will be taken to identify or manage unknown
potential new sources of contamination. During redevelopment activities, it is not uncommon
that unknown tanks, drums, fuel lines, landfills, or other waste materials are encountered.
Notification to DEQ Brownfields Project Manager, UST Section, Fire Department, and/or other
officials, as necessary and appropriate, is required when new potential source(s) of
contamination are discovered. These Notification Requirements were outlined on Page 1 of this
EMP.
Should potentially impacted materials be identified that are inconsistent with known site
impacts, the DEQ Brownfields Project Manager will be notified and a sampling plan will be
prepared based on the EMP requirements and site-specific factors. Samples will generally be
collected to document the location of the potential impacts.
Check the following chemical analysis that are to be conducted on newly identified releases:
܈ Volatile organic compounds (VOCs) by EPA Method 8260
܈ Semi-volatile organic compounds (SVOCs) by EPA Method 8270
܈ Metals RCRA List (8) (arsenic, barium, cadmium, chromium, mercury, lead, selenium and
silver)
EPA Methods 6020/7471
23
EMP Version 2, January 2021
܆܆ Pesticides: Specify Analytical Method Number(s):
Click or tap here to enter text.
܆ PCBs: Specify Analytical Method Number(s):
Click or tap here to enter text.
܈ Other Constituents & Analytical Method(s) (i.e. Hexavalent Chromium, Herbicides, etc.)
Please note, if field observations indicate the need for additional analyses, they should
be conducted, even if not listed here.
Hexavalent Chromium by EPA Method 7199
Please provide details on the proposed methods of managing the following commonly
encountered issues during redevelopment of Brownfields Properties.
During construction activities, contractors may encounter unknown sub-surface environmental
conditions (i.e., tanks, drums, or waste materials) that if encountered, will require proper
management. In the event that such conditions are encountered during construction activities, the
actions noted below will be taken. Sampling data for potentially impacted soil and the disposition
of impacted soil will be provided to DEQ when the data becomes available.
Underground Storage Tanks:
In the event a UST or impacts associated with a UST release are discovered at the Site during the
activities, the UST and/or UST related impacts will be addressed through the Brownfields Program.
DEQ Brownfields will be notified within 48-hours of discovery of the UST.
If a UST is encountered, the UST will be removed, if possible and the UST will be transported off-Site
for disposal at a suitable facility. If the UST contains residual fluids, the fluids will be sampled for
VOCs, SVOCs, and RCRA metals (unless the fluids are a known product such as fuel oil), and
transported off-Site for disposal at a suitable facility based on the laboratory analytical results prior
to removing the UST from the ground. If a UST is encountered that cannot be removed or does not
require removal for geotechnical or construction purposes, it may be abandoned in-place with prior
DEQ approval and construction will proceed. Where appropriate, the bottom may be penetrated
after removal of residual fluids and before abandonment to prevent fluid accumulation. Impacted
soil in the vicinity of the UST will be managed in accordance with the Managing On-Site Soil section
outlined above in the EMP. DEQ UST Program protocol (or other protocol approved in advance by
the DEQ Brownfields Program) will be followed for UST abandonment procedures.
Sub-Grade Feature/Pit:
If a sub-grade feature or pit is encountered and does not require removal for geotechnical or
construction purposes, it will be filled with soil or suitable fill and construction will proceed. Where
appropriate, the bottom may be penetrated before back filling to prevent fluid accumulation. If the
pit has waste in it, the waste will be set aside in a secure area and will be sampled for waste
disposal purposes for TCLP VOCs, TCLP SVOCs, and TCLP metals and disposed off-Site at a permitted
facility or the waste will be managed in accordance with Part 1.A. Section 4 outlined above in the
24
EMP Version 2, January 2021
EMP, whichever is most applicable based on the type of waste present. If the pit must be removed
and the observed waste characteristics indicate the concrete may potentially be contaminated to a
significant degree, the concrete will be sampled and analyzed by methods specified by the disposal
facility.
Buried Waste Material – Note that if buried waste, non-native fill, or any obviously filled materials
is encountered, the DEQ Brownfields Program must be notified to determine if investigation of
landfill gases is required:
If excavation into buried wastes or significantly impacted soils occurs, the contractor is instructed to
stop work in that location and notify the environmental consultant. The environmental consultant
will review the materials and collect samples, if warranted. In this event, confirmation sampling will
be conducted at representative locations in the base and the sidewalls of the excavation after the
waste or significantly impacted soil is removed. The confirmation samples will be analyzed for
VOCs, SVOCs, and RCRA metals plus hexavalent chromium. Areas of suspected contaminated soil
that remain at the Site after excavation is complete above the DEQ IHSB Industrial PSRGs will be
managed pursuant to this plan.
Re-Use of Impacted Soils On-Site:
Please refer to description outlined in the Part 1.A. Section 4 of the EMP above.
If unknown, impacted soil is identified on-site, management on-site can be considered after the
project team provides the necessary information, outlined in Part 1.A. Item 11, for Brownfields
Project Manager approval prior to final placement on-site.
If other potential contingency plans are pertinent, please provide other details or scenarios as
needed below:
Click or tap here to enter text.
POST-REDEVELOPMENT REPORTING
܈܈ Check this box to acknowledge that a Redevelopment Summary Report will be required for the
project. If the project duration is longer than one year, an annual update is required and will be
due by January 31 of each year, or 30 days after each one-year anniversary of the effective date of
this EMP (as agreed upon with the Project Manager). These reports will be required for as long as
physical redevelopment of the Brownfields Property continues, except that the final
Redevelopment Summary Report will be submitted within 90 days after completion of
redevelopment. Based on the estimated construction schedule, the first Redevelopment Summary
Report is anticipated to be submitted on 3/1/2022
The Redevelopment Summary Report shall include environment-related activities since the last
report, with a summary and drawings, that describes:
1. actions taken on the Brownfields Property;
2. soil grading and cut and fill actions;
25
EMP Version 2, January 2021
3. methodology(ies) employed for field screening, sampling and laboratory analysis of
environmental media;
4. stockpiling, containerizing, decontaminating, treating, handling, laboratory analysis and
ultimate disposition of any soil, groundwater or other materials suspected or confirmed
to be contaminated with regulated substances; and
5. removal of any contaminated soil, water or other contaminated materials (for example,
concrete, demolition debris) from the Brownfields Property (copies of all legally required
manifests shall be included).
܈ Check box to acknowledge consent to provide a NC licensed P.G. or P.E. sealed, Redevelopment
Summary Report in compliance with the site’s Brownfields Agreement.
27
EMP Version 2, January 2021
“P” Building(Eastern Fence)SITE MAPFIGURE NO. 2
0200400APPROXIMATESCALE IN FEETNTITLEPROJECTP BUILDING AREA DETAILFORMER DURAFIBER TECHNOLOGIESSALISBURY, NORTH CAROLINADATE:JOB NO:REVISION NO:FIGURE:9-28-21 03OAN-001P BUILDINGAPPROX. SOIL DISTURBANCE AREAS
050100APPROXIMATESCALE IN FEETNTITLEPROJECTP BUILDING SOIL DISTURBANCE AREA DETAILFORMER DURAFIBER TECHNOLOGIESSALISBURY, NORTH CAROLINADATE:JOB NO:REVISION NO:FIGURE:9-28-21 04OAN-001New Power PolePower Line Trench(~1 ft W x 100 ft L x 1.5 ft D )Blower Pad (install on existing ground)Blower Pad (install on existing ground)Mixer/Cooler Foundation (~12 ft x 16 ft x 2.5 ft D)Liquid Stabilizer Pad/Containment (~20 ft x 20 ft x 2.5 ft D)(3) Silos Pad(~18 ft x 48 ft x 2.5 ft D)(2) Silos Pad(~16 ft x 33 ft x 2.5 ft D
Appendix A
Construction Drawings
Appendix B
Draft Brownfields Plat and Contaminant Tables
VESTED IN:Salisbury Investments I LLCBook 1307, Page 44APN: 750 002APN: 750 030APN: 750 031STATESVILLE ROAD [U.S. HIGHWAY 70]NORFOLK SOUTHERN RAILROADNORFOLK SOUTHERN RAILROADRICHARD ROADLYNN ROADWWTP LAND AREA:5,387,936 Square Feet123.690 AcresNow or Formerly:DAVID B. MCSWAIN & FELECIA S. MCSWAINb762 p598826 020Now or Formerly:LAUREN KENEMORE & RYAN KASHOLAb1343 p636826 011Now or Formerly:MARGARET DOBBIN GUDEb1247 p893454 129Now or F
o
r
m
er
l
y
:
THOMAS
G
R
E
G
O
R
Y
T
A
Y
L
O
R
&
J
E
S
S
I
C
A
D
A
W
N
E
L
L
I
S
b1255 p
8
6
9
750 042 Now or Formerly:TODD T. SHUPINGb1236 p524750 041Now or Formerly:JOE D. PADGETT & VICKI J. PADGETTb860 p184750 003Now or Formerly:MICHAEL E. SLUSARZb1172 p788750 032Now or Formerly:TAMARA KEPLEY & JEFFREY M. KEPLEYb796 p432750 029Now or Formerly:JOE HAMPTON & ROBIN HAMPTONb1318 p681750 051Now or Formerly:JOE HAMPTON & ROBIN HAMPTONb1316 p109750 004Now or Formerly:PERRY MARTIN BARBEE & DORIS R. BARBEEb1273 p949751 019Now or Formerly:BRAD A. STROUDb1036 p279751 009Now or Formerly:SHIRLEY J. HILDERBRAND751 045751 007Now or Formerly:PERRY MARTIN BARBEE & DORIS R. BARBEEb1273 p949751 019Now or Formerly:BRAD A. STROUDb1150 p775751 044Now or Formerly:SALISBURY INVESTMENTS I LLCb1307 p44827 014HILDEBRAND ROAD Now or Formerly: MERI (NC) LLC 826 013Now or Formerly:JERRY LEE HILDERBRAND 751 048Surveyor's SealNORTHSheet No.2of2PRELIMINARYFOR REVIEW ONLYEXHIBIT B to the Notice of Brownfields Property - SURVEY PLATProspective Developer and Property Owner: Salisbury Investments I, LLCTax Parcel IDs 750 002, 750 030, 750 031, 827 0147401 Statesville Blvd., Salisbury, NCBrownfields Project No.: 22030-18-080Brownfields Project Name: DurafiberBOUNDARY SURVEY4800 The Woods RoadKitty Hawk, NC 27949Phone: 252-351-0018Corporate Headquarters4111 Bradley Circle NWCanton, OH 44718Phone: 800-520-1010Fax: 330-342-0834PM:Drafter:SMRDWGMSI Project No. 48149PC: JJL
22030-18-080/Durafiber (20200923)
1
DRAFT
Exhibit 2
The most recent environmental sampling at the Property reported in the Environmental
Reports occurred on July 10, 2020.The following tables set forth, for contaminants present at the
Property above commercial/industrial use standards or screening levels, the concentration found
at each sample location, and the applicable standard or screening level. Screening levels and
groundwater and surface water standards are shown for reference only and are not set forth as
cleanup levels for purposes of this Agreement.
GROUNDWATER
Groundwater contaminants in micrograms per liter (the equivalent of parts per billion),
the standards for which are contained in Title 15A of the North Carolina Administrative Code,
Subchapter 2L (2L), Rule .0202, (April 1, 2013 version):
Groundwater
Contaminant
Sample
Location
Date of
Sampling
Concentration
Exceeding
Standard (Pg/L)
Standard
(Pg/L)
Aluminum
4A-80 5/22/1993 345
NE
4A-218 5/23/1993 230
4B-250 5/23/1993 252
CCC-155 6/20/1993 2,140
DDD-154 6/2/1993 722
EW-1 6/2/1993 214
EW-3 6/2/1993 227
EW-4 6/2/1993 975
EW-6 6/8/1993 216
EW-10 5/19/1993 1,070
EW-12 5/20/1993 1,260
EW-13 5/20/1993 294
EW-16 6/3/1993 212
EW-23 6/9/1993 791
EW-27 6/3/1993 1,840
EW-28 6/8/1993 1,210
EW-29 5/25/1993 557
EW-30 5/24/1993 2,250
EW-31 5/24/1993 3,440
EW-32 5/21/1993 4,760
EW-33 5/23/1993 1,310
EW-34 6/8/1993 6,730
EW-35 6/10/1993 5,640
22030-18-080/Durafiber (20200923)
2
EW-36 6/9/1993 2,000
YYY-180 5/19/1993 335
LLL-200 5/19/1993 919
UUU-100 5/24/1993 7,270
UUU-200 5/25/1993 618
VVV-145 5/21/1993 376
Barium Z-90 6/10/2020 3,020 700
Benzene
S-58/DUP 6/10/2020 61.2 J/58.4 J
1 GG-43 1/1995 1.3 J
X-156 1/1995 8.7
Benzyl Alcohol Z-90 6/10/2020 1,780 NE
1,1-Biphenyl
4A-80 1/1995 736
400
4A-218 9/9/2019 758
4G-77 9/9/2019 391
EW-11 5/9/1993 406
T-60 9/11/2019 447
X-156 8/1995 9,760
Bis(2-
ethylhexyl)phthalate
BBB-15 1/1995 5.1 J
3
CCC-37 1/1995 36.4
QQ-250 1/1995 5.6 J
R-57 1/1995 6.8 J
X-156 1/1995 8.6 J
S-58/GW-
DUP 6/10/2020 3.7 J/4.6 J
Cadmium Z-90 6/10/2020 9.66 2
EW-9 5/25/1993 53
EW-10 5/25/1993 109
EW-11 9/10/2019 82.5
EW-12 5/20/1993 116
HH-97 9/11/2019 1,100
Q-59 9/10/2019 273
QQ-75 9/10/2019 99.3
S-58/DUP 6/10/2020 12,500/12,500
Y-119 9/10/2019 244
YY-37 6/10/2020 53.4
Z-90 6/10/2020 9.66
1-Chlorophenol S-58/DUP 6/10/2020 14.8/13.5 NE
Chromium
4A-80 5/22/1993 139
10
4B-250 5/23/1993 14
CCC-155 6/20/1993 16
DD-40 6/10/2020 10.6
EW-29 5/25/1993 23
22030-18-080/Durafiber (20200923)
3
EW-32 5/21/1993 12
EW-34 6/8/1993 22
EW-35 6/10/1993 14
GG-43 6/10/2020 190
RR-102 6/10/2020 69.4
UUU-100 5/24/1993 18
UUU-200 5/25/1993 33
VVV-145 5/21/1993 29
YYY-180 5/19/1993 134
Z-90 6/10/2020 13.6
Hexavalent
Chromium
DD-40 6/10/2020 3.86
NE GG-43 6/10/2020 3.97
RR-102 6/10/2020 9.51
TT-34 6/10/2020 0.16
1,2-Dichlorobenzene
AA-71 9/10/2019 59.1
20
GG-43/DUP 9/11/2019 464/438
EW-11 5/19/1993 63
EW-12 5/20/1993 34
EW-21 6/7/1993 74
HH-97 1/1995 3.6 J
PP-2 1/1995 31.2
Q-59 1/1995 50.2
QQ-75 1/1995 29.3
YY-37 6/10/2020 248
1,4-Dichlorobenzene S-58/DUP 6/10/2020 140/137 6
1,1-Dichloroethane
4A-80 1/1995 16.7
6
EW-2 6/2/1993 102
EW-24 6/10/1993 22
M-104 1/1995 15.8
Y-119 1/1995 115 J
1-4-Dioxane
4A-80 9/9/2019 233
3
4A-218 9/9/2019 64.7
4G-77 9/9/2019 195
4G-231/DUP 9/9/2019 53/49.3
AA-71 9/10/2019 371
CCC-155 9/8/2019 377
DDD-154 9/9/2019 34
EE-58 9/11/2019 1,740
EEE-14 10/2/2017 15.5
EEE-114 9/9/2019 17
EEE-368 9/9/2019 4
EW-01 9/10/2019 51
22030-18-080/Durafiber (20200923)
4
EW-02 9/10/2019 2,050
EW-03 9/10/2019 269
EW-04 9/10/2019 834
EW-05 9/10/2019 876
EW-6 6/8/1993 2,055
EW-7 5/25/1993 2,102
EW-8 5/25/1993 5,775
EW-9 5/25/1993 3,258
EW-10 5/25/1993 3,874
EW-11 9/10/2019 2,200
EW-12 5/20/1993 2,067
EW-13 5/20/1993 894
EW-14 5/21/1993 41
EW-15 5/21/1993 218
EW-16 6/3/1993 10
EW-20 6/15/1993 115
EW-21 6/7/1993 22
EW-22 6/7/1993 144
EW-23 6/9/1993 14
EW-24 6/10/1993 18
EW-25 6/10/1993 20
EW-26 6/11/1993 19
EW-27 6/3/1993 875
EW-28 6/8/1993 898
EW-29 5/25/1993 1,036
EW-30 5/24/1993 166
EW-31 5/24/1993 312
EW-32 5/21/1993 1,184
EW-34 6/8/1993 43
EW-35 6/10/1993 80
EW-36 6/9/1993 10
FFF-51 1/1995 21.3
FFF-101 1/1995 9,500
GG-43/DUP 9/11/2019 155/155
HH-97 9/11/2019 774
K-50 1/1995 2,390
L-41 1/1995 6.8 J
LLL-25 9/10/2019 5.2
LLL-96 9/10/2019 5.3
M-104 8/1995 126
PP-3 1/1995 1,600
PP-4 1/1995 1,430
22030-18-080/Durafiber (20200923)
5
PPP-27 8/1995 7,270
PPP-100 8/1995 1,980
Q-59 9/10/2019 2,390
QQ-48 9/10/2019 73
QQ-75 9/10/2019 631
R-30 9/11/2019 63.8
R-57 9/11/2019 951
RR-102 9/11/2019 4.2
S-58 9/11/2019 20,300
SI-2 9/11/2019 17.1
T-60 9/11/2019 1,620
TT-34 9/10/2019 873
TT-84 9/10/2019 1,430
UUU-200 9/8/2019 21
V-47 1/1995 194
VVV-145 9/10/2019 1,060
WWW-154 9/9/2019 940
X-156 8/1995 287
XXX-116 9/10/2019 6.3
Y-119 9/10/2019 1,020
YY-37 9/11/2019 1,810
YY-96 9/11/2019 1,630
Z-90 9/10/2019 1,400
Diphenyl Ether
4A-80 9/9/2019 2,130
NE
4A-218 9/9/2019 2,280
4B-230 9/9/2019 36.7
4G-231/DUP 9/9/2019 764/902
4G-77 9/9/2019 1,430
AA-71 9/10/2019 51.2
CCC-155 1/1995 11.9
EE-58 9/11/2019 698
EEE-114 1/1995 4.9 J
EW-5 10/4/2019 21.2
EW-6 6/8/1993 56
EW-7 5/25/1993 34
EW-8 5/25/1993 192
EW-9 5/25/1993 15
EW-10 5/25/1993 79
EW-11 9/10/2019 47.8
EW-12 5/20/1993 170
EW-21 6/7/1993 10
EW-22 6/7/1993 69
22030-18-080/Durafiber (20200923)
6
EW-24 6/10/1993 910
EW-29 5/25/1993 14
FFF-51 1/1995 15.9
FFF-101 1/1995 68.1
GG-43/DUP 9/11/2019 116 J/167 J
HH-97 9/11/2019 540
K-50 8/1995 400
M-104 1/1995 3.4 J
PP-2 1/1995 28.4
PP-4 1/1995 14.1
PPP-27 1/1995 9.1 J
QQ-48 9/10/2019 53.7
Q-59 9/10/2019 157
QQ-75 9/10/2019 311
QQ-250 1/1995 22.6
R-57 9/11/2019 34.7
S-58 9/11/2019 322
T-60 9/11/2019 2,620
VVV-145 9/10/2019 43.1
WWW-154 9/9/2019 14.7
X-156 8/1995 32,500
Y-119 9/10/2019 238
YY-37 9/11/2019 70.8
YY-96 9/11/2019 28.2
Z-90 9/10/2019 131
Fluoranthene Y-119 1/1995 975 300
Iron 4A-80 5/22/1993 1,030
300
4C-200 5/23/1993 345
CCC-155 6/20/1993 2,430
DDD-154 6/2/1993 660
EW-1 6/2/1993 10,100
EW-2 6/2/1993 9,710
EW-3 6/2/1993 6,070
EW-4 6/2/1993 6,050
EW-5 6/8/1993 7,100
EW-6 6/8/1993 10,000
EW-7 5/25/1993 3,000
EW-8 5/25/1993 7,160
EW-9 5/25/1993 42,600
EW-10 5/25/1993 4,700
EW-11 5/19/1993 2,170
EW-12 5/20/1993 7,560
22030-18-080/Durafiber (20200923)
7
EW-13 5/20/1993 11,100
EW-14 5/21/1993 7,710
EW-15 5/21/1993 2,930
EW-16 6/3/1993 4,350
EW-17 6/14/1993 14,100
EW-18 6/14/1993 10,600
EW-19 6/15/1993 2,520
EW-20 6/15/1993 2,750
EW-21 6/7/1993 685
EW-22 6/7/1993 2,220
EW-23 6/9/1993 42,600
EW-24 6/10/1993 2,710
EW-25 6/10/1993 5,100
EW-26 6/11/1993 2,950
EW-27 6/3/1993 2,150
EW-28 6/8/1993 906
EW-29 5/25/1993 608
EW-30 5/24/1993 2,120
EW-31 5/24/1993 3,920
EW-32 5/21/1993 8,000
EW-33 5/23/1993 1,950
EW-34 6/8/1993 10,800
EW-35 6/10/1993 8,000
EW-36 6/9/1993 3,430
LLL-200 5/19/1993 687
UUU-100 5/24/1993 3,630
UUU-200 5/25/1993 726
VVV-145 5/21/1993 621
YYY-180 5/19/1993 1,440
Lead CCC-155 6/2/1993 16 15
Manganese
CCC-155 6/20/1993 57
50
DDD-154 6/2/1993 77
EW-1 6/2/1993 63
EW-2 6/2/1993 386
EW-3 6/2/1993 92
EW-4 6/2/1993 90
EW-5 6/8/1993 139
EW-6 6/8/1993 116
EW-7 5/25/1993 141
EW-8 5/25/1993 1,140
EW-9 5/25/1993 679
EW-10 5/25/1993 683
22030-18-080/Durafiber (20200923)
8
EW-11 5/19/1993 475
EW-12 5/20/1993 155
EW-13 5/20/1993 169
EW-14 5/21/1993 113
EW-17 6/14/1993 179
EW-18 6/14/1993 76
EW-22 6/7/1993 122
EW-23 6/9/1993 223
EW-24 6/10/1993 50
EW-25 6/10/1993 71
EW-27 6/3/1993 56
EW-28 6/8/1993 271
EW-29 5/25/1993 85
EW-31 5/24/1993 172
EW-32 5/21/1993 488
EW-34 6/8/1993 397
EW-35 6/10/1993 107
EW-36 6/9/1993 114
LLL-200 5/19/1993 54
UUU-100 5/24/1993 93
Methylene Chloride
EW-29 5/25/1993 25
5 EW-31 5/24/1993 6
K-50 1/1995 5.5 B
Y-119 1/1995 105 J
3&4-Methylphenol Z-90 6/10/2020 58.9 NE
4-Methylphenol Y-119 1/1995 947 40
Naphthalene X-156 1/1995 28.7 6
Phenol K-50 1/1995 19,900 30 Z-90 6/10/2020 2,730
Tetrachloroethene
GG-43 1/1995 7
0.7 K-50 1/1995 11.1
M-104 1/1995 9.2
Y-119 1/1995 70 J
1,1,1-Trichloroethane
EW-29 5/25/1993 8,915
200 EW-30 5/24/1993 1,284
EW-31 5/24/1993 882
Trichloroethene
GG-43 1/1995 3.1 J
3 K-50 1/1995 147
M-104 1/1995 4.9
Y-119 1/1995 150 J
J = Concentration is estimated value detected between laboratory method detection limit and
reporting liming
22030-18-080/Durafiber (20200923)
9
B = Analyte detected in method blank
GROUNDWATER VAPOR INTRUSION RISK
Groundwater contaminants with potential for vapor intrusion (VI) in micrograms per liter
(the equivalent of parts per billion), the vapor intrusion screening levels for which are derived
from the Non-Residential Vapor Intrusion Screening Levels of the Division of Waste
Management (July 2020 version):
Groundwater
Contaminant with
Potential for Vapor
Intrusion
Sample
Location
Date of
Sampling
Concentration
Exceeding
Screening
Level (Pg/L)
Non-
Residential VI
Screening
Level1
(Pg/L)
1,1-Biphenyl
4A-80 9/9/2019 103
28
4A-218 9/9/2019 758
4B-230 9/9/2019 36.7
4G-77 9/9/2019 391
4G-231 9/9/2019 149
EW-5 6/8/1993 71
EW-6 6/8/1993 56
EW-7 5/25/1993 34
EW-8 5/25/1993 192
EW-10 5/25/1993 79
EW-11 5/19/1993 406
EW-12 5/20/1993 170
EW-24 6/10/1993 290
GG-43 8/1995 169
HH-97 1/1995 36.4
K-50 8/1995 230
S-58 9/11/2019 27.6
T-60 9/11/2019 447
X-156 8/1995 9,760
Z-90 9/10/2019 20.1
Chlorobenzene
HH-97 9/11/2019 1,100
340 S-58/DUP 6/10/2020 12,500/12,500
Z-90 6/10/2020 1,500
1,2-Dichlorobenzene GG-43 1/1995 8,840 2,200
Diphenyl Ether
4A-80 9/9/2019 2,130
31 4A-218 9/9/2019 2,280
4B-230 9/9/2019 36.7
22030-18-080/Durafiber (20200923)
10
4G-231 9/9/2019 764/902
4G-77 9/9/2019 1,430
AA-71 9/10/2019 51.2
EE-58 9/11/2019 698
EW-5 10/4/2019 21.2
EW-6 6/8/1993 56
EW-7 5/25/1993 34
EW-8 5/25/1993 192
EW-10 5/25/1993 79
EW-11 9/10/2019 47.8
EW-12 5/20/1993 170
EW-22 6/7/1993 69
EW-24 6/10/1993 910
FFF-101 1/1995 68.1
GG-43/DUP 9/11/2019 116 J/167 J
HH-97 9/11/2019 540
K-50 8/1995 400
QQ-48 9/10/2019 53.7
Q-59 9/10/2019 157
QQ-75 9/10/2019 311
R-57 9/11/2019 34.7
S-58 9/11/2019 322
T-60 9/11/2019 2,620
VVV-145 9/10/2019 43.1
X-156 8/1995 32,500
Y-119 9/10/2019 238
YY-37 9/11/2019 70.8
Z-90 9/10/2019 131
Tetrachloroethene Y-119 1/1995 70 J 48
1,1,1-Trichloroethane EW-29 5/25/1993 8,915 6,200
Trichloroethene
K-50 1/1995 147
4.4 M-104 1/1995 4.9
Y-119 1/1995 150 J
J - Concentration is estimated value detected between laboratory method detection limit and
reporting liming
1 Screening levels displayed for non-carcinogens are for a hazard quotient equal to 0.2. Screening levels
displayed for carcinogens are for a 1.0E-5 lifetime incremental cancer risk.
22030-18-080/Durafiber (20200923)
11
SOIL
Soil contaminants in milligrams per kilogram (the equivalent of parts per million), the
screening levels for which are derived from the Preliminary Industrial Health- Based Soil
Remediation Goals of the Inactive Hazardous Sites Branch of DEQ’s Superfund Section (July
2020 version):
Soil
Contaminant
Sample
Location
Depth
(ft)
Date of
Sampling
Concentration
Exceeding
Screening
Level
(mg/kg)
Non-
Residential
Screening
Level1
(mg/kg)
Antimony
GRUB-1 15 1991-1994 6,880
93
GRUB-2 5 1991-1994 9,690
GRUB-3 10 1991-1994 8,800
GRUB-4 10 1991-1994 5,960
GRUB-5 10 1991-1994 8,880
GRUB-6 15 1991-1994 6,000
GRUB-7 15 1991-1994 7,400
GRUB-8 5 1991-1994 6,010
GRUB-9 10 1991-1994 5,850
GRUB-10 10 1991-1994 6,450
GRUB-11 5 1991-1994 5,989
GRUB-12 15 1991-1994 6,490
GRUB-13 10 1991-1994 6,970
GRUB-14 15 1991-1994 828
GRUB-15 5 1991-1994 2,940
GRUB-18 15 1991-1994 16,399
PP-01-3B NR 5/11/1994 369
PP-01-4B NR 5/12/1994 625
Arsenic
GRUB-5 10 1991-1994 3.1
3
GRUB-11 5 1991-1994 4.5
GRUB-13 10 1991-1994 6.9
GRUB-15 5 1991-1994 15.6
GRUB-18 15 1991-1994 4.4
PP-01-3B NR 5/11/1994 5.12
PP-01-4B NR 5/12/1994 8.9
1,1-biphenyl
GRUB-1 15 1991-1994 69.498 D
43 GRUB-2 5 1991-1994 247.537 D
GRUB-5 10 1991-1994 129.464 D
GRUB-6 15 1991-1994 366
22030-18-080/Durafiber (20200923)
12
GRUB-8 5 1991-1994 56.979
GRUB-10 10 1991-1994 402.752
GRUB-11 5 1991-1994 60.912
GRUB-12 15 1991-1994 81.913
GRUB-13 10 1991-1994 214.133 DJ
GRUB-14 15 1991-1994 133.796
GRUB-15 5 1991-1994 495.223
GRUB-18 15 1991-1994 190.855
Biphenyl ether
GRUB-1 15 1991-1994 220.077 D
NE
GRUB-2 5 1991-1994 996.305 D
GRUB-4 10 1991-1994 73.005 J
GRUB-5 10 1991-1994 426.339 D
GRUB-6 15 1991-1994 4,354
GRUB-8 5 1991-1994 181.938
GRUB-9 10 1991-1994 75.862
GRUB-10 10 1991-1994 1,503.376
GRUB-11 5 1991-1994 145.603
GRUB-12 15 1991-1994 240.367
GRUB-13 10 1991-1994 578.158 DJ
GRUB-14 15 1991-1994 413.58 D
GRUB-15 5 1991-1994 1,689.172 D
GRUB-18 15 1991-1994 607.555
PP-01-4B NR 5/12/1994 276
DTHA-1 3.5 6/1986 1,603
DTHA-2 3.5 6/1986 106
5.0 68.1
DTHA-3 3.0 6/1986 98.5
DTHA-4 3.5 6/1986 2,665
8.0 1,417
DTHA-5 7.5 6/1986 5,299
DTHA-6 6.5 6/1986 1,054
DTHA-7 3.5 6/1986 841
4.5 1,498
DTHA-8 3.0 6/1986 181
7.0 2,786
DTHA-8 3.0 6/1986 181
DT-4SS
15
(DUP)
1991-1994 0.126 J/
0.064 J
20 0.065 J
DT-5SS 20 1991-1994 0.124
25 0.13
DT-6SS 10 1991-1994 0.095 J
22030-18-080/Durafiber (20200923)
13
DTPT-
1SS 5 1991-1994 0.16 J
DTPT-
2SS
5 1991-1994 5.065
10 0.634
15 0.109 J
20 0.359 J
25 0.236 J
40 0.225 J
45 0.119 J
POND-3 5-10 1/25/1991 24.603
Calcium
DTPT-
1SS
5 1991-1994 3,331
NE
15 4,467
20 5,192
25 1,791
30 1,967
35 8,728
DTPT-
2SS
5 1991-1994 2,606
10 2,957
15 6,218
20 3,657
25 3,462
35 3,946
40 7,687
45 3,594
DT-3SS
5 1991-1994 4,650
10
(DUP) 2,740/2,410
15 4,370
20 5,270
25 4,470
DT-4SS
5 1991-1994 1,720
10 543 B
15
(DUP) 92.9 B/79.7 B
20 752 B
25 2,430
30 4,120
35 5,110
DT-5SS
5 1991-1994 5,100
10 3,590
15 5,220
22030-18-080/Durafiber (20200923)
14
20
(DUP) 6,310/6,810
25 2,880
DT-6SS
5 1991-1994 2,130
10 1,700
15
(DUP) 1,000/1,800
20 1,620
25 2,520
30 2,970
PP-01-1B NR 5/11/1994 1,660
PP-01-2B NR 5/11/1994 1,180
PP-01-3B NR 5/11/1994 6,330
PP-01-4B NR 5/12/1994 5,590
PP-02-1 NR 5/11/1994 2,210
PP-02-2 NR 5/11/1994 2,130
PP-02-1 NR 5/12/1994 441
PP-03-2 NR 5/12/1994 1,250
PP-04-1 NR 5/12/1994 2,800
PP-04-2 NR 5/12/1994 1,060
Chromium
GRUB-1 15 1991-1994 199
6.5
GRUB-2 5 1991-1994 84.7
GRUB-3 10 1991-1994 9.5
GRUB-4 10 1991-1994 7.1
GRUB-5 10 1991-1994 48.5
GRUB-6 15 1991-1994 33.6
GRUB-7 15 1991-1994 27.2
GRUB-8 5 1991-1994 18.7
GRUB-9 10 1991-1994 34.9
GRUB-10 10 1991-1994 21.8
GRUB-11 5 1991-1994 27.6
GRUB-13 10 1991-1994 7.5
GRUB-14 15 1991-1994 47.1
GRUB-15 5 1991-1994 8,020
GRUB-18 15 1991-1994 32.3
GRUB-1 30 1991-1994 20.8
GRUB-8 20 1991-1994 16.1
PP-01-1B NR 5/11/1994 92.3
PP-01-2B NR 5/11/1994 56.7
PP-01-3B NR 5/11/1994 2,150
PP-01-4B NR 5/12/1994 3,320
PP-02-1 NR 5/11/1994 21.4
22030-18-080/Durafiber (20200923)
15
PP-02-2 NR 5/11/1994 40.5
PP-03-1 NR 5/12/1994 19.5
PP-03-2 NR 5/12/1994 30.4
PP-04-1 NR 5/12/1994 16.6
PP-04-2 NR 5/12/1994 29.3
DTPT-
1SS
5
1991-1994
62
15 77.4
20 386
25 12.8
30 9.6
35 16.5
DTPT-
2SS
5
1991-1994
14.9
10 16.6
15 37.6
20 27.8
25 26.3
35 10.3
40 11.1
45 10.2
DT-3SS
5
1991-1994
57.5
10
(DUP) 202/194
15 22.6
20 28
25 57.8
DT-4SS
5
1991-1994
47.3
10 14.5
15
(DUP) 10.8/12
20 14
25 19.1
30 13
35 11.9
DT-5SS
5
1991-1994
40.4
10 45
15 25
20
(DUP) 80.9/51.4
25 7.8
5
73.4
10 67.6
22030-18-080/Durafiber (20200923)
16
DT-6SS 15
(DUP)
1991-1994 148/77
20 38.3
25 20.3
30 16.7
CRU-1SS
5
1991-1994
44.4
10 35.6
15 25.8
25 14.7
30 23.2
CRU-2SS
5
1991-1994
50.1
10 60.2
15 35.1
20 36
25 27.8
30 16
35 12.6
CRU-3SS 5 1991-1994 60
10 138
CRU-4SS
5
1991-1994
46.9
10 12.1
15 19.1
Cobalt DT-3SS 10 1991-1994 132 70 15 80
Magnesium
PP-01-1B NR 5/11/1994 1,090
NE
PP-01-2B NR 5/11/1994 3,880
PP-01-3B NR 5/11/1994 3,340
PP-01-4B NR 5/12/1994 2,210
PP-02-1 NR 5/11/1994 2,620
PP-02-2 NR 5/11/1994 2,830
PP-03-1 NR 5/12/1994 1,560
PP-03-2 NR 5/12/1994 2,260
PP-04-1 NR 5/12/1994 5,660
PP-04-2 NR 5/12/1994 2,490
DTPT-
1SS
5
1991-1994
3,910
15 4,880
20 19,011
25 4,114
30 4,744
35 3,720
5
2,374
10 4,796
22030-18-080/Durafiber (20200923)
17
DTPT-
2SS
15
1991-1994
13,514
20 4,649
25 4,198
35 3,059
40 4,068
45 5,832
DT-3SS
5
1991-1994
3,810
10
(DUP) 3,990/4,580
15 6,500
20 5,600
25 3,030
DT-4SS
5
1991-1994
1,940
10 1,600
15
(DUP) 3,180/2,200
20 3,160
25 11,000
30 5,160
35 4,270
DT-5SS
5
1991-1994
3,530
10 3,400
15 5,760
20
(DUP) 9,410/10,000
25 3,390
DT-6SS
5
1991-1994
3,430
10 2,970
15
(DUP) 1,670/2,860
20 3,590
25 6,450
30 3,630
1,4-
Dichlorobenzene GRUB-10 10 1991-1994 13.714 12
1,4-Dioxane
GRUB-6 15 1991-1994 31.154
25 GRUB-7 15 1991-1994 47.536 D
GRUB-12 15 1991-1994 51.344
GRUB-18 15 1991-1994 28.936
POND-3 5-10 1/21/1991 34.284 D
p-Isopropyltoluene SB-3DUP 2-4 6/9/2020 0.0608 NE
Potassium PP-01-1B NR 5/11/1994 457 NE
22030-18-080/Durafiber (20200923)
18
PP-01-2B NR 5/11/1994 1,720
PP-01-3B NR 5/11/1994 1,750
PP-01-4B NR 5/12/1994 1,190
PP-02-1 NR 5/11/1994 103
PP-02-2 NR 5/11/1994 497
PP-03-1 NR 5/12/1994 550
PP-03-2 NR 5/12/1994 1,200
PP-04-1 NR 5/12/1994 300
PP-04-2 NR 5/12/1994 1,520
DTPT-
1SS
5
1991-1994
1,075
15 521 B
20 743 B
25 1,299
30 2,326
35 666 B
DTPT-
2SS
5
1991-1994
1,664
15 695 B
20 496 B
25 453 B
DT-3SS
5
1991-1994
1,610
10
(DUP) 607 B/864 B
15 813 B
20 672 B
25 574 B
DT-4SS
5
1991-1994
789 B
10 694 B
15
(DUP) 1,170/728 B
20 409 B
25 4,470
30 1,390
35 433 B
DT-5SS
5
1991-1994
1,390
10 1,300
15 455 B
20
(DUP) 1,660/1,630
25 999 B
5
929 B
10 650 B
22030-18-080/Durafiber (20200923)
19
DT-6SS 15 1991-1994 692 B
25 685 B
30 944 B
Sodium
PP-01-1B NR 5/11/1994 224
PP-01-2B NR 5/11/1994 166
PP-01-3B NR 5/11/1994 1,440
PP-01-4B NR 5/12/1994 1,570
PP-02-1 NR 5/11/1994 188
PP-02-2 NR 5/11/1994 235
PP-03-1 NR 5/12/1994 186
PP-03-2 NR 5/12/1994 312
PP-04-1 NR 5/12/1994 188
PP-04-2 NR 5/12/1994 235
DTPT-
1SS
5
1991-1994
233 B
15 318 B
20 326 B
25 204 B
30 208 B
35 460 B
DTPT-
2SS
5
1991-1994
332 B
10 209 B
15 419 B
20 289 B
25 302 B
35 243 B
40 257 B
45 197 B
DT-3SS
5
1991-1994
1,180
10
(DUP) 556 B/541 B
15 312 B
20 228 B
25 247 B
DT-4SS
5
1991-1994
551 B
15
(DUP) 246 B/250 B
20 317 B
25 304 B
30 389 B
35 271 B
5
886 B
10 896 B
22030-18-080/Durafiber (20200923)
20
DT-5SS 15 1991-1994 333 B
20
(DUP) 259 B/274 B
DT-6SS
5
1991-1994
210 B
30 254 B
Trichloroethene
GRUB-1 15 1991-1994 11.088
4 GRUB-8 5 1991-1994 7.42
GRUB-12 15 1991-1994 15.538
1Screening levels displayed for non-carcinogens are for a hazard quotient equal to 0.2. Screening levels
displayed for carcinogens are for a 1.0E-6 lifetime incremental cancer risk.
NE – No established screening level
J – Estimated value
D – Secondary dilution required
SUB-SLAB VAPOR OR SOIL GAS
Soil gas contaminants in micrograms per cubic meter, the screening levels for which are
derived from Non-Residential Vapor Intrusion Screening Levels of the Division of Waste
Management (July 2020 version):
Soil Gas Contaminant
Sample
Location
Date of
Sampling
Concentration
Exceeding
Screening Level
(Pg/m3)
Non-Residential
Screening
Limit1
(Pg/m3)
cis-1,2-
Dichloroethylene SS-7 6/9/2020 1.0 NE
Ethanol
SS-1 6/10/2020 1,000
NE
SS-2 6/10/2020 630
SS-3/DUP 6/10/2020 910/690
SS-4 6/9/2020 560
SS-5 6/9/2020 860
SS-6 6/9/2020 900
SS-7 6/9/2020 530
SS-8 6/9/2020 560
SS-9 6/9/2020 3,600
SS-10 6/9/2020 1,700
SS-11 6/9/2020 750
4-Ethyltoluene
SS-8 6/9/2020 2.4
NE SS-9 6/9/2020 0.73 J
SS-10 6/9/2020 2.0
SS-11 6/9/2020 5.9
22030-18-080/Durafiber (20200923)
21
Trichlorofluoromethane
SS-1 6/10/2020 3.6 J
NE
SS-2 6/10/2020 1.9 J
SS-3/DUP 6/10/2020 2.0 J/2.0 J
SS-4 6/9/2020 2.1J
SS-5 6/9/2020 1.7 J
SS-6 6/9/2020 1.6 J
SS-7 6/9/2020 1.3 J
SS-8 6/9/2020 1.6 J
SS-9 6/9/2020 2.1 J
SS-10 6/9/2020 3.1 J
SS-11 6/9/2020 1.5 J
1Screening levels displayed for non-carcinogens are for a hazard quotient equal to 0.2. Screening levels
displayed for carcinogens are for a 1.0E-5 lifetime incremental cancer risk.
NE-No established screening level
SURFACE WATER
Surface water contaminants (in micrograms per liter, the equivalent of parts per billion),
the unrestricted use standards for which are contained in Title 15A of the North Carolina
Administrative Code, Subchapter 2B, Rule .0208 (June 2019):
Surface Water Contaminant Sample
Location
Date of
Sampling
Concentration
Exceeding
Standard
(Pg/L)
Standard
(Pg/L)
1,4-Dioxane
SW-2 9/10/2019 5.9
NE
SW-3 9/10/2019 6.3
SW-4 9/9/2019 2.4
SW-
5/DUP
9/9/2019 7.6/7.8
SW-6 9/9/2019 4.3
NE-No established standard
Appendix C
Soil Vapor Sample Location Map and Data Summary
Table 5Summary of Sub-Slab Soil Vapor Analytical DataSalisbury Investments Salisbury, North CarolinaH&H Job No. FDP-058Evaluation AreaSample IDSS-1 SS-2 SS-4 SS-5 SS-6 SS-7 SS-8 SS-9 SS-10 SS-11Sample DateSlab Thickness (in)16 9 12141817 8 121112UnitsVOCs (TO-15)Acetone (2)120380360340861101901202102904602302,700,000Benzene1.0<0.26<0.260.40<0.26<0.26<0.260.51 J 0.31 J<0.26<0.260.59 J1,6002-Butanone (MEK)7.3 J6.6 J7.4 J8.3 J5.3 J8.7 J12 J6.0 J8.1 J16 J605.5 J440,000Carbon Disulfide2.7 J<0.43<0.43<0.43<0.43<0.43<0.435.9 J<0.43<0.43<0.43<0.4361,000Carbon Tetrachloride0.83 J<0.41<0.41<0.41<0.41<0.41<0.41<0.41<0.41<0.41<0.41<0.412,000Chloroform3.9<0.36<0.36<0.36<0.36<0.36<0.364.8<0.361.0<0.36<0.36530 Dichlorodifluoromethane (Freon 12)3.12.12.52.52.11.91.91.71.91.9<0.431.98,8001,1-Dichloroethane17<0.25<0.25<0.25<0.25<0.25<0.25<0.25<0.25<0.25<0.25<0.257,7001,1-Dichloroethylene210<0.43<0.43<0.43<0.43<0.43<0.43<0.43<0.43<0.43<0.43<0.4318,000cis-1,2-Dichloroethylene<0.32<0.32<0.32<0.32<0.32<0.32<0.321.0<0.32<0.32<0.32<0.32NEEthanol (2)1,0006309106905608609005305603,6001,700750NEEthyl Acetate12<0.54<0.54<0.54<0.547.8<0.54<0.545.610<0.54116,100Ethylbenzene0.50 J<0.50<0.50<0.50<0.500.56 J<0.50<0.501.10.66 J1.22.44,9004-Ethyltoluene<0.60<0.60<0.60<0.60<0.60<0.60<0.60<0.602.40.73 J2.05.9NEHeptane0.82<0.48<0.48<0.48<0.48<0.48<0.48<0.48<0.48<0.48<0.481.135,0002-Hexanone (MBK)<0.48<0.48<0.48<0.48<0.48<0.48<0.48<0.48<0.48<0.4815<0.482,600Isopropanol2002201701602222362121427017 J18,000Methylene Chloride8.41.3 J1.8 J1.3 J1.7 J6.7 J1.4 J2.6 J1.5 J2.3 J2.2 J5.6 J53,0004-Methyl-2-pentanone (MIBK)<0.43<0.432.52.8<0.43<0.43<0.43<0.43<0.4314<0.4334260,000Naphthalene<0.80<0.80<0.80<0.800.82 J<0.80<0.800.88 J4.55.74.09.2260Styrene0.63 J<0.53<0.53<0.53<0.53<0.53<0.53<0.530.920.901.32.488,000Tetrachloroethylene752.29.79.56100.84 J2601.3 J33530693.93,500Tetrahydrofuran<0.59<0.59<0.59<0.59<0.59<0.59<0.599.1<0.59<0.59<0.59<0.59180,000Toluene4.01.30.68 J 0.63 J1.34.61.61.53.02.53.17.4440,0001,1,1-Trichloroethane4.2132.62.50.79 J<0.412.9<0.41<0.411.1<0.41<0.41440,000Trichloroethylene17<0.43<0.43<0.43<0.43<0.43<0.430.82 J<0.43<0.43<0.43<0.43180 Trichlorofluoromethane (Freon 11)3.6 J1.9 J2.0 J2.0 J2.1 J1.7 J1.6 J1.3 J1.6 J2.1 J3.1 J1.5 JNE1,1,2-Trichloro-1,2,2-trifluoroethane (Freon 113)<1.2<1.2<1.2<1.2<1.2<1.2<1.2<1.2<1.2<1.23.8 J<1.2440,0001,2,4-Trimethylbenzene<0.63<0.63<0.63<0.63<0.63<0.63<0.63<0.63<0.63<0.63<0.63255,3001,3,5-Trimethylbenzene<0.62<0.62<0.62<0.62<0.62<0.62<0.62<0.624.61.34.0125,300m&p-Xylene1.7 J2.01.2 J1.5 J1.1 J1.8 J1.3 J1.2 J103.98.3218,800o-Xylene0.69 J 0.69 J<0.54<0.54<0.540.82 J 0.57 J 0.61 J3.41.42.97.18,800Notes:1) North Carolina Department of Environment Quality (DEQ) Division of Waste Management (DWM) Non-Residential Sub-slab and Exterior Soil Gas Screening Levels (SGSLs) dated February 20182) Concentrations were reported with the V-06 laboratory qualifier. V-06 = Continuing calibration verification did not meet method specifications and was biased on the high side for the compound.Only constituents detected in at least one sample are shown in the table above.Compound concentrations are reported in micrograms per cubic meter (μg/m3).Compound concentrations are reported to the laboratory detection limits.Laboratory analytical method is shown in parentheses. J = Compound was detected above the laboratory method detection limit, but below the laboratory reporting limit resulting in a laboratory estimated concentration. VOCs = Volatile Organic Compounds; in = Inches; NE = Not Established 6/9/2020 6/9/2020Non-Residential SGSLs (1)μg/m3SS-3 / SS-DUPFilament WarehouseStaple Warehouse Maintenance Building Training Building6/10/2020136/9/2020S:\AAA-Master Projects\ForSite Development Partners (FDP)\FDP-058 Durafiber Celanese Salisbury\Brownfields\Assessment\Tables\Data Table FDP-0587/8/2020Table 5 (Page 1 of 1) Hart & Hickman, PC
POLISHINGPONDPOLISHINGPONDPOLISHINGPONDPOLISHINGPONDDIGESTORPROCESSWATERPONDABANDONED AERATION BASINREC CLUBHOUSEFIBERLAKESTAPLE WAREHOUSEFILAMENTWAREHOUSECLARIFIERDOW STORAGESB-1SB-2SB-3SB-4SB-5SB-6SB-7SS-2SS-5SS-1SS-3SS-4SS-6SS-7SS-8SS-9SS-10SS-11SW-4SW-1BG-1BG-2PARKINGPARKINGCELANESE DRIVE TT-34YY-37R-30Z-90RR-102S-58DD-40GG-43FORMER GRUB LANDFILLDOWTHERM AREAWASTE WATERTREATMENT PLANTDOW REBOILERSDOW STORAGEDOW BOILERSFUEL OIL STORAGEMAINTENANCE BUILDINGTRAINING BUILDINGEQUALIZATION TANKS(FORMER CRU BASIN)REVISION NO. 0JOB NO. FDP-058DATE: 7-8-20FIGURE NO. 4SALISBURY INVESTMENTS7401 STATESVILLE BOULEVARDSALISBURY, NORTH CAROLINASAMPLE LOCATION MAP2923 South Tryon Street-Suite 100Charlotte, North Carolina 28203704-586-0007(p) 704-586-0373(f)License # C-1269 / #C-245 GeologyNOTES:1. AERIAL IMAGERY OBTAINED FROM NC ONEMAP,2019.2. PARCEL DATA OBTAINED FROM ROWAN COUNTYGIS, 2020.LEGENDBROWNFIELDS PROPERTY BOUNDARYSECOND CREEKRAILROAD SPURDOWTHERM AREA SOIL SAMPLEFUEL OIL STORAGE SOIL SAMPLECOOLING TOWER SOIL SAMPLEBACKGROUND SOIL SAMPLEGROUNDWATER MONITORING WELLSURFACE WATER SAMPLESUB-SLAB SOIL VAPOR SAMPLES:\AAA-Master Projects\ForSite Development Partners (FDP)\FDP-058 Durafiber Celanese Salisbury\Figures\Sample Location Map.dwg, FIG 4, 7/16/2020 12:23:08 PM, sperry
Appendix D
Liquid Stabilizer SDS