HomeMy WebLinkAbout23018_Corey Transmission - Environmental Management Plan (EMP) - Fully Executed_03-10-20201
EMP Version 2, June 2018
NORTH CAROLINA BROWNFIELDS PROGRAM
ENVIRONMENTAL MANAGEMENT PLAN
This form is to be used to prepare an Environmental Management Plan (EMP) for projects in
the North Carolina Brownfields Program at the direction of a Brownfields project manager.
The EMP is a typical requirement of a Brownfields Agreement (BFA). Its purpose is to clarify
actions to be taken during the demolition and construction at Brownfields properties in an
effort to avoid delays in the event of the discovery of new contamination sources or other
environmental conditions. The EMP provides a means to document redevelopment plans and
environmental data for each applicable environmental medium to inform regulatory-compliant
decision-making at the site. As much detail as possible should be included in the EMP,
including contingency planning for unknowns. Consult your project manager if you have
questions.
Prospective Developers and/or their consultants must complete and submit this form and all
pertinent attachments, see checklist below, to their Brownfields project manager prior to any
earthmoving or other development-related activities that have the potential to disturb soil at
the Brownfields Property, including demolition. For the resultant EMP to be valid for use, it
must be completed, reviewed by the program, signed by all parties working on the project,
and approved by the Brownfields project manager. Failure to comply with the requirements of
the EMP could jeopardize project eligibility, or in the event of a completed agreement, be
cause for a reopener
So that the EMP provides value in protecting brownfields eligibility and public health, the
preparer shall ensure that the following steps have been completed prior to submitting the
EMP for review. Any EMP prepared without completing these steps is premature.
☒Site sampling and assessment that meets Brownfields’ objectives is complete and has
been reviewed and approved by the Brownfields Project Manager.
☒Specific redevelopment plans, even if conceptual, have been developed for the project,
submitted and reviewed by the Brownfields Project Manager.
2
EMP Version 2, June 2018
Please submit, along with the completed EMP form, the following attachments, as relevant
and applicable to the proposed redevelopment:
☒ A set of redevelopment plans, including architectural/engineering plans, if available; if
not conceptual plans may suffice if updated when detailed plans are drafted.
☒ A figure overlaying redevelopment plans on a map of the extent of contamination for
each media.
☒ Site grading plans that include a cut and fill analysis.
☐ A figure showing the proposed location and depth of impacted soil that would remain
on site after construction grading.
☐ Any necessary permits for redevelopment (i.e. demolition, etc.).
☐ A detailed construction schedule that includes timing and phases of construction.
☒ Tabulated data summaries for each impacted media (i.e. soil, groundwater, soil gas,
etc.) applicable to the proposed redevelopment.
☒ Figures with the sampling locations and contamination extents for each impacted media
applicable to the proposed redevelopment.
☐ A full final grade sampling and analysis plan, if the redevelopment plan is final.
☐ If known, information about each proposed potential borrow soil source, such as aerial
photos, historic site maps, historic Sanborn maps, a site history, necessary for
brownfields approval.
☐ Information and, analytical data if required, for quarries, or other borrow sources,
detailing the type of material proposed for importation to the Brownfields Property.
☐ A work plan for the sampling and analysis of soil to be brought onto the Brownfields
Property. Refer to Issue Resolution 15 in Brownfields Program Guidelines.
☐ A map of the Brownfields Property showing the location of soils proposed for export
and sampling data from those areas.
☐ If a Vapor Mitigation System is required by the Brownfields Program, the Vapor
Intrusion Mitigation System (VIMS) plan will be signed and sealed by a NC Professional
Engineer. The VIMS Plan may also be submitted under separate cover.
3
EMP Version 2, June 2018
GENERAL INFORMATION
Date: 3/9/2020 Revision Date (if applicable): Click or tap to enter a date.
Brownfields Assigned Project Name: Corey Transmission Service
Brownfields Project Number: 23018-19-060
Brownfields Property Address: 511 & 527 West Tremont Avenue, Charlotte, Mecklenburg County,
North Carolina
Brownfields Property Area (acres): 5.58
Is Brownfields Property Subject to RCRA Permit?.......................☐ Yes ☒ No
If yes enter Permit No.: Click or tap here to enter text.
Is Brownfields Property Subject to a Solid Waste Permit….……..☐ Yes ☒ No
If yes, enter Permit No.: Click or tap here to enter text.
COMMUNICATIONS
A copy of this EMP shall be distributed to all the parties below as well as any contractors or site workers
that may be exposed to site vapors, soil, groundwater, and/or surface water. Additionally, a copy of the
EMP shall be maintained at the Brownfields Property during redevelopment activities. NOTE, THE EMP
DOES NOT TAKE THE PLACE OF A SITE-SPECIFIC HEALTH AND SAFETY PLAN.
Prospective Developer (PD): TAC Tremont,LLC
Contact Person: Tyson Reilly
Phone Numbers: Office: (803) 548-4656 Mobile: 248-361-8842
Email: treilly@theardentcompanies.com
Contractor for PD: Altura Development Group, LTD
Contact Person: Mr. Chris Granelli
Phone Numbers: Office: Click or tap here to enter text. Mobile: 704-534-4898
Email: cmg@alturagroup.net
Environmental Consultant: ECS Southeast, LLP
Contact Person: Joseph Nester, P.G., P.E.
Phone Numbers: Office: 704.525.5152 Mobile: 704-280-7422
Email: jnestor@ecslimited.com
Brownfields Program Project Manager: Cody Cannon
Phone Numbers: Office: 704-235-2168 Mobile: 704-798-0352
Email: cody.cannon@ncdenr.gov
4
EMP Version 2, June 2018
Other DEQ Program Contacts (if applicable, i.e., UST Section, Inactive Hazardous Site Branch,
Hazardous Waste, Solid Waste):
Click or tap here to enter text.
NOTIFICATIONS TO THE BROWNFIELDS PROGRAM
Written advance Notification Times to Brownfields Project Manager: Check each box to accept
minimum advance notice periods (in calendar days) for each type of onsite task:
On-site assessment or remedial activities:……………………………………….…… 10 days Prior ☒
Construction or grading start:……………………………………….………………………. 10 days Prior ☒
Discovery of stained soil, odors, USTs, buried drums or waste, landfill, or other signs of previously
unknown contamination: ……………………………….……………………………………. Within 48 hours ☒
Implementation of emergency actions (e.g. dewatering, flood or soil erosion control measures in
area of contamination, ventilation of work zones):…………….……….……… Within 48 hours ☒
Installation of mitigation systems:………………………….………………….……….. 10 days Prior ☒
Other notifications as required by local, state or federal agencies to implement redevelopment
activities: (as applicable): ……………………….…………………………………………..… Within 30 days ☒
REDEVELOPMENT PLANS
1) Type of Redevelopment (check all that apply):
☒Residential ☐Recreational ☐Institutional ☐Commercial ☐Office ☐Retail ☐Industrial
☐Other specify:
The current site redevelopment plans include the construction of approximately 100 townhome
units, including small private yards and shared open space consistent with the approved zoning
of the property.
2) Check the following activities that will be conducted prior to commencing earth-moving activities
at the site:
☒ Review of historic maps (Sanborn Maps, facility maps)
☐ Conducting geophysical surveys to evaluate the location of suspect UST, fuel lines, utility
lines, etc.
☐ Interviews with employees/former employees/facility managers/neighbors
3) Summary of Redevelopment Plans (MANDATORY: attach detailed plans or conceptual plans, if detailed plans are not available. EMP review without such information would be premature):
5
EMP Version 2, June 2018
Provide brief summary of redevelopment plans, including demolition, removal of building
slabs/pavement, grading plans and planned construction of new structures:
A CD of complete re-development plans will be provided to North Carolina Brownfields Program.
In addition, these plans may be downloaded from the following link:
Download all associated files
Appendix A includes pertinent excerpts from the complete plans including an ALTA/ASCM Land
Title Survey (Pre-redevelopment), C2-00 Existing Condition & Demolition Plan, C3-00 – Site Plan,
and C4-00 – Grading Plan. In addition, a cut and fill analysis is included in Appendix A.
Construction activities are scheduled to begin in April 2020 and occupancy is expected by
September 2020.
4) Do plans include demolition of structure(s)?:
☒ Yes ☐ No ☐ Unknown
☒ If yes, please check here to confirm that demolition will be conducted in accordance with
applicable legal requirements, including without limitation those related to lead and asbestos
abatement that are administered by the Health Hazards Control Unit within the Division of Public
Health of the North Carolina Department of Health and Human Services. If available, please
provide a copy of your demolition permit.
5) Are sediment and erosion control measures required by federal, state, or local regulations?
☒ Yes ☐ No ☐ Unknown
☒ If yes, please check here to confirm that demolition will be conducted in accordance with
applicable legal requirements. If soil disturbance is necessary to install sediment and erosion
control measures, they may not begin until this EMP is approved.
6) Which category of risk-based screening level is used or is anticipated to be specified in the
Brownfields Agreement? Note: If children frequent the property, residential screening levels shall
be cited in the Brownfields Agreement for comparison purposes.
☒ Residential ☐ Non-Residential or Industrial/Commercial
7) Schedule for Redevelopment (attach construction schedule):
a) Construction start date: 4/1/2020
b) Anticipated duration (specify activities during each phase):
Anticipated 4 months of construction.
c) Additional phases planned? ☐ Yes ☐ No
If yes, specify the start date and/or activities if known:
Start Date: Additional phases are not planned
Planned Activity:
Not Applicable
6
EMP Version 2, June 2018
Start Date: Additional phases are not planned
Planned Activity:
Not Applicable
Start Date: Additional phases are not planned
Planned Activity:
Not Applicable d) Provide the planned date of occupancy for new buildings: Occupancy of units is expected to
start 4th quarter of 2020 and complete occupancy anticipated by end of 2021.
CONTAMINATED MEDIA
1) Contaminated Media on the Brownfields Property
Part 1. Soil:……………………………………….……………. ☒ Yes ☐ No ☐ Suspected
Part 2. Groundwater:.……………………….……..……. ☒ Yes ☐ No ☐ Suspected
Part 3. Surface Water:.……………...……..…………… ☐ Yes ☒ No ☐ Suspected
Part 4. Sediment:.……………...……..…………………… ☐ Yes ☒ No ☐ Suspected
Part 5. Soil Vapor:…..…………...……..…………………. ☒ Yes ☐ No ☐ Suspected
Part 6. Sub-Slab Soil Vapor:……...……..…………….. ☐ Yes ☐ No ☒ Suspected
Part 7. Indoor Air:...……..…………………………………. ☐ Yes ☒ No ☐ Suspected
2) For the Area of Proposed Redevelopment on the Brownfields Property, attach tabulated data
summaries for each impacted media and figure(s) with sample locations.
PART 1. Soil – Please fill out the information below, using detailed site plans, if available, or estimate
using known areas of contaminated soil and a conceptual redevelopment plan. Provide a figure
overlaying new construction onto figure showing contaminated soil and groundwater locations.
1) Known or suspected contaminants in soil (list general groups of contaminants):
Appendix B includes figures from previous environmental assessment reports which show the
locations of sampling points of various environmental media superimposed over aerial
photographs of how the site appeared at the time of sampling. Appendix C includes figures
showing the locations of sampling points of various environmental media superimposed over the
site plan. Appendix D includes tables from previous environmental assessment reports which
summarize analytical results for samples taken from the sampling points. Soil samples were
analyzed for VOCs, SVOCs, RCRA metals, and hexavalent chromium.
VOCs
The VOC, acetone, was detected in three soil samples and a duplicate sample at estimated
concentrations (i.e., J-flagged) ranging from 0.0177 to 0.0727 mg/Kg and were below PSRGs.
7
EMP Version 2, June 2018
Benzene was detected in one soil sample at an estimated concentration (i.e., J-flagged) of 0.0013
mg/Kg and was below PSRGs
SVOCs
SVOCs were detected in several composite soil samples collected on August 19, 2019 and August
20, 2019. ECS compared detected concentrations for SVOCs to preliminary soil remediation goals
(PSRGs) for residential or industrial/commercial exposure scenarios and the leaching from soil to
groundwater exposure scenario.
Several SVOCs were detected in composite soil samples at concentrations below their respective
PSRGs, with the exception of benzo(a)pyrene. Benzo(a)pyrene was detected at a concentration of
0.322 mg/Kg, which exceeds the residential PSRG (0.11 mg/Kg) and the groundwater PSRG
(0.12mg/Kg), however, the detected concentration is below the industrial/commercial PSRG (2.1
mg/Kg).
Metals
RCRA metals were detected in each of the five composite soil samples. With the exception of
total chromium, none of the detected concentrations of RCRA metals exceeded
industrial/commercial PSRGs.
The detected concentrations of total chromium ranged from 17.7 mg/Kg for sample DUP-2 to
104 mg/Kg. The concentrations of total chromium exceeded the industrial/commercial PSRG for
total chromium (6.5 mg/Kg). Hexavalent chromium was detected at estimated concentrations of
0.509 mg/Kg and 0.316 mg/Kg in two samples and exceeded the residential PSRG but not
industrial/commercial PSRG or groundwater PSRG. These results were J-flagged by the
laboratory indicating that the estimated concentration was above the adjusted method
detection limit and below the adjusted reporting limit. Hexavalent chromium was not detected in
the remaining three soil samples or the duplicate sample. The calculated concentrations of
trivalent chromium for the soil samples collected in August 2019 did not exceed PSRGs. ECS
calculated the concentration of trivalent chromium in soil samples by subtracting the detected
concentration of hexavalent chromium from the detected concentration of total chromium. In
cases in which hexavalent chromium was reported as not detected by laboratory, ECS assumed
the concentration of hexavalent chromium was at the laboratory method detection limit (MDL)
and subtracted this value from the concentration for total chromium.
Arsenic was detected in soil samples at 1.0 and 1.5 mg/Kg concentrations, exceeding the
residential use PSRG (0.68 mg/Kg), but below the industrial/commercial PSRG (3.0 mg/Kg) and
protection of groundwater PSRG (5.8 mg/Kg). The concentrations of arsenic in soil are consistent
with expected concentrations of naturally occurring arsenic in this region and is not necessarily
indicative of a release of hazardous substances. .
2) Depth of known or suspected contaminants (feet):
Soil samples were collected from 0 to 2 feet below surface.
8
EMP Version 2, June 2018
3) Area of soil disturbed by redevelopment (square feet):
Approximately 246,691
4) Depths of soil to be excavated (feet):
Maximum depth of materials to be excavated estimated at 7 feet
5) Estimated volume of soil (cubic yards) to be excavated (attach grading plan):
11,630 cubic yards cubic yards (See attached Grading Plan and Cut & Fill analysis in Appendix A)
6) Estimated volume of excavated soil (cubic yards) anticipated to be impacted by contaminants:
11,630 cubic yards cubic yards
7) Estimated volume of contaminated soil expected to be disposed of offsite, if applicable:
11,630 cubic yards
Part 1.A. MANAGING ONSITE SOIL
If soil is anticipated to be excavated from the Brownfield Property, relocated on the Brownfields
Property, or otherwise disturbed during site grading or other redevelopment activities, please
provide a grading plan that clearly illustrates areas of cut and fill (approximate areas & volumes are
acceptable, if only preliminary data available).
1) HAZARDOUS WASTE DETERMINATION:
a) Does the soil contain a LISTED WASTE as defined in the North Carolina Hazardous
Waste Section under 40 CFR Part 261.31-261.35?....................................... ☐Yes ☒No
☐ If yes, explain why below, including the level of knowledge regarding processes
generating the waste (include pertinent analytical results as needed).
Click or tap here to enter text.
☐ If yes, do the soils exceed the “Contained-Out” levels in Attachment 1 of the
North Carolina Contained-In Policy?................................................. ☐ Yes ☐ No
b) NOTE: IF SOIL MEETS THE DEFINITION OF A LISTED HAZARDOUS WASTE AND EXCEEDS
THE CONTAINED-OUT LEVELS IN ATTACHMENT 1 TO THE NORTH CAROLINA
CONTAINED-IN POLICY THE SOIL MAY NOT BE RE-USED ON SITE AND MUST BE
DISPOSED OF IN ACCORDANCE WITH DEQ HAZARDOUS WASTE SECTION RULES AND
REGULATIONS.
c) Does the soil contain a CHARACTERISTIC WASTE?.................................... ☐ Yes ☒ No
☐ If yes, mark reason(s) why below (and include pertinent analytical results).
☐ Ignitability Click or tap here to enter text.
☐ Corrosivity Click or tap here to enter text.
☐ Reactivity Click or tap here to enter text.
9
EMP Version 2, June 2018
☐ Toxicity Click or tap here to enter text.
☐ TCLP results Click or tap here to enter text.
☐ Rule of 20 results (20 times total analytical results for an individual
hazardous constituent on TCLP list cannot, by test method, exceed regulatory
TCLP standard)
Click or tap here to enter text.
☒ If no, explain rationale:
Rule of 20 Results for VOCS, SVOCS, and metal; and professional judgment for
ignitability, corrosivity, reactivity, and toxicity.
d) NOTE: IF SOIL MEETS THE DEFINITION OF A CHARACTERISTIC HAZARDOUS WASTE, THE
SOIL MAY NOT BE RE-USED ON SITE AND MUST BE DISPOSED OF IN ACCORDANCE
WITH DEQ HAZARDOUS WASTE SECTION RULES AND REGULATIONS.
2) Screening criteria by which soil disposition decisions will be made (e.g., left in place, capped in
place with low permeability barrier, removed to onsite location and capped, removed offsite):
☒ Preliminary Health-Based Residential SRGs
☐ Preliminary Health-Based Industrial/Commercial SRGs
☒ Division of Waste Management Risk Calculator (For Brownfields Properties Only)
☐ Site-specific risk-based cleanup level. Please provide details of methods used for
determination/explanation.
Click or tap here to enter text.
Additional comments:
If field observations suggest contamination which was not previously noted, samples will be
collected and analyzed and screening criteria will be applied.
3) If known impacted soil is proposed to be reused within the Brownfields Property Boundary,
please check the measures that will be utilized to ensure safe placement and documentation of
same. Please attach a proposed location diagram/site map.
☒ Provide documentation of analytical report(s) to Brownfields Project Manager
☒ Provide documentation of final location, thickness and depth of relocated soil on site map
to Brownfields Project Manager once known
☐ Geotextile to mark depth of fill material.
Provide description of material:
Click or tap here to enter text.
☒ Manage soil under impervious cap ☐ or clean fill ☒
☒ Describe cap or fill:
10
EMP Version 2, June 2018
Hardscaping or 2 feet of clean fill will be placed over areas of known surficial soil
contamination.
☒ Confer with NC BF Project Manager if Brownfield Plat must be revised (or re-recorded if
actions are Post-Recordation).
☒ GPS the location and provide site map with final location.
☐ Other. Please provide a description of the measure:
4) Please describe the following action(s) to be taken during and following excavation and
management of site soils:
Management of fugitive dust from site
☒ Yes, describe the method will include:
Typical construction measures involving a water truck will be used as necessary to address
visible dust.
☐ No, explain rationale:
Click or tap here to enter text.
Field Screening of site soil
☒ Yes, describe the field screening method, frequency of field screening, person conducting
field screening:
Soil will be monitored via human sensory observations, including visual observations for
staining, debris, or indications of fill and olfactory observations for unusual odors. These
observations can be augmented by a photoionization detector (PID) to evaluate VOC
presence as needed during soil excavation activities at the site. The contractor will be
instructed to contact ECS should field observations suggest the presence of impacts. Field
instrument screening of excavated soils will occur on an as-needed basis while excavation
is occurring and use of field instrumentation will be used more frequently in areas of
suspected impact. ECS will also conduct periodic site visits during site grading activities to
observe and document site conditions.
☐ No, explain rationale:
Click or tap here to enter text.
Soil Sample Collection
☒ Yes, describe the sampling method (e.g., in-situ grab, composite, stockpile, etc.):
If human sensory observations or PID field screening suggest impacts grab samples will be
collected for characterization purposes.
☐ No, explain rationale:
Click or tap here to enter text.
Click or tap here to enter text.
11
EMP Version 2, June 2018
If soil samples are collected for analysis, please check the applicable chemical analytes:
☒ Volatile organic compounds (VOCs) by EPA Method 8260
☒ Semi-volatile organic compounds (SVOCs) by EPA Method 8270
☒ Metals RCRA List (8) (arsenic, barium, cadmium, chromium, mercury, lead, selenium
and silver): Specify Analytical Method Number(s): EPA Method 6010 for silver EPA Method 6020 for arsenic, barium, cadmium, chromium, lead, and selenium EPA Method 7471 for Mercury
☐ Pesticides: Specify Analytical Method Number(s): Click or tap here to enter text.
☐ PCBs: Specify Analytical Method Number(s): Click or tap here to enter text.
☒ Other Constituents & Respective Analytical Method(s) (i.e. Hexavalent Chromium, Herbicides, etc.): Specify Analytical Method Number(s): Hexavalent chromium by EPA Method 7199
☒ Check to confirm that stockpiling of known or suspected impacted soils will be conducted
in accordance with Figure 1 of this EMP. Stockpile methodology should provide erosion
control, prohibiting contact between surface water/precipitation and contaminated soil,
and preventing contaminated runoff. Explain any variances or provide additional details as
needed:
☒ Final grade sampling of exposed native soil (i.e., soil that will not be under buildings or
permanent hardscape). Select chemical analyses for final grade samples with check boxes
below (Check all that apply):
☒ Volatile organic compounds (VOCs) by EPA Method 8260
☒ Semi-volatile organic compounds (SVOCs) by EPA Method 8270
☒ Metals RCRA List (8) (arsenic, barium, cadmium, chromium, mercury, lead, selenium and silver): Specify Analytical Method Number(s): Silver by EPA Method 6010; arsenic, barium, cadmium, chromium lead, & selenium by 6020 EPA Method; and mercury by EPA Method 7471
☐ Pesticides: Specify Analytical Method Number(s): Click or tap here to enter text.
☐ PCBs: Specify Analytical Method Number(s): Click or tap here to enter text.
☒ Other Constituents & Respective Analytical Method(s) (i.e. Hexavalent Chromium, Herbicides, etc.):
Click or tap here to enter text.
12
EMP Version 2, June 2018
Hexavalent chromium by EPA Method 7199
Please provide a scope of work for final grade sampling, including a diagram of soil
sampling locations, number of samples to be collected, and brief sampling methodology.
Samples should be collected from 0-2 ft below ground surface, with the exception of VOCs
which should be taken from 1-2 ft below ground surface. Alternatively, a work plan for
final grade sampling may be submitted under separate cover.
It is expected that the approximately 60 to 70 percent of the site will be covered by
buildings or hardscaping. Areas which are not buildings or hardscaping and are not covered
by a minimum of 2 feet of documented clean fill will be sampled. A separate work plan will
be prepared to address these area.
☐ If final grade sampling was NOT selected please explain rationale:
Click or tap here to enter text.
Part 1.B. IMPORTED FILL SOIL
NO SOIL MAY BE BROUGHT ONTO THE BROWNFIELDS PROPERTY WITHOUT PRIOR APPROVAL
FROM THE BROWNFIELDS PROGRAM. According to the Brownfields IR 15, “Documenting
imported soil (by sampling, analysis, and reporting in accordance with review and written
approval in advance by the Brownfields Program), will safeguard the liability protections provided by the brownfields agreement and is in the best interest of the prospective developer/property
owner.”
Requirements for importing fill:
1) Will fill soil be imported to the site?................................................ ☒ Yes ☐ No ☐ Unknown
2) If yes, what is the estimated volume of fill soil to be imported?
2500 cubic yards
3) If yes, what is the anticipated depth that fill soil will be placed at the property? (If a range
of depths, please list the range.)
0 to 7 feet
4) Provide the source of fill, including: location, site history, nearby environmental concerns,
etc. Attach aerial photos, maps, historic Sanborn maps and a borrow source site history:
Soils imported to the site will be pre-approved by the NCBP Project Manager. We anticipate the
soils coming from Martin Marietta Quarry on Beatties Ford Road.
5) PRIOR TO ITS PLACEMENT AT THE BROWNFIELDS PROPERTY, provide a plan to analyze fill
soil to demonstrate that it meets acceptable standards applicable to the site and can be
approved for use at the Brownfields property.
Unless the imported soil comes from a source which has been pre-approved by the NCBP,
13
EMP Version 2, June 2018
Composite samples will be collected from each 1,000 cubic yards and analyzed for SVOCs, RCRA
Metals, and hexavalent chromium as described below. A single grab sample will be collected for
each 1,000 cubic yards and will be analyzed for VOCs as described below:
6) Please check the applicable chemical analytes for fill soil samples. (Check all that apply):
☒ Volatile organic compounds (VOCs) by EPA Method 8260
☒ Semi-volatile organic compounds (SVOCs) by EPA Method 8270
☒ Metals RCRA List (8) (arsenic, barium, cadmium, chromium, mercury, lead, selenium and silver): Specify Analytical Method Number(s): Silver by EPA Method 6010; arsenic, barium, cadmium, chromium lead, & selenium by 6020 EPA Method; and mercury by EPA Method 7471
☐ Pesticides: Specify Analytical Method Number(s): Click or tap here to enter text.
☐ PCBs: Specify Analytical Method Number(s): Click or tap here to enter text.
☒ Other Constituents & Respective Analytical Method(s) (i.e. Hexavalent Chromium, Herbicides, etc.): Hexavalent chromium by EPA Method 7199
7) The scope of work for import fill sampling may be provided below or in a Work Plan
submitted separately for DEQ review and approval. Attach specific location maps for in-situ
borrow sites. If using a quarry, provide information on the type of material to be brought
onto the Brownfields Property.
If imported fill is needed, it will be obtained from Martin Marietta Quarry of Beatties Ford Road in
Charlotte, or another source which has been pre-approved by the Brownfields Program. The
Brownfields Program will be notified before fill is imported to the site.
Part 1.C. EXPORTED SOIL
NO SOIL MAY LEAVE THE BROWNFIELDS PROPERTY WITHOUT APPROVAL FROM THE
BROWNFIELDS PROGRAM. FAILURE TO OBTAIN APPROVAL MAY VIOLATE A BROWNFIELDS
AGREEMENT CAUSING A REOPENER OR JEOPARDIZING ELIGIBILITY IN THE PROGRAM,
ENDANGERING LIABILITY PROTECTIONS AND MAKING SAID ACTION POSSIBLY SUBJECT TO
ENFORCEMENT. JUSTIFICATIONS PROVIDED BELOW MUST BE APPROVED BY THE PROGRAM IN
WRITING PRIOR TO COMPLETING TRANSPORT ACTIVITIES. Please refer to Brownfields IR 15 for
additional details.
1) If export from a Brownfields Property is anticipated, please provide details regarding the
proposed export actions. Volume of exported soil, depths, location from which soil will
be excavated on site, related sampling results, etc. Provide a site map with locations of
export and sampling results included.
Excavated soil will be used to the extent reasonably possible on the site. However, some of this
14
EMP Version 2, June 2018
excavated soil may not be suitable for reuse due to geotechnical properties and will be exported
form the site. Approximately 11,630 cubic yards of soil are expected to be exported. It is
anticipated that exported soil will be transported to a Subtitle D Landfill or another Brownfields
Site (with approval of the Brownfields Program). If soil is taken to Subtitle D Landfill samples will
be collected and analyzed per the requirement of that landfill. If soil is taken to another
Brownfields Site, samples will be collected and analyzed per the requirement of the Brownfields
Program. The locations where exported soil will be transported is to be determined at a later
time and the NCBP will be notified in advance.
If soil is to be exported to another Brownfields site, samples will be collected to characterize the
exported soil. These samples will be collected either from stockpiles of soils to exported or situ
and in either case, samples will be collected to represent each 1,000 cubic yards of soil to be
exported. Sampling will be performed at a frequency of 1 composite sample for SVOCs and
RCRA metals (comprised of 3-5 grab samples) per 1,000 cubic yards of material. One grab
sample per composite should be selected based on field observations/PID screening for VOC
analysis. A work plan will be submitted to NCBP for each such sampling event.
2) To what type of facility will the export Brownfields soil be sent?
☒ Subtitle D/Municipal Solid Waste Landfill (analytical program to be determined by landfill)
☐ Permitted but Unlined Landfill (i.e. LCID, C&D, etc.) Analytical program to be
determined by the accepting Landfill;
☐ Landfarm or other treatment facility
☒ Use as fill at another suitable Brownfields Property – determination that a
site is suitable will require, at a minimum, that similar concentrations of the same or
similar contaminants already exist at both sites, use of impacted soil will not increase
the potential for risk to human health and the environment at the receiving Brownfields
property, and that a record of the acceptance of such soil from the property owner of
the receiving site is provided to Brownfields. Please provide additional details below.
☐ Use as Beneficial Fill off-site at a non-Brownfields Property - Please provide
documentation of approval from the property owner for receipt of fill material. This will
also require approval by the DEQ Solid Waste Section. Additional information is
provided in IR 15. Please provide additional details below.
3) Additional Details: (if transfer of soil to another property is requested above, please provide
details related to the proposed plans).
It is anticipated that exported soil will be transported to a Subtitle D Landfill or another
Brownfields Site (with approval of the Brownfields Program).
Part 1.D. MANAGEMENT OF UTILITY TRENCHES
☐ Install liner between native impacted soils and base of utility trench before filling with clean fill
15
EMP Version 2, June 2018
(Preferred)
☒ Last out, first in principle for impacted soils (if soil can safely be reused onsite and is not a
hazardous waste), i.e., impacted soils are placed back at approximately the depths they
were removed from such that impacted soil is not placed at a greater depth than the original
depth from which it was excavated.
☐ Evaluate whether necessary to install barriers in conduits to prevent soil vapor transport,
and/or degradation of conduit materials due to direct impact with contaminants?
☐ If yes, provide specifications on barrier materials:
Click or tap here to enter text.
☐ If no, include rationale here:
Click or tap here to enter text.
Other comments regarding managing impacted soil in utility trenches:
Click or tap here to enter text.
PART 2. GROUNDWATER – Please fill out the information below.
1) What is the depth to groundwater at the Brownfields Property?
Approximately 5 feet bgs in northern portions of site to approximately 20 feet bgs in the
southern portions of the site.
2) Is groundwater known to be contaminated by ☐onsite ☐offsite ☐both or ☒unknown
sources? Describe source(s):
There is evidence of chlorinated- and petroleum related compounds in groundwater in samples
collected at onsite samples points and at offsite sample points including upgradient offsite
sample points. It is not completely clear if groundwater contamination on the subject
Brownfields site originated from offsite sources, onsite sources, or both based upon available
data.
3) What is the direction of groundwater flow at the Brownfields Property?
Northwesterly
4) Will groundwater likely be encountered during planned redevelopment activities?
☐Yes ☒No
If yes, describe these activities:
Click or tap here to enter text. Regardless of the answer; in the event that contaminated groundwater is encountered during redevelopment activities (even if no is checked above), list activities for contingent management of groundwater (e.g., dewatering of groundwater from excavations or foundations, containerizing, offsite disposal, discharge to sanitary sewer, NPDES permit, or sampling procedures).
16
EMP Version 2, June 2018
In the event that groundwater is encountered, it would likely be limited to relatively small
quantities and deep utilities. If encountered, water would be displaced in the excavation and/or
pumped into a tanker truck, frac tank or other container approved by the ECS. Sampling and
analysis would be conducted as needed to characterize the water for disposal purposes based
on the requirements of the disposal facility
5) Are monitoring wells currently present on the Brownfields Property?.................☒Yes ☐No
If yes, are any monitoring wells routinely monitored through DEQ or other
agencies?..................................................................................................................☐Yes ☒No
6) Please check methods to be utilized in the management of known and previously
unidentified wells.
☒ Abandonment of site monitoring wells in accordance with all applicable regulations. It
is the Brownfields Program’s intent to allow proper abandonment of well(s) as
specified in the Brownfields Agreement, except if required for active monitoring
through another section of DEQ or the EPA.
☐ Location of existing monitoring wells marked
☐ Existing monitoring wells protected from disturbance
☐ Newly identified monitoring wells will be marked and protected from further
disturbance until notification to DEQ Brownfields can be made and approval for
abandonment is given.
7) Please provide additional details as needed:
Please note, disturbance of existing site monitoring wells without approval by DEQ is not
permissible. If monitoring wells are damaged and/or destroyed, DEQ may require that the PD
be responsible for replacement of the well.
PART 3. SURFACE WATER -Please fill out the information below.
1) Is surface water present at the property? ☐ Yes ☒ No
2) Attach a map showing the location of surface water at the Brownfields Property.
3) Is surface water at the property known to be contaminated? ☐ Yes ☒ No
4) Will workers or the public be in contact with surface water during planned redevelopment
activities? ☐ Yes ☒ No
5) In the event that contaminated surface water is encountered during redevelopment
activities, or clean surface water enters open excavations, list activities for management of
such events (e.g. flooding, contaminated surface water run-off, stormwater impacts):
In the event that contaminated surface water is encountered during redevelopment activities, or
clean surface water enters open excavations, it will be allowed to infiltrate into the ground
Monitoring wells will be abandoned before grading operations begin.
17
EMP Version 2, June 2018
and/or containerized and managed in accordance with local, state, and federal regulations.
PART 4. SEDIMENT – Please fill out the information below.
1) Are sediment sources present on the property? ☐ Yes ☒ No
2) If yes, is sediment at the property known to be contaminated: ☐ Yes ☒ No
3) Will workers or the public be in contact with sediment during planned redevelopment
activities? ☐ Yes ☒ No
4) Attach a map showing location of known contaminated sediment at the property.
5) In the event that contaminated sediment is encountered during redevelopment activities, list
activities for management of such events (stream bed disturbance):
Not Applicable
PART 5. SOIL VAPOR – Please fill out the information below.
1) Do concentrations of volatile organic compounds at the Brownfields property exceed the following vapor intrusion screening levels (current version) in the following media:
IHSB Residential Screening Levels:
Soil Vapor:………..☒ Yes ☐ No ☐ Unknown
Groundwater:.….☐ Yes ☒ No ☐ Unknown
IHSB Industrial/Commercial Screening Levels:
Soil Vapor:………..☒ Yes ☐ No ☐ Unknown
Groundwater:…..☒ Yes ☐ No ☐ Unknown
2) Attach a map showing the locations of soil vapor contaminants that exceed site
screening levels.
3) If applicable, at what depth(s) is soil vapor known to be contaminated?
4) Will workers encounter contaminated soil vapor during planned redevelopment activities?
☐ Yes ☐ No ☒ Unknown
5) In the event that contaminated soil vapor is encountered during redevelopment activities
(trenches, manways, basements or other subsurface work,) list activities for management
of such contact:
The contractor will be instructed that before workers may enter enclosed subsurface areas
where vapors may accumulate, ECS needs to be contacted to perform an evaluation of such
5 feet
18
EMP Version 2, June 2018
areas. ECS will utilize a PID or similar instrument to evaluate the presence/absence of such
vapors and relative concentrations if present. If an evaluation of such an area occurs in the
northwestern portion of the site near soil gas sample point SG-7, ECS will collect a gas sample
using sorbent tubes for mercury vapor analysis. Workers will not be permitted in these areas
until vapor concentrations are determined to be below appropriate risk levels or engineering
controls are in place (e.g., fans to reduce vapor concentrations).
PART 6. SUB-SLAB SOIL VAPOR – Please fill out the information below if existing buildings or
foundations will be retained in the redevelopment.
1) Are sub-slab soil vapor data available for the Brownfields Property? ☐ Yes ☒ No ☐ Unknown
2) If data indicate that sub-slab soil vapor concentrations exceed screening levels, attach a map
showing the location of these exceedances.
3) At what depth(s) is sub-slab soil vapor known to be contaminated? ☐0-6 inches ☐Other, please
describe:
Not Applicable
4) Will workers encounter contaminated sub-slab soil vapor during planned redevelopment
activities? ☐ Yes ☐ No ☒ Unknown
5) In the event that contaminated soil vapor is encountered during redevelopment activities, list
activities for management of such contact
The contractor will be instructed that when existing building slabs are removed, ECS needs to be
contacted to perform an evaluation of such areas. ECS will utilize a PID or similar instrument to
evaluate the presence/absence of such vapors and relative concentration, if present. Workers
will not be permitted in these areas until vapor concentrations are determined to be below
appropriate risk levels or engineering controls are in place (e.g., fans to reduce vapor
concentrations).
PART 7. INDOOR AIR – Please fill out the information below.
1) Are indoor air data available for the Brownfields Property? ☐ Yes ☒ No ☐ Unknown
2) Attach a map showing the location(s) where indoor air contaminants exceed site screening levels.
3) If the structures where indoor air has been documented to exceed risk-based screening levels will
not be demolished as part of redevelopment activities, will workers encounter contaminated
indoor air during planned redevelopment activities? ☐ Yes ☐ No ☐ Unknown
4) In the event that contaminated indoor air is encountered during redevelopment activities, list
activities for management of such contact:
Existing buildings will be demolished and this item is not applicable.
19
EMP Version 2, June 2018
VAPOR INTRUSION MITIGATION SYSTEM – Please fill out the information below.
Is a vapor intrusion mitigation system (VIMS) proposed for this Brownfields Property?
☒ Yes ☐ No ☐ Unknown
If yes, ☐ VIMS Plan Attached or ☒ VIMS Plan to be submitted separately
If submitted separately provide date:
A VIMS plan is expected to be submitted in February 2020. VIMS Plan shall be signed and sealed by a NC Professional Engineer If no, please provide a brief rationale as to why no vapor mitigation plan is warranted:
Click or tap here to enter text.
CONTINGENCY PLAN – encountering unknown tanks, drums, or other waste materials
In this section please provide actions that will be taken to identify or manage unknown
potential new sources of contamination. During redevelopment activities, it is not uncommon
that unknown tanks, drums, fuel lines, landfills, or other waste materials are encountered.
Notification to DEQ Brownfields Project Manager, UST Section, Fire Department, and/or other
officials, as necessary and appropriate, is required when new potential source(s) of
contamination are discovered. These Notification Requirements were outlined on Page 1 of this
EMP.
Should potentially impacted materials be identified that are inconsistent with known site
impacts, the DEQ Brownfields Project Manager will be notified and a sampling plan will be
prepared based on the EMP requirements and site-specific factors. Samples will generally be
collected to document the location of the potential impacts.
Check the following chemical analysis that are to be conducted on newly identified releases:
☒ Volatile organic compounds (VOCs) by EPA Method 8260
☒ Semi-volatile organic compounds (SVOCs) by EPA Method 8270
☒ Metals RCRA List (8) (arsenic, barium, cadmium, chromium, mercury, lead, selenium and
silver)
Silver by EPA Method 6010; arsenic, barium, cadmium, chromium, lead, & selenium by
6020 EPA Method; and mercury by EPA Method 7471
☐ Pesticides: Specify Analytical Method Number(s):
Click or tap here to enter text.
20
EMP Version 2, June 2018
☐ PCBs: Specify Analytical Method Number(s):
Click or tap here to enter text.
☒ Other Constituents & Analytical Method(s) (i.e. Hexavalent Chromium, Herbicides, etc.)
Please note, if field observations indicate the need for additional analyses, they should
be conducted, even if not listed here.
Hexavalent chromium by EPA Method 7199
Please provide details on the proposed methods of managing the following commonly
encountered issues during redevelopment of Brownfields Properties.
Click or tap here to enter text.
Underground Storage Tanks:
If encountered, the contents of the UST will be evaluated, and based on the contents; the UST will
be removed or closed in place. Brownfield Project Manager approval will be obtained before
closing in place. If UST is removed, soil samples will be collected (one per 10 feet length of UST)
from the base of the UST excavation and submitted for laboratory analysis of VOCs, SVOCS, and
RCRA Metals
Sub-Grade Feature/Pit:
If encountered, the contents of the pit and the pit itself will be removed. Soil samples will be
collected from the base of the pit excavation and submitted for laboratory analysis of VOCs, SVOCS,
RCRA Metals, and hexavalent chromium.
Buried Waste Material:
If encountered, the waste will be removed, characterized, and disposed of off-site. Soil samples will
be collected from the base and side-walls (one for every 10 feet of base/side-wall) of the excavated
material and submitted for laboratory analysis of VOCs, SVOCs, RCRA Metals, and hexavalent
chromium.
Re-Use of Impacted Soils On-Site:
If impacted soil is re-used on site, it will be covered with hardscaping or with a minimum of 2 feet of
clean fill.
If unknown, impacted soil is identified on-site, management on-site can be considered after the
project team provides the necessary information, outlined in Part 1.A. Item 11, for Brownfields
Project Manager approval prior to final placement on-site.
If other potential contingency plans are pertinent, please provide other details or scenarios as
needed below:
Concrete produced during demolition which is unstained will be transported to a Construction and
Debris landfill for disposal. Concrete produced during demolition which is stained will be
transported to a Subtitle D landfill for disposal.
21
EMP Version 2, June 2018
POST-REDEVELOPMENT REPORTING
☒ Check this box to acknowledge that a Redevelopment Summary Report will be required for the
project. If the project duration is longer than one year, an annual update is required and will be
due by January 31 of each year, or 30 days after each one-year anniversary of the effective date of
this EMP (as agreed upon with the Project Manager). These reports will be required for as long as
physical redevelopment of the Brownfields Property continues, except that the final
Redevelopment Summary Report will be submitted within 90 days after completion of
redevelopment. Based on the estimated construction schedule, the first Redevelopment Summary
Report is anticipated to be submitted on 1/31/2021
The Redevelopment Summary Report shall include environment-related activities since the last
report, with a summary and drawings, that describes:
1. actions taken on the Brownfields Property;
2. soil grading and cut and fill actions;
3. methodology(ies) employed for field screening, sampling and laboratory analysis of
environmental media;
4. stockpiling, containerizing, decontaminating, treating, handling, laboratory analysis and
ultimate disposition of any soil, groundwater or other materials suspected or confirmed
to be contaminated with regulated substances; and
5. removal of any contaminated soil, water or other contaminated materials (for example,
concrete, demolition debris) from the Brownfields Property (copies of all legally required
manifests shall be included).
☒ Check box to acknowledge consent to provide a NC licensed P.G. or P.E. sealed, Redevelopment
Summary Report in compliance with the site’s Brownfields Agreement.
23
EMP Version 2, June 2018
APPENDIX A
-0.0690.0750.001
0.639
0.626
0.270
0.108
5.622
7.097
6.6186.0826.6276.7922.245-1.770-1.630-1.341-1.308-0.6041.4242.309-0.373-0.0400.068
0.017
1.922
2.481
2.855
3.316
5.019
5.907
6.371
3.950
1.647
1.229
0.716
0.7902.3293.1184.0960.594-2.272-0.895-0.575-1.515-0.6710.6711.881-0.4280.427-0.001
-1.442
-1.447
-0.567
0.431
1.262
3.605
5.074
6.459
4.917
2.643
2.959
3.464
3.5984.1914.2735.2140.039-3.496-3.546-2.821-2.790-1.2760.7292.410-1.3440.419-0.001
-1.250
0.225
2.178
2.918
3.404
5.091
5.964
6.732
4.246
2.195
2.210
2.516
2.4403.1413.4283.986-1.031-3.974-4.219-3.793-3.754-2.278-0.4471.794-1.4110.2580.002
-0.849
0.807
2.358
2.836
3.113
4.480
5.258
5.879
3.334
1.769
2.213
2.061
2.0892.8022.9393.041-1.984-4.117-4.796-4.555-4.300-2.709-0.6401.705-2.472-0.2230.007
-0.354
-0.273
1.955
2.269
2.787
4.123
4.561
5.208
2.353
1.553
1.105
1.949
1.9982.6002.7512.851-2.091-3.307-5.253-5.279-4.671-3.066-1.4340.995-2.3910.2190.062-0.012
-0.151
-1.220
1.499
2.098
2.502
3.345
3.795
4.386
1.805
1.863
0.501
1.554
2.1032.2952.3551.829-2.318-2.660-4.851-4.752-5.064-4.085-3.085-1.617-0.7150.2500.0890.000
-0.285
0.034
1.456
1.773
1.874
2.523
2.426
2.109
2.113
2.086
2.294
2.660
2.584
1.5280.574-0.508-1.635-2.743-3.863-4.865-5.660-5.729-4.567-3.594-2.156-0.5800.0680.000
-0.899
-2.816
0.671
1.281
1.548
1.523
1.215
0.529
0.779
0.923
1.385
1.568
1.490
0.585-0.473-1.511-2.503-3.501-4.562-5.520-6.456-6.705-5.852-4.424-2.705-1.0880.0130.002
-1.464
-2.746
1.090
1.716
1.092
0.019
0.029
0.697
1.086
1.370
1.912
1.408
1.024
0.226-0.864-1.904-2.940-3.912-4.375-5.092-6.120-6.997-6.110-4.756-2.854-1.416-0.136-0.032
-2.279
-3.105
1.570
1.472
0.923
0.688
0.810
1.893
2.782
3.561
3.296
2.737
2.019
0.966-0.016-0.827-1.765-2.489-3.103-3.877-6.017-6.031-4.788-2.166-1.034-1.6620.094
-3.279
-0.271
0.551
1.252
1.466
2.161
1.914
3.007
5.157
5.331
3.500
3.247
2.636
0.4370.351-0.414-1.228-1.716-2.459-2.764-5.768-5.503-2.839-1.096-0.466-1.2510.045
-4.541
-0.272
0.273
0.507
2.610
3.429
2.988
3.454
5.546
3.644
3.337
2.446
2.085
0.6000.220-0.060-0.924-2.059-2.200-2.705-4.347-4.165-2.321-0.6210.126-0.689-0.371
-2.322
-2.978
-0.472
-0.372
1.072
2.903
3.720
2.050
1.167
3.509
3.365
2.344
2.135
1.501
0.6590.177-0.487-1.293-1.862-2.138-2.453-2.836-2.7763.990-0.648-0.021-0.7380.089-0.014
-1.137
-4.748
-1.020
-0.357
0.376
1.473
2.535
2.143
0.626
-0.216
2.752
2.444
2.000
1.615
1.180
0.8560.232-0.289-0.755-1.183-1.553-1.899-1.997-2.0060.6890.0550.692-0.125-0.331-0.121
-0.639
-2.810
-4.378
-1.074
0.201
0.826
0.999
0.488
0.178
-0.008
0.157
1.562
2.645
2.116
1.430
0.581
0.7821.1171.1900.692-0.386-1.356-1.510-1.668-1.493-1.188-1.012-0.694-0.627-0.174-0.117
0.392
-1.457
-4.196
-1.307
-0.427
-0.186
0.671
0.322
0.123
-0.113
0.298
0.098
0.112
2.365
2.355
1.568
0.596
0.5921.4281.1691.5880.606-0.680-1.129-1.426-2.522-2.966-3.065-2.017-0.848-0.363-0.140
1.837
-0.876
-2.034
-2.593
-0.171
0.767
0.392
0.529
1.033
-0.080
0.344
0.110
-0.195
0.408
1.435
1.991
1.613
0.984
0.8881.3302.0711.6940.355-0.869-1.493-1.960-2.525-3.521-3.605-2.858-1.107-0.649-0.013
3.175
0.390
-1.159
-4.118
-0.129
0.659
0.568
0.271
0.574
0.448
0.730
0.666
-0.090
0.179
1.020
1.132
1.746
1.590
1.042
1.2981.2991.6770.816-0.541-1.333-1.593-1.589-1.985-3.585-3.677-3.240-0.961-0.663-0.062
0.666
-1.925
-1.693
0.317
0.306
0.397
-0.116
0.232
0.964
2.824
2.708
-0.884
0.8170.6090.4570.510-0.988-1.652-1.563-1.411-1.494-3.645-3.692-3.216-0.904-0.3270.030
-1.727
-0.060
0.193
-0.133
-0.067
0.057
0.860
2.642
3.485
4.493
-0.237
-0.677-0.684-0.684-2.097-1.861-2.552-1.053-0.507-0.077
-2.035
-0.125
0.033
0.424
1.218
1.970
3.023
3.984
5.427
-0.4270.139-0.063
-3.125
0.299
1.352
2.805
3.183
3.759
5.130
0.088
2.475
3.773
4.193
5.402
2.759
4.483
5.397
Elevations TableNumber12345678910Minimum Elevation-8.000-6.000-4.000-2.0000.0002.0004.0006.0008.00010.000Maximum Elevation-6.000-4.000-2.0000.0002.0004.0006.0008.00010.00012.000Color1/8/2020 4:48 PM JFLEHAN N:\_2018\1018435\CAD\EXHIBITS\2020-01-06 - TREMONT - CUT FILL ANALYSIS.DWGPN1018435 | 2019.09.09 | ARDENT PROPERTIES527 W TREMONT AVE TOWNS ▪ CHARLOTTE, NC ▪ EARTHWORK ANALYSISSCALE:1"=30'15'30'45'75'0
APPENDIX B
FIGURE 3
SAMPLE LOCATION MAP
511 and 527 West Tremont Avenue
Charlotte, Mecklenburg County, North Carolina
ECS Project Number 49:4913-A
SOURCE:
GOOGLE EARTH, DATED 2017
SCALE:
1-inch = ~ 90 feet
APPROXIMATE GROUNDWATER SAMPLE LOCATION
APPROXIMATE SITE BOUNDARY
LEGEND
1’90’45’
APPROXIMATE SOIL SAMPLE LOCATION
APPROXIMATE SOIL GAS SAMPLE LOCATION
SB-1/TW-DRY
SB-2
SB-3/TW-1/SG-1
SB-4/TW-2/SG-2
SB-6/SG-3/TW-DRY
SB-5
SB-7/SG-4/TW-DRY
SB-8/SG-5/TW-DRY
IMPACTED GEOTECHNICAL BORING
B-2
B-4
B-8
B-9 B-10
From Draft Report of Environmental Assessment dated October 24, 2017
APPENDIX C
EXISTING
BUILDING
EXISTING
BUILDING
GROUNDWATER SAMPLE LOCATIONS
APPROXIMATE LOCATION OF MONITORING WELLS
SEE ATTACHED TABLES FOR SUMMARY OF ANALYTICAL RESULTS
MW-1
APPROXIMATE LOCATION OF GEOPROBE GROUNDWATER
SAMPLE POINT
MW-5
MW-1
MW-2
MW-3
MW-4 TW-2
TW-1
SUBSECTION B FOR COMPOSITE SOIL SAMPLE
EXISTING
BUILDING
EXISTING
BUILDING
SUBSECTION A FOR COMPOSITE SOIL SAMPLE
SUBSECTION C FOR COMPOSITE SOIL SAMPLE
SUBSECTION D FOR COMPOSITE SOIL SAMPLE
SUBSECTION E FOR COMPOSITE SOIL SAMPLE
B
A
E
D
C
AREAS REPRESENTED BY
COMPOSITE SOIL SAMPLES
SEE ATTACHED TABLES FOR SUMMARY OF ANALYTICAL RESULTS
EXISTING
BUILDING
EXISTING
BUILDING
VOC SOIL SAMPLE LOCATIONS
APPROXIMATE LOCATION OF VOC SOIL SAMPLE
SEE ATTACHED TABLES FOR SUMMARY OF ANALYTICAL RESULTS
B-2
B-1
A-3
A-2
E-3
D-4
E-5
D-1
C-2
C-3
C-2
EXISTING
BUILDING
EXISTING
BUILDING
SOIL GAS SAMPLE LOCATIONS
SG-4
SG-2
SG-1
SG-8
SG-7SG-5
SG-6
SG-5
APPROXIMATE LOCATION OF SOIL GAS SAMPLE
SEE ATTACHED TABLES FOR SUMMARY OF ANALYTICAL RESULTS
APPENDIX D
TABLE 1: SUMMARY OF SOIL ANALYTICAL RESULTSWEST TREMONT AVENUE511 AND 627 WEST TREMONT AVENUECHARLOTTE, MECKLENBURG COUNTY, NORTH CAROLINAECS PROJECT NO. 49-4913-AParameterCOMPARISION CRITERIASample ID SB-1 SB-2SB-3SB-4SB-5SB-6SB-7SB-8Collection Depth (feet bgs) 2-4 3-5 1-3 2-4 3-5 8-100-20-2Collection DateDiesel Range Organics by XRFGROBRL2.3BRL1.98.5BRLBRL1.150Gasoline Range Organics by XRFDRO0.63.299.14.819.83.9389.613.1100Notes:Results presented in milligrams per kilogram (mg/kg), analogous to parts per million (ppm)Feet bgs = Feet below ground surfaceAction Level = North Carolina Department of Environmental Quality Action Levels for total petroleum hydrocarbonsBold denotes concentration exceeds the North Carolina Action Level Action LevelANALYTICAL RESULTS9/21/17
TABLE 2: SUMMARY OF GROUNDWATER ANALYTICAL RESULTS
WEST TREMONT AVENUE
511 AND 627 WEST TREMONT AVENUE
CHARLOTTE, MECKLENBURG COUNTY, NORTH CAROLINA
ECS PROJECT NO. 49-4913-A
Parameter
Sample ID TW-1 TW-2
Collection Date
Semi-Volatile Organic Compounds by 625
Fluoranthene 3.6 J BRL 300 300
Docosene 27 BRL NE NE
Hexadecanoic acid 11 230 NE NE
Cyclic octaatomic sulfer BRL 120 NE NE
Eicosanol BRL 29 NE NE
Volatile Organic Compounds by SM6200B
1,2,4-Trimethylbenzene BRL 3.6 400 28,500
1,3,5-Trimethylbenzene BRL 0.92 400 25,000
m,p-Xylenes BRL 0.85 J 500 85,500
Methyl-tert-Butyl Ether BRL 4.5 20 20,000
Naphthalene BRL 0.72 J 6 6,000
Xylenes, total BRL 0.85 J 500 85,500
Notes:
Results presented in micrograms per liter (ug/L), analogous to parts per billion (ppb)
NC2LGWQS = North Carolina Department of Environmental Quality 2L Groundwater Quality Standards
GCL= Gross Contamination Levels
BRL = below the laboratory reporting limit
J = Estimated Concentration
FROM DRAFT REPORT OF ENVIRONEMNTAL ASSESSMENT DATED OCTOBER 24, 2017
COMPARISION CRITERIA
NC2LGWQS
(ug/L)
NC GCL
(ug/L)
ANALYTICAL RESULTS
9/21/17
TABLE 3: SUMMARY OF SOIL GAS ANALYTICAL RESULTS
WEST TREMONT AVENUE
511 AND 627 WEST TREMONT AVENUE
CHARLOTTE, MECKLENBURG COUNTY, NORTH CAROLINA
ECS PROJECT NO. 49-4913-A
Parameter
Sample ID SG-1 SG-2 SG-3 SG-4 SG-5
Collection Date
Chloromethane 7.1 18 91 59 8.0 626 7,880
Vinyl Chloride BRL 4.5 17 9.7 BRL 76.8 2,790
Chloroethane BRL BRL 9.9 11 BRL 69,500 876,000
Tertiary-butyl alcohol (TBA)7.1 72 21 27 19 NE NE
Carbon Disulfide 25 81 14 16 BRL 4,870 61,300
Methyl tertiary-butyl ether (MTBE)7.8 5,300 BRL BRL BRL 3,600 47,200
2-Butanone (MEK)57 93 43 31 BRL 34,800 438,000
cis-1,2-Dichloroethene BRL 8.6 BRL BRL BRL NE NE
Diisopropyl ether (DIPE)BRL 140 BRL BRL BRL 4,870 61,300
Ethyl tert-butyl ether (ETBE)BRL 15 BRL BRL BRL NE NE
1,2-Dichloroethane (DCA)BRL 4.7 BRL BRL BRL 36 472
Benzene 23 90 54 61 16 120 1,570
Tertiary amyl methyl ether (TAME)BRL 1,300 BRL BRL BRL NE NE
4-methyl-1-2-pentanone (MIBK)BRL 21 BRL 62 BRL 20,900 263,000
Toluene 54 89 47 BRL 24 34,800 438,000
2-Hexanone (MBK)BRL BRL BRL 12 BRL 209 2,630
Tetrachloroethene BRL BRL BRL 7.2 13 278 3,500
Ethylbenzene 7.7 260 22 16 BRL 374 4,910
m,p-Xylenes 19 880 18 26 BRL 695 8,760
Styrene 4.4 8.8 28 16 BRL 6,950 87,600
o-Xylenes 11 130 8.2 21 BRL 695 8,760
4-Ethyltoluene BRL 130 BRL BRL BRL NE NE
1,3,5-Trimethylbenzene BRL 130 BRL 70 BRL NE NE
1,2,4-Trimethylbenzene 7.3 340 12 50 7.3 48.7 613
Notes:
Comparison Criteria = North Carolina DWM Soil Gas Screening Level (SGSL) from IHSB Levels
DWM Vapor Intrusion Screening dated October 2016.
Results presented in micrograms per cubic meter (ug/m3)
NE = No Established Standard
BRL = below the laboratory reporting limit
Residential
SGSL
Non-Residential
SGSL
Target Volatile Organic Compounds by TO-15
COMPARISON CRITERIAANALYTICAL RESULTS
9/21/17