Loading...
HomeMy WebLinkAbout23053 Former Cotton Seed Oil Mill EMP 20200110 Environmental Management Plan Former Cotton Seed Oil Mill Brownfields Project ID: 23053-19-060 300 Rampart Street Charlotte, North Carolina January 10, 2020 H&H Job No. JMC-009 #C-1269 Engineering #C-245 Geology CONTENTS Completed EMP Form Tables Table 1 Summary of Groundwater Analytical Results Table 2 Summary of Soil Analytical Results Table 3 Summary of Sub-Slab Vapor and Soil Gas Analytical Results Table 4 Summary of DEQ Risk Assessment Results for Sub-Slab Vapor and Soil Gas Figures Figure 1 Site Location Map Figure 2 Sample Location Map Appendices Appendix A Site Plans – Phase I Development Appendix B Construction Schedule 1 EMP Version 2, June 2018 NORTH CAROLINA BROWNFIELDS PROGRAM ENVIRONMENTAL MANAGEMENT PLAN This form is to be used to prepare an Environmental Management Plan (EMP) for projects in the North Carolina Brownfields Program at the direction of a Brownfields project manager. The EMP is a typical requirement of a Brownfields Agreement (BFA). Its purpose is to clarify actions to be taken during the demolition and construction at Brownfields properties in an effort to avoid delays in the event of the discovery of new contamination sources or other environmental conditions. The EMP provides a means to document redevelopment plans and environmental data for each applicable environmental medium to inform regulatory-compliant decision-making at the site. As much detail as possible should be included in the EMP, including contingency planning for unknowns. Consult your project manager if you have questions. Prospective Developers and/or their consultants must complete and submit this form and all pertinent attachments, see checklist below, to their Brownfields project manager prior to any earthmoving or other development-related activities that have the potential to disturb soil at the Brownfields Property, including demolition. For the resultant EMP to be valid for use, it must be completed, reviewed by the program, signed by all parties working on the project, and approved by the Brownfields project manager. Failure to comply with the requirements of the EMP could jeopardize project eligibility, or in the event of a completed agreement, be cause for a reopener So that the EMP provides value in protecting brownfields eligibility and public health, the preparer shall ensure that the following steps have been completed prior to submitting the EMP for review. Any EMP prepared without completing these steps is premature. ☒ Site sampling and assessment that meets Brownfields’ objectives is complete and has been reviewed and approved by the Brownfields Project Manager. ☒ Specific redevelopment plans, even if conceptual, have been developed for the project, submitted and reviewed by the Brownfields Project Manager. 2 EMP Version 2, June 2018 Please submit, along with the completed EMP form, the following attachments, as relevant and applicable to the proposed redevelopment: ☒ A set of redevelopment plans, including architectural/engineering plans, if available; if not conceptual plans may suffice if updated when detailed plans are drafted. ☐ A figure overlaying redevelopment plans on a map of the extent of contamination for each media. ☒ Site grading plans that include a cut and fill analysis. ☐ A figure showing the proposed location and depth of impacted soil that would remain on site after construction grading. ☐ Any necessary permits for redevelopment (i.e. demolition, etc.). ☒ A detailed construction schedule that includes timing and phases of construction. ☒ Tabulated data summaries for each impacted media (i.e. soil, groundwater, soil gas, etc.) applicable to the proposed redevelopment. ☒ Figures with the sampling locations and contamination extents for each impacted media applicable to the proposed redevelopment. ☐ A full final grade sampling and analysis plan, if the redevelopment plan is final. ☒ If known, information about each proposed potential borrow soil source, such as aerial photos, historic site maps, historic Sanborn maps, a site history, necessary for brownfields approval. ☒ Information and, analytical data if required, for quarries, or other borrow sources, detailing the type of material proposed for importation to the Brownfields Property. ☒ A work plan for the sampling and analysis of soil to be brought onto the Brownfields Property. Refer to Issue Resolution 15 in Brownfields Program Guidelines. ☐ A map of the Brownfields Property showing the location of soils proposed for export and sampling data from those areas. ☐ If a Vapor Mitigation System is required by the Brownfields Program, the Vapor Intrusion Mitigation System (VIMS) plan will be signed and sealed by a NC Professional Engineer. The VIMS Plan may also be submitted under separate cover. 3 EMP Version 2, June 2018 GENERAL INFORMATION Date: 1/10/2020 Revision Date (if applicable): Brownfields Assigned Project Name: Cotton Seed Oil Mill Brownfields Project Number: 23053-19-060 Brownfields Property Address: 300 Rampart Street Charlotte, North Carolina Brownfields Property Area (acres): The Site consists of one approximate 2.4-acre parcel. Is Brownfields Property Subject to RCRA Permit?.......................☐ Yes ☒ No If yes enter Permit No.: Click or tap here to enter text. Is Brownfields Property Subject to a Solid Waste Permit….……..☐ Yes ☒ No If yes, enter Permit No.: Click or tap here to enter text. COMMUNICATIONS A copy of this EMP shall be distributed to all the parties below as well as any contractors or site workers that may be exposed to site vapors, soil, groundwater, and/or surface water. Additionally, a copy of the EMP shall be maintained at the Brownfields Property during redevelopment activities. NOTE, THE EMP DOES NOT TAKE THE PLACE OF A SITE-SPECIFIC HEALTH AND SAFETY PLAN. Prospective Developer (PD): 300 Rampart Owner, LLC Contact Person: Chris Deppoliti Phone Numbers: Office: (347)573-0657 Mobile: Email: cdeppoliti@jmcholdingsllc.com Contractor for PD: To be determined Contact Person: Phone Numbers: Office: Mobile: Email: Environmental Consultant: Hart & Hickman, PC Contact Person: Matt Bramblett Phone Numbers: Office: (704) 887-4620 Mobile: Email: Mbramblett@harthickman.com Brownfields Program Project Manager: William Schmithorst Phone Numbers: Office: (919) 707-8159 Mobile: Email: William.Schmithorst@ncdenr.gov Other DEQ Program Contacts (if applicable, i.e., UST Section, Inactive Hazardous Site Branch, 4 EMP Version 2, June 2018 Hazardous Waste, Solid Waste): David Mattison, NC DEQ VCC Project Manager (919) 707-8336 NOTIFICATIONS TO THE BROWNFIELDS PROGRAM Written advance Notification Times to Brownfields Project Manager: Check each box to accept minimum advance notice periods (in calendar days) for each type of onsite task: On-site assessment or remedial activities:……………………………………….…… 10 days Prior ☒ Construction or grading start:……………………………………….………………………. 10 days Prior ☒ Discovery of stained soil, odors, USTs, buried drums or waste, landfill, or other signs of previously unknown contamination: ……………………………….……………………………………. Within 48 hours ☒ Implementation of emergency actions (e.g. dewatering, flood or soil erosion control measures in area of contamination, ventilation of work zones):…………….……….……… Within 48 hours ☒ Installation of mitigation systems:………………………….………………….……….. 10 days Prior ☒ Other notifications as required by local, state or federal agencies to implement redevelopment activities: (as applicable): ……………………….…………………………………………..… Within 30 days ☒ REDEVELOPMENT PLANS 1) Type of Redevelopment (check all that apply): ☒Residential ☒Recreational ☐Institutional ☒Commercial ☒Office ☒Retail ☐Industrial ☒Other specify: The Site is planned to be redeveloped in multiple phases. The current phase of construction (identified as Phase 1) involves adaptive reuse of the central and eastern warehouse buildings for commercial office and retail use. During Phase 1 of redevelopment, partial demolition of the western warehouse building (building slab to remain in-place) will occur for additional parking space. Future phases of construction may include the potential future vertical build-out for multi- occupant residential development. A preliminary Site Plan for Phase 1 is included in Appendix A. 2) Check the following activities that will be conducted prior to commencing earth-moving activities at the site: ☒ Review of historic maps (Sanborn Maps, facility maps) ☒ Conducting geophysical surveys to evaluate the location of suspect UST, fuel lines, utility lines, etc. ☐ Interviews with employees/former employees/facility managers/neighbors 5 EMP Version 2, June 2018 3)Summary of Redevelopment Plans (MANDATORY: attach detailed plans or conceptual plans, if detailed plans are not available. EMP review without such information would be premature): Provide brief summary of redevelopment plans, including demolition, removal of building slabs/pavement, grading plans and planned construction of new structures: Current redevelopment plans include the partial demolition of the approximate 14,600-square foot (sq ft) western warehouse building and an approximate 550-sq ft built-out addition to the eastern portion of the eastern warehouse building. The western warehouse building walls will be demolished to 4 ft above finished floor. The current building slab in this area will remain and will be utilized for parking. A ramp will be constructed to access this parking area from Rampart Street. Additionally, rip rap will be removed from the rear of the building and this area will be paved with asphalt and a newly installed ramp to access the new parking area from the rear. A 16 ft wide sidewalk with tree pits will be installed from the existing edge of the pavement along Rampart Street inward towards the building. Existing asphalt between the sidewalk and front of the building will be removed. According to the preliminary grading plans, a balanced Site is expected with a potential of approximately 332 cubic yards of soil to be stockpiled or reused on-Site. A preliminary Site plan which includes current and proposed grades is included as Appendix A. 4)Do plans include demolition of structure(s)?: ☒Yes ☐ No ☐ Unknown ☒If yes, please check here to confirm that demolition will be conducted in accordance with applicable legal requirements, including without limitation those related to lead and asbestos abatement that are administered by the Health Hazards Control Unit within the Division of Public Health of the North Carolina Department of Health and Human Services. If available, please provide a copy of your demolition permit. 5)Are sediment and erosion control measures required by federal, state, or local regulations? ☒Yes ☐ No ☐ Unknown ☒If yes, please check here to confirm that demolition will be conducted in accordance with applicable legal requirements. If soil disturbance is necessary to install sediment and erosion control measures, they may not begin until this EMP is approved. 6)Which category of risk-based screening level is used or is anticipated to be specified in the Brownfields Agreement? Note: If children frequent the property, residential screening levels shall be cited in the Brownfields Agreement for comparison purposes. ☒ Residential ☒ Non-Residential or Industrial/Commercial 7)Schedule for Redevelopment (attach construction schedule): a)Construction start date: 1/16/2020 b)Anticipated duration (specify activities during each phase): 6 EMP Version 2, June 2018 Demolition of interior partitions are anticipated to begin in January 2020. Additional demolition activities and the installation of sediment and erosion control measures are anticipated to begin on June 9, 2020, followed structural repairs and sub-grade utility installation (July 2020), roof and window installation and mechanical, electrical, and plumbing trim out (August 2020), grading, sitework, and painting (September 2020), landscaping (October 2020), and inspections (November 2020). Note that these construction milestones are subject to change. c) Additional phases planned? ☐ Yes ☐ No If yes, specify the start date and/or activities if known: Start Date: To be determined Planned Activity: A 2nd development phase with vertical development is anticipated for the Site (identified as Phase 2). Construction plans for Phase 2 have not been developed. Start Date: Click or tap to enter a date. Planned Activity: Click or tap here to enter text. Start Date: Click or tap to enter a date. Planned Activity: Click or tap here to enter text. d) Provide the planned date of occupancy for new buildings: 12/3/2020 CONTAMINATED MEDIA 1) Contaminated Media on the Brownfields Property Part 1. Soil:……………………………………….……………. ☒ Yes ☐ No ☐ Suspected Part 2. Groundwater:.……………………….……..……. ☐ Yes ☒ No ☐ Suspected Part 3. Surface Water:.……………...……..…………… ☐ Yes ☒ No ☐ Suspected Part 4. Sediment:.……………...……..…………………… ☐ Yes ☒ No ☐ Suspected Part 5. Soil Vapor:…..…………...……..…………………. ☐ Yes ☒ No ☐ Suspected Part 6. Sub-Slab Soil Vapor:……...……..…………….. ☐ Yes ☒ No ☐ Suspected Part 7. Indoor Air:...……..…………………………………. ☐ Yes ☒ No ☐ Suspected 2) For the Area of Proposed Redevelopment on the Brownfields Property, attach tabulated data summaries for each impacted media and figure(s) with sample locations. 7 EMP Version 2, June 2018 PART 1. Soil – Please fill out the information below, using detailed site plans, if available, or estimate using known areas of contaminated soil and a conceptual redevelopment plan. Provide a figure overlaying new construction onto figure showing contaminated soil and groundwater locations. 1) Known or suspected contaminants in soil (list general groups of contaminants): H&H completed Phase I and II ESA activities at the Site in September 2019. The results of Phase I and II ESA indicate that a portion of the Site was historically occupied by a portion of the former Virginia Carolina Chemical (VCC), Charlotte Facility. This facility formerly operated as a phosphate fertilizer plant from at least the 1890s until the 1930s. Soil at the Site is impacted with elevated levels of arsenic and lead as a result of the former activities, and ExxonMobil is identified as the responsible party for the cleanup. ExxonMobil has removed source area soils from feasible locations on the Site to Site-Specific Target Levels for arsenic (27 mg/kg) and lead (270 mg/kg), but impacts remain under the building and near building foundations. A brief summary of the Phase II ESA soil assessment results is provided below: VOCs Analytical results indicate that no VOCs were detected in the soil samples at concentrations exceeding DEQ Inactive Hazardous Sites Branch (IHSB) Residential or Industrial/Commercial Preliminary Soil Remediation Goals (PSRGs). SVOCs Analytical results indicate that no SVOCs were detected in the soil samples at concentrations exceeding DEQ IHSB Residential or Industrial/Commercial PSRGs. Metals The results of the metals analyses indicate that elevated levels of arsenic (up to 156 milligrams per kilogram – mg/kg) are present in the western portion of the Site at concentrations exceeding NC DEQ Residential and Industrial/Commercial PSRGs. Additionally, potentially elevated levels of chromium and hexavalent chromium were detected in soil samples collected beneath the building slab. Hexavalent chromium was detected in several shallow soil samples at concentrations exceeding Residential PSRGs, but below Industrial/Commercial PSRGs. Laboratory analytical results of the soil samples collected at the Site during previous assessment activities are summarized in Table 2. Sample locations are presented on Figure 2. 2) Depth of known or suspected contaminants (feet): Arsenic was detected above PSRGs at depths ranging from zero to 7 ft bgs in the western portion of the Site. Potentially elevated levels of hexavalent chromium were detected above PSRGs at depths ranging from zero to 7 ft bgs in the western portion of the Site and at depths ranging from zero to 2 ft bgs in the central and eastern portions of the Site. 3) Area of soil disturbed by redevelopment (square feet): 8 EMP Version 2, June 2018 Approximately 30,000 sq ft is estimated to be disturbed during Phase 1 of Site redevelopment. Grading activities will be conducted in accordance with applicable local, state, and federal regulations. The grading contractor will utilize grading equipment (i.e., backhoes, front end loaders, bull dozers, etc.) and will implement best management practices (i.e., installation of silt fencing) to manage soil on-Site during Site redevelopment activities. During Phase 2 of Site redevelopment, the entire Site would be expected to be disturbed. 4) Depths of soil to be excavated (feet): Soil in the southwestern portion of the Site will be excavated to depths up to 4 ft bgs. Soils in additional areas of the Site will generally be excavated to shallow depths (up to 2 ft bgs) for the installation of utility trenches or for grading purposes. Additional soil disturbance areas will be generally shallow due to removal of asphalt or concrete. Significant changes to Site grade are not anticipated. 5) Estimated volume of soil (cubic yards) to be excavated (attach grading plan): N/A – A balanced Site is anticipated. 6) Estimated volume of excavated soil (cubic yards) anticipated to be impacted by contaminants: N/A 7) Estimated volume of contaminated soil expected to be disposed of offsite, if applicable: No soil is planned to be disposed off-Site at this time. Rip rap will be removed from the northern portion of the Site. Efforts will be made to remove rip rap while maintaining underlying soil in- place. Should soil or buried debris need to be exported from the Brownfields property during redevelopment, a sampling plan will be developed and submitted to DEQ Brownfields for review and approval once the volume of soil for export is known. Part 1.A. MANAGING ONSITE SOIL If soil is anticipated to be excavated from the Brownfield Property, relocated on the Brownfields Property, or otherwise disturbed during site grading or other redevelopment activities, please provide a grading plan that clearly illustrates areas of cut and fill (approximate areas & volumes are acceptable, if only preliminary data available). 1) HAZARDOUS WASTE DETERMINATION: a) Does the soil contain a LISTED WASTE as defined in the North Carolina Hazardous Waste Section under 40 CFR Part 261.31-261.35?....................................... ☐Yes ☒No ☐ If yes, explain why below, including the level of knowledge regarding processes generating the waste (include pertinent analytical results as needed). ☐ If yes, do the soils exceed the “Contained-Out” levels in Attachment 1 of the 9 EMP Version 2, June 2018 North Carolina Contained-In Policy?................................................. ☐ Yes ☐ No b) NOTE: IF SOIL MEETS THE DEFINITION OF A LISTED HAZARDOUS WASTE AND EXCEEDS THE CONTAINED-OUT LEVELS IN ATTACHMENT 1 TO THE NORTH CAROLINA CONTAINED-IN POLICY THE SOIL MAY NOT BE RE-USED ON SITE AND MUST BE DISPOSED OF IN ACCORDANCE WITH DEQ HAZARDOUS WASTE SECTION RULES AND REGULATIONS. c) Does the soil contain a CHARACTERISTIC WASTE?.................................... ☐ Yes ☒ No ☐ If yes, mark reason(s) why below (and include pertinent analytical results). ☐ Ignitability Click or tap here to enter text. ☐ Corrosivity Click or tap here to enter text. ☐ Reactivity Click or tap here to enter text. ☐ Toxicity Click or tap here to enter text. ☒ TCLP results ☐ Rule of 20 results (20 times total analytical results for an individual hazardous constituent on TCLP list cannot, by test method, exceed regulatory TCLP standard) Click or tap here to enter text. ☒ If no, explain rationale: Soil analytical data does not indicate exceedances of TCLP criteria based on soil analytical data collected during previous Phase II ESA activities. TCLP analytical results are provided in Table 2. d) NOTE: IF SOIL MEETS THE DEFINITION OF A CHARACTERISTIC HAZARDOUS WASTE, THE SOIL MAY NOT BE RE-USED ON SITE AND MUST BE DISPOSED OF IN ACCORDANCE WITH DEQ HAZARDOUS WASTE SECTION RULES AND REGULATIONS. 2) Screening criteria by which soil disposition decisions will be made (e.g., left in place, capped in place with low permeability barrier, removed to onsite location and capped, removed offsite): ☒ Preliminary Health-Based Residential SRGs ☐ Preliminary Health-Based Industrial/Commercial SRGs ☒ Division of Waste Management Risk Calculator (For Brownfields Properties Only) ☐ Site-specific risk-based cleanup level. Please provide details of methods used for determination/explanation. Click or tap here to enter text. Additional comments: Click or tap here to enter text. 10 EMP Version 2, June 2018 3) If known impacted soil is proposed to be reused within the Brownfields Property Boundary, please check the measures that will be utilized to ensure safe placement and documentation of same. Please attach a proposed location diagram/site map. ☒ Provide documentation of analytical report(s) to Brownfields Project Manager ☒ Provide documentation of final location, thickness and depth of relocated soil on site map to Brownfields Project Manager once known ☐ Geotextile to mark depth of fill material. Provide description of material: Click or tap here to enter text. ☒ Manage soil under impervious cap ☒ or clean fill ☒ ☒ Describe cap or fill: Should potentially impacted soil or fill materials be encountered during redevelopment that do not require removal for geotechnical or construction purposes and meets the definition of beneficial fill as outlined in the Beneficial Fill rule (15A NCAC 13B.0562), the potentially impacted soil or fill materials may be placed beneath impervious surfaces (asphalt pavement, sidewalks, access roads, buildings, etc.) or a minimum of 2 ft of clean fill. ☒ Confer with NC BF Project Manager if Brownfield Plat must be revised (or re-recorded if actions are Post-Recordation). ☒ GPS the location and provide site map with final location. ☐ Other. Please provide a description of the measure: 4) Please describe the following action(s) to be taken during and following excavation and management of site soils: Management of fugitive dust from site ☒ Yes, describe the method will include: The grading contractor will consider conditions such as wind speed, wind direction, and moisture content of soil during soil grading and stockpiling activities to minimize dust generation. In the unlikely event that contaminated soil is encountered during Site redevelopment that requires excavation, particular attention will be paid by contractors to implement dust control measures as needed based on Site and atmospheric conditions (i.e. by controlled water application, hydro-seeding, and/or mulch, stone, or plastic cover). Potentially impacted soil will be managed as described below. ☐ No, explain rationale: Click or tap here to enter text. Field Screening of site soil Click or tap here to enter text. 11 EMP Version 2, June 2018 ☒ Yes, describe the field screening method, frequency of field screening, person conducting field screening: During soil disturbance at the Site, the workers or contractors will observe soils for evidence of potential significantly impacted soil. Evidence of potential significantly impacted soil includes a distinct unnatural color, strong odor, or filled or previously disposed materials of concerns (i.e. chemicals, tanks, drums, etc.). Should the above be noted during sitework, the contractor will contact the environmental professional to observe the suspect condition. If the environmental professional confirms that the material may be impacted, then the procedures below will be implemented. In addition, the environmental professional will contact the DEQ Brownfields project manager within two business days to advise that person of the condition. ☐ No, explain rationale: Soil Sample Collection ☐ Yes, describe the sampling method (e.g., in-situ grab, composite, stockpile, etc.): Click or tap here to enter text. ☒ No, explain rationale: Collection of additional soil samples is not anticipated based on results of previous Site assessment activities and the fact that this is a balanced Site. Beneficial fill, if any, will be tested prior to placement at the Site. If significant soil impact is encountered during grading and/or installation or removal of utilities, excavation will proceed only as far as needed to allow grading and/or construction of the utility to continue and/or only as far as needed to allow alternate corrective measures described below. Suspect significantly impacted soil or other buried fill materials excavated during grading and/or utility line installation or removal may be stockpiled and covered in a secure area to allow construction to progress. Suspect significantly impacted soil or other buried fill materials will be underlain by and covered with minimum 10-mil plastic sheeting. At least one representative sample of the soil will be collected per 1,000 cubic yards of material for analysis of total VOCs, SVOCs, and RCRA metals plus hexavalent chromium. If the results of analysis of the sample indicate that the soil could potentially exceed toxicity characteristic hazardous waste criteria, then the soil will also be analyzed by TCLP for those compounds that could exceed the toxicity characteristic hazardous waste criteria. Impacted soil will be handled in the manner described below based upon the laboratory analyses: i. If no organic compounds are detected in a sample (other than which are attributable to sampling or laboratory artifacts) and metals are below Residential PSRGs or are 12 EMP Version 2, June 2018 consistent with Site-specific background levels, then the soil will be deemed suitable for use as on-Site fill or as off-Site fill. The proposed location(s) for off-Site placement of soil (other than a permitted facility) along with the receiving facility’s written approval for acceptance of the soil will be provided to DEQ for approval prior to taking the soil off-Site. ii. If detectable levels of compounds are found which do not exceed the Residential PSRGs (other than which are attributable to sampling or laboratory artifacts or which are consistent with background levels for metals) and the TCLP concentrations are below hazardous waste criteria, then the soil may be used on-Site as fill without conditions. iii. If detectable levels of compounds are found which exceed the Residential PSRGs (other than which are attributable to sampling or laboratory artifacts or which are consistent with background levels for metals) and the TCLP concentrations are below hazardous waste criteria, then the soil, with DEQ’s written approval, may be used on-Site as fill below an impervious surface (i.e. parking lot or building foundation), or at least 2 ft of compacted clean soil. If the impacted soil with concentrations above Residential PSRGs is moved to an on-Site location, its location and depth will be documented, and its location will be provided to DEQ in an updated survey plat. iv. Impacted soil may be transported to a permitted facility such as a landfill provided that the soil is accepted at the disposal facility. If soil is transported to a permitted facility, the permitted facility’s written approval to dispose of soil from the Site will be included with the final EMP report. In the unlikely event that the sample data indicate concentrations above TCLP hazardous waste criteria, then the soil must be transported off-Site to a permitted disposal facility that can accept or treat hazardous waste. If soil samples are collected for analysis, please check the applicable chemical analytes: ☒ Volatile organic compounds (VOCs) by EPA Method 8260 ☒ Semi-volatile organic compounds (SVOCs) by EPA Method 8270 ☒ Metals RCRA List (8) (arsenic, barium, cadmium, chromium, mercury, lead, selenium and silver): Specify Analytical Method Number(s): EPA Methods 6020/7471 ☐ Pesticides: Specify Analytical Method Number(s): Click or tap here to enter text. ☐ PCBs: Specify Analytical Method Number(s): Click or tap here to enter text. ☒ Other Constituents & Respective Analytical Method(s) (i.e. Hexavalent Chromium, Herbicides, etc.): Specify Analytical Method Number(s): Hexavalent chromium by EPA Method 7196 (assuming appropriate method detection limits can be met by the laboratory) or 7199 ☒ Check to confirm that stockpiling of known or suspected impacted soils will be conducted in accordance with Figure 1 of this EMP. Stockpile methodology should provide erosion 13 EMP Version 2, June 2018 control, prohibiting contact between surface water/precipitation and contaminated soil, and preventing contaminated runoff. Explain any variances or provide additional details as needed: ☒ Final grade sampling of exposed native soil (i.e., soil that will not be under buildings or permanent hardscape). Select chemical analyses for final grade samples with check boxes below (Check all that apply): ☒ Volatile organic compounds (VOCs) by EPA Method 8260 ☒ Semi-volatile organic compounds (SVOCs) by EPA Method 8270 ☒ Metals RCRA List (8) (arsenic, barium, cadmium, chromium, mercury, lead, selenium and silver): Specify Analytical Method Number(s): EPA Methods 6020/7471 ☐ Pesticides: Specify Analytical Method Number(s): Click or tap here to enter text. ☐ PCBs: Specify Analytical Method Number(s): Click or tap here to enter text. ☒ Other Constituents & Respective Analytical Method(s) (i.e. Hexavalent Chromium, Herbicides, etc.): Hexavalent chromium by EPA Method 7199 Please provide a scope of work for final grade sampling, including a diagram of soil sampling locations, number of samples to be collected, and brief sampling methodology. Samples should be collected from 0-2 ft below ground surface, with the exception of VOCs which should be taken from 1-2 ft below ground surface. Alternatively, a work plan for final grade sampling may be submitted under separate cover. Following completion of soil disturbance for any future Site development (i.e. after grading and utility construction), an environmental professional will be contracted to assess the Site for areas that are not covered with a minimum of 2 ft of clean fill soil or topsoil from a landscaping company, building foundations, sidewalks, or asphalt or concrete parking areas, driveways or other impervious surfaces. If such areas exist, a Work Plan will be prepared for final grade sampling for DEQ review and approval. If no such areas exist, documentation will be provided to DEQ. ☐ If final grade sampling was NOT selected please explain rationale: Click or tap here to enter text. Part 1.B. IMPORTED FILL SOIL 14 EMP Version 2, June 2018 NO SOIL MAY BE BROUGHT ONTO THE BROWNFIELDS PROPERTY WITHOUT PRIOR APPROVAL FROM THE BROWNFIELDS PROGRAM. According to the Brownfields IR 15, “Documenting imported soil (by sampling, analysis, and reporting in accordance with review and written approval in advance by the Brownfields Program), will safeguard the liability protections provided by the brownfields agreement and is in the best interest of the prospective developer/property owner.” Requirements for importing fill: 1) Will fill soil be imported to the site?................................................ ☐ Yes ☒ No ☐ Unknown 2) If yes, what is the estimated volume of fill soil to be imported? Based on preliminary grading plans, fill soil will not need to be imported to the Site. However, the PD may import limited amounts of organic rich topsoil from a commercial landscape material vendor for use in proposed landscaped areas. 3) If yes, what is the anticipated depth that fill soil will be placed at the property? (If a range of depths, please list the range.) 4) Provide the source of fill, including: location, site history, nearby environmental concerns, etc. Attach aerial photos, maps, historic Sanborn maps and a borrow source site history: As noted above, fill soil is not anticipated to be imported to the Site. However, if future activities indicate the need for fill, the procedures outlined below will be followed. 5) PRIOR TO ITS PLACEMENT AT THE BROWNFIELDS PROPERTY, provide a plan to analyze fill soil to demonstrate that it meets acceptable standards applicable to the site and can be approved for use at the Brownfields property. To demonstrate that imported soil (if required) is suitable for use at this property, the fill soil will be sampled and approved by DEQ Brownfields prior to being brought to the Site. A sampling plan will be developed and submitted for DEQ Brownfields review under separate cover. DEQ approval of the sampling plan and analytical results is required prior to bringing soil on Site. Soil will be considered suitable for use at the Site if it does not contain compound concentrations above Residential PSRGs or background levels for metals. 6) Please check the applicable chemical analytes for fill soil samples. (Check all that apply): ☒ Volatile organic compounds (VOCs) by EPA Method 8260 ☒ Semi-volatile organic compounds (SVOCs) by EPA Method 8270 ☒ Metals RCRA List (8) (arsenic, barium, cadmium, chromium, mercury, lead, selenium and silver): Specify Analytical Method Number(s): EPA Methods 6020/7471 ☐ Pesticides: Specify Analytical Method Number(s): Click or tap here to enter text. 15 EMP Version 2, June 2018 ☐ PCBs: Specify Analytical Method Number(s): ☒ Other Constituents & Respective Analytical Method(s) (i.e. Hexavalent Chromium, Herbicides, etc.): Hexavalent chromium by EPA Method 7199 7) The scope of work for import fill sampling may be provided below or in a Work Plan submitted separately for DEQ review and approval. Attach specific location maps for in-situ borrow sites. If using a quarry, provide information on the type of material to be brought onto the Brownfields Property. Based on preliminary grading plans, import fill will not be required at the Site. However, if future activities indicate the need for import fill, the PD will follow the procedures outlined below. If the PD plans to import fill material from the Vulcan Materials Company quarry located near Pineville, NC or from the Martin Marietta quarry located on Beatties Ford Road in Charlotte, NC, and given that the material is virgin cut soil from said quarry, no samples of the import material will be collected. Adequate analytical data are available in the DEQ Brownfields database to demonstrate material from these facilities is suitable for use as fill at a Brownfields property. If fill soil is obtained from an off-Site property that is not a known permitted quarry, a sampling plan will be developed and submitted for DEQ review. DEQ approval of the sampling plan and analytical results will be obtained prior to transporting import soil to the Site. The specific sampling rate will be outlined in the aforementioned sampling plan. However, if the proposed borrow source has not been previously developed (i.e., virgin land), soil samples will be collected for laboratory analyses indicated above at a general rate of one per 1,000 cubic yards. If the borrow source property has been previously developed, soil samples will be collected for laboratory analyses indicated above at a general rate of approximately one per 500 cubic yards. Fill soil will be considered suitable for use at the Site if it does not contain compound concentrations above DEQ IHSB Residential PSRGs or typical metals concentrations which are consistent with background levels. The PD does not plan to collect samples of landscaping materials prior to placement at the Site. Part 1.C. EXPORTED SOIL NO SOIL MAY LEAVE THE BROWNFIELDS PROPERTY WITHOUT APPROVAL FROM THE BROWNFIELDS PROGRAM. FAILURE TO OBTAIN APPROVAL MAY VIOLATE A BROWNFIELDS AGREEMENT CAUSING A REOPENER OR JEOPARDIZING ELIGIBILITY IN THE PROGRAM, ENDANGERING LIABILITY PROTECTIONS AND MAKING SAID ACTION POSSIBLY SUBJECT TO ENFORCEMENT. JUSTIFICATIONS PROVIDED BELOW MUST BE APPROVED BY THE PROGRAM IN WRITING PRIOR TO COMPLETING TRANSPORT ACTIVITIES. Please refer to Brownfields IR 15 for additional details. 1) If export from a Brownfields Property is anticipated, please provide details regarding the 16 EMP Version 2, June 2018 proposed export actions. Volume of exported soil, depths, location from which soil will be excavated on site, related sampling results, etc. Provide a site map with locations of export and sampling results included. Based on review of the proposed grading plan, export soil is not anticipated at this time. Should soil need to be exported from the Brownfields property during redevelopment, a sampling plan will be developed and submitted to DEQ Brownfields for review and approval once the volume of soil for export is known. Generally, soil samples will be collected from export soil at a rate of 1 sample per every 500 cubic yards of export. DEQ approval of the sampling plan and analytical results will be obtained prior to transporting export soil from the Site. Based on analytical results of soil samples collected from the export soil, the soil will be transported off-Site to a suitable location. The PD will notify DEQ Brownfields of the location receiving the export soil. If not a permitted facility, DEQ Brownfields approval and written approval from the receiving facility will be obtained prior to transporting the soil off-Site. 2) To what type of facility will the export Brownfields soil be sent? ☒ Subtitle D/Municipal Solid Waste Landfill (analytical program to be determined by landfill) ☒ Permitted but Unlined Landfill (i.e. LCID, C&D, etc.) Analytical program to be determined by the accepting Landfill; ☒ Landfarm or other treatment facility ☒ Use as fill at another suitable Brownfields Property – determination that a site is suitable will require, at a minimum, that similar concentrations of the same or similar contaminants already exist at both sites, use of impacted soil will not increase the potential for risk to human health and the environment at the receiving Brownfields property, and that a record of the acceptance of such soil from the property owner of the receiving site is provided to Brownfields. Please provide additional details below. ☒ Use as Beneficial Fill off-site at a non-Brownfields Property - Please provide documentation of approval from the property owner for receipt of fill material. This will also require approval by the DEQ Solid Waste Section. Additional information is provided in IR 15. Please provide additional details below. 3) Additional Details: (if transfer of soil to another property is requested above, please provide details related to the proposed plans). The environmental professional will contact DEQ Brownfields to obtain DEQ Brownfields and DEQ Solid Waste approval prior to exporting soil off-Site. Part 1.D. MANAGEMENT OF UTILITY TRENCHES ☐ Install liner between native impacted soils and base of utility trench before filling with clean fill (Preferred) 17 EMP Version 2, June 2018 ☒ Last out, first in principle for impacted soils (if soil can safely be reused onsite and is not a hazardous waste), i.e., impacted soils are placed back at approximately the depths they were removed from such that impacted soil is not placed at a greater depth than the original depth from which it was excavated. ☒ Evaluate whether necessary to install barriers in conduits to prevent soil vapor transport, and/or degradation of conduit materials due to direct impact with contaminants? ☐ If yes, provide specifications on barrier materials: Click or tap here to enter text. ☒ If no, include rationale here: Results of risk calculators conducted for the Site did not indicate the presence of a vapor intrusion concern. Other comments regarding managing impacted soil in utility trenches: In the event contaminated soil and/or vapors are encountered in utility trenches during redevelopment activities, the trench will be evacuated, and appropriate safety screening of the vapors will be performed to protect workers. If results indicate further action is warranted in response to vapors to protect workers, appropriate engineering controls (such as use of industrial fans) will be implemented. The contractor and workers will observe soil for potential impacts during utility installation activities. Evidence of potential significant impacted soil includes a distinct unnatural color, strong odor, or filled or previously disposed materials of concerns (i.e. chemicals, tanks, drums, etc.). Should the above be noted during utility work, the contractor will contact the environmental professional to observe the suspect condition and screen the soil using a calibrated photo-ionization detector (PID) or similar vapor field screening instrument. If the environmental professional confirms that the material may be impacted, then the procedures outlined in Part 1.A. Managing On-Site Soil above will be implemented. In addition, the environmental professional will contact the DEQ Brownfields project manager within two business days to advise that person of the condition. PART 2. GROUNDWATER – Please fill out the information below. 1) What is the depth to groundwater at the Brownfields Property? During previous Phase II ESA activities conducted at the Site in August, 2019, depth to groundwater was identified to be between approximately 17 ft bgs in the southwestern portion of the Site and approximately 20 ft bgs in the northeastern portion of the Site. 2) Is groundwater known to be contaminated by ☐onsite ☐offsite ☐both or ☐unknown sources? Describe source(s): Previous groundwater assessment activities did not indicate the presence of VOCs, SVOCs, or metals in Site groundwater at concentrations above 2L Standards or the Residential and Non- 18 EMP Version 2, June 2018 Residential Vapor Intrusion Groundwater Screening Levels (GWSLs). Groundwater laboratory analytical results are summarized in Table 1. Groundwater sample locations are presented on Figure 2. 3) What is the direction of groundwater flow at the Brownfields Property? Groundwater in the northern portion of the Site is expected to generally flow to the west towards a tributary of Irwin Creek. 4) Will groundwater likely be encountered during planned redevelopment activities? ☐Yes ☒No If yes, describe these activities: Click or tap here to enter text. Regardless of the answer; in the event that contaminated groundwater is encountered during redevelopment activities (even if no is checked above), list activities for contingent management of groundwater (e.g., dewatering of groundwater from excavations or foundations, containerizing, offsite disposal, discharge to sanitary sewer, NPDES permit, or sampling procedures). Although not anticipated, if groundwater suspected to be impacted (based on strong odor, unnatural color, sheen, etc.) is encountered during Site work, the contractor will contact the environmental professional to observe the suspect condition. If the environmental professional determines that the excavation likely contains impacted groundwater, then appropriate worker safety measures will be undertaken to manage groundwater that gathers in an open excavation within an area determined to be impacted during construction activities. The accumulated water will be allowed to evaporate (if feasible), tested and disposed off-Site (if impacted), tested and discharged to the storm sewer (if not impacted above DEQ surface water standards) in accordance with applicable municipal and State regulations for erosion control and construction stormwater control, or used for dust control at the Site (with Brownfields prior approval). In addition, the environmental professional will contact the DEQ Brownfields project manager within 48 hours regarding the condition. 5) Are monitoring wells currently present on the Brownfields Property?.................☐Yes ☒No If yes, are any monitoring wells routinely monitored through DEQ or other agencies?..................................................................................................................☐Yes ☐No 6) Please check methods to be utilized in the management of known and previously unidentified wells. ☒ Abandonment of site monitoring wells in accordance with all applicable regulations. It is the Brownfields Program’s intent to allow proper abandonment of well(s) as specified in the Brownfields Agreement, except if required for active monitoring through another section of DEQ or the EPA. ☒ Location of existing monitoring wells marked ☒ Existing monitoring wells protected from disturbance ☒ Newly identified monitoring wells will be marked and protected from further 19 EMP Version 2, June 2018 disturbance until notification to DEQ Brownfields can be made and approval for abandonment is given. 7) Please provide additional details as needed: Please note, disturbance of existing site monitoring wells without approval by DEQ is not permissible. If monitoring wells are damaged and/or destroyed, DEQ may require that the PD be responsible for replacement of the well. PART 3. SURFACE WATER -Please fill out the information below. 1) Is surface water present at the property? ☐ Yes ☒ No 2) Attach a map showing the location of surface water at the Brownfields Property. 3) Is surface water at the property known to be contaminated? ☐ Yes ☒ No 4) Will workers or the public be in contact with surface water during planned redevelopment activities? ☐ Yes ☒ No 5) In the event that contaminated surface water is encountered during redevelopment activities, or clean surface water enters open excavations, list activities for management of such events (e.g. flooding, contaminated surface water run-off, stormwater impacts): As noted above, surface water is not present at the Site. PART 4. SEDIMENT – Please fill out the information below. 1) Are sediment sources present on the property? ☐ Yes ☒ No 2) If yes, is sediment at the property known to be contaminated: ☐ Yes ☒ No 3) Will workers or the public be in contact with sediment during planned redevelopment activities? ☐ Yes ☒ No 4) Attach a map showing location of known contaminated sediment at the property. 5) In the event that contaminated sediment is encountered during redevelopment activities, list activities for management of such events (stream bed disturbance): As noted above, sediment sources are not present on the Site property. No existing monitoring wells are present at the Site. 20 EMP Version 2, June 2018 PART 5. SOIL VAPOR – Please fill out the information below. 1) Do concentrations of volatile organic compounds at the Brownfields property exceed the following vapor intrusion screening levels (current version) in the following media: IHSB Residential Screening Levels: Soil Vapor:………..☐ Yes ☒ No ☐ Unknown Groundwater:.….☐ Yes ☒ No ☐ Unknown IHSB Industrial/Commercial Screening Levels: Soil Vapor:………..☐ Yes ☒ No ☐ Unknown Groundwater:…..☐ Yes ☒ No ☐ Unknown 2) Attach a map showing the locations of soil vapor contaminants that exceed site screening levels. 3) If applicable, at what depth(s) is soil vapor known to be contaminated? 4) Will workers encounter contaminated soil vapor during planned redevelopment activities? ☐ Yes ☒ No ☐ Unknown 5) In the event that contaminated soil vapor is encountered during redevelopment activities (trenches, manways, basements or other subsurface work,) list activities for management of such contact: As noted above, we do not anticipate workers will encounter contaminated soil vapor during planned redevelopment activities. However, the environmental professional will remain on call on an as-needed-basis during redevelopment activities at the Site. If contaminated soil vapors are suspected during redevelopment activities (based on unusual odors, headaches, dizziness, nausea, etc.), the excavation area will immediately be evacuated, and the environmental professional will be called to perform appropriate safety screening of the vapors. Safety screening activities include monitoring the worker breathing zone with a calibrated multi-gas monitor (or similar instrument[s] capable of detecting VOCs and combustible gases) for VOCs, methane, oxygen, carbon dioxide, and/or hydrogen sulfide photoionization detector. If results indicate further action is warranted, appropriate engineering controls (such as use of industrial fans) will be implemented. In addition, the environmental professional will contact the DEQ Brownfields project manager within 48 hours regarding the condition. As noted above, volatile organic compounds have not been detected at the Site at concentrations exceeding IHSB Residential or Industrial/Commercial Screening Levels. Sub-slab vapors were sampled twice during different times of the year. Sub-slab vapor and soil gas analytical results are provided in Table 3. Sub-slab vapor and soil gas sample locations are presented on Figure 2. 21 EMP Version 2, June 2018 PART 6. SUB-SLAB SOIL VAPOR – Please fill out the information below if existing buildings or foundations will be retained in the redevelopment. 1) Are sub-slab soil vapor data available for the Brownfields Property? ☒ Yes ☐ No ☐ Unknown 2) If data indicate that sub-slab soil vapor concentrations exceed screening levels, attach a map showing the location of these exceedances. 3) At what depth(s) is sub-slab soil vapor known to be contaminated? ☐0-6 inches ☐Other, please describe: Based on two prior assessment events, contaminated sub-slab vapor is not anticipated to be present at the Site. 4) Will workers encounter contaminated sub-slab soil vapor during planned redevelopment activities? ☐ Yes ☒ No ☐ Unknown 5) In the event that contaminated soil vapor is encountered during redevelopment activities, list activities for management of such contact Although contaminated sub-slab vapor is not anticipated to be present at the Site, in the event that contaminated soil vapors are encountered during future redevelopment activities, the area will be evacuated, and appropriate safety screening of the vapors will be performed. If results indicate further action is warranted, appropriate engineering controls (such as use of industrial fans) will be implemented. PART 7. INDOOR AIR – Please fill out the information below. 1) Are indoor air data available for the Brownfields Property? ☐ Yes ☒ No ☐ Unknown 2) Attach a map showing the location(s) where indoor air contaminants exceed site screening levels. 3) If the structures where indoor air has been documented to exceed risk-based screening levels will not be demolished as part of redevelopment activities, will workers encounter contaminated indoor air during planned redevelopment activities? ☐ Yes ☐ No ☒ Unknown 4) In the event that contaminated indoor air is encountered during redevelopment activities, list activities for management of such contact: Indoor air samples have not been collected at the Site. However, based on sub-slab vapor analytical results, contaminated indoor air is not anticipated to be present at the Site. In the unlikely event there is evidence of potential indoor air issues (i.e. unusual odors) during future redevelopment activities, the area will be evacuated, and appropriate safety screening of the indoor air will be performed. If warranted, safety screening procedures will include periodically screening indoor air for volatile organic vapors with a calibrated photoionization detector. If results indicate further action is warranted, appropriate engineering controls (i.e. use of industrial fans) will be implemented. 22 EMP Version 2, June 2018 VAPOR INTRUSION MITIGATION SYSTEM – Please fill out the information below. Is a vapor intrusion mitigation system (VIMS) proposed for this Brownfields Property? ☐ Yes ☒ No ☐ Unknown If yes, ☐ VIMS Plan Attached or ☐ VIMS Plan to be submitted separately If submitted separately provide date: A VIMS is not proposed for this Site. VIMS Plan shall be signed and sealed by a NC Professional Engineer If no, please provide a brief rationale as to why no vapor mitigation plan is warranted: H&H has conducted soil, groundwater, sub-slab vapor, and soil gas sampling at the Site. Results of risk calculators prepared for the Site do not indicate the presence of a vapor intrusion concern. CONTINGENCY PLAN – encountering unknown tanks, drums, or other waste materials In this section please provide actions that will be taken to identify or manage unknown potential new sources of contamination. During redevelopment activities, it is not uncommon that unknown tanks, drums, fuel lines, landfills, or other waste materials are encountered. Notification to DEQ Brownfields Project Manager, UST Section, Fire Department, and/or other officials, as necessary and appropriate, is required when new potential source(s) of contamination are discovered. These Notification Requirements were outlined on Page 1 of this EMP. Should potentially impacted materials be identified that are inconsistent with known site impacts, the DEQ Brownfields Project Manager will be notified and a sampling plan will be prepared based on the EMP requirements and site-specific factors. Samples will generally be collected to document the location of the potential impacts. Check the following chemical analysis that are to be conducted on newly identified releases: ☒ Volatile organic compounds (VOCs) by EPA Method 8260 ☒ Semi-volatile organic compounds (SVOCs) by EPA Method 8270 ☒ Metals RCRA List (8) (arsenic, barium, cadmium, chromium, mercury, lead, selenium and silver) EPA Methods 6020/7471 ☐ Pesticides: Specify Analytical Method Number(s): Click or tap here to enter text. 23 EMP Version 2, June 2018 ☐ PCBs: Specify Analytical Method Number(s): ☒ Other Constituents & Analytical Method(s) (i.e. Hexavalent Chromium, Herbicides, etc.) Please note, if field observations indicate the need for additional analyses, they should be conducted, even if not listed here. Hexavalent chromium by EPA Method 7199 Please provide details on the proposed methods of managing the following commonly encountered issues during redevelopment of Brownfields Properties. During construction activities, contractors may encounter unknown sub-surface environmental conditions (i.e. tanks, drums, or waste materials) that if encountered, will require proper management. Prior to beginning Site work, H&H will attend a pre-construction kick-off meeting with the PD and the redevelopment contractors to discuss the DEQ approved EMP and various scenarios when it would be appropriate and necessary to notify H&H of the discovery of unknown subsurface features or potentially impacted media at the Site. In the event that such conditions are encountered during Site redevelopment activities, the environmental actions noted below will be used to direct environmental actions to be taken during these activities and sampling data for potentially impacted soil and the disposition of impacted soil will be provided to DEQ when the data are available. Underground Storage Tanks: In the event a previously unidentified UST or impacts associated with a UST release are discovered at the Site during redevelopment activities, the UST and/or UST related impacts will be addressed through the Brownfields Program. However, UST removals will be conducted in general accordance with NC DEQ UST Section guidance. If the UST contains residual fluids, the fluids will be removed, sampled for VOCs, SVOCs, and RCRA metals, and transported off-Site for disposal at a suitable facility based on the laboratory analytical results. Impacted soil will be managed in accordance with Part 1.A. above. Sub-Grade Feature/Pit: If a sub-grade feature or pit is encountered and does not require removal for geotechnical or construction purposes, it will be filled with soil or suitable fill and construction will proceed. Where appropriate, the bottom may be penetrated before back filling to prevent fluid accumulation. If the pit has waste in it, the waste will be set aside in a secure area and will be sampled for waste disposal purposes for TCLP VOCs, SVOCs, and metals and disposed off-Site at a permitted facility or the waste will be managed in accordance with Part 1.A. above, whichever is most applicable based on the type of waste present. If the pit must be removed and the observed waste characteristics indicate the concrete may potentially be contaminated to a significant degree, the concrete will be sampled and analyzed by methods specified by the disposal facility. Buried Waste Material: If excavation activities result in removal of buried wastes, significantly impacted soils, or significantly 24 EMP Version 2, June 2018 impacted unconsolidated fill material (concrete, lime, bricks, etc.), the contractor will be directed to stop work at that location and notify the environmental professional. The environmental professional will review the soil/materials and collect samples if warranted. If the buried materials or soil do not require removal for geotechnical or construction purposes, meets the definition of beneficial fill as outlined in the Beneficial Fill rule (15A NCAC 13B.0562), and based on the sample results (as discussed in Part 1.A. above), they will remain in-place and construction will proceed. If the fill material is to be removed, confirmation sampling will be conducted at representative locations in the base and the sidewalls of the excavation after the waste or significantly impacted media is removed. The confirmation samples will be analyzed for VOCs, SVOCs, and RCRA metals plus hexavalent chromium. Areas of suspected contaminated soil that remain at the Site after excavation is complete above the Residential PSRGs will be managed pursuant to this plan and incorporated into the final Brownfields plat. Re-Use of Impacted Soils On-Site: Please refer to Part 1.A. above. If unknown, impacted soil is identified on-site, management on-site can be considered after the project team provides the necessary information, outlined in Part 1.A. Item 11, for Brownfields Project Manager approval prior to final placement on-site. If other potential contingency plans are pertinent, please provide other details or scenarios as needed below: POST-REDEVELOPMENT REPORTING ☒ Check this box to acknowledge that a Redevelopment Summary Report will be required for the project. If the project duration is longer than one year, an annual update is required and will be due by January 31 of each year, or 30 days after each one-year anniversary of the effective date of this EMP (as agreed upon with the Project Manager). These reports will be required for as long as physical redevelopment of the Brownfields Property continues, except that the final Redevelopment Summary Report will be submitted within 90 days after completion of redevelopment. Based on the estimated construction schedule, the first Redevelopment Summary Report is anticipated to be submitted on 1/31/2021 The Redevelopment Summary Report shall include environment-related activities since the last report, with a summary and drawings, that describes: 1. actions taken on the Brownfields Property; 25 EMP Version 2, June 2018 2. soil grading and cut and fill actions; 3. methodology(ies) employed for field screening, sampling and laboratory analysis of environmental media; 4. stockpiling, containerizing, decontaminating, treating, handling, laboratory analysis and ultimate disposition of any soil, groundwater or other materials suspected or confirmed to be contaminated with regulated substances; and 5. removal of any contaminated soil, water or other contaminated materials (for example, concrete, demolition debris) from the Brownfields Property (copies of all legally required manifests shall be included). ☒ Check box to acknowledge consent to provide a NC licensed P.G. or P.E. sealed, Redevelopment Summary Report in compliance with the site’s Brownfields Agreement. 27 EMP Version 2, June 2018 28 EMP Version 2, June 2018 Tables Table 1Summary of Groundwater Analytical ResultsCharlotte Salvage CompanyCharlotte, North CarolinaH&H Job No. JMC-007Sample IDTMW-1TMW-2Trip BlankDate8/30/20198/30/20198/30/20198/30/20198/30/2019Location DescriptionNorthwestern portion of SiteSouthwestern (downgradient) portion of Site--UnitsVOCs (8260B)Acetone26.8<6.2 <6.2 <6.2 <6.26,000 4,500,000 19,000,000SVOCs (8270D)NANA------RCRA Metals (6020A-B, 7470A)ArsenicNA <0.2500.323J 0.298JNA10-- --BariumNA78.8 81.5 81.7NA700-- --CadmiumNA0.698J<0.160 <0.160 NA2-- --ChromiumNA0.756J 5.91 3.75NA10-- --LeadNA0.244J 0.263J 0.283JNA15-- --MercuryNA <0.0490 <0.0490 <0.0490 NA1 0.18 0.75SeleniumNA0.400J 0.684J 0.742JNA20-- --SilverNA<0.310<0.310<0.310NA20----Turbidity (NTU)>1,0003.988.418.41--------Notes:1) North Carolina Department of Environmental Quality (DEQ) 15A NCAC 02L.0202 Groundwater Standards (2L Standards) (April 2013)2) NC DEQ Division of Waste Management (DWM) Residential Vapor Intrusion Groundwater Screening Level (GWSLs) (February 2018)3) NC DEQ DWM Non-Residential Vapor Intrusion GWSLs (February 2018)With the exception of metals, only constituents detected in at least one sample are shownCompound concentrations are reported to the laboratory method detection limits (MDLs)VOCs = Volatile Organic Compounds; SVOCs = Semi-Volatile Organic Compounds; NTU = Nephelometric Turbidity UnitsNA = Not Analyzed for specified constituent; -- = Not ApplicableJ = estimated value between the laboratory method detection limit and the laboratory reporting limitAll Below MDLsµg/Lµg/LNon-Residential GWSL(3)NC 2L Groundwater Standards (1) Residential GWSL(2)TMW-3 / TMW-DUPNortheastern (upgradient) portion of SiteS:\AAA-Master Projects\JMC Holdings\JMC.007 300 Rampart ESA\Tables\JMC-007 Data Tables9/17/2019Table 1(Page 1 of 1) Hart & Hickman, PC Table 2Summary of Soil Analytical ResultsCharlotte Salvage CompanyCharlotte, North CarolinaH&H Job No. JMC-007Sample IDWASTE CHARDate 8/30/2019 8/29/2019 8/29/2019 8/29/2019 8/29/2019 8/30/2019 8/30/2019 8/30/2019 8/30/2019 8/30/2019 8/30/2019 8/30/2019 8/30/20198/29/2019 8/30/2019Area of Potential ConcernSoil drumsDepth (ft bgs)1-2 5-7 7-10 0-2 2-5 0-2 3-5 0-2 3-5 0-2 3-5 0-2 3-53-5--Range MeanUnitsVOCs (8260B)AcetoneNA <0.00830.018J<0.0072 <0.00740.044J 0.013J 0.0086J<0.00990.012J 0.015J<0.0083 <0.00840.012J<0.00790.019JNA12,000 140,000 25-- ----SVOCs (8270D)FluorantheneNA0.13J<0.15 <0.59 <0.58 <0.13 <0.14 <0.11 <0.14 <0.13 <0.13 <0.13 <0.13 <0.12 <0.12 <0.12 NA480 6,000 670-- ----PyreneNA0.15J<0.14 <0.54 <0.53 <0.11 <0.13 <0.10 <0.13 <0.12 <0.11 <0.12 <0.12 <0.11 <0.11 <0.11 NA360 4,500 440-- ----Metals (6020B/7471B/7199)Arsenic0.8851563.366.906.063.60 1.87 3.07 2.150 4.11 1.62 3.40 2.07 1.43 1.41 1.31NA0.68 3.0 5.81.0 - 18 4.8--Barium184 69.7 41.9 85.5 84.4 42.7 15.5 42.2 93.5 38.8 21.8 18.4 12.9 23.7 17.4 21.0NA3,100 47,000 58050 - 1,000 356--Cadmium<0.113 <0.101 <0.1110.116J 0.106J<0.101 <0.111 <0.1010.423J<0.104 <0.103 <0.106 <0.102 <0.0963 <0.0975 <0.0940 NA14 200 3.01.0 - 10 (3)4.3 (3)--Chromium (total)11.1 41.3 73.3 37.9 44.5 51.0 72.8 30.4 129 301 198 72.5 72.2 18.7 21.7 25.1NANS NS NS7.0 - 300 65--Hexavalent Chromium<0.359<0.323NA <0.308 NA0.528JNA0.601JNA1.43NA <0.338NA <0.307 <0.311NANA0.31 6.53.8NSNS--Trivalent Chromium10.74 40.98NA37.59NA50.47NA29.80NA299.6NA72.16NA18.39 21.39NANA23,000 350,000 360,000NSNS--Lead8.25 122 15 44.5 41.8 15.4 9.58 18.0 7.33 12.2 6.38 8.75 9.28 8.24 3.46 4.46NA400 800270ND - 50 16--Mercury0.0104J 0.0208J 0.0478 0.110 0.104 0.132 0.0312 0.0173J 0.0454 0.543 0.0467 0.104 0.0518 0.0187J 0.0195J 0.0191JNA2.3 9.7 1.00.03 - 0.52 0.12--Selenium0.423J 0.853 0.604J 0.881 0.847 0.789 1.14 0.913 1.41 1.38 0.867 0.764 1.030.409J 0.544J 0.393JNA78 1,200 2.1<0.1 - 0.8 0.42--Silver<0.2180.250J<0.215 <0.187 <0.185 <0.196 <0.215 <0.195 <0.205 <0.202 <0.199 <0.0205 <0.198 <0.187 <0.189 <0.182 NA78 1,200 3.4ND - 5.0 (3)NS--TCLP RCRA Metals (6010/7470)ArsenicNA <0.0047 NA0.0050JNA <0.0047 NA <0.0047 NA <0.0047 NA <0.0047 NA <0.00470.010JNA <0.0047-- -- -- -- --5.0BariumNA0.63NA0.45NA0.26NA0.29NA0.21JNA0.12JNA0.20J 0.22JNA0.17J-- -- -- -- --100CadmiumNA <0.00040 NA <0.00040 NA0.0010JNA0.00067JNA <0.00040 NA <0.00040 NA <0.000400.00069JNA0.00062J-- -- -- -- --1.0Chromium (total)NA0.0084JNA <0.0010 NA0.0032JNA0.0022JNA <0.0010 NA <0.0010 NA0.0015J<0.0010 NA0.0013J-- -- -- -- --5.0LeadNA0.010JNA0.016JNA0.010JNA0.036NA0.0064JNA0.0038JNA0.0035J 0.0075JNA0.017J-- -- -- -- --5.0MercuryNA <0.00010 NA <0.00010 NA <0.00010 NA <0.00010 NA <0.00010 NA <0.00010 NA <0.00010 <0.00010 NA <0.00010-- -- -- -- --0.2SeleniumNA <0.0047 NA <0.0047 NA <0.0047 NA <0.0047 NA <0.0047 NA <0.0047 NA <0.0047 <0.0047 NA <0.0047----------1.0SilverNA <0.0025 NA <0.0025 NA <0.0025 NA <0.0025 NA <0.0025 NA <0.0025 NA <0.0025 <0.0025 NA <0.0025----------5.0Notes:1) North Carolina Department of Environmental Quality (DEQ) Inactive Hazardous Sites Branch (IHSB) Preliminary Soil Remediation Goals (PSRGs) (May 2019)2) Range and mean values of background metals for North Carolina soils taken from Elements in North American Soils by Dragun and Chekiri, 20053) Background values reported for soils of the southeastern United States4) Obtained from Chapter Seven of the Environmental Protection Agency (EPA) SW-846 Compendium: Introductory and Regulatory Definitions Pertaining to Hazardous Waste Characteristics (2004)With the exception of metals, only constituents detected in at least one sample are shownCompound concentrations are reported to the laboratory method detection limitsBold indicates concentration exceeds DEQ IHSB Protection of Groundwater (POG) PSRG and above the mean background metals in North Carolina soils for metals as preliminary comparison Underlined indicates concentration exceeds DEQ IHSB Residential PSRGs and above the mean background metals in North Carolina soils for metals as preliminary comparisonGray shading indicates concentration exceeds DEQ IHSB Industrial/Commercial PSRGs and above the mean background metals in North Carolina soils for metals as preliminary comparisonTrivalent chromium calculated as total chromium minus hexavalent chromiumVOCs = Volatile Organic Compounds; SVOCs = Semi-Volatile Organic Compounds; TCLP RCRA Metals = Toxicity Characteristic Leaching Procedure Resource Conservation and Recovery Act Metalsft bgs= feet below ground surface; NA = Not Analyzed for specified constituent; -- = Not Applicable; NS = Not SpecifiedJ = estimated value between the laboratory method detection limit and the laboratory reporting limitPublished Background Metals Concentrations for North Carolina Soils (2)SB-1mg/kg (8260B, 8270D, 6020B/7471B/7199) ; mg/L (TCLP)Maximum Concentration of Contaminants for Toxicity Characteristic (4)mg/kg (8260B, 8270D, 6020B/7471B/7199) ; mg/L (TCLP)Residential PSRGs (1)Industrial/ Commercial PSRGs (1)Protection of Groundwater PSRGs (1)SB-7 / SOIL-DUPSB-2 SB-3 SB-4 SB-5 SB-60-28/29/2019Northwestern portion of western warehouseSouthwestern portion of SiteNorthwestern portion of eastern warehouse and near potential former paint mixing areaNortheastern portion of eastern warehouseEastern floor drain in eastern warehouseNortheastern portion of SiteWestern floor drain in eastern warehouseS:\AAA-Master Projects\JMC Holdings\JMC.007 300 Rampart ESA\Tables\JMC-007 Data Tables9/17/2019Table 2 (Page 1 of 1)Hart & Hickman, PC Table 3 Summary of Sub-Slab Vapor and Soil Gas Analytical Results Charlotte Salvage Company Charlotte, North Carolina H&H Job No. JMC-007 Sample IDSample LocationSlab Thickness (in)Screen Depth (ft bgs)Sample DateAnalytical MethodAcetoneBenzeneBromomethane2-Butanone (MEK)Carbon DisulfideChloroformChloromethaneCyclohexane1,3-Dichlorobenzene1,4-DichlorobenzeneDichlorodifluoromethane (Freon 12)1,1-Dichloroethane1,1-Dichloroethylenecis-1,2-DichloroethyleneEthyl AcetateEthylbenzene4-EthyltolueneHeptaneHexane8/29/2019 114 1.1 <0.44 30.4 5.5 <0.38 <0.30 1.9J 4.1 <1.9 2.2 <0.44 <0.53 <0.42 2.0 2.7 1.9J 2.9 4.2 12/3/2019 57.2 0.41 J <0.44 5.0 J 1.2 J <0.38 <0.30 0.72 J <1.1 <1.9 3.2 <0.44 <0.53 <0.42 <0.37 <0.59 <1.1 <0.74 9.5 8/29/2019 100 0.84 <0.46 13.6 1.5 <0.40 <0.32 <0.71 6.0 <2.0 2.2 <0.45 <0.55 <0.44 <0.38 3.4 2.7J <0.77 4.1 12/3/2019 64.5 1.9 <0.44 4.1 J 0.74 J <0.38 0.38 J 1.7 J <1.1 <1.9 3.3 <0.44 <0.53 <0.42 1.3 J <0.59 <1.1 <0.74 7.8 8/29/2019 158 1.2 <0.46 19.9 7.4 <0.40 2.1 <0.71 3.9 <2.0 2.3 9.0 <0.55 14.1 <0.38 3.0 1.9J <0.77 4.6 12/3/2019 136 0.66 <0.44 9.9 <0.42 <0.38 0.73 J 1.4 J <1.1 3.1 J 3.6 <0.44 <0.53 <0.42 <0.37 <0.59 <1.1 1.5 J 5.9 SSV-4 Can 2255 67.6 <0.30 <0.44 5.9 0.63 J <0.38 0.45 J <0.68 <1.1 <1.9 2.4 <0.44 <0.53 <0.42 1.1 J <0.59 <1.1 0.90 J 4.1 SSV-DUP 71.5 <0.30 <0.44 5.0 J <0.42 <0.38 <0.30 <0.68 <1.1 <1.9 2.2 <0.44 <0.53 <0.42 <0.37 <0.59 <1.1 <0.74 4.1 SSV-5 Can 1023 Southern portion of eastern warehouse 6.0 --12/3/2019 116 <0.31 0.50 J 8.3 <0.44 0.44 J 1.1 <0.71 <1.2 <2.0 2.7 <0.45 <0.55 <0.44 <0.38 <0.62 <1.2 0.92 J 8.7 SG-1 Northeastern (upgradient) portion of Site 6.0 10.0 8/30/2019 57.9 36.9 <0.46 <0.75 55.5 11.0 10.6 34.3 45.3 <2.0 2.2 <0.45 6.5 <0.44 <0.38 9.0 3.4J 24.8 53.8 220,000 120 35 35,000 4,900 41 630 42,000 NS 85 700 580 1,400 NS 490 370 NS 2,800 4,900 2,700,000 1,600 440 440,000 61,000 530 7,900 530,000 NS 1,100 8,800 7,700 18,000 NS 6,100 4,900 NS 35,000 61,000 Notes: 1) North Carolina Department of Environment Quality (DEQ) Division of Waste Management (DWM) Residential Sub-slab and Exterior Soil Gas Screening Levels (SGSLs) (February 2018)2) North Carolina DWM Non-Residential SGSLs (February 2018)Only constituents detected in at least one sample are shownCompound concentrations and SGSLs are reported in micrograms per cubic meter (µg/m3) Compound concentrations are reported to the laboratory detection limits Bold indicates concentration exceeds Residential SGSL Bold and Underlined indicates concentration exceeds Non-Residential SGSL Gray and underlined values are method detection limits that exceed Residential SGSL or both the Residential SGSL and Non-Residential SGSL.ft bgs = feet below ground surface; NS = Not Specified; -- = Not ApplicableJ = estimated value between the laboratory method detection limit and the laboratory reporting limit -- --12/3/2019 DWM Non-Residential SGSL (2)DWM Residential SGSL (1) TO-15 Central portion of western warehouseSSV-1 Western portion of eastern warehouseSSV-2 Eastern portion of eastern warehouseSSV-3 Northern portion of eastern warehouse 6.0 -- 6.0 6.0 6.0 -- \\HARTHICKMAN.LOCAL\Shares\MasterFiles\AAA-Master Projects\JMC Holdings\JMC.007 300 Rampart ESA\Tables\JMC-007 Data Tables 12/17/2019 Table 3 (Page 1 of 2) Hart & Hickman, PC Table 3 Summary of Sub-Slab Vapor and Soil Gas Analytical Results Charlotte Salvage Company Charlotte, North Carolina H&H Job No. JMC-007 Sample IDSample LocationSlab Thickness (in)Screen Depth (ft bgs)Sample DateAnalytical Method8/29/2019 12/3/2019 8/29/2019 12/3/2019 8/29/2019 12/3/2019 SSV-4 Can 2255 SSV-DUP SSV-5 Can 1023 Southern portion of eastern warehouse 6.0 --12/3/2019 SG-1 Northeastern (upgradient) portion of Site 6.0 10.0 8/30/2019 -- --12/3/2019 DWM Non-Residential SGSL (2)DWM Residential SGSL (1) TO-15 Central portion of western warehouseSSV-1 Western portion of eastern warehouseSSV-2 Eastern portion of eastern warehouseSSV-3 Northern portion of eastern warehouse 6.0 -- 6.0 6.0 6.0 --2-Hexanone (MBK)Methylene Chloride4-Methyl-2-pentanone (MIBK)NaphthalenePropeneStyreneTetrachloroethyleneTetrahydrofuranToluene1,1,1-TrichloroethaneTrichloroethyleneTrichlorofluoromethane (Freon 11)1,2,4-Trimethylbenzene1,3,5-TrimethylbenzeneVinyl AcetateVinyl Chloridem&p-Xyleneo-Xylene1.7J 6.8J <1.0 5.1J 4.4 1.5J <0.61 3.2 8.2 <0.60 2.5 <0.71 8.8 1.9J <0.52 <0.24 10.5 5.0 2.1 J 96.5 <1.0 4.2 J 3.6 1.6 J 1.2 J 0.60 J 1.8 <0.60 <0.49 1.8 J <0.88 <0.77 3.2 <0.24 <1.4 <0.67 1.6J 11.7 <1.0 5.5 0.91 1.6J 1.7 3.7 8.2 <0.62 <0.52 <0.74 12.2 2.6 <0.55 <0.25 13.4 6.6 <1.4 81.7 <1.0 <2.5 3.8 <0.67 0.63 J <0.51 2.6 <0.60 <0.49 2.8 <0.88 <0.77 <0.52 <0.24 <1.4 0.76 J 2.4J 13.5 3.5J 4.3J 2.1 1.4J 9.5 3.7 11.4 0.80J 3.6 <0.74 9.3 2.1 <0.55 <0.25 11.6 5.3 4.6 J 37.2 1.1 J 2.9 J 5.4 <0.67 13.9 <0.51 2.1 0.64 J <0.49 5.9 0.89 J <0.77 <0.52 <0.24 <1.4 0.69 J <1.4 31.7 <1.0 <2.5 <0.27 1.1 J 1.6 <0.51 2.3 <0.60 <0.49 2.0 J <0.88 <0.77 <0.52 <0.24 <1.4 <0.67 <1.4 31.5 <1.0 <2.5 <0.27 1.1 J 0.70 J <0.51 0.89 J <0.60 <0.49 2.0 J <0.88 <0.77 <0.52 <0.24 <1.4 <0.67 <1.5 82.1 1.4 J <2.6 <0.28 <0.69 3.2 <0.53 1.4 J 8.2 <0.51 3.3 <0.91 <0.81 <0.55 <0.25 <1.4 <0.69 <1.5 7.4 4.6J 6.0 439 11.0 1.4 <0.53 26.0 <0.62 <0.52 3.7 12.4 3.5 <0.55 3.4 16.7 6.7 210 4,200 21,000 21 21,000 7,000 280 14,000 35,000 35,000 14 NS 420 420 1,400 56 700 700 2,600 53,000 260,000 260 260,000 88,000 3,500 180,000 440,000 440,000 180 NS 5,300 5,300 18,000 2,800 8,800 8,800 Notes: 1) North Carolina Department of Environment Quality (DEQ) Division of Waste Management (DWM) Residential Sub-slab and Exterior Soil Gas Screening Levels (SGSLs) (February 2018)2) North Carolina DWM Non-Residential SGSLs (February 2018)Only constituents detected in at least one sample are shown.Compound concentrations and SGSLs are reported in micrograms per cubic meter (µg/m3). Compound concentrations are reported to the laboratory detection limits. Bold indicates concentration exceeds Residential SGSL Bold and Underlined indicates concentration exceeds Non-Residential SGSL Gray and underlined values are method detection limits that exceed Residential SGSL or both the Residential SGSL and Non-Residential SGSL.ft bgs = feet below ground surface; NS = Not Specified; -- = Not Applicable; NM = Not MeasuredJ = estimated value between the laboratory method detection limit and the laboratory reporting limit \\HARTHICKMAN.LOCAL\Shares\MasterFiles\AAA-Master Projects\JMC Holdings\JMC.007 300 Rampart ESA\Tables\JMC-007 Data Tables 12/17/2019 Table 3 (Page 2 of 2) Hart & Hickman, PC Table 4 Summary of DEQ Risk Assessement Results for Sub-Slab Vapor and Soil Gas Charlotte Salvage Company Charlotte, North Carolina H&H Job No. JMC-007 Calculated LICR Calculated HI Calculated LICR Calculated HI Worst Case 8-29-19 9.2E-06 0.19 NO 6.6E-07 0.015 NO Worst Case 12-3-19 2.2E-06 0.07 NO 1.7E-07 0.005 NO Notes: 1) Based on the North Carolina Department of Environmental Quality (DEQ) Risk Calculator for Residential Use Scenario of the Soil Gas to Indoor Air Exposure Pathway (Version May 2019) 2) Based on the DEQ Risk Calculator for Non-Residential Use Scenario of the Soil Gas to Indoor Air Exposure Pathway (Version May 2019) LICR = Lifetime Incremental Cancer Risk HI = Non-Carcinogenic Hazard Index Sample ID Resident (1)Risk Exceeded?Non-Residential Worker (2)Risk Exceeded? File: \\HARTHICKMAN.LOCAL\Shares\MasterFiles\AAA-Master Projects\JMC Holdings\JMC.007 300 Rampart ESA\Tables\JMC-007 Data TablesJMC-007 Data TablesDate: 12/17/2019 Table 4 Hart & Hickman, PC Figures 0 2000 4000 APPROXIMATE SCALE IN FEETN U.S.G.S. QUADRANGLE MAP QUADRANGLE 7.5 MINUTE SERIES (TOPOGRAPHIC) CHARLOTTE EAST, NORTH CAROLINA 1991 TITLE PROJECT SITE LOCATION MAP CHARLOTTE SALVAGE COMPANY300 RAMPART STREET CHARLOTTE, NORTH CAROLINA DATE: JOB NO: REVISION NO: FIGURE: 8-23-2019 0 1JMC-007 SITE REVISION NO. 0 JOB NO. JMC-009 DATE: 12-10-19 FIGURE NO. 2 CHARLOTTE SALVAGE COMPANY 300 RAMPART STREET CHARLOTTE, NORTH CAROLINA SAMPLE LOCATION MAP LEGEND SITE PROPERTY BOUNDARY PARCEL BOUNDARY TEMPORARY MONITORING WELL AND SOIL BORING LOCATION SOIL BORING LOCATION (H&H; 2019) SOIL BORING LOCATION (ARCADIS; 2012) SUB-SLAB VAPOR SAMPLE LOCATION SOIL GAS SAMPLE LOCATION FLOOR DRAIN DUMPSTER POLE-MOUNTED TRANSFORMER 2923 South Tryon Street-Suite 100 Charlotte, North Carolina 28203 704-586-0007(p) 704-586-0373(f) License # C-1269 / #C-245 Geology RAMPART ST R E E T RAMPART S T R E E T HAW KI N S S T R E E T HAW KI N S S T R E E TS. TRYON STREETS.TRYON STREETTHE PENROSE APARTMENTS / FORMER VCC CHARLOTTE (349 W. TREMONT AVENUE) THE PENROSE APARTMENTS / FORMER VCC CHARLOTTE (349 W. TREMONT AVENUE) VACANT (2129 S. TRYON STREET) VACANT (2129 S. TRYON STREET) K9 PLAYLAND (2139 S. TRYON STREET) K9 PLAYLAND (2139 S. TRYON STREET) MUTLI-TENANT COMMERCIAL BUILDINGS (2204-2228 HAWKINS STREET) MUTLI-TENANT COMMERCIAL BUILDINGS (2204-2228 HAWKINS STREET) KEG N CUE (2131 S. TRYON STREET) KEG N CUE (2131 S. TRYON STREET) MAACO FLEET SOLUTIONS (2217 S. TRYON STREET) MAACO FLEET SOLUTIONS (2217 S. TRYON STREET) NOTES: 1. AERIAL IMAGERY OBTAINED FROM MECKLENBURG COUNTY GIS (2019). GMI (222 RAMPART STREET) GMI (222 RAMPART STREET) APPROXIMATE LOCATION OF INK SPILL SGP-1 TMW-3/SB-7 SB-6 SSV-3 SB-5 SB-4 SSV-2 SB-3 SSV-1 TMW-1 SB-1 TMW-2/SB-2 APPROXIMATE LOCATION OF PAINT SPLATTER SB-8 CH-SB-97 CH-SB-98 CH-SB-90 CH-SB-91 CH-SB-92 CH-SB-93 CH-SB-94 CH-SB-95 SSV-4 SSV-5 S:\AAA-Master Projects\JMC Holdings\JMC.007 300 Rampart ESA\Figures\Site Map.dwg, FIG 2 121019, 12/10/2019 8:49:30 AM, sperry Appendix A Site Plans – Phase I Development Appendix B Construction Schedule IDTask ModeTask NameDuration Start Finish1MILESTONES177 daysFri 3/27/20Fri 12/4/202Obtain Site Development Permit1 dayFri 3/27/20Fri 3/27/203Record Brownfield Agreement1 dayThu 5/14/20Thu 5/14/204Obtain Building Permits1 dayMon 6/8/20Mon 6/8/205Substantial Completion1 dayFri 12/4/20Fri 12/4/206BROWNFIELDS APPLICATION PROCESS155 daysFri 10/4/19Thu 5/14/207Receive Letter of Eligibility1 dayFri 10/4/19Fri 10/4/198Issue Brownfields Assessment Report1 dayMon 10/7/19Mon 10/7/199DEQ Kick-Off Meeting12 daysTue 10/8/19Wed 10/23/1910DEQ Request for Additional Assessment9 daysThu 10/24/19Tue 11/5/1911Prepare Brownfields Additional Assessment Work Plan7 daysWed 11/6/19Thu 11/14/1912DEQ Review & Approval of Add'l Assessment Work Plan2 daysFri 11/15/19Mon 11/18/1913Perform Additional Testing & Submit Report to DEQ35 daysTue 11/19/19Mon 1/13/2014DEQ Review of Additional Assessment Testing15 daysTue 1/14/20Mon 2/3/2015DEQ Preparation of Brownfields Agreement20 daysTue 2/4/20Mon 3/2/2016Brownfields Agreement Negotiation20 daysTue 3/3/20Mon 3/30/2017Finalize Plat Map According to Agreement5 daysTue 3/31/20Mon 4/6/2018Receive Written Approval from DEQ to Proceed w/ Public Notice& Pay Final Fee1 dayTue 4/7/20Tue 4/7/201930 Day Public Comment Period22 daysWed 4/8/20Thu 5/7/2020Execute and Record Final Platt & Agreement5 daysFri 5/8/20Thu 5/14/2021Complete EMP20 daysTue 12/3/19Thu 1/2/2022DEQ Review & Approval of EMP15 daysFri 1/3/20Thu 1/23/2023CIVIL DESIGN / PERMIT97 daysThu 11/7/19Fri 3/27/2024Complete Topographic Survey1 dayThu 11/7/19Thu 11/7/1925Complete 50% Drawings20 daysFri 11/8/19Mon 12/9/1926Review & Pricing10 daysFri 11/15/19Mon 12/2/1927Complete Permit Drawings30 daysTue 12/3/19Thu 1/16/2028Submit for Permit20 daysFri 1/17/20Thu 2/13/2029Respond to First Round Comments5 daysFri 2/14/20Thu 2/20/2030Resubmit for Permit20 daysFri 2/21/20Thu 3/19/2031Respond to Second Round Comments5 daysFri 3/20/20Thu 3/26/2032Obtain Permit1 dayFri 3/27/20Fri 3/27/2033BUILDING DESIGN & PERMIT150 daysMon 11/4/19Mon 6/8/2034Complete As-Built & Model15 daysMon 11/4/19Fri 11/22/1935Complete 50% Drawings30 daysTue 12/3/19Thu 1/16/2036Owner Review / Contractor Pricing10 daysFri 1/17/20Thu 1/30/2037Complete 90% Drawings20 daysFri 1/31/20Thu 2/27/2038Owner Review / Contractor Pricing10 daysFri 2/28/20Thu 3/12/2039Complete Construction Drawings10 daysFri 3/13/20Thu 3/26/2040Submit for Permit20 daysFri 3/27/20Thu 4/23/2041Respond to First Round Comments5 daysFri 4/24/20Thu 4/30/2042Resubmit for Permit20 daysFri 5/1/20Fri 5/29/2043Respond to Second Round Comments5 daysMon 6/1/20Fri 6/5/2044Obtain Permit1 dayMon 6/8/20Mon 6/8/2045CONSTRUCTION229 daysTue 1/14/20Thu 12/3/2046Interior Demolition5 daysTue 1/14/20Mon 1/20/2047Exterior Demolition20 daysTue 6/9/20Mon 7/6/2048Structural Repairs20 daysTue 7/7/20Mon 8/3/2049Install Sub Grade Utilities20 daysTue 7/7/20Mon 8/3/2050Install New Roof15 daysTue 8/4/20Mon 8/24/2051Install Windows20 daysTue 8/4/20Mon 8/31/2052Site Work40 daysTue 9/1/20Tue 10/27/2053Landscaping5 daysWed 10/28/20Tue 11/3/2054Paint10 daysTue 9/1/20Tue 9/15/2055MEP Trim Out20 daysTue 8/25/20Tue 9/22/2056Inspections20 daysWed 11/4/20Thu 12/3/2012/44/711/712/91/16JulAugSepOctNovDecJanFebMarAprMayJunJulAugSepOctNovDec2020TaskSplitMilestoneSummaryProject SummaryInactive TaskInactive MilestoneInactive SummaryManual TaskDuration-onlyManual Summary RollupManual SummaryStart-onlyFinish-onlyExternal TasksExternal MilestoneDeadlineCriticalCritical SplitProgressManual Progress300 RampartUPDATED Fri 1/10/20 Page 1