August 29, 2011
Subject: Stormwater Permit No. S W61 10803
Turnberry Section 1
Hoke County
Dear Mr. Floyd:
MW
Dee Freeman
Secretary
The Stormwater Permitting Unit received a complete Stormwater Management Permit Application for Turnberry
Section I on August 11, 2011. Staff review of the plans and specifications has determined that the project, as
proposed, will comply with the Stormwater Regulations set forth in Title 15A NCAC 2H.1000 and Session Law
2006-246. We are forwarding Permit No. SW61 10803, dated August 29, 2011, for the construction, operation and
maintenance of the subject project and the stormwater BMPs.
This permit shall be effective from the date of issuance until April 13, 2018, and shall be subject to the conditions and
limitations as specified therein. Please pay special attention to the Operation and Maintenance requirements in this
permit. Failure to establish an adequate system for inspection and maintenance of the stormwater management system
will result in future compliance problems.
If any parts, requirements, or limitations contained in this permit are unacceptable, you have the right to request an
adjudicatory hearing upon written request within thirty (30) days following receipt of this permit. This request must be
in the form of a written petition, conforming to Chapter 150B of the North Carolina General Statutes, and filed with
the Office of Administrative Hearings, P.O. Drawer 27447, Raleigh, NC 2761 1-7447. Unless such demands are made
this permit shall be final and binding.
This project will be kept on file at the Fayetteville Regional Office. If you have any questions, or need additional
information concerning this matter, please contact Mike Randall at (919) 807-6374; or mike.randall@ncdenr.gov.
Sincerely,
for Coleen H. Sullins
cc: Fayetteville Regional Office
SPU Files
Wetlands and Stomnvater Branch
1617 Mail Service Center, Raleigh, North Carolina 27699-1617
Location: 512 N. Salisbury St. Raleigh, North Carolina 27604
Phone: 919-807-63001 FAX: 919-807-64941 Customer Service: 1-877-623-6748
Internet: w .ncwaterquality.org
An Equal Opportunity 1 Affrma6ve Action Employer
Nne
orthCarolina
Naturally
State Stormwater Permit
Permit No.SW6110803
STATE OF NORTH CAROLINA
DEPARTMENT OF ENVIRONMENT AND NATURAL RESOURCES
DIVISION OF WATER QUALITY
STATE STORMWATER MANAGEMENT PERMIT
HIGH DENSITY DEVELOPMENT
In accordance with the provisions of Article 21 of Chapter 143, General Statutes of
North Carolina as amended, and other applicable Laws, Rules, and Regulations
PERMISSION IS HEREBY GRANTED TO
Gregory W. Floyd, Floyd Properties and Development Inc.,
Turnberry Section 1
NC Hwy 401 South, McLauchin, North Carolina, Hoke County
FOR THE
construction, operation and maintenance of a wet detention basin in compliance with
the provisions of 15A NCAC 2H .1000 and S.L. 2006-246 (hereafter referred to as the
"stormwaterrules') and the approved stormwater management plans and specifications
and other supporting data as attached and on file with and approved by the Division of
Water Quality and considered a part of this permit.
This permit shall be effective from the date of issuance until August 28, 2021, and shall
be subject to the following specified conditions and limitations:
I. DESIGN STANDARDS
This permit is effective only with respect to the nature and volume of stormwater
described in the application and other supporting data.
2. This stormwater system has been approved for the management of stormwater
runoff as described in the plans and this permit. The stormwater control has
been designed to handle the runoff from 878,513 square feet of impervious area.
3. The tract will be limited to the amount of built -upon area indicated in this permit,
and per approved plans.
4. All stormwater collection and treatment systems must be located in either
dedicated common areas or recorded easements. The final plats for the project
will be recorded showing all such required easements, in accordance with the
approved plans.
5. The runoff from all built -upon area within the permitted drainage area number 1
of this project must be directed into the permitted stormwater control system.
Page 1 of 4
State Stormwater Permit
Permit No.SW6110803
6. The following design criteria have been provided in the wet detention pond and
must be maintained at design condition:
a.
Drainage Area, ft2:
2,196,282
b.
Total Impervious Surfaces, ft2:
878,513
Buildings ft2:
650,091
Roads/Parking, ft2:
228,421
c.
Pond Depth, feet:
1.8
d..TSS
removal efficiency:
90%
e.
Design Storm:
1.0 inch
f.
Permanent Pool Elevation, FMS�:
234.5
g.
Permitted Surface Area @PP, ft :
35,150
h.
Temporary Pool Volume, ft3:
79,013
i.
Temporary Pool Elevation, FMSL:
236.30
j.
Controlling Orifice:
3.0"0 pipe
k.
Permanent Pool Volume, ft3:
201,627
I.
Forebay Volume, ft3:
40,714
m.
Receiving Stream/River Basin: Beaver Creek / Cape Fear
n.
Stream Index Number:
18-31-19-5
o.
Classification of Water Body:
"C"
It. SCHEDULE OF COMPLIANCE
1. During construction, erosion shall be kept to a minimum and any eroded areas of
the system will be repaired immediately.
2. The permittee shall at all times provide the operation and maintenance necessary to
assure the permitted stormwater system functions at optimum efficiency. The
approved Operation and Maintenance Plan must be followed in its entirety and
maintenance must occur at the scheduled intervals including, but not limited to:
a. Semiannual scheduled inspections (every 6 months).
b. Sediment removal.
C. Mowin.9 and revegetation of slopes and the vegetated filter.
d. Immediate repair of eroded areas.
e. Maintenance of all slopes in accordance with approved plans and
specifications.
f. Debris removal and unclogging of outlet structure, orifice device, flow
spreader, catch basins and piping.
g. Access to the outlet structure must be available at all times.
4. Records of maintenance activities must be kept and made available upon
request to authorized personnel of DWQ. The records will indicate the date,
activity, name of person performing the work and what actions were taken.
5. The facilities shall be constructed as shown on the approved.plans. This permit
shall become voidable unless the facilities are constructed in accordance with
the conditions of this permit, the approved plans and specifications, and other
supporting data.
Page 2 of 4
State Stormwater Permit
Permit No.SW6110803
Upon completion of construction a certification must be received from an
appropriate designer for the system installed certifying that the permitted facility
has been installed in accordance with this permit, the approved plans and
specifications, and other supporting documentation. Any deviations from the
approved plans and specifications must be noted on the Certification. A
modification may be required for those deviations.
7. If the stormwater system was used as an Erosion Control device, it must be
restored to design condition prior to operation as a stormwater treatment device,
and prior to occupancy of the facility.
8. Access to the stormwater facilities shall be maintained via appropriate
easements at all times.
The permittee shall submit to the Director and shall have received approval for
revised plans, specifications, and calculations prior to construction, for any
modification to the approved plans, including, but not limited to, those listed
below:
a. Any revision to any item shown on the approved plans, including the
stormwater management measures, built -upon area, details, etc.
b. Project name change.
C. Transfer of ownership.
d. Redesign or addition to the approved amount of built -upon area or to the
drainage area.
e. Further subdivision, acquisition, lease or sale of all or part of the project
area. The project area is defined as all property owned by the permittee,
for which Sedimentation and Erosion Control Plan approval or a CAMA
Major permit was sought.
f. Filling in, altering, or piping of any vegetative conveyance shown on the
approved plan.
10. The permittee shall submit final site layout and grading plans for any permitted
future areas shown on the approved plans, prior to construction.
11. A copy of the approved plans and specifications shall be maintained on file by
the Permittee for a minimum of ten years from the date of the completion of
construction.
12. The Director may notify the permittee when the permitted site does not meet one
or more of the minimum requirements of the permit. Within the time frame
specified in the notice, the permittee shall submit a written time schedule to the
Director for modifying the site to meet minimum requirements. The permittee
shall provide copies of revised plans and certification in writing to the Director
that the changes have been made.
III. GENERAL CONDITIONS
1. This permit is not transferable except after notice to and approval by the Director. In
the event of a change of ownership, or a name change, the permittee must submit a
completed Name/Ownership Change form, to the Division of Water Quality, signed
by both parties, and accompanied by supporting documentation. The project must
be in good standing with the Division. The approval of this request will be
considered on its merits and may or may not be approved.
2. The permittee is responsible for compliance with all permit conditions until such time
as the Division approves the transfer request.
Page 3 of 4
State Stormwater Permit
Permit No.SW6110803
3. Failure to abide by the conditions and limitations contained in this permit may
subject the Permittee to enforcement action by the Division of Water Quality, in
accordance with North Carolina General Statute 143-215.6A to 143-215.6C.
4. The issuance of this permit does not preclude the Permittee from complying with
any and all statutes, rules, regulations, or ordinances, which may be imposed by
other government agencies (local, state, and federal) having jurisdiction.
5. In the event that the facilities fail to perform satisfactorily, including the creation of
nuisance conditions, the Permittee shall take immediate corrective action, including
those as may be required by this Division, such as the construction of additional or
replacement stormwater management systems.
6. The permittee grants DENR Staff permission to enter the property during normal
business hours for the purpose of inspecting all components of the permitted
stormwater management facility.
7. The permit issued shall continue in force and effect until revoked or terminated. The
permit may be modified, revoked and reissued or terminated for cause. The filing of
a request for a permit modification, revocation and re -issuance or termination does
not stay any permit condition.
8. Unless specified elsewhere, permanent seeding requirements for the stormwater
control must follow the guidelines established in the North Carolina Erosion and
Sediment Control Planning and Design Manual.
9. Approved plans and specifications for this project are incorporated by reference and
are enforceable parts of the permit.
10. The issuance of this permit does not prohibit the Director from reopening and
modifying the permit, revoking and reissuing the permit, or terminating the permit as
allowed by the laws, rules and regulations contained in Session Law 2006-246, Title
15A NCAC 21-1.1000, and NCGS 143-215.1 et.al.
11. The permittee shall notify the Division of any name, ownership or mailing address
changes at least 30 days prior to making such changes.
12. The permittee shall submit a renewal request with all required forms and
documentation at least 180 days prior to the expiration date of this permit.
Permit issued this the 29th day of August, 2011.
NORTH CAROLINA ENVIRONMENTAL MANAGEMENT COMMISSION
Division of Water Quality
By Authority of the Environmental Management Commission
Page 4 of 4
State Stormwater Permit
Permit No.SW6110803
Turnberry Section 1
Stormwater Permit No. SW6110803
Hoke Countv
Designer's Certification
I, , as a duly registered
in the State of North Carolina, having been authorized to observe (periodically/ weekly/
full time) the construction of the project,
Turnberry Section 1
(Project)
for (Project Owner) hereby state that, to the
best of my abilities, due care and diligence was used in the observation of the project
construction such that the construction was observed to be built within substantial
compliance and intent of the approved plans and specifications.
The checklist of items on page 2 of this form is included in the Certification.
Noted deviations from approved plans and specification:
Signature
Registration Number
Date
SEAL
Page 1 of 2
State Stormwater Permit
Permit No.SW6110803
Certification Requirements:
1. The drainage area to the system contains approximately the permitted
acreage.
2. The drainage area to the system contains no more than the permitted
amount of built -upon area.
3. All the built -upon area associated with the project is graded such that the
runoff drains to the system.
4. All roof drains are located such that the runoff is directed into the system.
5. The outlet/bypass structure elevations are per the approved plan.
6. The outlet structure is located per the approved plans.
7. Trash rack is provided on the outlet/bypass structure.
8. All slopes are grassed with permanent vegetation.
9. Vegetated slopes are no steeper than 3:1.
.10. The inlets are located per the approved plans and do not cause short-
circuiting of the system.
11. The permitted amounts of surface area and/or volume have been
provided.
12. Required drawdown devices are correctly sized per the approved plans.
13. All required design depths are provided.
14. All required parts of the system are provided, such as a vegetated shelf,
and a forebay.
15. The required system dimensions are provided per the approved plans.
Please submit this Designer's Certification to: Fayetteville DWQ Regional Office
Surface Water Protection
Page 2 of 2