HomeMy WebLinkAboutSW6220301_Long Point Stormwater Plan_20221116CONSTRUCTION SEQUENCE FOR WET DETENTION POND: 1. INSTALL EROSION CONTROLS. 2. CONSTRUCT DAM BASE AND AREAS BELOW THE NORMAL POOL CONSTRUCTION TO BE PERFORMED UNDER THE INSPECTION OF THE GEOTECHNICAL ENGINEER. SEED UPON COMPLETION. ` 4' MIN 3. INSTALL OUTLET PIPE, RIP -RAP APRON AND EMBANKMENT WIDTH STONE FILTER RING. 4. CONSTRUCT OUTLET STRUCTURE. 6' TOPSOIL FOR ALL AREAS ABOVE THE TRASH RACK 5. REMOVE ACCUMULATED SEDIMENT AND SEED NORMAL POND ELEVATION REFER TO DETAIL UPON COMPLETION. THIS SHEET 24 ' HOPE WITH WATER TIGHT SEAL PIPE TO BEDDED TOP OF EMBANKMENT ELEVATION=263.5 PER DIRECTION OF GEOTECHNICAL 6" TOPSOIL ABOVE NOTE: 1.0' STORM ELEVATION IS 259.17 AND INTERMEDIATE WEIR IS ELEVATION 259.8. THERE IS ADDITIONAL STORAGE ENGINEER 2 I _ _ I I I 6' CLAY LINER REFER TO DETAIL inn YEAR MQRM E EVAilON=262.71 DESIGNED FROM THE 1.0' STORM ELEVATION TO THE J ON LITTORAL SHELF FOR INCREMENTAL INTERMEDIATE WEIR ELEVATION. 1 6" CLAY SOIL I 3 WEIR LINER ON INSIDE - �- FACE OF I 10 YEAR STORM FI FVATION=261.46 EMBANKMENT !� 1 41 PRECAST 6FT LITTORAL ° 11 1 CONCRETE RISER 2 YEAR STORM ELEVATION=260.49 SHELF (INSTALL STEPS - i ! AS NECESSARY) 1 YEAR STORM ELEVAIlON=260.18 1.0-INCH STORM ELEVATION=259.17 EXISTING GRADE=262.0t INV=259.0 NORMAL POND ELEVATION=259.0 PVC. ELBOW SEE DETAIL 3' MIN 1 ELEV=257.0 '' a ;' i I �' I� 1.75 NOTE PUMPS SHALL BE USED TO DRAIN i 1 THE POND WHEN NECESSARY. REFER TO DETAIL -'�THIS SHEET FOR DEWATERING REQUIREMENTS. `I11 4' IIN. ASTM 0-923 SEAL j KEY BETWEEN BARREL. arc RISER. RISER BASE TO BE FILLED .� CUTOFF TRENCH WITH CONC. TO INVERT OF BOTTOM OF POND (TOP OF SEDIMENT STORACE)=251A SHALL BE APPROXIMATE SIZE BARREL CONCRETE D �N RISER AFTER EXCAVATE AND BACK8"X8'XI"X1Y LONG ANGLE (6 TOT. REQUIRED) TO ANCHOR RISER TO ANGLES ARE SECURED (_ (BOTTOM OF SEDIMENT STORAGE)=250.0 WITH COMPACTED BASE. PROVIDE 2-3 a A307 BOLTS FROM ANGLE TO RISER AND TO BASE AND RISER. 2-A307 7 HOOKS 3/4° DIA. X 12' LONG FROM ANGLE TO BASE. STRUCTURAL FILL AS ANGLE TO BE FIELD COATED WiTH ZINC RICH PAINT AFTER I i DIRECTED BY GEOTECHNICAL CONSTRUCTION. "J' HOOKS TO BE PLACED UNDER LOWER REINFORCING ENGINEER STEEL 6" CLAY SOIL 5'x5'xl.5' CONC. BASE REINFORCE WITH #4 BARS AT 12" O.C. TOP LINER AND BOTTOM OF EACH DIRECTION PROVIDE 3" MIN. CLEARANCE MAIN POOL BETWEEN EDGE OF CONC, AND STEEL REINFORCING 26'-24' HOPE 0 3.85% PROFILE OF WET POND DETENTION SYSTEM SCALE: N.T.S. LTER MEDIA (SEE NOTE 2) SILT FENCE AS NEEDED LIMP FL STORMWATER MANAGEMENT NOTES; 1. THE DEVELOPER OR HIS AGENT SHALL CONTACT THE DESIGN ENGINEER WHEN _ THE BEST MANAGEMENT PRACTICE(S)ARE CONSTRUCTED AND ABOUT TO BECOME OPERATIONAL 50 A FINAL INSPECTION CAN BE PERFORMED TO DETERMINE COMPLIANCE WITH THE APPROVED PLAN CAN BE PERFORMED. TRASH RACK AIER LEVEL 2. ANNUAL MAINTENANCE INSPECTION AND REPORT REQUIRED THE OWNER OF NOTES: A PERMITTED STRUCTURAL STORMWATER BMP/CONTROL SHALL ANNUALLY SUBMIT A MAINTENANCE AND INSPECTION REPORT FOR EACH BMP TO THE 1. PRIOR TO INSTALLATION, MANUFACTURER SPECIFICATIONS OF FILTER MEDIA SHALL BE REVIEWED TO _ STORMWATER ADMINISTRATOR ANNUAL INSPECTIONS SHALL BEGIN WITHIN ONE YEAR OF THE RECORDATION OF ANY DEED(S) SHOWING STORMWATER ENSURE THAT DISCHARGE FROM FILTER MEDIA SHALL MEET OR EXCEED THE PROVISIONS OF THE CLEAN I I WATER ACT. ° BMPs/CONTROL STRUCTURES I t 2. ENSURE THAT PUMP PRESSURE DOES NOT EXCEED FILTER MEDIA PRESSURE RATING. 3. UPON COMPLETION OFTHE PROJECT, AND BEFORE A CERTIFICATE OF _ OCCUPANCY SHALL BE GRANTED, THE ENGINEER OF RECORD SHALL CERTIFY I I 3. FILTER MEDIA MAY BE, BUT NOT LIMITED 70, SAND MEDIA FILTRATION DEVICES, RATED FILTER FABRIC I _ - THAT THE COMPLETED PROJECT IS IN ACCORDANCE WITH THE APPROVED I I BAGS OR POLYMER BASED DEWATERING PRACTICES. 7`- STORMWATER MANAGEMENT PLANS AND DESIGNS. 4. PUMP STRAINER SHALL NOT BE IN CONTACT IMTH BOTTOM OF POND, ilk 4. A FINAL INSPECTION OF THE SITE AND STORMWATER MANAGEMENT I I j I I 11I r BMP/CONTROLS TO BE SCHEDULED WiTH AND COMPLETED BY THE PROJECT I ENGINEER. BMP POND DEWATERING LOW POINT 5. NCDEQ AND THOR ASSIGNS HAVE RIGHT TO ACCESS THE STORMWATER RIS CONTROL(s) FOR INSPECTIONS OR MAINTENANCE AS NECESSARY. , 6. THE ENGINEER'S CERTIFICATION OF COMPLETION WILL BE REQUIRED PRIOR TO SEEDBED PREPARATION: THE FINAL PLAT OR CERTIFICATE OF OCCUPANCY THE STORMWATER CONTROL IS TO BE INSPECTED TO ENSURE IT IS FUNCTIONING AS DESIGNED 1 CHISEL COMPACTED ALAS AND SPREAD TOPSOIL THREE INCHES DEEP OVER ADVERSE SOIL CONDITIONS, IF AND HAS FULL DESIGN VOLUME PRIOR TO ISSUANCE OF THE FINAL AVAILABLE, CERTIFICATE OF OCCUPANCY. 2. RIP THE ENTIRE AREA TO SIX INCHES DEEP, 3. REMOVE ALL LOOSE ROCK, ROOTS AND OTHER OBSTRUCTIONS, LEAVING SURFACE REASONABLY SMOOTH AND 7. THE PROPERTY OWNER IS RESPONSIBLE FOR MAINTAINING THE STORMWATER UNIFORM. CONTROLS(s) ACCORDING TO THE APPROVED MAINTENANCE PLAN AND 4 APPLY AGRICULTURAL LIME, FERTILIZER, AND SUPERPHOSPHATE UNIFORMLY AND MIX WITH SOIL (SEE SEEDING DIRECTION OF NCDEQ. MIXTURE). 5. CONTINUE TILLAGE UNTIL 'A WELL -PULVERIZED, FIRM, REASONABLY UNIFORM SEEDBED 15 PREPARED FOUR TO SIX ,��. �-. �-;�. ��,� moo. ,fir �®^��,�.® �- ""��..P• �.-.�®"'��^ ®"` �s� p�-. �� �" ��'" �./'' ��� ���I""� I °�A' � �^I' INCHES DEEP. 6. SEED ON A FRESHLY PREPARED QED AND COVER SEED LIGHTLY WITH SEEDING EQUIPMENT OR CULTIPACK AFTER SEEDING. 7. MULCH IMMEDIATELY AFTER SEEDING AND ANCHOR MULCH. 8. INSPECT ALL SEEDED AREAS AND MAKE NECESSARY REPAIRS OR RE-SEEDINGS WITHIN THE PLANTING SEASON, IF j � � d .3 POSSIBLE. IF STAND SHOULD BE MORE THAN 60% DAMAGED, RE-ESTABUSH FOLLOWING THE ORIGINAL LIME, FERTILIZER AND SEEDING RATES 9. CONSULT S&EC ENVIRONMENTAL ENGINEERS ON MAINTENANCE TREATMENT AND FERTILIZATION AFTER PERMANENT �OD�A�EAS ABOVE"': `` >` A ACOVER IS ESTABLISHED. o\\� N ° RM L POOL LANDSCAPING NOTES: ° Et VATIflN ALL LANDSCAPING SHALL BE IN COMPLIANCE WITH THE NCOED BMP REQUIREMENTS. NG SURVIVAL REPLACEMENT. ° LANDSCAPE CONTRACTOR SHALL PROVIDE A TWO-YEAR WARRANTY FOR BMP PLANET / TOTAL LITTORAL S ELF AT THE END OF THE FIRST YEAR AND AT THE END OF THE TWO-YEAR WARRANTY PERIOD, ALL PLANTS THAT DO NOT ( ! / .row AREA=4,490�.> SURVIVE MUST BE REPLACED. �. � } ! � � REFER TO �7r ETAIL w BERM �l ESTABLISHMENT PROCEDURES SUCH AS CONTROL. OF INVASIVE WEEDS, ANIMAL AND VANDAL DAMAGE, MULCHING, FOR LPL 1JANGS �a `Iv , RE -STAKING WATERING TO THE EXTEND AND MESH OR TUBE PROTECTION REPLACEMENT, SHALL BE IMPLEMENTED �., , �✓"""� NEEDED TO ENSURE PLANT SURVIVAL, STAKING MUST BE REMOVED AFTER ESTABLISHMENT (APPROXIMATELY 12 MONTHS , TO PREVENT GIRDLING STRANGLING OF ALL WOODY PLANTS. �l aura �\ ` } (STRANGLING) TOP OF EM-�NKMEfdT _ � ASS 2 R -��P �\ SOD WITHIN BMP AND SURROUNDING AREAS TO BE BERMUDA OR CENTIPEDE GRASS. ELEV 263.5 1, MUST BE APPLIED AT THE RATES SPECIFIED BY THE SUPPLIERS. IF PLANT �f EeR ® CL-SS A,RIP-RAP i GRASS OR WILDFLOWER SEED M NOT BE ACHIEVED WITH SEEDING BY THE TIME OF SUBSTANTIAL' COMPLETION OF THE STORMWATER ,r , ' y !' ESTABLISHMENT CANNOT � .� � �R FILTER FABRIC. FACILITY PORTION 4F THE PROJECT, THEN THE CONTRACTOR SHALL PLANT THE AREA.WITHI WILDFLOWER SOD, PLUGS, f 5 (� \ CONTAINER PLANTS, OR OTHER MEANS TO COMPLETE THE SPECIFIED PLANTING AND PROTECT AGAINST EROSION AIN POND `� AT,,POREBAY WEIR LoTr 43 BEFORE WATER IS ALLOWED TO ENTER THE STORMWATER BMP FACILITY. AREA a �i� ✓ �� \� ��irSF P� ALL MATERIALS SHALL BE ACQUIRED FROM AN APPROVED NCDEQ PLANT VENDOR. PLANT MATERIAL SHOULD BE i�/ FORE134Y \� f PURCHASED FROM A LOCAL SOURCE TO ENSURE SURVIVABILITY. LOCAL VENDORS FOR THIS SITE INCLUDE i CILL IDE NATIVE PLANT NURSERY 919-662-5566 F�S y / `i r � Y / WEIR � �� • i - GROWING WILD NURSERY 910-259-6361 7 \ / NC FOREST SERVICE 919-731-7988 ENV--a.0 - PLANT DELIGHTS NURSERY 919-772-4794 f K .: '. j r~ �' f 1 TARHEEL NATIVE TREES 919-553-5927 ✓ + _ �' ..� FOREBpyY ! s l} AREA/ li IMMEDIATELY AFTER THE WET DETENTION BASIN IS ESTABLISHED, THE PLANTS ON THE VEGETATED SHELF AND 26' PERIMETER OF THE BASIN SHOULD BE WATERED TWICE WEEKLY IF NEEDED UNTIL THE PLANTS BECOME ESTABLISHED �. 1 (COMMONLY SIX WEEKS) � •85% 0 1rwa FES STORM OT 44 WAI R- GHT ( . DRAINAGE 24,014 NO PORTION OF THE WET DETENTION POND SHOULD BE FERTILIZED AFTER THE FIRST INITIAL FERTILIZATION THAT IS 1 I p -;-r° � �, BY OTHER / REQUIRED TO ESTABLISH THE PLANTS ON THE VEGETATED SHELF. _� I4 � 1 ST 1X1VIWATT ' NAG MENT LANDSCAPING NOTES:, \ 1. CONTRACTOR SHALL COMPLY WiTH ALL APPLICABLE CODES AND ORDINANCES REGARDING LANDSCAPING. , 0 a TL T C0 TROL 1 t ERASE ENT 2. IT IS THE RESPONSIBILITY E CONTRACTOR TO ESTABLISH A HEALTHY STAND OF GRASS ON ALL SEEDED 1 i f AREAS. OF TH S�UCTURE 3. CONTRACTOR SHALL PROVIDE NATURAL TOPSOIL THAT IS FERTILE, FRIABLE, WITHOUT MIXTURE OF SUBSOIL EFER TO ET LS 1 ` '` r v 1 ✓ /r / I7 MATERIALS, AND OBTAINED FROM A WELL DRAINED, AVAILABLE SITE. IT SHALL NOT CONTAIN SUBSTANCES s IS SHE'T SCREENED AND FREE FROM CLAY LUMPS 1 / WHICH MAY BE HARMFUL TO PLANT GROWTH. TOPSOIL SHALL BE SC , ,% : OTHER OBJECTS / ENV 25 .0 STONES, ROOTS, PLANTS, OR SIMILAR SUBSTANCES 1 OR MORE IN DIAMETER DEBRIS,,OR �, -E � o WHICH MIGHT BE A HINDERANCE r0 PLANTING OPERATIONS TOPSOIL SHALL CONTAIN AT LEAST 4-67. ORGANIC / / MATTER BY WEIGHT AND HAVE A PH RANGE O F 5.5 TO 7.0. / \ .� ' 4. CONTRACTOR SHALL BE RESPONSIBLE FOR THE WATERING AND THE MAINTENANCE OF ALL LANDSCAPED AREAS / I` UNTIL THE LATER OF, (a) THIRTY (30) DAYS FOLLOWING THE PLANTING CP THE GRASS AND SHRUBS, OR (b) IIF - THE DATE THAT STORE OPENS FOR BUSINESS TO THE PUBIC. CONTRACTOR SHALL ALSO BE RESPONSIBILITYt ' "\�''-FOR THE SURVIVAL OF THE BMP PLANTING MATERIALS DURING THE TWO-YEAR WARRANTY PERIOD AND SHALL REPLACE ALL PLANTS THAT DO NOT SURVIVE AT THE END OF THE FIRST YEAR AND AT THE END OF THE SECOND YEAR OF THE WARRANTY PERIOD. GRAPHIC SCALE 5. CONTRACTOR TO VERIFY QUANTITIES PRIOR TO COMMENCING WORK. 6. ANY DISTURBED AREAS NOT SCHEDULED FOR HANDSCAPE, PLANTINGS, OR MULCH SHALL BE SEEDED LAWN. 50 0 25 50 100 200 REFER TO 51TE PLAN FOR LOCATION OF AREAS TO BE SODDED. 7. NO PLANT SUBSTITUTIONS ARE PERMITTED WITHOUT WRITTEN APPROVAL OF THE OWNER5 REPRESENTATIVE PLAN VIEW 8. FOR NEW PLANTING AREAS, REMOVE ALL PAVEMENT, GRAB SUB -BASE AND CONSTRUCTION DEBRIS; REMOVE COMPACTED SOIL AND ADD 18" NEW TOPSOIL, OR TILL AND AMEND THE TOP 18' OF EXISTING SOIL TO MEET TOPSOIL/PLANTING MIX STANDARDS FOR TREES ( IN FEET 9, ADJUST TREE PLANTING LOCATIONS TO AVOID UNDERGROUND UTILITIES, PLANT VY FROM ALL UNDERGROUND 1 inch = 50 ft. UTILITIES (SEWER AND STORM DRAINAGE, GAS, WATER, PHONE, AND ELECTRICAL LINES.) Cad file name: P: 046-DoubleD\022-Long'Point Road -missing permit (220061)\CADD\0413-022-SWD #1,dwg TOP OF STRUCTURE NOT SHOWN FOR CLARITY (REMOVABLE TRASH RACK) 1 OUTLET CONTROL STRUCTURE -INCREMENTAL WEIR SCALE: N.T.S. 6' TOPSOIL FOR ALL AREAS ABOVE THE NORMAL POND ELEVATION FOREBAY BER 6' TOPSOIL ABOVE 6' CLAY LINER 3:1 ON LITTORAL SHELF i_ 6FT LITTORAL SHELF6:1 I _ CLASS 2 RIP -RAP COVERED WiTH CLASS A RIP -RAP OVER FILTER FABRIC MIN. 7' WEIR AT ELEV=258.0 NOTES i. SEE DESIGN PLANS FOR SPECIFIED DIMENSIONS OF RISER. 2. TRASH RACK DIMENSION CRITERIA SPECIFIED IS APPROXIMATE AND VARIES BY MANUFACTURER. 3. INSTALLATION OF TRASH RACK SHALL BE ACCORDING TO MANUFACTURER'S RECOMMENDATIONS. 4. ALL COMPONENTS OF TRASH RACK SHALL BE OF STAINLESS STEEL OR OTHER NON -CORROSIVE MATERIAL. 5. ALL MOUNTING HARDWARE SHALL BE OF STAINLESS STEEL OR OTHER NON -CORROSIVE MATERIAL, TRASH RACK DN CORROSIVE MATERIAL /! w 5.5" 0 5.5' SPACING i 1 � O I 1 t RISER TRASH RACK SHALL BE INSPECTED PERIODICALLY AND ANY DEBRIS ON THE TRASH RACK IS TO BE REMOVED AND PROPERLY DISPOSED OF TRASH RACK DETAIL FOFLEBAY TOP ELEV= 261.0 WIDTH AT TOP = 2.0 FT FOREBAY ENTRANCE SHALL BE - DEEPER THAN FOREBAY EXIT POND ELEV.=259.0 e PVC SCREW CAP FOR CLEANING ACCESS 12' MIN. 4"x4' PVC le MIN. l f DIA. HOLE DRILLE INTO BOTTOM CAP PVC DRAIN OUTLET SCALE: N.T.S. NOTE: PUMPS SHALL BE USED TO DRAIN SEDIMENT STORAGE THE FOREBAY WHEN NECESSARY. REFER TO DETAIL TOP THIS SHEET FOR DEWATERING REQUIREMENTS. FOREBAY BOTTOM S� ELEV=257.5 NORMAL POND ELEVATION BOTTOM LITTORAL SHELF ELEV, f-1 BOTTOM OF SEDIMENT STORAGE/EXIT E-EV=257.0 FOREBAY ENTRANCE SHALL BE FOREBAY DEEPER THAN FOREBAY EXIT �- - 6" TOPSOIL FOR ALL AREAS ABOVE THE NORMAL POND ELEVATION BOTTOM OF SEDIMENT STORAGE/ENTRANCE Ei EV=256.5 SHALLOW LAND ZONE HERSA41OUS PLANTS SHALLOW WATER ZONE HERMACEOUS PLANTS POND _ (NORMAL POOL) 1 6 TYPICAL LITTORAL SHELF VEGETATION DETAIL SCALE: N.T.S. SCIENTIFIC NAME COMMON NAME PLANTING ZONE QUANTITY NURSERY CONTAINERTYPE SPACING PLANTING SEASON Janus effesus Soft Rush SHALLOW WATER 188 PEAT POT 6' O.C. SPRING/SUMMER Iris Wrglnfca Blue Flag Iris SHALLOW WATER 188 PEAT POT 6' O.C. SPRING/SUMMER Schoenoplectus tobernoemontani Soft Stem Bulrush SHALLOW WATER 188 PEAT POT 6' O.C. SPRING/SUMMER Eupatoriodelphus maculatus Spotted Trumpetweed SHALLOW WATER 188 PEAT POT 6, O.C. SPRING/SUMMER Eupatorfum purpureum Joe-Pye Weed SHALLOW WATER 188 PEAT POT 6' O.C. SPRING/SUMMER Rhynchospora colorata Starrush Whitetop SHALLOW WATER 188 PEAT POT 6' O.C. SPRING/SUMMER STORMWATER MANAGEMENT DESIGN WET DETENTION -POND #1: RIVER BASIN: RECEIVING STREAM: STREAM INDEX: STREAM CLASS: HUC: PROJECT COORDINATES: POND DESIGN SUMMARY CAPE FEAR LITTLE RIVER (LOWER LITTLE RIVER) 18-23-(10.7) WS-III;HOW 0303000403 35.237786'N,-79.278201 DRAINAGE AREA TO POND: 8.83 ACRES SITE IMPERVIOUS AREA TO POND: AREA 7o POND: 3,21 ACRES 0.0 ACRES_- OFF -SITE DESIGN IMPERVIOUS TOTAL DESIGN IMPERVIOUS AREA TO POND: 3.21 ACRES PRE -DEVELOPED POST -DEVELOPED POST DEVELOPED TO POND THROUGH POND DRAINAGE AREA: TO POND 8.83 AC 8.83 AC CURVE NUMBER: 67.4 80.4 TIME OF CONCENTRATION: 18.1 MIN 5 MIN 1.0" STORM EVENT 0.319 CFS 0.024 CFS 1-YEAR STORM EVENT: 5.557 CFS 20.11 CFS 1.660 CFS 2-YEAR STORM EVENT: 9.398 CFS 27.54 CFS 3.889 CFS 10-YEAR STORM EVENT: 21.71 CFS 49.16 CFS 12.03 CFS ®100-YEAR STORM EVENT: 44.48 CFS 84.04 CFS 24.56 CFS STAGE/STORAGE TABLE STAGE (FT) ELEVATION (FT) CONTOUR AREA (SF) INCREMENTAL STORAGE (CF) TOTAL STORAGE (CO 0.0 259. 13835 0 0 0.5 259.5 16365 7550 7550 0.8 259.8 17215 5037 12587 (WQV) 1.0 260.0 17785 3500 16087 2.0 261.0 20665 19225 35312 3.0 262.0 23895 22280 57592 4.0 263.0 26330 25113 82705 4.5 263.5 27570 13475 96180 TYPICAL LITTORAL SHELF PLANTING SCHEDULE OPERATION & MAINTENANCE BMP element: Potential roblem: How I will remediate the problem The entire BMP Trash debris is present Remove the trash debris ® enm er of the wet etention bosun Areas of bare soil and/or erosive gullies have formed egr'I e nec e s essary o remove the gully, and then plant a ground cover and water until it is established. Provide Ilme and a one-time fertilizer application Vegetation is too short or too long Main a n v on a s e g of approximately six inches. The Inlet device: pipe or ®Ie The pipe is dogged. Unclog the pipe. Dispose of the sediment off -site. The p pe s craC a or otherwise dame ace e pipe. r an c nil in the swole, Regre a e swa a necessary to n oth it over and provide erosion control devices such as reinforced turf matting our riprop to avoid future problems with erosion. e farebay Sediment has accumulated to a depth greater than the alainal deslgn depth for sediment storage. Search for the source of the sediment and remedy the problem if possible. Remove the sediment and dispose of it in a location where it will not case Impacts to streams or the Bi roaon hue occu row e a I was erosion protection such as reinforced turf mattm or riprop if needed to revel future erosion Rroblerns. ee s are present Remove the wee s, pr era y by hand. If t.cide is used, wipe It on the pants rather than in s ra . The vegetated s es '"fessiond practices show that pruning Is needed to maintain optimal plant hedih. Prune according to best professional practices Plants are dead, diseased or dying. Determine the source of the problem: soils, hydrology, disease, etc. Remedy the problem and replace plants. Provide a one-time fertilizer application to establish the ground cover If a sot test indicates it is necessar . Weeds are present emote the wee s1 preferably DX hand. If pesticide Is used, Imps It on the plants rather than sran. The main treatment area Sediment has accumulated to a depth greater than the original design sediment storage depth. Search far the source of the sediment and remedy the problem if possible. Remove the sediment and dispose ofit in a location where it will not case hDacts to streams or the BMP. Al gar growth covers over of the area. Consulta o ess ono o remove and control the al a arowth. aI s, ragm a other Invasive plants cover 50% Ofthen Remove a plants wiping with pesticide do no the basin surface. s ra e em n en ru s ave s a e o grow on the embankment emote shrubs man ar e y. w ence -9f muskrat or beaver activity is present. Use traps to remove mus a s and consult a professional to remove beavers. A tree has started to grow on the embankment. An annual innspection by an appropriate professional shows that the embankment needs Consult a dam safety specialist to remove the tree. Make all needed repayi repair. if applicable) The outlet device Clogging has occurred. can out a ou a ce. Dispose of the sediment off -site. The oailet device is damaged Reppir or replace the outlet device. e receiving water Erosion or other signs of damage have occurred at the outlet, Contact the local NC Division of Water Quality Re glonai Office, our the 401 Oversight Unit at 919-733-17B6. 75 F_ U M cc 09 (0 0 9- c+9 0) C\I C� Z LLI J 0 cr) 1.0 o 0- E W 3 o Z E co 0 17- LJJ *: -„s" r:' Mir .,: r,. 0 C 0 CIO 0 R + p4;FESsr�;y®�y+® SEAL ° 051571 Po e •. FL 1�1`'l��� 1 C' ®•NGI NEON' r,rrArrs+ PLAN STATUS 01 /26/22 INITIAL SUBMISSION 03/14/22 LAYOUT REVISION 11/14/22 NCDEQ COMMENTS DATE CEP DESIGN DESCRIPTION CEP CEP DRAWN CHKD rF ONSTRUCTION SEQUENCE OR WET DETENTION POND: 1. INSTALL EROSION CONTROLS. 2. CONSTRUCT DAM BASE AND AREAS BELOW THE NORMAL POOL. CONSTRUCTION TO BE PERFORMED UNDER THE INSPECTION OF THE GEOTECHNICAL ENGINEER. SEED UPON COMPLETION. 4' MIN 3. INSTALL OUTLET PIPE, RIP -RAP APRON AND EMBANKMENT WIDTH STONE FILTER RING, 4. CONSTRUCT OUTLET STRUCTURE. a TOPSOIL FOR ALL AREAS ABOVE THE TRASH RACK 5, REMOVE ACCUMULATED SEDIMENT AND SEED NORMAL POND ELEVATION REFER TO DETAIL UPON COMPLETION. THIS SHEET roo c�, �R e Z5s4 c �6'•�@ TOP OF STRUCTURE NOT SHOWN FOR CLARITY (REMOVABLE TRASH RACK) 24' HDPE WITH WATER TIGHT SEAL PIPE TO BE BEDDED TOP of EMBANKMENT ELEVATION=257.0 OUTLET CONTROL STRUCTURE - INCREMENTAL WEIR PER DIRECTION OF GEOTECHNICAL 6" TOPSOIL ABOVE NOTE: EL STORM ELEVATION IS IS AD AND INTERMEDIATE _ _ _ _ WtIR IS ELEVATION 253.8. THERE IS ADDITIONAL STORAGE SCALE: N.T.S. ENGINEER 2 6" CLAY LINER REFER TO DETAIL Too YEAR STORM ELEVATION=255.93 - �-� DESIGNED FROM. THE 1.0° STORM ELEVATION TO THE _� ON LITTORAL SHELF FOR INCREMENTAL INTERMEDIATE WEIR ELEVATION. 1 I 6 CLAY SOIL 3 WEIR fi LINER ON INSIDE ^I I TOPSOIL FOR ALL FACE OF ,. AREAS ABOVE THE EMBANKMENT 10 WAR STORM EI FVATlON=255.32 ' Iv 1 NORMAL POND ELEVATION I, g Iz - 44' PRECAST FOREBAY BER 6FT LITTORAL I Imo- I 1 QUSCRETE REIPS 2 YEAR STORM ELEVATION=254.55 SHELF -- ATALL STEPS S NECESSARY) -�-1 ,-- 1 YEAR STORM ELEVATION=254.23 6' TOPSOIL ABOVE 6" CLAY LINER 3:1 I ON LITTORAL SHELF INV--253.0 1.0-INCH STORM ELEVATION=253.26 EXISTING GRADE=254.0t ff NORMAL POND ELEVATION=253.0 `I 6FT U SHELF 6.1 I jam/ s PVC ELBOW 3' MIN SEE DETAIL'...a® �..a�'e.��'� ..�`��..�'e.�`•,_..�' ....� `.� 1 ELEV--251.0 9A rs I I (� 1.75 NOTE: PUMPS SHALL BE USED TO GRAIN A 1 THE POND WHEN NECESSARY. REFER TO DETAIL THIS SHEET FOR DEWATERING REQUIREMENTS. 4' IN. ASTM 0-923 SEAL KEY BETWEEN BARREL. & RISER. RISER BASE TO BE FILLED CUTOFF TRENCH WITH CONC. TO INVERT OF III � BOTTOM OF POND (TOP OF SEDIMENT STORAGE)=248.0 APPROXIMATE SIZE BARREL Offia TE SHALL BE EXCAVATE AND BACKFILL 8'X8°Xi'X12' LONG ANGLE (6 TOT. REQUIRED) TO ANCHOR RISER TO PLACED IN A RISER AFTER I I I WITH COMPACTED BASE PROVIDE 2-3/47tl A307 BOLTS FROM ANGLE TO RISER AND ANGLES 0 BASE ARE ND RISER.SECURED�_� f�-�(BOTTOM OF SEDIMENT STORAGE)=247.0 STRUCTURAL FILL AS 2-A307 J" HOOKS 3/4 DIA. X 12" LONG FROM ANGLE TO BASE. ANGLE TO BE FIELD COATED WiTH ZINC RICH PAINT AFTER DIRECTED BY GEOTECHNICAL CONSTRUCTION. "J" HOOKS TO BE PLACED UNDER LOWER REINFORCING ENGINEER STEEL 6" CLAY SOIL 5'x5'x1.5' OONC. BASE REINFORCE WITH #4 BARS AT 12" O.C. TOP LINER AND BOTTOM OF EACH DIRECTION PROVIDE 3° MIN. CLEARANCE MAIN POOL 73'-24" HOPE ® 4.11% BETWEEN EDGE OF CONC, AND STEEL REINFORCING. PROFILE OF WET POND DETENTION SYSTEM SCALE: N.T.S. LTER MEDIA (SEE NOTE 2) SILT FENCE AS NEEDED LIMP FL STORMWATER MANAGEMENT NOTES: ( 1. THE DEVELOPER OR HIS AGENT SHALL CONTACT THE DESIGN ENGINEER WHEN _ ,c2 THE BEST MANAGEMENT PRACTICE(S) ARE CONSTRUCTED AND ABOUT TO 0*_ BECOME OPERATIONAL 50 A FINAL INSPECTION CAN BE PERFORMED TO DETERMINE COMPLIANCE WITH THE APPROVED PLAN CAN BE PERFORMED, TRASH RACK NM: ATER LEVEL 2, ANNUAL MAINTENANCE INSPECTION AND REPORT REQUIRED - THE OWNER OF A PERMITTED STRUCTURAL STORMWATER BMP/CONTROL SHALL ANNUALLY SUBMIT A MAINTENANCE AND INSPECTION REPORT FOR EACH BMP TO THE 1. PRIOR TO INSTALLATION, MANUFACTURER SPECIFICATIONS OF FILTER MEDIA SHALL BE REVIEWED TO STORMWATER ADMINISTRATOR. ANNUAL INSPECTIONS SHALL 13EGIN WITHIN ENSURE THAT DISCHARGE FROM FILTER MEDIA SHALL MEET OR EXCEED THE PROVISIONS OF THE CLEAN ONE YEAR OF THE RECORDATION OF ANY DEED(S) SHOWING STORMWATER I I WATER ACT. ji j BMPs/CONTROL STRUCTURES Z ENSURE THAT PUMP PRESSURE DOES NOT EXCEED FILTER MEDIA PRESSURE RATING. l 3. UPON COMPLETION OF THE PROJECT, AND BEFORE A CERTIFICATE OF I I OCCUPANCY SHALL BE GRANTED, THE ENGINEER OF RECORD SHALL CERTIFY 3. FILTER MEDIA MAY BE, BUT NOT LIMITED TO, SAND MEDIA FILTRATION DEVICES, RATED FILTER FABRIC 1- THAT THE COMPLETED PROJECT IS IN ACCORDANCE WITH THE APPROVED I I BAGS OR POLYMER BASED DEWATERING PRACTICES. -Ir'r- STORMWATER MANAGEMENT PLANS AND DESIGNS. - I r 4. A FINAL INSPECTION OF THE SITE AND STORMWATER MANAGEMENT F flu 4. PUMP STRAINER SHALL NOT BE IN CONTACT WiTH BOTTOM OF POND. ��_ - j�1 - 11 � BMP/CONTROLS TO BE SCHEDULED WITH AND COMPLETED BY THE PROJECT jj I I I i ENGINEER. BMP POND DEWATERING LOW POINT 5. NCDEQ AND THEIR ASSIGNS HAVE RIGHT TO ACCESS THE STORMWATER CONTROL(s) FOR INSPECTIONS OR MAINTENANCE AS NECESSARY. RiSC U. THE ENGINEER'S %E_ "riCATION OF CIIvIPLETION WALL BE REQUIRED PRIOR TO SEEDBED PREPARATION: THE FINAL PLAT OR CERTIFICATE OF OCCUPANCY, THE STORMWATER 1. CHISEL COMPACTED AREAS AND SPREAD TOPSOIL THREE INCHES DEEP OVER ADVERSE SOIL CONDITIONS, IF CONTROL IS TO BE INSPECTED TO ENSURE IT IS FUNCTIONING AS DESIGNED AND HAS FULL DESIGN VOLUME PWOR TO ISSUANCE OF THE FINAL AVAILABLE. 2. RIP THE ENTIRE AREA TO SIX INCHES DEEP. CERTIFICATE OF OCCUPANCY. J. REMOVE ALL LOOSE ROCK, ROOTS AND OTHER OBSTRUCTIONS, LEAVING SURFACE REASONABLY SMOOTH AND 7. THE PROPERTY OWNER IS RESPONSIBLE FOR MAINTAINING THE STORMWATER UNIFORM. CONTROLSW ACCORDING TO THE APPROVED MAINTENANCE PLAN AND 4. APPLY AGRICULTURAL LIME, FERTILIZER, AND SUPERPHOSPHATE UNIFORMLY AND MIX WITH SOIL (SEE SEEDING DIRECTION OF NCDEQ MIXTURE). 5. CONTINUE TiLLAGE UNTIL A WELL -PULVERIZED, FiRM, REASONABLY UNIFORM SEEDBED IS PREPARED FOUR TO SIX �\ �� �► � ��,,o �\ � - - - - - - - INCHES DEEP. 6. SEED ON A FRESHLY PREPARED SEEDBED AND COVER SEED LIGHTLY WITH SEEDING EQUIPMENT OR CULTiPACK AFTER SEEDING. 7. MULCH IMMEDIATELY AFTER SEEDING AND ANCHOR MULCH. 8. INSPECT ALL SEEDED AREAS AND MAKE NECESSARY REPAIRS OR_RE-SEEDINGS WITHIN THE PLANTING SEASON, IF / �\ POSSIBLE. IF STAND SHOULD BE MORE THAN 60% DAMAGED, RE-ESTABLISH FOLLOWING THE ORIGINAL LIME, \� FER11UZER AND SEEDING RATES.- 9. 'CONSULT 5&EC ENVIRONMENTAL ENGINEERS ON MAINTENANCE TREATMENT AND FERTILIZATION AFTER PERMANENT COVER IS ESTABLISHED. LANDSCAPING NOTES: �' , OP 0 EMBA ' ELE' ALL LANDSCAPING SHALL BE IN COMPLIANCE WITH THE NCDEQ BMP REQUIREMENTS. ;LANDSCAPE CONTRACTOR SHALL. PROVIDE ATWO-YEAR WARRANTY FOR BMP PLANTING SURVIVAL/REPLACEMENi. AT THE END OF THE FIRST YEAR AND AT THE END OF THE TWO-YEAR WARRANTY PERIOD, ALL PLANTS THAT DO NOT SURVIVE MUST BE REPLACED. ESTABLISHMENT PROCEDURES, SUCH AS CONTROL OF INVASIVE WEEDS, ANIMAL AND VANDAL DAMAGE, MULCHING, RE -STAKING, WATERING, AND MESH OR TUBE PROTECTION REPLACEMENT, SHALL BE IMPLEMENTED TO THE EXTEND �•,, � � 1, NEEDED TO ENSURE PLANT SURVNAL. STAKING MUST BE REMOVED AFTER ESTABLISHMENT (APPROXIMATELY 12 -� MONTHS), TO PREVENT GIRDLING (STRANGLING) OF ALL WOODY PLANTS. �\ SOD WITHIN BMP AND SURROUNDING AREAS TO BE BERMUDA OR CENTIPEDE GRASS, '- -'''� U I GRASS OR WILDFLOWER SEED MUST BE APPLIED AT THE RATES SPECIFIED BY THE SUPPLIERS. IF PLANT ESTABLISHMENT CANNOT BE ACHIEVED WITH SEEDING BY THE TIME OF SUBSTANTIALCOMPLETON OF THE STORMWATER E FACILITY PORTION OF THE PROJECT, THEN THE CONTRACTOR SHALL PLANT THE AREA WITH WILDFLOWER SOD, PLUGS, CONTAINER PLANTS, OR OTHER MEANS TO COMPLETE THE SPECIFIED PLANTING AND PROTECT AGAINST EROSION BEFORE WATER IS ALLOWED TO LINTER THE STORMWATER BMP FACILITY. ALL MATERIALS SHALL BE ACQUIRED FROM AN APPROVED NCDEq PLANT VENDOR. 'PLANT MATERIAL 5'FIOIILD BE PURCHASED FROM A LOCAL SOURCE TO ENSURE SURVIVABILITY. LOCAL VENDORS FOR THIS SITE INCLUDE: - CILL IDE NATIVE PLANT NURSERY 919-662-5566 �� 3y-2(i'nH - GROWING WILD NURSERY 910-259-6361 `o 1 0 NC FOREST SERVICE 919-731-7988 `. R-GH - PLANT DELIGHTS NURSERY 919-772-4794 TARHEEL NATIVE TREES 919-553-5927 IMMEDIATELY AFTER THE WET DETENTION BASIN IS ESTABLISHED, THE PLANTS ON THE VEGETATED SHELF AND PERIMETER OF THE BASIN SHOULD BE WATERED TWICE WEEKLY IF NEEDED UNTIL THE PLANTS BECOME ESTABLISHED ` s (COMMONLY SIX WEEKS) _ NO PORTION OF THE WET DETENTION POND SHOULD BE FERTILIZED AFTER THE FIRST INITIAL FERTILIZATION THAT IS REQUIRED TO ESTABLISH THE PLAITS ON THE VEGETATED SHELF. LANDSCAPING NOTES: 1. CONTRACTOR SHALL COMPLY WITH ALL APPLICABLE CODES AND ORDINANCES REGARDING LANDSCAPING, 2. IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO ESTABLISH A HEALTHY STAND OF GRASS ON ALL SEEDED AREAS. CATC qASI 3, CONTRACTOR SHALL PROVIDE NATURAL TOPSOIL THAT IS FERTILE, FRIABLE, WITHOUT MIXTURE OF SUBSOIL MATERIALS, AND OBTAINED FROM A WELL DRAINED, AVAILABLE SITE. IT SHALL NOT CONTAIN SUBSTANCES 1V= 5OI WHICH MAY BE HARMFUL TO PLANT GROWTH. TOPSOIL SHALL BE SCREENED AND FREE FROM CLAY, LUMPS, STONES, ROOTS, PLANTS, OR SIMILAR SUBSTANCES 1" OR MORE IN DIAMETER, DEBRIS, OR OTHER OBJECTS WHICH MIGHT BE A HINDERANCE TO PLANTING OPERATIONS. TOPSOIL SHALL CONTAIN AT LEAST 4-67. ORGANIC MATTER BY WEIGHT AND HAVE A PH RANGE OF 5.5 TO 7.0. 4. CONTRACTOR SHALL BE RESPONSIBLE FOR THE WATERING AND THE MAINTENANCE OF ALL LANDSCAPED AREAS UNTIL THE LATER OR (a) THIRTY (30) DAYS FOLLOWING THE PLANTING OF THE GRASS AND SHRUBS, OR (b) THE DATE THAT STORE OPENS FOR BUSINESS TO THE PUBLIC. CONTRACTOR SHALL ALSO BE RESPONSIBILITY q FOR THE SURVIVAL OF THE BMP PLANTING MATERIALS DURING THE TWO-YEAR WARRANTY PERIOD AND SHALL REPLACE ALL PLANTS THAT DO NOT SURVIVE AT THE END OF THE FIRST YEAR AND AT THE END OF THE T SECOND YEAR OF THE WARRANTY PERIOD. GRAPHIC. SCALE 5. CONTRACTOR TO VERIFY QUANTITIES PRIOR TO COMMENCING WORK. 6. ANY DISTURBED AREAS NOT SCHEDULED FOR HANDSCAPE, PLANTINGS, OR MULCH SHALL BE SEEDED LAWN. 40 a 20 40 80 180 REFER TO SITE PLAN FOR LOCATION OF AREAS TO BE SODDED. 7. NO PLANT SUBSTITUTIONS ARE PERMITTED WITHOUT WRITTEN APPROVAL OF THE OWNERS REPRESENTATIVE. PLAN VIEW 8. FOR NEW PLANTING AREAS, REMOVE ALL PAVEMENT, GRAVEL SUB -BASE AND CONSTRUCTION DEBRIS; REMOVE COMPACTED SOiL AND ADD 18" NEW TOPSOIL, OR TILL AND AMEND THE TOP 18' OF EXISTING SOIL TO MEET TOPSOIL/PLANTING MIX STANDARDS FOR TREES. ( IN FEET ) 9. ADJUST TREE PLANTING LOCATIONS TO AVOID UNDERGROUND UTILITIES, PLANT 15 FROM ALL UNDERGROUND 1 inch = 40 ft. UTILITIES (SEWER AND STORM DRAINAGE, GAS, WATER, PHONE, AND ELECTRICAL LINES.) Cad file name: P48- : 0DoubleD 022-Long Point Road77issinq permit 220061 CADD 048-022-SWD #2.dwq RISER STRUCTURE 4" PVC SCREW CAP - FOR CLEANING ACCESS 12' MIN. 4"x4" PVC TEE 1"DIA, HOLE DRILLED INTO BOTTOM CAP PVC DRAIN OUTLET SCALE: N.T.S. NOTE: PUMPS SHALL BE USED TO DRAIN SEDIMENT STORAGE THE FOREBAY WHEN NECESSARY. REFER TO DETAIL TOP THIS SHEET FOR DEWATERING REQUIREMENTS, FOREBAY BOTTOM 'y1 ELEV=251.5 NORMAL POND ELEVATION BOTTOM LITTORAL SHELF EI.EV. __e� CLASS 2 RIP -RAP COVERED WITH CLASS A RIP -RAP OVER FILTER FABRICi MIN. 6' WEIR AT ELEV=252.5 ILI -i - 6 TOPSOIL FOR ALL I -.,s - FOREBAY ENTRANCE SHALL BE 4 --I � �. -� I I- - AREAS ABOVE THE DEEPER THAN FOREBAY EXIT NORMAL POND ELEVATION BOTTOM OF SEDIMENT STORAGE/EXIT BOTTOM OF SEDIMENT ELEV=251.0 STORAGE/ENTRANCE ELEV=250.5 FOREBAY ENTRANCE SHALL BE FOREBAY DEEPER THAN FOREBAY EXIT 1. SEE DESIGN PLANS FOR SPECIFIED DIMENSIONS OF RISER. 2. TRASH RACK DIMENSION CRITERIA SPECIFIED IS APPROXIMATE AND VARIES BY MANUFACTURER, 3. INSTALLATION OF TRASH RACK SHALL BE ACCORDING TO MANUFACTURER'S RECOMMENDATIONS. 4. ALL COMPONENTS OF TRASH RACK SHALL BE OF STAINLESS STEEL OR OTHER NON -CORROSIVE MATERIAL 5. ALL MOUNTING HARDWARE SHALL BE OF STAINLESS STEEL OR OTHER NON -CORROSIVE MATERIAL. TRASH RACK ON CORROSIVE MATERIAL i i i �� 5.5 0 5.5° SPACING t RISER TRASH RACK SHALL BE INSPECTED PERIODICALLY AND ANY DEBRIS ON THE TRASH RACK IS TO BE REMOVED AND PROPERLY DISPOSED OF TRASH RACK DETAIL FOREBAY TOP E-EV 255.0 WIDTH AT TOP = 2.0 FT SHALLOW LAND ZONE HERBACEOUS PLANTS SHALLOW WATER ZONE HERBACEOUS PLANTS POND (NORMAL POOL) s TYPICAL LITTORAL SHELF VEGETATION DETAIL SCALE. N.T.S. SCIENTIFIC NAME COMMON NAME PLANTING ZONE QUANTITY NURSERY CONTAINERTYPE SPACING PLANTING SEASON Jancus effesus Soft Rush SHALLOW WATER 69 PEAT POT 6' O.C. SPRING/SUMMER Iris virgintca Blue Flag Iris SHALLOW WATER 69 PEAT POT 6' O.C. SPRING/SUMMER Schoenoplectus tobemaementani Soft Stem Bulrush SHALLOW WATER 69 PEAT POT 6' O.C. SPRING/SUMMER Eupotoriadelphus maculatus Spotted Trumpetweed SHALLOW WATER 69 PEAT POT 6' O.C. SPRING/SUMMER Eupatorium purpureum Joe-Pye Weed SHALLOW WATER 69 PEAT POT 6' O.G. SPRING/SUMMER Rhynchosporo colorata Starrush Whltetop SHALLOW WATER 69 PEAT POT 6' O.C. SPRING/SUMMER STORMWATER MANAGEMENT DESIGN WET DETENTION POND #2: RIVER BASIN: CAPE FEAR RECEIVING STREAM: LITTLE RIVER (LOWER LITTLE RIVER) STREAM INDEX: 18 23-(107) STREAM CLASS: WS-111;HQW HUC: 0303000403 PROJECT COORDINATES: 35.237786'N,-79.278200'W POND DESIGN SUMMARY DRAINAGE AREA TO POND: 2.62 ACRES SITE IMPERVIOUS AREA TO POND: 1.09 ACRES OFF-SIIE DESIGN IMPERVIOUS AREA To POND: 0.0 ACRES TOTAL DESIGN IMPERVIOUS AREA TO POND: 1.09 ACRES PRE -DEVELOPED POST -DEVELOPED POST DEVELOPED DRAINAGE AREA: 2.62 AC 2.62 AC CURVE NUMBER: 74.9 84.0 TiME OF CONCENTRATION: 10 MIN 5 MIN 1.0" STORM EVENT: 0.250 CFS 0.012 CFS 1-YEAR STORM EVENT: 3.729 CFS 7.017 CFS 0,958 CFS 2-YEAR STORM EVENT: 5.452 CFS 9.366 CFS 2.182 CFS 10-YEAR STORM EVENT: 10.69 CFS 15.91 CFS 6.084 CFS 100-YEAR STORM EVENT: 19.60 CFS 26.26 CFS 19.11 CFS STAGE/STORAGE TABLE STAGE (FT) EIEVATI((NNN (F T) CONTOUR AREA (SF) INCREMENTAL STORAGE (CF) TOTAL STORAGE (CF) 0.0 253.0 4180 0 0 0.5 253.5 5300 2385 2385 0.8 253,E 5765 1669 4054 (WQV) 1.0 254.0 6040 1181 5234 2.0 255.0 6760 6400 11634 3.0 256.0 8165 7463 19097 4.0 257.0 9590 8878 27974 STORMWATER MANAGEMENT SYSTEM DETAILS 1 NOT TO SCALE TYPICAL LITTORAL SHELF PLANTING SCHEDULE OPERATION & MAINTENANCE BMP element: Potential roblem: How I will remediate the problem e entire BMP Trash debris is present Remove the trash debris e Perimeter at e wet etention bash Areas of bare soil and/or erosive gullies have formed Regrade the soll If necessary o remove the gully, and then plant a Bound cove and water until it is established. Provide lime and a one-time fertilizer application Vegetation is too short or too iong Maintain vegetation at s height of approximately six Inches. e inlet device: pie or wale The pipe is dogged. Unclog the �tpe. Dispose of the sediment o -site. e p e s crac or otherwise dame Replace the pipe. Froslon is occurring in e Swale. egra e e swa c necessary to SI11aath tt over and provide erosion control devices Bch as reinforced turf matting or riprap to avoid future problems with erosion. e forebay Sediment has accumulated to Search for the source of the a depth greater than the orkinal design depth for se, ment storage. sediment and remedy the problem if possible. Remove the sediment and dispose of it in a location where it will not cause Impacts to streams or the BMP• Erosion has occur . Provide aciditional erosion protection such as reinforced turf matting or riprap if needed to revent future erosion Problems. ee s _arepreseflE Remove the weeds, preferably by hand. If pesticide is used, vmpe it on the pants rather than wain. e vegetated shelf Bestprofessional practices show that pruning is needed to maintain optimal plant health. Prune according to best professional practices Plants are dead, diseased or Determine the source of the dying. problem: soils, hydrology, disease, etc. Remedy the problem and replace plants. Provide a one-time fertilizer application to establish the ground cover if a soli test Indicates it is necessary. fiedu are ixesenRemove the weeds, prefera y y hand. If pesticide is used, wipe it on the plants rather than spraying. e main treatment area Sediment has accumulated to Search for the source of the a depth greater than the original dalqn sediment storage depth. sediment and remedy the problem if possible. Remove the sediment and dispose of it in a location whore it will not cause impacts to streams or the BMP. ga gro coves over of the area. onsu a pro ess one o remove and control the alqal Qrowth. Cottat s, ragm es or er invasive plants cover 50% of the basin surface. emove a an s wiping them with pesticide do no spray) e embankment Shru s have started to grow on the embankment Remove shrubs Immediately. v7 ence of muskrat or beaver activity is present. Use rope o remove mu3kralis and consult a professional to remove beavers. A Iree has started to grow on the embankment. Consult a dam safety specialist to remove the tree, An annual innspeetion by an ��propprtate rofessional shows thai the embankment needs Mace all needed repairs. re air, if applicable) e outlet device Clogging has occurred. Disco of the sediment off -site, -out the outlet The outlet device is damaged Keppir or replace the outlet devim e receiving water Erosion or other signs of domoge have occurred at the vut►et. Contact the local NC Division of Water Quality Regional Office, or the 401 Overslght Unit at 919-733-1786. j 0 c ❑ � � c 4 N C'7 Ein D 0 ULU Z U Q 3 C E Co U) Z 0 -0 Z _j c c 3 r," 3 CL m M Uj M M LU it .. .. 0 1 ..:. CL ®,�®rutgro+ RO o ®o pF rGSS/Ry :/" Svr SEAL 051571 '•q'�� 0, AN STATUS 01 /26/2 INITIAL SUBMISSION 0311412re LAYOUT REVISION 11/14/22 NCDEQ COMMENTS DATE CEP DESIGN DESCRIPTION CEP CEP DRAWN CHKD SCALE H: i = 4U• V: OB No. 048-022 DATE JANUARY 26, 202 FILE No. SHEET RIP -RAP PRE-TREATMENT FOREBAY AT PIPE INLETS SEE DETAIL THIS SHEET STORMWATER MANAGEMENT NOTES: TOP OF EN 100-YEAR STORM E 1. THE DEVELOPER OR HIS AGENT SHALL CONTACT THE DESIGN ENGINEER WHEN THE BEST MANAGEMENT PRACTKE(S) ARE CONSTRUCTED AND ABOUT TO SPILLWAY I BECOME OPERATIONAL SO A FINAL INSPECTION CAN BE PERFORMED TO 10-YEAR STORM E DETERMINE COMPLIANCE WITH THE APPROVED PLAN CAN BE PERFORMED; 2. ANNUAL MAINTENANCE INSPECTION AND REPORT REQUIRED - THE OWNER OF EXISTING GRADE = 248.3 2-YEAR STORM EL A PERMITTED STRUCTURAL STORMWATER BMP/CONTROL SHALL ANNUALLY SUBMIT A MAINTENANCE AND INSPECTION REPORT FOR EACH BMP TO THE STORMWATER ADMINISTRATOR. ANNUAL INSPECTIONS SHALL BEGIN WITHIN 1-YEAR STORM E ONE YEAR OF THE RECORDATION OF ANY DEED(S) SHOWING STORMWATER 1.0' RAINFALL El BMPe/CONTROL STRUCTURES BOTTOi 3. UPON COMPLETION OF THE PROJECT, AND BEFORE A CERTIFICATE OF OCCUPANCY SHALL BE GRANTED, THE ENGINEER OF RECORD SHALL CERTIFY THAT THE COMPLETED PROJECT IS IN ACCORDANCE WITH THE APPROVED �•...®' STORMWATER MANAGEMENT PLANS AND DESIGNS. 4, A FINAL INSPECTION OF THE SITE AND STORMWATER MANAGEMENT BMP/CONTROLS TO BE SCHEDULED WITH AND COMPLETED BY THE PROJECT ENGINEER, 5. NCDEQ AND THEIR ASSIGNS HAVE RIGHT TO ACCESS THE STORMWATER CL CONTROL(s) FOR INSPECTIONS OR MAINTENANCE AS NECESSARY. c 6. THE ENGINEER'S CERTIFICATION OF COMPLETION WILL BE REQUIRED PROR TO r THE FINAL PLAT OR CERTIFICATE OF OCCUPANCY. THE STORMWATER CONTROL IS TO BE INSPECTED TO ENSURE IT IS FUNCTIONING AS DESIGNED AND HAS FULL DESIGN VOLUME PRIOR TO ISSUANCE OF THE FINAL CERTIFICATE OF OCCUPANCY. z 7. THE PROPERTY OWNER IS RESPONSIBLE FOR MAINTAINING THE STORMWATER N CONTROLS(s) ACCORDING TO THE APPROVED MAINTENANCE PLAN AND DIRECTION OF NCDEQ. SEASONAL HIGI OPERATION & MAINTENANCE PROVISIONS (INFILTRATION) BMP element: Potentialproblem: How to remediate the problem e entire infiltration basil Trash/debris is present Remove the trash/debris e grass filter strip or other pretreatment Areas of bare sail and/or erosive gullies Regrade the son if necessary to remove area have farmed the gully, plant ground cover and water until established. Provide lime and a one-time fertilize- application Sediment has accumulated to a depth Search for the source of the sediment and greater than three inches remedy the problem if possible. Remove the sediment and dispose of it In a location where it will not cause impacts to streams or the SCM e flow diversion structure (if applicable) The structure is dogged Unclog the conveyance and dispose of any sediment In a location where It will not cause impacts to streams or the SCM The structure is damaged Make any necessary repairs or replace if damage is too much for repair e inlet device The inlet pipe Is dogged (if applicable) Unclog the pipe and dispose of any sediment. in a location where it will not cause impacts to streams or the SCM The inlet pipe is cracked or otherwise damaged (if applicable) Repair or replace the pipe Erosion is occurring in the Swale Regrade the Swale if necessary and (if applicable) provide erosion control devices such as reinforced turf matting or rip -rap to avoid future erosion problems Stone verge Is dogged or covered in Remove sediment and clogged stone and sediment (if applicable) replace with dean stone e basin More than four aches of sediment has Search for the source of the sediment and accumulated remedy the problem if possible. Remove the sediment and dispose of it in a location where it wil not cause impacts to streams or the SCM Erosion of the bash surface has occurred Provide additional erosion protection such or riprop is displaced as reinforced turf matting or riprop if needed to prevent future erosion problems Water is standing more than three days after a storm event Replace the top few aches of soil to see if this corrects the standing water problem. If not, consult an appropriate professional for a more extensive repair e embankment Shrubs or trees are growing on the Remove trees and shrubs immediately embankment An annual inspection by an appropriate Make needed repairs Immediately professional shows that the embankment needs repair e outlet device Clogging has occurred Clean out the outlet device and dispose of sediment in a location where it will not cause impacts to streams or the SCM The outlet device is damaged Repair or replace the outlet device e receiving water Erosion or other signs of damage have Repair the damage and improve the flow occurred at the outlet dissipation structure Discharges from the infiltration trench are Contact the local NCDEQ Regional Office casing erosion or sedimentation in the receiving water GR SO •k d Iy n ry"i S vt t � � fr � i 'r a t yl 1 Y ty - t 7 . >r m ? i n v.a Pti ksJ4i J 4 ti Y '� i! t. i ft ,! INFILTRATION BASIN TYPICAL SECTION NTS AND NOTE: PERCHED WATER LAYER SHALL BE REMOVED WHEN ENCOUNTERED AND REPLACED WITH THE SAND THE FILTER MIXTURE ABOVE. GRASS SOD NOTE: ASS SOD SHALL BE EITHER HYBRID BERMUDA GRASS OR CENTIPEDE THAT HAS BEEN GROWN IN A IL THAT IS FREE OF AN IMPERMEABLE LAYER (SUCH AS CLAY). NOTES: 1. ALL INFILTRATION BASINS SHALL HAVE AN ACCESS EASEMENT CONNECTING TO A DEDICATED PUBLIC RIGHT OF WAY. 2. ALL DRAINAGE AREAS TO AN INFILTRATION BASIN ARE TO BE STABILIZED PRIOR TO INSTALLATION OF SOILS OR GRASS SOD. 3. THE DRAINAGE AREA OF THE INFILTRATION BASIN WILL BE CAREFULLY MANAGED TO REDUCE THE SEDIMENT LOAD TO THE SAND FILTER SYSTEM. 4, THE WATER LEVEL IN THE MONITORING WELL(S) WILL BE RECORDED ONCE A MONTH AND AFTER EVERY STORM EVENT GREATER THAN 1.5 INCHES 5. IMMEDIATELY AFTER THE INFILTRATION BASIN IS ESTABLISHED, THE VEGETATION WILL BE WATERED TWICE WEEKLY IF NEEDED UNTIL PLANTS BECOME ESTABLISHED (COMMONLY SIX WEEKS) 6. NO PORTION OF THE INFILTRATION BASIN WILL BE FERTILIZED AFTER THE INITIAL FERTILIZATION THAT IS REQUIRED TO ESTABLISH THE VEGETATION. 7, THE VEGETATION IN AND AROUND THE BASIN WILL BE MAINTAINED AT A HEIGHT OF APPROXIMATELY SIX INCHES. BERM a, u DRAINAGE BY OTHERS �► \ \` \ \ �A� FES -- 1 �\ FES \\ \ > I \ \ p a Ilk via A. a. e R 1 � I\ � p - a, STORM' f TOR' OF EMBAN!&1v1ENT, ' Q AIN� GE� \ E EV=252.0 BY OTH RSI , A � A I \ �c OBSERVATION Io WELL (TYI-)_ AINAGEvI �T `\ EASE ENT % a, a, a AL l4 ail GASS SiPLLWAY I I R FER " DEif L t THIS SHET ` ` --� a, a,,-- i�� GRAPHIC SCALE 0 0 20 40 80 160 ( IN FEET) PLAN VIEW 1 inch 40 ft. STORMWATER MANAGEMENT SYSTEM DETAILS 1 NOT TO SCALE FILTER FABRIC INFILi SANE REMOVABLE CAP 6° SCHEDULE 40 PVC, SOR35, OR SMOOTH WALL CORRUGATED PLASTIC PIPE WITH 3/le PERFORATIONS 0 6" ON CENTER (4 HOLES PER ROW) FLUSH WiTH PAVEMENT IN PERMEABLE PAVEMENT AREAS i�V d �Y IS tint{� IY Y i 1 ;Y„�Y 9`y 4Y�b I�'; 1 Yd'. o O IAti f eY'r$4 r,v rdrHh .Jm �v'. ti qq; N 7 .e" f yftt.i R i p Q O b •1 § t t Yt 6f u .i f� d I,. +,yi '}"i 'ir tAl, 4 i ItN Jt '1, •vttT Op0 y S y y h^'- ✓ d^ rpr d Id4Y ati�i� _ wa i+i`�iY pti y4,t YI ;2Aai Jay}w Op0 ,�� •^• Z d,nf Y�>Iti Y+ltdr4/ fS�ih tJil4r a. ittl" 000 RATION ,t d A(S p �� t 4riFf. MEDIA .�-!„7 Si4 16h dnrsk �{i'at r°o°"{� jL� O �A YprYx d iS Ixikdl S $Y S�Yt� OpO VN 'I YAgYJtb Siygd\rf 'fit w��t Jr'Li '!a p Op0 �'�fd �� yt Sa�r�;a tth� Y CL {, VI .. ri�titvl ,1,6,b 0 oG fix• �,7t �h y 5 o drq t''i <i %'yiy 1, 4'a �ttayt opo }v y r 4v a 1s i'� aM ° r' Rt, kr � u o o-r,� i 8 s {sst i a,'•J 4 w• k j �; .,,, tt' aYt'.9;� opo J s 4 b t ywi O o now 000"+' nRKV Y7 �•t.;t�rk 1�,tY���,tntt°-,:�:v!f� �.�JF,,` vs•�vl&r7+,hdy, VNUISiURUED S 05LIL INSERT 4"-6" INTO IN -SITU SOIL BASE OBSERVATION WELL SCALE: N.T.S. STORM DRAINAGE PIPE OR CONCRETE FLUME OUTFALL INTO POND LENGTH dt WIDTH DIMENSIONS 7BE PER RIP -RAP APRON DETAIL FILTER BED ELEVATION ram` BIO-RETENTION POND 17 l --- Tr -r TAPER DEPTH it=t-l{h-i�-�i-i- I 11=III=iI I NTN FOREBAY,q°9�q�O�Od0�099�tlp `- 6' CLASS B RIP -RAP FOREBAY FILiERFABR c SCALE: N.TS. LTER MEDIA (SEE NOTE 2) SILT FENCE AS NEEDED MP �- 'FLOW - SOW NOTES- 1. PRIOR TO INSTALLATION, MANUFACTURER SPECIFICATIONS OF FILTER MEDIA SHALL BE REVIEWED TO ENSURE THAT DISCHARGE FROM FILTER MEDIA SHALL MEET OR EXCEED THE PROVISIONS OF THE CLEAN WATER ACT. 2. ENSURE THAT PUMP PRESSURE DOES NOT EXCEED FILTER MEDIA PRESSURE RATING. _ 3. FILTER MEDIA MAY BE, BUT NOT LIMITED TO, SAND MEDIA FILTRATION DEVICES, RATED FILTER FABRIC L BAGS OR POLYMER BASED DEWATERING PRACTICES 4. PUMP STRAINER SHALL NOT BE IN CONTACT WITH BOTTOM OF POND. I BMP POND DEWATERING LOW POINT m SPILLWAY FLOW Q(100) LONG SLOPE(%) H 8 W SS CHANNEL LINING TOP OF EMBANKMENT ELEVATION SPILLWAY ELEVATION INFILTRATION SPILLWAY 34J0 CFS 3.33� 1.T 10.0' 20.2' 3:1 STRAW WITH NET NAG SHOREMAX W/ P300 252.0 250.3 w EXTEND LINING TO EXTEND LINING TO TOP OF SPILLWAY TOP OF SPILLWAY TOP OF EMBANKMENT=252.0 � H CHANNEL LINING sS SPILLWAY ELEVATION=250.3 MATTING SHALL BE AS NOTED OR APPROVED EQUAL. 13 GRASS SPILLWAY DETAIL GRASS SOD ON SPILLWAY AND SIDE SLOPES STAGE/STORAGE TABLE STAGE (FT) ELEVATION (FT) CONTOUR AREA (SF) INCREMENTAL STORAGE (CF) TOTAL STORAGE (CF) 0.0 246.0 11195 0 0 1.0 247.0 12725 11960 11960 1.1 247.1 12800 1280 13240 (WQV) 2.0 248.0 14SIO 12236 25476 3.0 249.0 15950 15130 40606 4.0 250.0 17650 16800 57406 5.0 251.0 19405 18528 75933 6.0 252.0 21215 20310 96243 STORMWATER MANAGEMENT DESIGN INFILTRATION SYSTEM #3: RIVER BASIN: CAPE FEAR RECEIVING STREAM: LITTLE RIVER (LOWER LITTLE RIVER) STREAM INDEX: 18-23-(10.7) STREAM CLASS, WS-III;HQW HUC: 0303000403 PROJECT COORDINATES: 35.237786N,-79,278200'W POND DESIGN SUMMARY 9.74 ACRES DRAINAGE AREA TO POND: SITE IMPERVIOUS AREA TO POND: 3.40 ACRES OFF SITE DESIGN IMPERVIOUS AREA TO POND: 0.0 ACRES TOTAL DESIGN IMPERVIOUS AREA TO POND: 3.40 ACRES PRE -DEVELOPED POND POST -DEVELOPED POST DEVELOPED TO POND THROUGH POND TO DRAINAGE AREA: 9.74 AC 9.74 AC CURVE NUMBER: 73.5 82.1 TiME OF CONCENTRATION: 18.5 MIN 5 MIN 1.0" STORM EVENT- 0.608 CFS 0,000 CFS 1-YEAR STORM EVENT 9,970 CFS 23.93 CFS 0.000 CFS 2-YEAR STORM EVENT: 14,97 CFS 32.47 CFS 0.000 CFS 10-YEAR STORM EVENT: 30.41 CFS 56.58 CFS 0,000 CFS 100-YEAR STORM EVENT: 57.06 CFS 95.10 CFS 3430 CFS � cc ❑ CD (D 11�C) L -0C Cal i0 LL1 d N G7 0� C7 E V a z m0 _ E �° to d Uj E m m F z 0 jjj W LIJ i1r 0 W ULJ 0/'t�+ .40 Cr 0 1 lW z 0 o O .�'FEssia•., ti ® SEAL 051571 z 01 /26/2 INITIAL SUBMISSION 03/14/22 LAYOUT REVISION 11/14/22 NCDEQ COMMENTS DATE CEP DESIGN DESCRIPTION CEP CEP DRAWN CHKD H• 1" = 40'