HomeMy WebLinkAboutSW6201201_1641 Supplement Wet Pond_20210120WET POND
1 Drainage area number
2 Minimum required treat
GENERAL MDC FROM 02H .1050
3
Is the SCM sized to treat the SW from all surfaces at build -out?
Yes
4
Is the SCM located away from contaminated soils?
Yes
5
What are the side slopes of the SCM (H:V)?
3:1
6
Does the SCM have retaining walls, gabion walls or other
engineered side slopes?
No
7
Are the inlets, outlets, and receiving stream protected from erosion
10-yea r storm)?
Yes
8
Is there an overflow or bypass for inflow volume in excess of the
design volume?
Yes
9
What is the method for dewatering the SCM for maintenance?
Pump (preferred)
10
If applicable, will the SCM be cleaned out after construction?
Yes
11
Does the maintenance access comply with General MDC (8)?
Yes
12
Does the drainage easement comply with General MDC (9)?
Yes
13
If the SCM is on a single family lot, does (will?) the plat comply with
General MDC (10)?
N/A
14
Is there an O&M Agreement that complies with General MDC (11)?
Yes
15
Is there an O&M Plan that complies with General MDC (12)?
Yes
161
Does the SCM follow the device specific MDC?
Yes
17
Was the SCM designed by an NC licensedprofessional?
Yes
WET POND
MDC FROM 02H .1053
18
Sizing method used
SA/DA
19
Has a stage/storage table been provided in the calculations?
Yes
20
Elevation of the excavated main pool depth (bottom of sediment
removal) (fmsl
361.00
21
Elevation of the main pool bottom (top of sediment removal) (fmsl)
363.00
221
Elevation of the bottom of the vegetated shelf (fmsl)
368.00
23
Elevation of the permanent pool (fmsl)
368.50
24
Elevation of the top of the vegetated shelf (fmsl)
369.00
25
Elevation of the temporary pool (fmsl)
371.02
26
Surface area of the main permanent pool (square feet)
11880
27
Volume of the main permanent pool (cubic feet)
67925 cf
28
Average depth of the main pool (feet)
5.71 ft
29
Average depth equation used
Equation 2
30
If using equation 3, main pool perimeter (feet)
31
If using equation 3, width of submerged veg. shelf (feet)
32
Volume of the forebay (cubic feet)
12441 cf
33
Is this 15-20% of the volume in the main pool?
Yes
34
Clean -out depth for forebay (inches)
24 in
35
Design volume of SCM (cu ft)
91433 cf
361
Is the outlet an orifice or a weir?
Orifice
37
If orifice, orifice diameter (inches)
3 in
38
If weir, weir height (inches)
39
If weir, weir length (inches)
40
Drawdown time for the temporary pool (days)
2.1
41
Are the inlet(s) and outlet located in a manner that avoids short-
circuiting?
Yes
42
Are berms or baffles provided to improve the flow path?
No
43
Depth of forebay at entrance (inches)
96 in
44
Depth of forebay at exit (inches)
90 in
45
Does water flow out of the forebay in a non -erosive manner?
Yes
46
Width of the vegetated shelf (feet)
6 ft
47
Slope of vegetated shelf (H:V)
6:1
48
Does the orifice drawdown from below the top surface of the
ermanent pooI?
Yes
49
Does the pond minimize impacts to the receiving channel from the 1-
r, 24-hr storm?
Yes
50
Are fountains proposed? (If Y, please provide documentation that
MDC 9 is met.
No
51
Is a trash rack or other device provided to protect the outlet system?
Yes
52
Are the dam and embankment planted in non -clumping turf grass?
Yes
53
Species of turf that will be used on the dam and embankment
Centepede
54
Hasa plantinq plan been provided for the vegetated shelf?
Yes
ADDITIONAL
INFORMATION
55
Please use this space to provide any additional information about
the wet pond(s):
Wet Pond 1 5:01 PM 1/20/2021